2. ● Project Charter
● Stakeholders
● Project Management Plan & Process
● Work Breakdown Structure
● Project schedule/Gantt chart
● Quality Check
● Post Project Review
INDEX
4. POSITION INTERESTS INTERNAL/
EXTERNAL
Government
Taxation, VAT, Legislation, employment, truthful reporting, diversity,
legalities, externalities.
External
Employees Rates of pay, job security, compensation, respect, truthful communication. Internal
Customers Value, quality, customer care, ethical products. External
Suppliers
Providers of products and services used in the end product for the
customer, equitable business opportunities.
External
Creditors Credit score, new contracts, liquidity. External
Community
Jobs, involvement, environmental protection, shares, truthful
communication.
External
Trade Unions Quality, worker protection, jobs. Internal
Owners
Profitability, longevity, market share, market standing, succession planning,
raising capital, growth, social goals.
Internal
Investors Return on investment, income. External
STAKEHOLDERS
5. Project Management Plan
Production Management Plan
Budgets & Schedules
Work Orders and Time Charging
Material Control & Work Order
Pallets
Technical Packages for Production
Tests & Quality Assurance
Contract Management Plan
Project Management Team
Change Order Management
Progress Milestones & Payment
Management
6. Project Management Process
•
• Management of Persons Involved
• Management of EnquiriesEnquiry Stage
• Database of Past Work
• Material & Supply Estimates
• Vendor Database
• Estimates of Quotes
Bidding Stage
• Planning | Coordination | Execution | Monitoring
• Avoiding Conflict of Process & Department
Execution Stage
• Regulatory Approvals
• Test & Trials
• Delivery
• Invoicing
Delivery Stage
• Follow Up
• Feedback
• Documentation of Future Project
Post Delivery
13. QUALITY CHECK
● Welding
● Cutting
● Electricity
● Wood works
● Plumbing
● Piping
● Auxiliary machinery
● Mooring Gear
● Safety Gear
● Accomodation
● Feeding System
● Fire systems
● Control system
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
14. Post Project Review
1. Performance review of every individual onboard for project.
2. Site Supervision & Reporting.
logistic Supply.
Proper surface preparation and coating application.
Safety and long-term maintenance.
3. Commissioning, Dock & Sea Trial Assistance
Monitoring.
Commissioning of machinery and system.
Equipment compliance as contracted.
4. Guarantee Claim Handling, Minimum vessel downtime
5. Equipment package review.
Serviceability.
Product suitability for intended type.
Load testing of all equipment.
6. Technical Specification Review.
Rulebook with all suppliers & makers list , with specification in central database.
7. Retrospection
15. TEAM
ABHINEK KUMAR
ABHISHEK SINGH
ARJUN REGHU
DHAIRYA SOLANKI
SRISHTI SINGH
TUSHAR BHAJIPALE
VED PRAKASH PAL
20191001
20191002
20191005
20191054
20191056
20191061
20191064