Jen Braly, Director, EPMO’s Program Management Team
Date: 15 Sep 15
Lunch and Learn
Getting to know the EPMO
Presenter:
2
• Introduction to the EPMO
- Mission
- EPMO Maturity: Yesterday, Today and Tomorrow
• Introduction to the Lunch and Learn series
• Portfolio Dashboards Session
Lunch and Learn Agenda
3
Agero EPMO Mission:
Through facilitation and collaboration, develop and implement governance
standards, processes and accountability measures that enable and assist the
enterprise to deliver quality products and services that align with Agero’s
strategic initiatives, on time, on budget, and with full transparency.
Key Responsibilities:
• Portfolio Governance: Responsible for governance standards, accountability
measures, conformance, auditing, analysis, reporting, training and
communication
• Program Management: Providing Program Management resources to support
Client Implementations, Product portfolios, and other key programs / projects
• Process Improvement: Identifying and addressing areas throughout Agero
that require improvement and to affect change through analysis, solutions
and implementation
Who Are We? - Mission
4
YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND)
• Enhanced Steering Committee
process to improve
prioritization, risk identification
and alignment to KI’s
• Establishing a Risk Tracker
and Risk Council to identify
problems early and
recommend corrective actions
• Enterprise risk tracking and
reporting
• Established Prioritization
Process and tracking
mechanism in Planview to align
resources to requirements and
cost tracking
• Tightly manage and understand
new work requests through
prioritization, steering and
change request processes
• Implementation of a series
of Benefits Tools for use in
decision making/prioritization
including Earned Value, NPV
and ROI calculations
• Established the Program
Management team and
processes to support our clients
and products
• Creation of a SharePoint
Knowledge Center as a single
repository of portfolio tools
and information
• Additional resources to
support new product
development and pilots
• Began weekly distribution of
Program Health Dashboards to
improve visibility of program
status’
• Continue to enhance the client
onboarding processes via
implementation tools,
complexity matrices, and client
work kits
• Provide corporate tools,
templates and processes for
use by all areas of the
organization
EPMO Maturity
5
YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND)
• Enhanced Steering Committee
process to improve
prioritization, risk identification
and alignment to KI’s
• Establishing a Risk Tracker
and Risk Council to identify
problems early and
recommend corrective actions
• Enterprise risk tracking and
reporting
• Established Prioritization
Process and tracking
mechanism in Planview to align
resources to requirements and
cost tracking
• Tightly manage and understand
new work requests through
prioritization, steering and
change request processes
• Implementation of a series
of Benefits Tools for use in
decision making/prioritization
including Earned Value, NPV
and ROI calculations
• Established the Program
Management team and
processes to support our clients
and products
• Creation of a SharePoint
Knowledge Center as a single
repository of portfolio tools
and information
• Additional resources to
support new product
development and pilots
• Began weekly distribution of
Program Health Dashboards to
improve visibility of program
status’
• Continue to enhance the client
onboarding processes via
implementation tools,
complexity matrices, and client
work kits
• Provide corporate tools,
templates and processes for
use by all areas of the
organization
EPMO Maturity
6
YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND)
• Enhanced Steering Committee
process to improve
prioritization, risk identification
and alignment to KI’s
• Establishing a Risk Tracker
and Risk Council to identify
problems early and
recommend corrective actions
• Enterprise risk tracking and
reporting
• Established Prioritization
Process and tracking
mechanism in Planview to align
resources to requirements and
cost tracking
• Tightly manage and understand
new work requests through
prioritization, steering and
change request processes
• Implementation of a series
of Benefits Tools for use in
decision making/
prioritization including
Earned Value, NPV and ROI
calculations
• Established the Program
Management team and
processes to support our clients
and products
• Creation of a SharePoint
Knowledge Center as a single
repository of portfolio tools
and information
• Additional resources to
support new product
development and pilots
• Began weekly distribution of
Program Health Dashboards to
improve visibility of program
status’
• Continue to enhance the client
onboarding processes via
implementation tools,
complexity matrices, and client
work kits
• Provide corporate tools,
templates and processes for
use by all areas of the
organization
EPMO Maturity
7
YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND)
• Enhanced Steering Committee
process to improve
prioritization, risk identification
and alignment to KI’s
• Establishing a Risk Tracker
and Risk Council to identify
problems early and
recommend corrective actions
• Enterprise risk tracking and
reporting
• Established Prioritization
Process and tracking
mechanism in Planview to align
resources to requirements and
cost tracking
• Tightly manage and understand
new work requests through
prioritization, steering and
change request processes
• Implementation of a series
of Benefits Tools for use in
decision making/
prioritization including
Earned Value, NPV and ROI
calculations
• Established the Program
Management team and
processes to support our clients
and products
• Creation of a SharePoint
Knowledge Center as a single
repository of portfolio tools
and information
• Additional resources to
support new product
development and pilots
• Began weekly distribution of
Program Health Dashboards to
improve visibility of program
status’
• Continue to enhance the client
onboarding processes via
implementation tools,
complexity matrices, and client
work kits
• Provide corporate tools,
templates and processes for
use by all areas of the
organization
EPMO Maturity
8
x1. Today – Portfolio Dashboards
2. November - EPMO Governance
3. New Client Implementation Process
4. Risk Management Process and the New Risk Council
Introduction to the Lunch and Learn Series
Planned Lunch and Learn Series
If you would like additional sessions or other topics in upcoming sessions,
please reach out to Jen Braly
9
EPMO Lunch and Learn: Session 1
Program Management Team’s Health Dashboards
10
1. Problem Statement and Goals
2. Portfolio Dashboards
• Introduction [Instructions, Key]
• Summary Charts [Executive Summary, Client Forecast]
• Database Views
3. Live Demo
4. Questions
Overview
Backup slides: Links and Preview of Program Scorecards
11
1. Limited visibility into health
and progress
2. Limited visibility into pipeline for
Client Implementation
3. Outdated or inconsistent display
of project information
4. Difficult to customize health
reports to each stakeholder’s
needs
5. Difficult to find information about
your project quickly
Problem Statement and Goals
PROBLEM STATEMENT GOALS
1. Provide visibility into health and
progress by centralizing information
in one location, online
2. Provide visibility into pipeline to
increase awareness of scheduled
go-lives [Forecast]
3. Establish reporting cadence
[weekly] to ensure current
information is available
4. Create custom views for major
stakeholders types
5. Make database searchable like
“google” so you can find info quickly
Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
12
1. Limited visibility into health
and progress
2. Limited visibility into pipeline for
Client Implementation
3. Outdated or inconsistent display
of project information
4. Difficult to customize health
reports to each stakeholder’s
needs
5. Difficult to find information about
your project quickly
Problem Statement and Goals
PROBLEM STATEMENT GOALS
1. Provide visibility into health and
progress by centralizing information
in one location, online
2. Provide visibility into pipeline to
increase awareness of scheduled
go-lives [Forecast]
3. Establish reporting cadence
[weekly] to ensure current
information is available
4. Create custom views for major
stakeholders types
5. Make database searchable like
“google” so you can find info quickly
Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
13
1. Limited visibility into health
and progress
2. Limited visibility into pipeline for
Client Implementation
3. Outdated or inconsistent display
of project information
4. Difficult to customize health
reports to each stakeholder’s
needs
5. Difficult to find information about
your project quickly
Mission
Problem Statement and Goals
PROBLEM STATEMENT GOALS
1. Provide visibility into health and
progress by centralizing information
in one location, online
2. Provide visibility into pipeline to
increase awareness of scheduled
go-lives [Forecast]
3. Establish reporting cadence
[weekly] to ensure current
information is available
4. Create custom views for major
stakeholders types
5. Make database searchable like
“google” so you can find info quickly
Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
14
Portfolio Dashboard
Introduction
Tab Name Tab Focus Target Audience Purpose
Executive
Summary
Health, Status, and
Workload
Executive
Leadership
To provide a Crayon view of the overall portfolio of programs' Health and
Status, and to see a snapshot of client launches, and project's health that are
"at risk" or "critical".
Forecast Planned Go-Lives
Executive
Leadership,
Sales / Client
Services
To provide a high-level forecast of the client launches for <3 months, then 3-6
months from current month.
Health View Health
Senior
Leadership
To provide a High-Level view of the overall portfolio of programs' Health,
filtered by health, to be able to quickly determine those which specific
constraints that are at risk [Scope, Benefits, Resources, Budget, Schedule].
PgM View Workload by PgM
Functional
Leadership
To provide a Team view of your specific program's Health, filtered by the
Program Manager and by phase, to determine if the program is on track or if
it has concerns.
Client View
New Client
Implementations
Client Services
and IT
To provide a Client view of your specific program's Health, filtered by the
program phase, then program type, to determine if the program is on track or
if it has concerns.
Product View
Product Programs
managed by EPMO
Product Team,
Marketing, and
IT
To provide a Product view of your specific program's Health, filtered by the
program phase, then program name, to determine if the program is on track
or if it has concerns.
Full Database
All Active
Programs
EPMO
To provide a the most detailed Team view of the entire portfolio of program,
without any filters, see the same as above, adding Program Manager priority
and expected effort required to see how the work is being sequenced. Data
can be searched, sorted, and filtered to meet specific needs
Completed
View
All Completed
Programs
Executive
Leadership,
EPMO
To provide list of Closed programs, without any filters, to highlight completed
work.
15
Portfolio Dashboard
Key
Category Question Answered via Key Key for Category Description of Key
Type
What type of Program is
this?
Planned
Finish
When is this Program
expected to Launch or be
complete?
Overall
Health
How is this Program Doing,
Overall?
Constraints
Health
What part of my program is
at risk?
[Overall Health is affected if two
or more constraints' health's are
un healthy]
Status
Is this Program Being
Worked on now?
Phase
If not Launched, How far
along is this Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching unrecoverable threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio; no plan to work on again
Client [Auto, Insurance, Other]
Product
Process Improvement
New Implementations, Existing Client Proj, Large Changes
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
[G3] Change
[G0] Pre-Proposal
[G1] Initiation
[G2] Planning
Execution
Launched
Change to Original Scope; may be a small project or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live complete; if active, closeout activity underway
16
Program Management Health Reporting
Health Standards
** Overall Health is affected if two or more constraints' health's are unhealthy, or if any constraint significantly
impacts the program’s ability to succeed.
17
Rating Overall Health Benefits Scope Resources Budget Schedule
Healthy
Under Control,
No Significant
Concerns
>95% KPI
Adherence,
On track to Full
Realization
>95% of Scope
adherence,
No Changes
Needs
Identified,
Approved, and
Available
On Track,
Spend 0-1%
Variance from
approved Plan
On track:
Critical Path on
track, <5%
Variance from
Plan
Early
Warning
Minor Concerns,
Recoverable
Impact
80-94% KPI
adherence,
Minor
Concerns for
Full Realization
Minor
Changes,
Sponsor
approval
required
Needs
Identified,
Approved, only
key resources
Available
Minor
Concerns,
Spend 2-5%
Variance from
approved Plan
Critical Path:
Minor
Concerns, 6-9%
Variance from
Plan
At Risk
Major Concerns,
Approaching
Unrecoverable
Threshold
60-79% KPI
adherence,
Full Realization
very unlikely
Major
Changes,
Gate 3
recommended
Needs
Identified,
Approved, key
resource(s) not
Available
Major
Concerns,
Spend 6-10%
Variance from
approved Plan
Critical Path:
Major
Concerns, 10-
19% Variance
from Plan
Critical
Out of control,
Unrecoverable
Impact
<60% KPI
adherence,
Full Realization
impossible
Out of Control,
Gate 3
Required
Needs not yet
Identified,
Approved, or
Available
Out of Control,
Spend > 10%
Variance from
approved Plan
Critical Path:
Unrecoverable,
>20% Variance
from Plan
Program Management Health Reporting
Health Standards
** Overall Health is affected if two or more constraints' health's are unhealthy, or if any constraint significantly
impacts the program’s ability to succeed.
18
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
19
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
20
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
21
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
22
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
23
Category Question Answered via Key Key for Category Description of Key
Type What type of Program is this?
Planned
Finish
When is this Program expected to
Launch or be complete?
Overall
Health
How is this Program Doing, Overall?
Constraints
Health
What part of my program is at risk?
[Overall Health is affected if two or
more constraints' health's are un
healthy]
Status Is this Program Being Worked on now?
Phase
If not Launched, How far along is this
Program?
Healthy
Early Warning
At Risk
Critical
Under control, no significant concerns
Under control, recoverable impact
Problems approaching critical threshold
Out of control, unrecoverable impact
Scope
Benefits
Resources
Budget
Schedule
Indicates the volatility of locking requirements down
Indicates likelihood of getting expected value at then end
Indicates if the team has the people they need to succeed
Indicates if the team is managing their budget to plan
Indicates the likelihood of adhering to planned finish
Change [G3]
Pre-Proposal [G0]
Initiation [G1]
Planning [G2]
Execution
Lanched
Change to Original Scope; may be a smallproject or Large CR
Phase 0 - Pre-Gate 0
Phase 1 - Post Gate 0, Pre-Gate 1
Phase 2 - Post Gate 1, Pre-Gate 2
Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure]
Go-Live Date has occurred; if still active, final closeout activity has begun
Client
Product
Proc. Improvm’t
New Client Implementations, Existing Client Proj's, Large Change Requests
New or Existing Product Programs
Internal to EPMO, or non -Client or Product
[DATE]
[DATE]
[DATE]
[DATE]
Finish within 31 - 60 days of Planned Finish Date
Finish > 61 days of Planned Finish Date or TBD
Finish within 1-30 days of Planned Finish Date
Finish Missed - Overdue
On Hold
Pipeline – In Queue
Active
Closed
Cancelled
Not planned to be worked on – not resourced
Planned to be worked on – not resourced
Actively being worked on – resourced
Completed – no longer resourced
Cancelled – Removed from portfolio of work; no plan to work on again
Portfolio Dashboard
Key
24
Executive Summary
Tab Name Tab Focus Target Audience Purpose
Executive
Summary
Health, Status,
and Workload
Executive
Leadership
To provide a Crayon view of the overall portfolio of
programs' Health and Status, and to see a snapshot of client
launches, and project's health that are "at risk" or "critical".
25
26
27
28
29
30
31
32
Program Forecast
Tab Name Tab Focus Target Audience Purpose
Forecast Planned Go-Lives
Executive Leadership,
Sales / Client Services
To provide a high-level forecast of the client
launches for <3 months, then 3-6 months
from current month.
33
Tab Name Tab Focus Target Audience Purpose
Health View Health
Senior
Leadership
To provide a High-Level view of the overall portfolio of programs'
Health, filtered by from most critical to healthy, to be able to
quickly determine those which are in trouble.
Health View
Header will appear when you scroll down, like “freeze” line in excel
34
Tab Name Tab Focus Target Audience Purpose
PgM View
Workload by
PgM
Individuals working
directly on specific
program
To provide a view of your specific program's Health, filtered
by the Program Manager, then by program Phase, to
determine if the program is on track or if it has concerns.
Program Manager View
35
Tab Name Tab Focus Target Audience Purpose
Client View
New Client
Implementations
Client Services and
IT
To provide a Client view of your specific program's Health,
filtered by the program phase, then program type, to
determine if the program is on track or if it has concerns.
Client View
36
Tab Name Tab Focus Target Audience Purpose
Product View
Product Programs
managed by EPMO
Product Team,
Marketing, and IT
To provide a Product view of your specific program's Health,
filtered by the program phase, then program name, to
determine if the program is on track or if it has concerns.
Product View
37
Tab Name Tab Focus Target Audience Purpose
Full
Database
All Active
Programs
Individuals
working directly
on specific
program
To provide a the most detailed Team view of the entire portfolio of
program, without any filters, see the same as above, adding Program
Manager priority and expected effort required to see how the work is
being sequenced. Data can be searched, sorted, and filtered to meet
specific needs
Full Database View
38
Tab Name Tab Focus Target Audience Purpose
Completed Program Senior Leadership, EPMO
To provide a more detailed Team view of Closed
programs, without any filters, to highlight
completed work.
Completed View
39
1. Problem Statement and Goals
2. Portfolio Dashboards
• Introduction [Instructions, Key]
• Summary Charts [Executive Summary, Client Forecast]
• Database Views
3. Live Demo – EPMO Portfolio Dashboards
4. Questions
Overview
Backup slides: Individual Program Scorecards – Preview
40
Portfolio Dashboard
Links
• Executive Summary
• Forecast
• Health View
• PgM View
• Client View
• Product View
• Full Database
• Completed
41
Preview
Program Scorecards
42
[Mitigation]
• [List Accomplishments]
• X
• X
• X
RISKS AND ISSUES
LOOK BACK LOOK AHEAD
[Justification]
HEALTHHealthy
1. [Mitigation]1. [Risk]
2. [Mitigation]2. [Risk]
3. [Mitigation]3. [Risk]
• [List Next Steps]
• X
• X
• X
Scorecard
Project: [Name] Sponsor: [Name]
P
I
P
I
P
I
Initiate Planning Execution Transition Closeout
Date Date Date Date Date
43
EPMO PROGRAM SCORECARD Priority
Program Category
Discussion
RISKS & ISSUES
8/12/201516:42
[Program Name]
LowPriority
Product - New
Owner
[Name]
[Name]
[Name]
[Name]
[Name]
[Name]
X
X
X
X
X
X
Early Warning
Current Rating
SCHEDULE & MILESTONES
Topic
X
X
X
X
X
X
Critical
N/A
Remove [X] by [date]
Increase [X] by [X% or #]
Reduce [X] by [X% or #]
Remove [X] by [X% or #]
Remove [X] by [X% or #]
Benefits Mitigation
Mitigation
Mitigation
Mitigation
Mitigation
Mitigation
HEALTH & BENEFITS
[x% or#]
[x% or#]
[x% or#]
[x% or#]
[x% or#]
[X % or #]
[X % or #]
[X % or #]
[X % or #]
[X % or #]
[date]
[date]
[date]
[date]
[date]
Prob Imp Score Risk Mitigation
[Name] 5 5
25%ProjectRisk Quality
Business Risk Safety
Area of Concern Health Mitigation
[comments about how to improve the health,includingscope changes,crashingschedule,addingfunding,mitigating
risks,andreassessingplannedbenefits]
Top Risk / Issue - #2 Owner Prob Imp Score Risk Mitigation
Score Risk MitigationProb Imp
85
Schedule
Legal / Compliance
ProjectRisk
Business Risk
Top Risk / Issue - #1
[Name]
Owner
40%
[Name] 1 8
8%ProjectRisk Resources
Business Risk Environ. Condition
Top Risk / Issue - #3 Owner
Current Rating DueCurrentTargetBenefits and KPIs
Healthy
Early Warning
At Risk
4
5
6
7
Project 1 or Phase
Project 1 or Phase
Project 1 or Phase
Project 1 or Phase
Project 1 or Phase
Project 1 or Phase
2
PM [Name] Sponsor [Name]
[Date]Early Warning
0
100
[deliverables for Milestone}
[deliverables for Milestone}
Major Milestone or Required Task Major Deliverables
[deliverables for Milestone}
[deliverables for Milestone}
[deliverables for Milestone}
[deliverables for Milestone}
[deliverables for Milestone}
[deliverables for Milestone}
[Key Milestone]
[Key Milestone]
[Key Milestone]
[Key Milestone]
[Key Milestone]
[Key Milestone]
[Key Milestone]
[Key Milestone]
10
11
Project 1 or Phase
Project 1 or Phase
[Date] [Date]At Risk
[Date] [Date]Early Warning
0
25
[deliverables for Milestone}
[deliverables for Milestone}
[Key Milestone]
[Key Milestone]
8
9
Project 1 or Phase
Project 1 or Phase
[Date] [Date]At Risk
[Date]
[Key Milestone]
[Date] [Date]At Risk
[Date] [Date]At Risk
25
90
[Date] [Date]Critical
[Date] [Date]N/A
60
0[deliverables for Milestone}
Open Items
4
[Date]Early Warning 10
%
Complete
Progress
Key Milestones and Deliverables
Progress
%
Complete
Finish
Planned Proj / Act
At Risk 34% [date] [date]
[General updates about Schedule]
Project 1 or Phase1
Comments
[comments about benefits healthoverall]
X [date]
4
1
5
6
PROGRESS UPDATES
5 X [date]
2
3
6 X [date]
2
Completed
1 X [date]
2 X [date]
X [date]
Look Ahead - Key Planned Activities Planned
3
Healthy
0
30
Project or Phase
Finish
Planned Proj / Act
[Date]
X [date]
Schedule Summary
4 X [date]
5 X [date]
3
X [date]
3
1 X [date]
Look Back - Key Accomplishments
[Date] [Date]Critical 65[deliverables for Milestone}[Key Milestone]12 Project 1 or Phase
6 X [date]
[Date] [Date]Early Warning
[Date] [Date]
Overall Health
Early Warning
Early Warning
Early Warning
Early Warning
Early Warning
Scope
Benefit
Resources
Budget
Schedule
[Indicate why youturnedthe overall healththe current rating]
Program Scorecards
Risk
Health
Progress
Roll-up: Scorecard health and mitigation would
be used as input to portfolio health dashboards
Highest Risks or issue for the week
Shows Progress and Open items in one place
Schedule Shows Milestone updates in one place
Objective: Consolidate weekly status updates to
stakeholders into repeatable and standardized format
44
Overall Health and Risks
Project: [Name] Sponsor: [Name]
[Select] [Select] [Name]
Project Risk
Business Risk
[Select] [Select] [Name]
Project Risk
Business Risk
[Select] [Select] [Name]
Project Risk
Business Risk
1 Situation [If this Occurs...]
2 Situation [If this Occurs...]
3 Situation [If this Occurs...]
Resources
Scope
KPI or Benefit
[how to improve schedule health including crashing schedule by adding resources, or removing scope]
[how to improve the budget health, including reassessing planned budget, adding funding]
[how to improve the resources health]
[how to improve the Scope health including reducing scope, clarifying scope]
[how to improve the benefit or KPI health, including reassessing planned benefits/KPIs]
Risk Mitigation [...Plan to reduce impact]Impact [...This will happen] = Risk/Issue
Impact [...This will happen] = Risk/Issue Risk Mitigation [...Plan to reduce impact]
Impact [...This will happen] = Risk/Issue Risk Mitigation [...Plan to reduce impact]
#VALUE![Select Category]
[Select Category]
OwnerProb Imp Score
#VALUE![Select Category]
[Select Category]
OwnerProb Imp Score
#VALUE![Select Category]
[Select Category]
TOP RISKS & ISSUES
OwnerProb Imp Score
[Select Health]
OVERALL HEALTH
Health Justification
Current Rating Area of Concern
[Impacting Overall Health]
Health Mitigation
[Select Health]
[Indicate why you turned the overall health the current rating] [Select Health]
[Select Health]
[Select Health]
[Select Health]
Schedule
Budget
KPI, Graphs, etc
45
1 1
2 2
3 3
4 4
5 5
Comments or Details
[date]
[date]
[date]
[date]
Accomplishments [Look Back]
X
X
X
X
X
Next Steps [Look Ahead]Completed
[date]
[date]
[date]
[date]
[date]
Planned
8
9
10
6
7
4
5
2
3
Actual
1
SCHEDULE
Progress
%
Complete
Finish Dates
Major Deliverables or Outcome Dependencies or CommentsPlannedMajor Phase, Milestone, or Task
[date]
4 X X [Name]
5 X X [Name]
2 X X [Name]
3 X X [Name]
Open Items [Parking Lot]
Topic or Decision Needed Owner
1 X X [Name]
PROGRESS UPDATES
Schedule and Progress
Project: [Name] Sponsor: [Name]
Initiate Planning Execution Transition Closeout
Date Date Date Date Date
Roadmap

More Related Content

What's hot

Erp-PMO
Erp-PMOErp-PMO
Erp-PMO
Sunayan Pal
 
Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508
Maria Cristina Co, MBA
 
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
Wellingtone
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
Ruffin Veal and Associates, Inc.
 
The IT PMO - A Handbook for Federal Programs
The IT PMO - A Handbook for Federal ProgramsThe IT PMO - A Handbook for Federal Programs
The IT PMO - A Handbook for Federal Programs
Vergys
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
An IT Governance program
An IT Governance programAn IT Governance program
An IT Governance program
John Goodpasture
 
ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiAli Kaabi
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
Flevy.com Best Practices
 
Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises
Ghayas Mansoor
 
Corporate Governance to Project Governance
Corporate Governance to Project GovernanceCorporate Governance to Project Governance
Corporate Governance to Project Governance
Richard_01
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plan
tigcap
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
Josh Folgado
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
Daniel Brody
 
PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2
Abdullah Ahmed, PMP, RMP
 
Project Management Office PMO portfolio
Project Management Office PMO portfolioProject Management Office PMO portfolio
Project Management Office PMO portfolio
Sylvain Gauthier
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elementsharoldtaylor1113
 

What's hot (20)

Erp-PMO
Erp-PMOErp-PMO
Erp-PMO
 
Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508Exec summ pmo_design_v1bwalttags_508
Exec summ pmo_design_v1bwalttags_508
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
Agile for PPM Professionals Training Course - Wellingtone | FuturePMO 2021
 
Program Management
Program ManagementProgram Management
Program Management
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
 
The IT PMO - A Handbook for Federal Programs
The IT PMO - A Handbook for Federal ProgramsThe IT PMO - A Handbook for Federal Programs
The IT PMO - A Handbook for Federal Programs
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
 
An IT Governance program
An IT Governance programAn IT Governance program
An IT Governance program
 
ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali Kaabi
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 
Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises
 
Corporate Governance to Project Governance
Corporate Governance to Project GovernanceCorporate Governance to Project Governance
Corporate Governance to Project Governance
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plan
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Pmo final 1
Pmo final 1Pmo final 1
Pmo final 1
 
PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2
 
Project Management Office PMO portfolio
Project Management Office PMO portfolioProject Management Office PMO portfolio
Project Management Office PMO portfolio
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
 

Viewers also liked

Program Workkit - Planning Documents_v1
Program Workkit - Planning Documents_v1Program Workkit - Planning Documents_v1
Program Workkit - Planning Documents_v1Jen Braly, PgMP, PMP
 
Program Workkit - Risk and Issue Register
Program Workkit - Risk and Issue RegisterProgram Workkit - Risk and Issue Register
Program Workkit - Risk and Issue RegisterJen Braly, PgMP, PMP
 
G0_Project_PMO Phase Gate Template_CLEAN
G0_Project_PMO Phase Gate Template_CLEANG0_Project_PMO Phase Gate Template_CLEAN
G0_Project_PMO Phase Gate Template_CLEANJen Braly, PgMP, PMP
 
G2_Program Phase Gate Template_CLEAN
G2_Program Phase Gate Template_CLEANG2_Program Phase Gate Template_CLEAN
G2_Program Phase Gate Template_CLEANJen Braly, PgMP, PMP
 
Jeff Jvancich Resume 2016
Jeff Jvancich Resume 2016Jeff Jvancich Resume 2016
Jeff Jvancich Resume 2016Jeff Jvancich
 
Project management _ cheat sheet _no1
Project management _ cheat sheet _no1Project management _ cheat sheet _no1
Project management _ cheat sheet _no1
Stephanus Roux C Eng , IntPE(uk) , FIET
 
Project Risk assesment matrix
Project Risk assesment matrixProject Risk assesment matrix
Project Risk assesment matrixKashif Mastan
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
Glen Alleman
 
Program Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd EditionProgram Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd Edition
Ricardo Viana Vargas
 
Program Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified VersionProgram Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified Version
Ricardo Viana Vargas
 
Project governance
Project governanceProject governance
Project governance
Glen Alleman
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
Mark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
TURKI , PMP
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
Ricardo Viana Vargas
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Ricardo Viana Vargas
 
Mapa procesos pmbok 5
Mapa procesos pmbok 5Mapa procesos pmbok 5
Mapa procesos pmbok 5Pedro Arcas
 

Viewers also liked (20)

Program Health Scorecard_v1
Program Health Scorecard_v1Program Health Scorecard_v1
Program Health Scorecard_v1
 
PgMP_Brain Dump
PgMP_Brain DumpPgMP_Brain Dump
PgMP_Brain Dump
 
Program Workkit - Planning Documents_v1
Program Workkit - Planning Documents_v1Program Workkit - Planning Documents_v1
Program Workkit - Planning Documents_v1
 
PMO_OneRingDB_CLEAN
PMO_OneRingDB_CLEANPMO_OneRingDB_CLEAN
PMO_OneRingDB_CLEAN
 
Program Workkit - Risk and Issue Register
Program Workkit - Risk and Issue RegisterProgram Workkit - Risk and Issue Register
Program Workkit - Risk and Issue Register
 
G0_Project_PMO Phase Gate Template_CLEAN
G0_Project_PMO Phase Gate Template_CLEANG0_Project_PMO Phase Gate Template_CLEAN
G0_Project_PMO Phase Gate Template_CLEAN
 
G2_Program Phase Gate Template_CLEAN
G2_Program Phase Gate Template_CLEANG2_Program Phase Gate Template_CLEAN
G2_Program Phase Gate Template_CLEAN
 
Jeff Jvancich Resume 2016
Jeff Jvancich Resume 2016Jeff Jvancich Resume 2016
Jeff Jvancich Resume 2016
 
Project management _ cheat sheet _no1
Project management _ cheat sheet _no1Project management _ cheat sheet _no1
Project management _ cheat sheet _no1
 
Project Risk assesment matrix
Project Risk assesment matrixProject Risk assesment matrix
Project Risk assesment matrix
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Pivots and Slicers_v5
Pivots and Slicers_v5Pivots and Slicers_v5
Pivots and Slicers_v5
 
Program Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd EditionProgram Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd Edition
 
Program Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified VersionProgram Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified Version
 
Project governance
Project governanceProject governance
Project governance
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
 
Mapa procesos pmbok 5
Mapa procesos pmbok 5Mapa procesos pmbok 5
Mapa procesos pmbok 5
 

Similar to Program Dashboards and Scorecards_CLEAN

sample5.pptx
sample5.pptxsample5.pptx
sample5.pptx
JasmineMichael1
 
NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017
CHC Connecticut
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
Erin Jones
 
The key to improving shared services capacity
The key to improving shared services capacityThe key to improving shared services capacity
The key to improving shared services capacity
Promapp Solutions
 
Unit IV_Monitoring_and_Evaluation.pptx
Unit IV_Monitoring_and_Evaluation.pptxUnit IV_Monitoring_and_Evaluation.pptx
Unit IV_Monitoring_and_Evaluation.pptx
MusondaMofu2
 
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
Wellingtone
 
Establishing an effective EPMO
Establishing an effective EPMOEstablishing an effective EPMO
Establishing an effective EPMO
Wael Genina, MBA, PMP
 
Common Assessment Framework
Common Assessment FrameworkCommon Assessment Framework
Common Assessment Framework
Seta Wicaksana
 
INTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
INTRODUCTION TO PROGRAMME DEVELOPMENT..pptINTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
INTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
modestuseveline
 
Measuring_HR_ROI-1.pdf
Measuring_HR_ROI-1.pdfMeasuring_HR_ROI-1.pdf
Measuring_HR_ROI-1.pdf
HarmanSingh510326
 
CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1Sherrill Moore
 
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptxSession Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
yuduf1
 
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
Mark Hocknell
 
Programme Evaluation
Programme EvaluationProgramme Evaluation
Programme Evaluation
zalinah69
 
Scottish comms network paul njoku - 14 and 15 may 2014
Scottish comms network   paul njoku - 14 and 15 may 2014Scottish comms network   paul njoku - 14 and 15 may 2014
Scottish comms network paul njoku - 14 and 15 may 2014
Jane Robson
 
2014 Process Management Strategic Overview
2014 Process Management Strategic Overview2014 Process Management Strategic Overview
2014 Process Management Strategic Overview
Riz Hasan
 
SAFe v4.6 full
SAFe v4.6 fullSAFe v4.6 full
SAFe v4.6 full
Alberto Gonzalez
 
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
Becky Lopanec
 

Similar to Program Dashboards and Scorecards_CLEAN (20)

sample5.pptx
sample5.pptxsample5.pptx
sample5.pptx
 
NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
 
The key to improving shared services capacity
The key to improving shared services capacityThe key to improving shared services capacity
The key to improving shared services capacity
 
Unit IV_Monitoring_and_Evaluation.pptx
Unit IV_Monitoring_and_Evaluation.pptxUnit IV_Monitoring_and_Evaluation.pptx
Unit IV_Monitoring_and_Evaluation.pptx
 
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
The Institute of Cancer Research - Our PMO Journey - FuturePMO 2018
 
Establishing an effective EPMO
Establishing an effective EPMOEstablishing an effective EPMO
Establishing an effective EPMO
 
Common Assessment Framework
Common Assessment FrameworkCommon Assessment Framework
Common Assessment Framework
 
INTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
INTRODUCTION TO PROGRAMME DEVELOPMENT..pptINTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
INTRODUCTION TO PROGRAMME DEVELOPMENT..ppt
 
Measuring_HR_ROI-1.pdf
Measuring_HR_ROI-1.pdfMeasuring_HR_ROI-1.pdf
Measuring_HR_ROI-1.pdf
 
CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1
 
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptxSession Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
 
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
Establishing measurable performance expectations Feb 2019 Criterion Conferenc...
 
Programme Evaluation
Programme EvaluationProgramme Evaluation
Programme Evaluation
 
Scottish comms network paul njoku - 14 and 15 may 2014
Scottish comms network   paul njoku - 14 and 15 may 2014Scottish comms network   paul njoku - 14 and 15 may 2014
Scottish comms network paul njoku - 14 and 15 may 2014
 
Lean_Sigma_Awareness
Lean_Sigma_AwarenessLean_Sigma_Awareness
Lean_Sigma_Awareness
 
Derek Brown CV
Derek Brown CVDerek Brown CV
Derek Brown CV
 
2014 Process Management Strategic Overview
2014 Process Management Strategic Overview2014 Process Management Strategic Overview
2014 Process Management Strategic Overview
 
SAFe v4.6 full
SAFe v4.6 fullSAFe v4.6 full
SAFe v4.6 full
 
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
Sustainability Techniques - Faculty Development Model - Competency-Based Educ...
 

Program Dashboards and Scorecards_CLEAN

  • 1. 1 Jen Braly, Director, EPMO’s Program Management Team Date: 15 Sep 15 Lunch and Learn Getting to know the EPMO Presenter:
  • 2. 2 • Introduction to the EPMO - Mission - EPMO Maturity: Yesterday, Today and Tomorrow • Introduction to the Lunch and Learn series • Portfolio Dashboards Session Lunch and Learn Agenda
  • 3. 3 Agero EPMO Mission: Through facilitation and collaboration, develop and implement governance standards, processes and accountability measures that enable and assist the enterprise to deliver quality products and services that align with Agero’s strategic initiatives, on time, on budget, and with full transparency. Key Responsibilities: • Portfolio Governance: Responsible for governance standards, accountability measures, conformance, auditing, analysis, reporting, training and communication • Program Management: Providing Program Management resources to support Client Implementations, Product portfolios, and other key programs / projects • Process Improvement: Identifying and addressing areas throughout Agero that require improvement and to affect change through analysis, solutions and implementation Who Are We? - Mission
  • 4. 4 YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND) • Enhanced Steering Committee process to improve prioritization, risk identification and alignment to KI’s • Establishing a Risk Tracker and Risk Council to identify problems early and recommend corrective actions • Enterprise risk tracking and reporting • Established Prioritization Process and tracking mechanism in Planview to align resources to requirements and cost tracking • Tightly manage and understand new work requests through prioritization, steering and change request processes • Implementation of a series of Benefits Tools for use in decision making/prioritization including Earned Value, NPV and ROI calculations • Established the Program Management team and processes to support our clients and products • Creation of a SharePoint Knowledge Center as a single repository of portfolio tools and information • Additional resources to support new product development and pilots • Began weekly distribution of Program Health Dashboards to improve visibility of program status’ • Continue to enhance the client onboarding processes via implementation tools, complexity matrices, and client work kits • Provide corporate tools, templates and processes for use by all areas of the organization EPMO Maturity
  • 5. 5 YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND) • Enhanced Steering Committee process to improve prioritization, risk identification and alignment to KI’s • Establishing a Risk Tracker and Risk Council to identify problems early and recommend corrective actions • Enterprise risk tracking and reporting • Established Prioritization Process and tracking mechanism in Planview to align resources to requirements and cost tracking • Tightly manage and understand new work requests through prioritization, steering and change request processes • Implementation of a series of Benefits Tools for use in decision making/prioritization including Earned Value, NPV and ROI calculations • Established the Program Management team and processes to support our clients and products • Creation of a SharePoint Knowledge Center as a single repository of portfolio tools and information • Additional resources to support new product development and pilots • Began weekly distribution of Program Health Dashboards to improve visibility of program status’ • Continue to enhance the client onboarding processes via implementation tools, complexity matrices, and client work kits • Provide corporate tools, templates and processes for use by all areas of the organization EPMO Maturity
  • 6. 6 YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND) • Enhanced Steering Committee process to improve prioritization, risk identification and alignment to KI’s • Establishing a Risk Tracker and Risk Council to identify problems early and recommend corrective actions • Enterprise risk tracking and reporting • Established Prioritization Process and tracking mechanism in Planview to align resources to requirements and cost tracking • Tightly manage and understand new work requests through prioritization, steering and change request processes • Implementation of a series of Benefits Tools for use in decision making/ prioritization including Earned Value, NPV and ROI calculations • Established the Program Management team and processes to support our clients and products • Creation of a SharePoint Knowledge Center as a single repository of portfolio tools and information • Additional resources to support new product development and pilots • Began weekly distribution of Program Health Dashboards to improve visibility of program status’ • Continue to enhance the client onboarding processes via implementation tools, complexity matrices, and client work kits • Provide corporate tools, templates and processes for use by all areas of the organization EPMO Maturity
  • 7. 7 YESTERDAY (JAN – AUG) TODAY (SEP - DEC) TOMORROW (2016 AND BEYOND) • Enhanced Steering Committee process to improve prioritization, risk identification and alignment to KI’s • Establishing a Risk Tracker and Risk Council to identify problems early and recommend corrective actions • Enterprise risk tracking and reporting • Established Prioritization Process and tracking mechanism in Planview to align resources to requirements and cost tracking • Tightly manage and understand new work requests through prioritization, steering and change request processes • Implementation of a series of Benefits Tools for use in decision making/ prioritization including Earned Value, NPV and ROI calculations • Established the Program Management team and processes to support our clients and products • Creation of a SharePoint Knowledge Center as a single repository of portfolio tools and information • Additional resources to support new product development and pilots • Began weekly distribution of Program Health Dashboards to improve visibility of program status’ • Continue to enhance the client onboarding processes via implementation tools, complexity matrices, and client work kits • Provide corporate tools, templates and processes for use by all areas of the organization EPMO Maturity
  • 8. 8 x1. Today – Portfolio Dashboards 2. November - EPMO Governance 3. New Client Implementation Process 4. Risk Management Process and the New Risk Council Introduction to the Lunch and Learn Series Planned Lunch and Learn Series If you would like additional sessions or other topics in upcoming sessions, please reach out to Jen Braly
  • 9. 9 EPMO Lunch and Learn: Session 1 Program Management Team’s Health Dashboards
  • 10. 10 1. Problem Statement and Goals 2. Portfolio Dashboards • Introduction [Instructions, Key] • Summary Charts [Executive Summary, Client Forecast] • Database Views 3. Live Demo 4. Questions Overview Backup slides: Links and Preview of Program Scorecards
  • 11. 11 1. Limited visibility into health and progress 2. Limited visibility into pipeline for Client Implementation 3. Outdated or inconsistent display of project information 4. Difficult to customize health reports to each stakeholder’s needs 5. Difficult to find information about your project quickly Problem Statement and Goals PROBLEM STATEMENT GOALS 1. Provide visibility into health and progress by centralizing information in one location, online 2. Provide visibility into pipeline to increase awareness of scheduled go-lives [Forecast] 3. Establish reporting cadence [weekly] to ensure current information is available 4. Create custom views for major stakeholders types 5. Make database searchable like “google” so you can find info quickly Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
  • 12. 12 1. Limited visibility into health and progress 2. Limited visibility into pipeline for Client Implementation 3. Outdated or inconsistent display of project information 4. Difficult to customize health reports to each stakeholder’s needs 5. Difficult to find information about your project quickly Problem Statement and Goals PROBLEM STATEMENT GOALS 1. Provide visibility into health and progress by centralizing information in one location, online 2. Provide visibility into pipeline to increase awareness of scheduled go-lives [Forecast] 3. Establish reporting cadence [weekly] to ensure current information is available 4. Create custom views for major stakeholders types 5. Make database searchable like “google” so you can find info quickly Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
  • 13. 13 1. Limited visibility into health and progress 2. Limited visibility into pipeline for Client Implementation 3. Outdated or inconsistent display of project information 4. Difficult to customize health reports to each stakeholder’s needs 5. Difficult to find information about your project quickly Mission Problem Statement and Goals PROBLEM STATEMENT GOALS 1. Provide visibility into health and progress by centralizing information in one location, online 2. Provide visibility into pipeline to increase awareness of scheduled go-lives [Forecast] 3. Establish reporting cadence [weekly] to ensure current information is available 4. Create custom views for major stakeholders types 5. Make database searchable like “google” so you can find info quickly Programs managed by EPMO [Client Implementations, Product Programs, Key Initiatives]:
  • 14. 14 Portfolio Dashboard Introduction Tab Name Tab Focus Target Audience Purpose Executive Summary Health, Status, and Workload Executive Leadership To provide a Crayon view of the overall portfolio of programs' Health and Status, and to see a snapshot of client launches, and project's health that are "at risk" or "critical". Forecast Planned Go-Lives Executive Leadership, Sales / Client Services To provide a high-level forecast of the client launches for <3 months, then 3-6 months from current month. Health View Health Senior Leadership To provide a High-Level view of the overall portfolio of programs' Health, filtered by health, to be able to quickly determine those which specific constraints that are at risk [Scope, Benefits, Resources, Budget, Schedule]. PgM View Workload by PgM Functional Leadership To provide a Team view of your specific program's Health, filtered by the Program Manager and by phase, to determine if the program is on track or if it has concerns. Client View New Client Implementations Client Services and IT To provide a Client view of your specific program's Health, filtered by the program phase, then program type, to determine if the program is on track or if it has concerns. Product View Product Programs managed by EPMO Product Team, Marketing, and IT To provide a Product view of your specific program's Health, filtered by the program phase, then program name, to determine if the program is on track or if it has concerns. Full Database All Active Programs EPMO To provide a the most detailed Team view of the entire portfolio of program, without any filters, see the same as above, adding Program Manager priority and expected effort required to see how the work is being sequenced. Data can be searched, sorted, and filtered to meet specific needs Completed View All Completed Programs Executive Leadership, EPMO To provide list of Closed programs, without any filters, to highlight completed work.
  • 15. 15 Portfolio Dashboard Key Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching unrecoverable threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio; no plan to work on again Client [Auto, Insurance, Other] Product Process Improvement New Implementations, Existing Client Proj, Large Changes New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue [G3] Change [G0] Pre-Proposal [G1] Initiation [G2] Planning Execution Launched Change to Original Scope; may be a small project or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live complete; if active, closeout activity underway
  • 16. 16 Program Management Health Reporting Health Standards ** Overall Health is affected if two or more constraints' health's are unhealthy, or if any constraint significantly impacts the program’s ability to succeed.
  • 17. 17 Rating Overall Health Benefits Scope Resources Budget Schedule Healthy Under Control, No Significant Concerns >95% KPI Adherence, On track to Full Realization >95% of Scope adherence, No Changes Needs Identified, Approved, and Available On Track, Spend 0-1% Variance from approved Plan On track: Critical Path on track, <5% Variance from Plan Early Warning Minor Concerns, Recoverable Impact 80-94% KPI adherence, Minor Concerns for Full Realization Minor Changes, Sponsor approval required Needs Identified, Approved, only key resources Available Minor Concerns, Spend 2-5% Variance from approved Plan Critical Path: Minor Concerns, 6-9% Variance from Plan At Risk Major Concerns, Approaching Unrecoverable Threshold 60-79% KPI adherence, Full Realization very unlikely Major Changes, Gate 3 recommended Needs Identified, Approved, key resource(s) not Available Major Concerns, Spend 6-10% Variance from approved Plan Critical Path: Major Concerns, 10- 19% Variance from Plan Critical Out of control, Unrecoverable Impact <60% KPI adherence, Full Realization impossible Out of Control, Gate 3 Required Needs not yet Identified, Approved, or Available Out of Control, Spend > 10% Variance from approved Plan Critical Path: Unrecoverable, >20% Variance from Plan Program Management Health Reporting Health Standards ** Overall Health is affected if two or more constraints' health's are unhealthy, or if any constraint significantly impacts the program’s ability to succeed.
  • 18. 18 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 19. 19 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 20. 20 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 21. 21 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 22. 22 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 23. 23 Category Question Answered via Key Key for Category Description of Key Type What type of Program is this? Planned Finish When is this Program expected to Launch or be complete? Overall Health How is this Program Doing, Overall? Constraints Health What part of my program is at risk? [Overall Health is affected if two or more constraints' health's are un healthy] Status Is this Program Being Worked on now? Phase If not Launched, How far along is this Program? Healthy Early Warning At Risk Critical Under control, no significant concerns Under control, recoverable impact Problems approaching critical threshold Out of control, unrecoverable impact Scope Benefits Resources Budget Schedule Indicates the volatility of locking requirements down Indicates likelihood of getting expected value at then end Indicates if the team has the people they need to succeed Indicates if the team is managing their budget to plan Indicates the likelihood of adhering to planned finish Change [G3] Pre-Proposal [G0] Initiation [G1] Planning [G2] Execution Lanched Change to Original Scope; may be a smallproject or Large CR Phase 0 - Pre-Gate 0 Phase 1 - Post Gate 0, Pre-Gate 1 Phase 2 - Post Gate 1, Pre-Gate 2 Phase 3 - Post Gate 2, Pre-Gate 3 [change] or 4 [closure] Go-Live Date has occurred; if still active, final closeout activity has begun Client Product Proc. Improvm’t New Client Implementations, Existing Client Proj's, Large Change Requests New or Existing Product Programs Internal to EPMO, or non -Client or Product [DATE] [DATE] [DATE] [DATE] Finish within 31 - 60 days of Planned Finish Date Finish > 61 days of Planned Finish Date or TBD Finish within 1-30 days of Planned Finish Date Finish Missed - Overdue On Hold Pipeline – In Queue Active Closed Cancelled Not planned to be worked on – not resourced Planned to be worked on – not resourced Actively being worked on – resourced Completed – no longer resourced Cancelled – Removed from portfolio of work; no plan to work on again Portfolio Dashboard Key
  • 24. 24 Executive Summary Tab Name Tab Focus Target Audience Purpose Executive Summary Health, Status, and Workload Executive Leadership To provide a Crayon view of the overall portfolio of programs' Health and Status, and to see a snapshot of client launches, and project's health that are "at risk" or "critical".
  • 25. 25
  • 26. 26
  • 27. 27
  • 28. 28
  • 29. 29
  • 30. 30
  • 31. 31
  • 32. 32 Program Forecast Tab Name Tab Focus Target Audience Purpose Forecast Planned Go-Lives Executive Leadership, Sales / Client Services To provide a high-level forecast of the client launches for <3 months, then 3-6 months from current month.
  • 33. 33 Tab Name Tab Focus Target Audience Purpose Health View Health Senior Leadership To provide a High-Level view of the overall portfolio of programs' Health, filtered by from most critical to healthy, to be able to quickly determine those which are in trouble. Health View Header will appear when you scroll down, like “freeze” line in excel
  • 34. 34 Tab Name Tab Focus Target Audience Purpose PgM View Workload by PgM Individuals working directly on specific program To provide a view of your specific program's Health, filtered by the Program Manager, then by program Phase, to determine if the program is on track or if it has concerns. Program Manager View
  • 35. 35 Tab Name Tab Focus Target Audience Purpose Client View New Client Implementations Client Services and IT To provide a Client view of your specific program's Health, filtered by the program phase, then program type, to determine if the program is on track or if it has concerns. Client View
  • 36. 36 Tab Name Tab Focus Target Audience Purpose Product View Product Programs managed by EPMO Product Team, Marketing, and IT To provide a Product view of your specific program's Health, filtered by the program phase, then program name, to determine if the program is on track or if it has concerns. Product View
  • 37. 37 Tab Name Tab Focus Target Audience Purpose Full Database All Active Programs Individuals working directly on specific program To provide a the most detailed Team view of the entire portfolio of program, without any filters, see the same as above, adding Program Manager priority and expected effort required to see how the work is being sequenced. Data can be searched, sorted, and filtered to meet specific needs Full Database View
  • 38. 38 Tab Name Tab Focus Target Audience Purpose Completed Program Senior Leadership, EPMO To provide a more detailed Team view of Closed programs, without any filters, to highlight completed work. Completed View
  • 39. 39 1. Problem Statement and Goals 2. Portfolio Dashboards • Introduction [Instructions, Key] • Summary Charts [Executive Summary, Client Forecast] • Database Views 3. Live Demo – EPMO Portfolio Dashboards 4. Questions Overview Backup slides: Individual Program Scorecards – Preview
  • 40. 40 Portfolio Dashboard Links • Executive Summary • Forecast • Health View • PgM View • Client View • Product View • Full Database • Completed
  • 42. 42 [Mitigation] • [List Accomplishments] • X • X • X RISKS AND ISSUES LOOK BACK LOOK AHEAD [Justification] HEALTHHealthy 1. [Mitigation]1. [Risk] 2. [Mitigation]2. [Risk] 3. [Mitigation]3. [Risk] • [List Next Steps] • X • X • X Scorecard Project: [Name] Sponsor: [Name] P I P I P I Initiate Planning Execution Transition Closeout Date Date Date Date Date
  • 43. 43 EPMO PROGRAM SCORECARD Priority Program Category Discussion RISKS & ISSUES 8/12/201516:42 [Program Name] LowPriority Product - New Owner [Name] [Name] [Name] [Name] [Name] [Name] X X X X X X Early Warning Current Rating SCHEDULE & MILESTONES Topic X X X X X X Critical N/A Remove [X] by [date] Increase [X] by [X% or #] Reduce [X] by [X% or #] Remove [X] by [X% or #] Remove [X] by [X% or #] Benefits Mitigation Mitigation Mitigation Mitigation Mitigation Mitigation HEALTH & BENEFITS [x% or#] [x% or#] [x% or#] [x% or#] [x% or#] [X % or #] [X % or #] [X % or #] [X % or #] [X % or #] [date] [date] [date] [date] [date] Prob Imp Score Risk Mitigation [Name] 5 5 25%ProjectRisk Quality Business Risk Safety Area of Concern Health Mitigation [comments about how to improve the health,includingscope changes,crashingschedule,addingfunding,mitigating risks,andreassessingplannedbenefits] Top Risk / Issue - #2 Owner Prob Imp Score Risk Mitigation Score Risk MitigationProb Imp 85 Schedule Legal / Compliance ProjectRisk Business Risk Top Risk / Issue - #1 [Name] Owner 40% [Name] 1 8 8%ProjectRisk Resources Business Risk Environ. Condition Top Risk / Issue - #3 Owner Current Rating DueCurrentTargetBenefits and KPIs Healthy Early Warning At Risk 4 5 6 7 Project 1 or Phase Project 1 or Phase Project 1 or Phase Project 1 or Phase Project 1 or Phase Project 1 or Phase 2 PM [Name] Sponsor [Name] [Date]Early Warning 0 100 [deliverables for Milestone} [deliverables for Milestone} Major Milestone or Required Task Major Deliverables [deliverables for Milestone} [deliverables for Milestone} [deliverables for Milestone} [deliverables for Milestone} [deliverables for Milestone} [deliverables for Milestone} [Key Milestone] [Key Milestone] [Key Milestone] [Key Milestone] [Key Milestone] [Key Milestone] [Key Milestone] [Key Milestone] 10 11 Project 1 or Phase Project 1 or Phase [Date] [Date]At Risk [Date] [Date]Early Warning 0 25 [deliverables for Milestone} [deliverables for Milestone} [Key Milestone] [Key Milestone] 8 9 Project 1 or Phase Project 1 or Phase [Date] [Date]At Risk [Date] [Key Milestone] [Date] [Date]At Risk [Date] [Date]At Risk 25 90 [Date] [Date]Critical [Date] [Date]N/A 60 0[deliverables for Milestone} Open Items 4 [Date]Early Warning 10 % Complete Progress Key Milestones and Deliverables Progress % Complete Finish Planned Proj / Act At Risk 34% [date] [date] [General updates about Schedule] Project 1 or Phase1 Comments [comments about benefits healthoverall] X [date] 4 1 5 6 PROGRESS UPDATES 5 X [date] 2 3 6 X [date] 2 Completed 1 X [date] 2 X [date] X [date] Look Ahead - Key Planned Activities Planned 3 Healthy 0 30 Project or Phase Finish Planned Proj / Act [Date] X [date] Schedule Summary 4 X [date] 5 X [date] 3 X [date] 3 1 X [date] Look Back - Key Accomplishments [Date] [Date]Critical 65[deliverables for Milestone}[Key Milestone]12 Project 1 or Phase 6 X [date] [Date] [Date]Early Warning [Date] [Date] Overall Health Early Warning Early Warning Early Warning Early Warning Early Warning Scope Benefit Resources Budget Schedule [Indicate why youturnedthe overall healththe current rating] Program Scorecards Risk Health Progress Roll-up: Scorecard health and mitigation would be used as input to portfolio health dashboards Highest Risks or issue for the week Shows Progress and Open items in one place Schedule Shows Milestone updates in one place Objective: Consolidate weekly status updates to stakeholders into repeatable and standardized format
  • 44. 44 Overall Health and Risks Project: [Name] Sponsor: [Name] [Select] [Select] [Name] Project Risk Business Risk [Select] [Select] [Name] Project Risk Business Risk [Select] [Select] [Name] Project Risk Business Risk 1 Situation [If this Occurs...] 2 Situation [If this Occurs...] 3 Situation [If this Occurs...] Resources Scope KPI or Benefit [how to improve schedule health including crashing schedule by adding resources, or removing scope] [how to improve the budget health, including reassessing planned budget, adding funding] [how to improve the resources health] [how to improve the Scope health including reducing scope, clarifying scope] [how to improve the benefit or KPI health, including reassessing planned benefits/KPIs] Risk Mitigation [...Plan to reduce impact]Impact [...This will happen] = Risk/Issue Impact [...This will happen] = Risk/Issue Risk Mitigation [...Plan to reduce impact] Impact [...This will happen] = Risk/Issue Risk Mitigation [...Plan to reduce impact] #VALUE![Select Category] [Select Category] OwnerProb Imp Score #VALUE![Select Category] [Select Category] OwnerProb Imp Score #VALUE![Select Category] [Select Category] TOP RISKS & ISSUES OwnerProb Imp Score [Select Health] OVERALL HEALTH Health Justification Current Rating Area of Concern [Impacting Overall Health] Health Mitigation [Select Health] [Indicate why you turned the overall health the current rating] [Select Health] [Select Health] [Select Health] [Select Health] Schedule Budget KPI, Graphs, etc
  • 45. 45 1 1 2 2 3 3 4 4 5 5 Comments or Details [date] [date] [date] [date] Accomplishments [Look Back] X X X X X Next Steps [Look Ahead]Completed [date] [date] [date] [date] [date] Planned 8 9 10 6 7 4 5 2 3 Actual 1 SCHEDULE Progress % Complete Finish Dates Major Deliverables or Outcome Dependencies or CommentsPlannedMajor Phase, Milestone, or Task [date] 4 X X [Name] 5 X X [Name] 2 X X [Name] 3 X X [Name] Open Items [Parking Lot] Topic or Decision Needed Owner 1 X X [Name] PROGRESS UPDATES Schedule and Progress Project: [Name] Sponsor: [Name] Initiate Planning Execution Transition Closeout Date Date Date Date Date Roadmap