SlideShare a Scribd company logo
1 of 23
1
Geotechnical Engineering–I [CE-221]
BSc Civil Engineering – 4th Semester
by
Dr. Muhammad Irfan
Assistant Professor
Civil Engg. Dept. – UET Lahore
Email: mirfan1@msn.com
Lecture Handouts: https://groups.google.com/d/forum/2016session-geotech-i
Lecture # 26
24-Apr-2018
2
Equivalent Hydraulic Conductivity of Stratified Soils
Total flow
Permeability Parallel to Stratification
 Velocity of flow ‘v’
 Hydraulic gradient ‘i’
nHn
HHHH
Hik
HikHikHikHik



332211
nHn
HHH
Hik
HikHikHikq



332211
H
HkHkHkHk
k nHnHHH
H


332211
→ sum of flows though each layer
→ same for each layer
→ different for all layers
Hikq H 
Taking third dimension (i.e. into the plane of paper) as unity
Avq  )1( Hvq 
3
Permeability Perpendicular to Stratification
 Velocity of flow ‘v’ and discharge ‘q’
 Hydraulic gradient ‘i’ and head loss ‘h’
nhhhhh  321
ikv v 
H
h
i 
Vn
n
VVVV k
Hv
k
Hv
k
Hv
k
Hv
k
Hv 









3
3
2
2
1
1
)1(332211  nn HiHiHiHih 
Also,
1
1
vk
v
i 
2
2
vk
v
i 
3
3
vk
v
i 
Replacing in eq. (1)
Vn
n
VVV
V
k
H
k
H
k
H
k
H
H
k



3
3
2
2
1
1
kv = average permeability perpendicular to
stratification
→ same through each layer
→ different through each layer
Equivalent Hydraulic Conductivity of Stratified Soils
4
Practice Problem #4
On close investigation of a sample it was found to
be in three layers 20mm, 60mm, and 40mm. The
permeability of these layers are 3x10-3mm/sec,
5x10-4mm/sec, and 17x10-4mm/sec respectively.
Find kH and kV, and the ratio kH/kV.
H
HkHkHkHk
k nHnHHH
H


332211
Vn
n
VVV
V
k
H
k
H
k
H
k
H
H
k



3
3
2
2
1
1
5
Practice Problem #5
H
HkHkHkHk
k nHnHHH
H


332211
Vn
n
VVV
V
k
H
k
H
k
H
k
H
H
k



3
3
2
2
1
1
6
Practice Problem #5
7
Practice Problem #6
8
Practice Problem #6
9
SIGNIFICANCE OF SEEPAGE STUDIES
Failure of Teton Dam
Newly completed Teton Dam as it appeared in mid May 1976, as the
reservoir was filling at the rate of 3 feet per day.
The rate of filling is usually limited to no more than 1 foot per day.
Mid May 1976
Newly completed Teton Dam
10
TETON DAM FAILURE
Leakage was initially noted around 7:00 AM on Saturday June 5, 1976. This
view shows a dozer being sent down to fill in the hole at elevation 5200
around 10:45 AM.
June 5, 1976
10:45 am
Idaho, USA
11
TETON DAM FAILURE
The dozer is lost in the expanding hole, around 11:20 AM on June 5th.
Note turbid nature of outflow along the abutment.
June 5, 1976
11:20 am
Idaho, USA
12
TETON DAM FAILURE
Rapidly deteriorating situation as it appeared around 11:30 AM. A massive
hole has developed in the downstream face of the embankment and is
migrating upward.
June 5, 1976
11:30 am
Idaho, USA
13
TETON DAM FAILURE
The hole continues to enlarge and rise toward the crest of the right abutment.
This is about 11:50 AM.
June 5, 1976
11:50 am
Idaho, USA
14
TETON DAM FAILURE
Dam crest beginning to breach at 11:55 AM on Saturday June 5, 1976. Note
increasing discharge.
June 5, 1976
11:55 am
Idaho, USA
15
TETON DAM FAILURE
Maximum flood discharge emanating from gap in dam’s right abutment, just after noon
on June 5th , 1976.
June 5, 1976
After noon
Idaho, USA
16
TETON DAM FAILURE
Present day situation
Idaho, USA
17
OROVILLE DAM
 The lake level is controlled using the main
spillway gate, which releases water down the
concrete spillway to get to the river below.
 The emergency spillway, which has a 30 ft
(9 m) high concrete wall at the top of a hill, is
unused.
Oriville Dam – Normal Operations
California, USA
18
OROVILLE DAM
 The lake level is controlled using the main
spillway gate, which releases water down the
concrete spillway to get to the river below.
 The emergency spillway, which has a 30 ft
(9 m) high concrete wall at the top of a hill, is
unused.
Despite concerns that the emergency spillway
is vulnerable to erosion, a $100 million
request by community groups to upgrade it to
a concrete-lined auxiliary spillway is rejected
by the federal regulators
Oriville Dam – Normal Operations 2005: Upgrade proposal rejected
California, USA
19
OROVILLE DAM FAILURE
Craters appear in the main spillway. To avoid
increasing the damage to the spillway, water
releases are slowed allowing the lake to rise.
Water flows over the emergency spillway
causing erosion and damage. This is by
design and prevents water going over the top
of the main dam. However the ground erodes
faster than expected.
7-Feb-2017: Main spillway fails 11-Feb-2017: Emergency spillway used
California, USA
20
OROVILLE DAM FAILURE
Rocks and concrete (1) are placed under the
emergency spillway weir to repair erosion damage
(2). The release of water into the main spillway is
increased, to lower the lake in preparation for more
rain. This erodes the adjacent hillside considerably,
generating a debris dam (3) that blocks the river and
forces the closure of the hydroelectric plant.
While the main 770 ft (230 m) dam is not
threatened, if the erosion on either spillway
reaches the top, it would cause the weir or
gate (respectively) to collapse, causing a large
uncontrolled water release and life-
threatening floods
13-Feb-2017: Repairs made Potential risks
California, USA
21
OROVILLE DAM FAILURE
While the main 770 ft (230 m) dam is not
threatened, if the erosion on either spillway
reaches the top, it would cause the weir or
gate (respectively) to collapse, causing a large
uncontrolled water release and life-
threatening floods
Potential risks
California, USA
22
OROVILLE DAM FAILURE
March 2011 7-Feb-2017 27-Feb-2017
Damage to the main spillway began as a crater in the middle (center) and eventually resulted in a
separate channel eroded to the side (right). At left, the main spillway is shown in March 2011 while at
its maximum discharge rate.
California, USA
23
CONCLUDED
REFERENCE MATERIAL
Principles of Geotechnical Engineering – (7th Edition)
Braja M. Das
Chapter #7 & 8

More Related Content

What's hot

Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]Geotechnical Engineering-II [Lec #7A: Boussinesq Method]
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #0: Course Material]
Geotechnical Engineering-II [Lec #0: Course Material]Geotechnical Engineering-II [Lec #0: Course Material]
Geotechnical Engineering-II [Lec #0: Course Material]Muhammad Irfan
 
3 a index properties of soil
3 a index properties of soil3 a index properties of soil
3 a index properties of soilSaurabh Kumar
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Muhammad Irfan
 
Permeability of Soil
Permeability of SoilPermeability of Soil
Permeability of SoilArbaz Kazi
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Muhammad Irfan
 
8 compressibility and consolidation
8 compressibility and consolidation8 compressibility and consolidation
8 compressibility and consolidationSaurabh Kumar
 
Class 5 Permeability Test ( Geotechnical Engineering )
Class 5   Permeability Test ( Geotechnical Engineering )Class 5   Permeability Test ( Geotechnical Engineering )
Class 5 Permeability Test ( Geotechnical Engineering )Hossam Shafiq I
 
SOIL PERMEABILITY PPT
SOIL PERMEABILITY PPTSOIL PERMEABILITY PPT
SOIL PERMEABILITY PPTJISMI JACOB
 
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...Cristian Soriano-Camelo
 
Class 7 Consolidation Test ( Geotechnical Engineering )
Class 7    Consolidation Test ( Geotechnical Engineering )Class 7    Consolidation Test ( Geotechnical Engineering )
Class 7 Consolidation Test ( Geotechnical Engineering )Hossam Shafiq I
 

What's hot (20)

Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
 
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
 
5 effective stress concept
5  effective stress concept5  effective stress concept
5 effective stress concept
 
Soil Mechanics
Soil MechanicsSoil Mechanics
Soil Mechanics
 
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]Geotechnical Engineering-II [Lec #7A: Boussinesq Method]
Geotechnical Engineering-II [Lec #7A: Boussinesq Method]
 
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]
Geotechnical Engineering-I [Lec #8: Hydrometer Analysis]
 
Geotechnical Engineering-II [Lec #0: Course Material]
Geotechnical Engineering-II [Lec #0: Course Material]Geotechnical Engineering-II [Lec #0: Course Material]
Geotechnical Engineering-II [Lec #0: Course Material]
 
3 a index properties of soil
3 a index properties of soil3 a index properties of soil
3 a index properties of soil
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
 
Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]Geotechnical Engineering-I [Lec #9: Atterberg limits]
Geotechnical Engineering-I [Lec #9: Atterberg limits]
 
Permeability of Soil
Permeability of SoilPermeability of Soil
Permeability of Soil
 
stress distribution in soils
stress distribution in soilsstress distribution in soils
stress distribution in soils
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]
 
Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]
 
8 compressibility and consolidation
8 compressibility and consolidation8 compressibility and consolidation
8 compressibility and consolidation
 
Class 5 Permeability Test ( Geotechnical Engineering )
Class 5   Permeability Test ( Geotechnical Engineering )Class 5   Permeability Test ( Geotechnical Engineering )
Class 5 Permeability Test ( Geotechnical Engineering )
 
SOIL PERMEABILITY PPT
SOIL PERMEABILITY PPTSOIL PERMEABILITY PPT
SOIL PERMEABILITY PPT
 
Lecture 6 soil permeability
Lecture 6 soil permeabilityLecture 6 soil permeability
Lecture 6 soil permeability
 
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...
Soil Dynamics - Local Site Effects - Ground response - Geotechnical Earthquak...
 
Class 7 Consolidation Test ( Geotechnical Engineering )
Class 7    Consolidation Test ( Geotechnical Engineering )Class 7    Consolidation Test ( Geotechnical Engineering )
Class 7 Consolidation Test ( Geotechnical Engineering )
 

Similar to Geotechnical Engineering-I [Lec #26: Permeability thru Stratified Soils]

Niagara
NiagaraNiagara
Niagaraaea_aa
 
Land Subsidence Introduction Of all water that r.docx
Land Subsidence  Introduction  Of all water that r.docxLand Subsidence  Introduction  Of all water that r.docx
Land Subsidence Introduction Of all water that r.docxsmile790243
 
ok final Natural Hazards 2 Landslides and Floods.pptx
ok final Natural Hazards 2 Landslides and Floods.pptxok final Natural Hazards 2 Landslides and Floods.pptx
ok final Natural Hazards 2 Landslides and Floods.pptxAnuragDavesar
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homeworkmrzislion
 
Rivers revision
Rivers revisionRivers revision
Rivers revisionLiz Smith
 
Rivers Revision
Rivers RevisionRivers Revision
Rivers RevisionLiz Smith
 
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...Marcellus Drilling News
 
Weathering, Erosion & Deposition
Weathering, Erosion & DepositionWeathering, Erosion & Deposition
Weathering, Erosion & DepositionJeanie Lacob
 
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Niraj Lamichhane
 
Module 3 cape unit 1 geography.
Module 3 cape unit 1 geography.Module 3 cape unit 1 geography.
Module 3 cape unit 1 geography.Oral Johnson
 
Liquefaction by alisha kaplan
Liquefaction by alisha kaplanLiquefaction by alisha kaplan
Liquefaction by alisha kaplanmk.amiri
 

Similar to Geotechnical Engineering-I [Lec #26: Permeability thru Stratified Soils] (20)

Niagara
NiagaraNiagara
Niagara
 
Land Subsidence Introduction Of all water that r.docx
Land Subsidence  Introduction  Of all water that r.docxLand Subsidence  Introduction  Of all water that r.docx
Land Subsidence Introduction Of all water that r.docx
 
ok final Natural Hazards 2 Landslides and Floods.pptx
ok final Natural Hazards 2 Landslides and Floods.pptxok final Natural Hazards 2 Landslides and Floods.pptx
ok final Natural Hazards 2 Landslides and Floods.pptx
 
Butler
ButlerButler
Butler
 
Upper san fernando dam
Upper san fernando damUpper san fernando dam
Upper san fernando dam
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homework
 
ChampagneSWFWMD_WBModel
ChampagneSWFWMD_WBModelChampagneSWFWMD_WBModel
ChampagneSWFWMD_WBModel
 
ChampagneSWFWMD_WBModel
ChampagneSWFWMD_WBModelChampagneSWFWMD_WBModel
ChampagneSWFWMD_WBModel
 
Flood-.ppt
Flood-.pptFlood-.ppt
Flood-.ppt
 
Rivers revision
Rivers revisionRivers revision
Rivers revision
 
Rivers Revision
Rivers RevisionRivers Revision
Rivers Revision
 
ENV 101 Ch08 lecture ppt_a
ENV 101 Ch08 lecture ppt_aENV 101 Ch08 lecture ppt_a
ENV 101 Ch08 lecture ppt_a
 
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
 
ENV 101 Ch07 lecture ppt_a
ENV 101 Ch07 lecture ppt_aENV 101 Ch07 lecture ppt_a
ENV 101 Ch07 lecture ppt_a
 
Weathering, Erosion & Deposition
Weathering, Erosion & DepositionWeathering, Erosion & Deposition
Weathering, Erosion & Deposition
 
ENV 101 Ch11 lecture ppt_a
ENV 101 Ch11 lecture ppt_aENV 101 Ch11 lecture ppt_a
ENV 101 Ch11 lecture ppt_a
 
water
waterwater
water
 
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
 
Module 3 cape unit 1 geography.
Module 3 cape unit 1 geography.Module 3 cape unit 1 geography.
Module 3 cape unit 1 geography.
 
Liquefaction by alisha kaplan
Liquefaction by alisha kaplanLiquefaction by alisha kaplan
Liquefaction by alisha kaplan
 

More from Muhammad Irfan

Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Muhammad Irfan
 
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)Muhammad Irfan
 
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #11: Settlement Computation]
Geotechnical Engineering-II [Lec #11: Settlement Computation]Geotechnical Engineering-II [Lec #11: Settlement Computation]
Geotechnical Engineering-II [Lec #11: Settlement Computation]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Muhammad Irfan
 

More from Muhammad Irfan (20)

Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
 
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]
Geotechnical Engineering-II [Lec #25: Coulomb EP Theory - Numericals]
 
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
 
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
 
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]
Geotechnical Engineering-II [Lec #22: Earth Pressure at Rest]
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
 
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
 
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
 
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
 
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
 
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
 
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]
Geotechnical Engineering-II [Lec #12: Consolidation Settlement Computation]
 
Geotechnical Engineering-II [Lec #11: Settlement Computation]
Geotechnical Engineering-II [Lec #11: Settlement Computation]Geotechnical Engineering-II [Lec #11: Settlement Computation]
Geotechnical Engineering-II [Lec #11: Settlement Computation]
 
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]
Geotechnical Engineering-II [Lec #9+10: Westergaard Theory]
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
 
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]
Geotechnical Engineering-II [Lec #7: Soil Stresses due to External Load]
 
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Geotechnical Engineering-I [Lec #26: Permeability thru Stratified Soils]

  • 1. 1 Geotechnical Engineering–I [CE-221] BSc Civil Engineering – 4th Semester by Dr. Muhammad Irfan Assistant Professor Civil Engg. Dept. – UET Lahore Email: mirfan1@msn.com Lecture Handouts: https://groups.google.com/d/forum/2016session-geotech-i Lecture # 26 24-Apr-2018
  • 2. 2 Equivalent Hydraulic Conductivity of Stratified Soils Total flow Permeability Parallel to Stratification  Velocity of flow ‘v’  Hydraulic gradient ‘i’ nHn HHHH Hik HikHikHikHik    332211 nHn HHH Hik HikHikHikq    332211 H HkHkHkHk k nHnHHH H   332211 → sum of flows though each layer → same for each layer → different for all layers Hikq H  Taking third dimension (i.e. into the plane of paper) as unity Avq  )1( Hvq 
  • 3. 3 Permeability Perpendicular to Stratification  Velocity of flow ‘v’ and discharge ‘q’  Hydraulic gradient ‘i’ and head loss ‘h’ nhhhhh  321 ikv v  H h i  Vn n VVVV k Hv k Hv k Hv k Hv k Hv           3 3 2 2 1 1 )1(332211  nn HiHiHiHih  Also, 1 1 vk v i  2 2 vk v i  3 3 vk v i  Replacing in eq. (1) Vn n VVV V k H k H k H k H H k    3 3 2 2 1 1 kv = average permeability perpendicular to stratification → same through each layer → different through each layer Equivalent Hydraulic Conductivity of Stratified Soils
  • 4. 4 Practice Problem #4 On close investigation of a sample it was found to be in three layers 20mm, 60mm, and 40mm. The permeability of these layers are 3x10-3mm/sec, 5x10-4mm/sec, and 17x10-4mm/sec respectively. Find kH and kV, and the ratio kH/kV. H HkHkHkHk k nHnHHH H   332211 Vn n VVV V k H k H k H k H H k    3 3 2 2 1 1
  • 5. 5 Practice Problem #5 H HkHkHkHk k nHnHHH H   332211 Vn n VVV V k H k H k H k H H k    3 3 2 2 1 1
  • 9. 9 SIGNIFICANCE OF SEEPAGE STUDIES Failure of Teton Dam Newly completed Teton Dam as it appeared in mid May 1976, as the reservoir was filling at the rate of 3 feet per day. The rate of filling is usually limited to no more than 1 foot per day. Mid May 1976 Newly completed Teton Dam
  • 10. 10 TETON DAM FAILURE Leakage was initially noted around 7:00 AM on Saturday June 5, 1976. This view shows a dozer being sent down to fill in the hole at elevation 5200 around 10:45 AM. June 5, 1976 10:45 am Idaho, USA
  • 11. 11 TETON DAM FAILURE The dozer is lost in the expanding hole, around 11:20 AM on June 5th. Note turbid nature of outflow along the abutment. June 5, 1976 11:20 am Idaho, USA
  • 12. 12 TETON DAM FAILURE Rapidly deteriorating situation as it appeared around 11:30 AM. A massive hole has developed in the downstream face of the embankment and is migrating upward. June 5, 1976 11:30 am Idaho, USA
  • 13. 13 TETON DAM FAILURE The hole continues to enlarge and rise toward the crest of the right abutment. This is about 11:50 AM. June 5, 1976 11:50 am Idaho, USA
  • 14. 14 TETON DAM FAILURE Dam crest beginning to breach at 11:55 AM on Saturday June 5, 1976. Note increasing discharge. June 5, 1976 11:55 am Idaho, USA
  • 15. 15 TETON DAM FAILURE Maximum flood discharge emanating from gap in dam’s right abutment, just after noon on June 5th , 1976. June 5, 1976 After noon Idaho, USA
  • 16. 16 TETON DAM FAILURE Present day situation Idaho, USA
  • 17. 17 OROVILLE DAM  The lake level is controlled using the main spillway gate, which releases water down the concrete spillway to get to the river below.  The emergency spillway, which has a 30 ft (9 m) high concrete wall at the top of a hill, is unused. Oriville Dam – Normal Operations California, USA
  • 18. 18 OROVILLE DAM  The lake level is controlled using the main spillway gate, which releases water down the concrete spillway to get to the river below.  The emergency spillway, which has a 30 ft (9 m) high concrete wall at the top of a hill, is unused. Despite concerns that the emergency spillway is vulnerable to erosion, a $100 million request by community groups to upgrade it to a concrete-lined auxiliary spillway is rejected by the federal regulators Oriville Dam – Normal Operations 2005: Upgrade proposal rejected California, USA
  • 19. 19 OROVILLE DAM FAILURE Craters appear in the main spillway. To avoid increasing the damage to the spillway, water releases are slowed allowing the lake to rise. Water flows over the emergency spillway causing erosion and damage. This is by design and prevents water going over the top of the main dam. However the ground erodes faster than expected. 7-Feb-2017: Main spillway fails 11-Feb-2017: Emergency spillway used California, USA
  • 20. 20 OROVILLE DAM FAILURE Rocks and concrete (1) are placed under the emergency spillway weir to repair erosion damage (2). The release of water into the main spillway is increased, to lower the lake in preparation for more rain. This erodes the adjacent hillside considerably, generating a debris dam (3) that blocks the river and forces the closure of the hydroelectric plant. While the main 770 ft (230 m) dam is not threatened, if the erosion on either spillway reaches the top, it would cause the weir or gate (respectively) to collapse, causing a large uncontrolled water release and life- threatening floods 13-Feb-2017: Repairs made Potential risks California, USA
  • 21. 21 OROVILLE DAM FAILURE While the main 770 ft (230 m) dam is not threatened, if the erosion on either spillway reaches the top, it would cause the weir or gate (respectively) to collapse, causing a large uncontrolled water release and life- threatening floods Potential risks California, USA
  • 22. 22 OROVILLE DAM FAILURE March 2011 7-Feb-2017 27-Feb-2017 Damage to the main spillway began as a crater in the middle (center) and eventually resulted in a separate channel eroded to the side (right). At left, the main spillway is shown in March 2011 while at its maximum discharge rate. California, USA
  • 23. 23 CONCLUDED REFERENCE MATERIAL Principles of Geotechnical Engineering – (7th Edition) Braja M. Das Chapter #7 & 8