SlideShare a Scribd company logo
1 of 29
Download to read offline
CASE STUDY
(INC: PROJECT DISCUSSION AND ANALYSIS)
School Nursery Refurbishment & Extension
Author: GRAHAME LANDERS BSc(Hons)
Building Surveyor Project Manager
Issued: 26th August 2006
Case Study
Contents Author: Grahame Landers
Building Surveyor Project Manager
CONTENTS
1.0 INTRODUCTION 1
1.1 Property Description 1
1.2 Clients Brief 1
1.3 Contract Particulars 2
2.0 PRE CONSTRUCTION PHASE 3
2.1 Statutory Requirements and Application 3
2.2 Specification Preparation 4
2.3 Construction (Design & Management) Regulations 1994 4
3.0 CONSTRUCTION PHASE 5
3.1 Site Monitoring and Progress Meetings 5
3.2 Interim Payments and Compensation Events 5
3.3 Practical Completion 5
4.0 PROJECT MANAGEMENT APPRAISALS & SOLUTIONS THROUGHOUT 7
4.1 Planning Issues and Programme 7
4.2 Working in the School Term / Health & Safety Considerations 8
4.3 Existing Roof 9
4.4 Contract Administration / Contractual Issues 10
5.0 APPRAISAL AND ANALYSIS AT COMPLETION 12
5.1 Planning Issues 12
5.2 Building Control Issues 12
5.3 Form of Contract 13
5.4 Administering the NEC 13
5.5 Contractual Issues 14
5.6 Health & Safety / CDM 15
5.7 Overarching Analysis – Project Manager 15
6.0 CONCLUSION 16
APPENDIX A: Drawings
APPENDIX B: Before & After Photographs
Case Study
Issue Date: August 2006 Page 1 Grahame John Landers
1.0 INTRODUCTION
1.1 Property Description
The detached single storey nursery is located in a residential area of Surrey, and was
constructed circa 1975. The nursery consists of WC, food preparation area, conservatory,
store room and large and small teaching rooms.
The building is of load bearing masonry construction with inner blockwork and external
facing brickwork cavity wall. The floor is a reinforced cast in-situ concrete. The roof is flat.
1.2 Client’s Brief
The Client was required to improve and update nursery facilities by complying with DfES
Guidelines; DDA legislation and food preparation hygiene standards.
Our brief was to assess and make recommendations on the Client’s requirement and to
provide a cost appraisal of the proposed works. A Feasibility Report produced by another in-
house Department recommended the following works:
• New extension, to provide a ‘quiet room’.
• Internal structural alterations to create an open plan main classroom.
• Levelling of the internal floor for disabled usage and insert a new disabled WC.
• External hard landscape remodelling for disabled access.
• Separate food preparation area away from the children’s WC, for hygienic purposes.
• General refurbishment and modernisation.
Case Study
Issue Date: August 2006 Page 2 Grahame John Landers
1.3 Contract Particulars
• Contract Value: £200,000.00
• Contract: New Engineering Contract 2005, with: -
• Core Clauses.
• Strategy Option A: (Contractor prices for
undefined work)
• Secondary Options: -
o X12 (Partnering).
o X16 (Retention)
• Actual Construction Period: 14 weeks
• Actual Lead-in (2weeks): 22nd
August 2005 – 3rd
September 2005
• Actual Start On-site Date: 5th
September 2005
• Actual Finish Date: 9th
December 2005
Case Study
Issue Date: August 2006 Page 3 Grahame John Landers
2.0 PRE CONSTRUCTION PHASE
2.1 Statutory Requirements and Applications
2.1.1 Planning Requirements
I prepared a Full Planning Application including existing and proposed AutoCAD drawings,
for the new extension and remodelling of the external hard and soft landscaping. Following
submission, I displayed site notices, for Public information. An objection to the development
was raised by the adjacent neighbour. Consequently I was advised by Planning: -
1. Remodelling of the new extension footprint was required, to ensure the four meter
buffer zone, which was imposed in the original Planning Approval Conditions, when the
existing nursery was built in 1975, was respected. This 1975 condition was not known at
prior to submitting the application.
2. The application would be determined at a public Committee meeting.
Waiting a lengthy time period for the next Committee meeting, delayed the start on-site date.
2.1.2 Building Regulations Application
I prepared, Full Building Regulation Plans Application, including existing and proposed
CAD drawings. Key considerations were: -
• DDA and internal disabled provisions.
• Internal structural demolitions and alterations.
• Thermal performance.
• New extension including new rainwater drainage.
• Fire Strategy (new fire/smoke alarm system, emergency lighting, escape routes).
Case Study
Issue Date: August 2006 Page 4 Grahame John Landers
3.2 Specification Preparation
As the Client appointed a Partnering Contractor, without formal Tender procedures,
production of Tender Documents was not necessary. Instead, I produced a specification that
included Materials and Workmanship clauses and a Schedule of Works.
2.3 Construction (Design & Management) Regulations 1994
As lead designer, I advised the Client that the project came under the remit of the CDM
Regulations 1994, as: -
• The project would exceed 30 working days.
• More than five people would be on site at any one time.
• The works entailed demolition.
The Client appointed a competent person to undertake Planning Supervision duties. To aid
the PS in the production of the Plan I forwarded all project information.
The PS requirements were included in the Plan Prelims - the works would only be
‘Practically Complete’ once all H&S File information had been received.
Case Study
Issue Date: August 2006 Page 5 Grahame John Landers
3.0 CONSTRUCTION PHASE
3.1 Site Meetings and Monitoring Progress
I chaired monthly site meetings throughout the course of the programme. During these
meetings, I dealt with all technical queries, contractual issues, compensation events, etc.
I used the Contractor’s programme, when monitoring progress, by comparing the actual
completed site works against the programmes, activity time durations. Also during the
monitoring meetings I assessed and advised on the quality of workmanship.
3.2 Interim Payments and Compensation Events
The Contractor submitted monthly valuations for works undertaken to date of submission,
which I checked and produced certificates.
Due to the time taken to confirm my site instructions, through Compensation Events, which
under the NEC can take up to 13 weeks (if a revised quote was not asked for), proved
impractical for the original 12 week programme. Through trust and partnering (NEC X12),
the Contractor immediately undertook my site instructions.
3.3 Practical Completion
3.3.1 Health & Safety File, Handover and Practical Completion Certification
Prior to programme completion date, I contacted the PS to discuss the information that the
Contractor would need to supply, for the H&S File. The PS’s request included: -
• List of all sub-Contractors and their specialist applications.
• List of all specialist materials supplied.
• Certificates, warranties and guarantees.
During the formal handover meeting, with the Client in attendance, I undertook a final snag
inspection and on being satisfied with the quality of workmanship and there being zero
defects, I advised the Client and PS that all works were complete.
Case Study
Issue Date: August 2006 Page 6 Grahame John Landers
After reviewing the H&S File contents with the PS and being satisfied with the contents, I
prepared the Practical Completion Certificate, which included the 12-months defects liability
period expiry date.
3.3.2 Final Account
On agreement of the Final Account, the Contractor issued an invoice for payment to the
Client. Half of the 5% retention which was kept during the course of the contract was
released, and added to the Final Account. The other 2.5% of the total cost of the works was
withheld for the defects liability period.
Case Study
Issue Date: August 2006 Page 7 Grahame John Landers
4.0 PROJECT MANAGEMENT APPRAISALS & SOLUTIONS THROUGHOUT
The following section identifies particular key issues which I was involved. In each case I
have looked at the reasons for the course of action selected and why I dismissed alternatives.
4.1 Planning Issues and Programme
As the adjacent neighbour objected to the development, the Planning decision had to be held
in public, by Committee. As next Committee meeting was 4 weeks into the programme
along with the Contractors lead-in time meant that works would not start at the beginning of
the summer holidays and house the nursery in the hall for four weeks as originally planned
but at the commencement of the new term. Consequently the nursery services would not
have accommodation, throughout the works duration. To have all the project duration in
term time was too long for the Nursery to be without adequate facilities.
Options available and choice made
1. Postpone the Project until 2006 Summer Holidays. This option meant the works
would not be undertaken during the teaching year and they could continue using the
existing nersury facilities. However, it would pose problems to the Client’s funding
arrangements and the costs would incur interest.
2. Look for Alternative Accommodation within the Vicinity of the School (i.e. Church
Hall). To avoid financial issues associated with option 1 and to prevent postponement,
moving the nursery services into a suitable alternative accommodation would allow the
nursery to function to DfES guidelines. The nursery would be detached from the school
and costs would be incurred from renting a suitable building for the works duration.
3. Provide a Temporary Modular Unit, with Associated Services, Located on the
Nursery Site. This option meant the nursery would remain on its existing site, function
to DfES guidelines and not be detached from the school. However, costs would be
incurred costs from the hire and fit out to DfES criteria and Planning approval.
I recommended option 3, to which the Client agreed.
Case Study
Issue Date: August 2006 Page 8 Grahame John Landers
4.2 Working in School Term Time / Health & Safety Considerations
In addition to the disruption to school and nursery teaching, caused by noisy works and site
operations, I also identified the following major H&S issues: -
• An access path and the playground abutted the nursery building.
• The Contractor would be in partial occupation of the nursery site, with the nursery
(housed within the modular unit) occupying the other side.
• A designated Contractor’s storage area was to the other side to the only school /
nursery entrance.
Options available and choice made
1. Postpone the Project until 2006 Summer Holidays: This avoided H&S risk to the
children and disruption to teaching, but costs would gain interest and cause problems to
the Client’s annual funding.
2. Out of Hours Working. To avoid problems associated with option 1, the Contractor
working weekends, before and after school hours would mean no disruptions to
teaching, the children could use the tarmac playground during winter and transporting
materials across the only school / nursery entrance would not prevent access, especially
during the children’s drop off and pick up times. However, working out of hours would
gain additional costs, possible neighbour disputes and gaining tradesmen.
3. Provide a Perimeter Barriers and Ensure Deliveries and Noisy Works are
Undertaken Out of Hours: In providing a high metal gate across the access path with a
lock, hoardings between the modular unit and the nursery building, having a zoned
hoarded perimeter area in the playground and enforcing out of school hours of
deliveries, noisy works and transportation of materials would prevent teaching
disruptions. However, this option needed careful programming by the Contractor.
I recommended option 3, to which the Client agreed. I requested method statements and risk
assessments from the Contractor.
Case Study
Issue Date: August 2006 Page 9 Grahame John Landers
4.3 Existing Roof
Works to the existing roof was not originally included in the feasibility works. In reviewing
the requirement of thermal performance and ventilation it became known by Client that
replacement of the existing roof covering was planned to be undertaken in the near future. I
therefore put a number of option appraisals, to the Client.
Options available and choice made
1. Cold Roof Construction: Provide a 25mm diameter ventilation gaps to the soffits and
200mm thick insulation quilt to the void. However, the advantages of saving money
from using the elevation scaffold access to the roof during these works would be lost
and further disruption to the nursery would occur in the near future.
2. Warm Roof Construction: Remove the covering and provide new tapered insulation
above the deck with a new covering. This option, took advantage of the scaffolding, the
replacement covering would have the same life span and 20 year warranty as the new
extension covering. The tapered insulation would provide good falls to gutters through
its service life, thus preventing ponding and no future planned works. However, the
existing roof and the new extension cold roof would be of a different construction and
the existing upstands would need to be built-up to accommodate the tapered insulation.
3. Cold Roof Construction and New Roof Covering: In consideration of the limited
Client’s additional funds, keeping the new and existing roof constructions the same
(cold) and the near future planned covering replacement, this third option, was a
comprise between options 1 and 2, by providing 25mm diameter ventilation gap,
200mm thick insulation quilt and covering replacement.
Discussions with the Contractor to establish timelines of undertaking the each of the above
options on-site, along with Building Control decision time was added to my calculated
design time. Each option timeline was determined and also put forward to the Client.
I recommended option 3, to which the Client agreed to the timeline and provided additional
monies for the works along. My additional specification and design was approved by
Building Control.
Case Study
Issue Date: August 2006 Page 10 Grahame John Landers
4.4 Contract Administration / Contractual Issues
Over the course of the project a 6 week delay occurred to the programme. I needed to
evaluate the amount of extension of time, I could grant to the Contractor.
Options available and choice made
Risks to the original programme included -
1. Neighbours’ Objection to the Development: This caused my Planning Application to
be decided by the Planning Committee, held in public. As the next Committee meeting
was four weeks into the programme, the start on-site date was delayed. Total delay of 4
weeks.
2. Breach of Structural Engineers Foundation Design. The Contractor in undertaking
the new extension foundation excavations did not adhere to the Structural Engineer’s
design, as more of the existing in-situ reinforced foundation, was removed. The design
allowed for the new foundations to be supported and joined to the existing. The
Structural Engineer need to check / revise his design and for Building Control
acceptance, caused a total delay of 2 weeks for the new quiet room extension works.
3. Additional Works: The works to upgrade the existing roof to include new insulation,
new cross internal ventilation, new roof covering, caused an on-site total delay of 2
weeks.
Impact from Delays upon the Programme and Resulting Extension of Time
• The critical path was affected by adjacent neighbour objecting to my Planning
application. It meant the application needed to be decided upon by the Planning
Committee, whose next meeting was four weeks in to the original programme. This
delayed the original date for the Contractor’s lead-in time by 4 weeks. I advised the
Contractor early enough to prevent any programme delays and delay costs from being
occurred. The Contractor did not raise an ‘early warning’ notice.
Case Study
Issue Date: August 2006 Page 11 Grahame John Landers
• The Contractor’s error in removing more existing foundation did not affect the critical
path. The critical path at that stage was undertaking the internal strip out and not the
building extension works. The Contractor did not raise an ‘early warning’ notice.
• The additional works to upgrade the roof did affect the critical path. The site works
added an extra 2 weeks on to the construction phase programme. The Contractor did
raise an ‘early warning’ notice.
I therefore decided that the 2 week delay resulting from the additional on-site roofing works
was not the Contractor’s fault and an extension of time, could be granted. The Client agreed.
I issued a ‘Compensation Event’.
The original programme was delayed by a total 6 weeks, due to the Planning Application
objection by the neighbour and from the additional roofing works.
Case Study
Issue Date: August 2006 Page 12 Grahame John Landers
5.0 APPRAISAL AND ANALYSIS AT COMPLETION
The following section is a critical analysis of my project involvement. Where appropriate I
have identified lessons learnt, reflective learning and professional development.
5.1 Planning Issues
I gained additional Planning experience when the neighbour objected to the development.
The original extension layout was unknowingly in breach of the original 1975 planning
consent condition as it did not maintain a four meter buffer zone. This experience was in the
way objections were dealt with at Committee level.
Although, remodelling of the new extension to be 4 meters away from the neighbour’s
boundary was an easy AutoCAD exercise, the objection caused a four delay to the start date
and caused disruption to nursery and school. Forward and flexible thinking was important to
minimise major problems, especially advising the Client that a temporary modular unit was a
solution.
5.2 Building Control Issues
I had to ensure that all proposed works met the requirements of the Building Regulations and
in addition the unforeseen works. This exposure to in achieving compliance increased my
knowledge of the Building Regulations, but also how Building Control Officers operate and
how they administer the Building Regulations. I also learnt that by establishing a close
relationship with Building Control Officers limits delays.
In providing option appraisals for undertaking replacement of the existing roof covering, I
demonstrated to the Client the advantages of bringing forward the replacement works and
incorporating them within the project. In formulating recommendations, I learnt how to
communicate effectively in writing.
Case Study
Issue Date: August 2006 Page 13 Grahame John Landers
5.3 Form of Contract
In using the NEC, I realised that there were many advantages to this Contract as oppose to
the traditional contracts, as ‘Early Warning’ highlighted problems to time, quality and
finances at an early stage, ‘Compensation Events’ provide final account figure during the
works and the X12 (Partnering) drives parties to mutually achieve the project aim and goals.
Although I was not involved in the recommendation for the NEC, which is a contract suited
for most major Engineering and Building works, I have since reflected reflect upon the
importance of advising the Client on a Contract that is best suited to a project’s scope,
budget, complexity and programme. A suitable contract for this project, is the JCT,
Intermediate Form of Contract 1998, as guidance given in the Practice Note 5, (Series 2),
states the IFC is usable where: -
• Value of the works up to £375,000.00 (2003 prices).
• Contract period does not exceed 12 months.
• Works are not complex or requiring complex trades.
Normal NEC practices require the need of multiple staff. Whilst acting as Project Manager
(under delegated powers); Designer, Building Surveyor, AutoCAD Technician,
Administrator of the Contract, co-ordinator of the Structural Engineer and M&E
Consultations, it became very onerous. I soon learnt that managing staff and information is
essential, to ensure smooth running of an NEC project.
5.4 Administering the NEC
I identified a major problem during the course of the works that it can take up to 13 week to
confirm my site instruction through a Compensation Event. As the actual works on-site
lasted for 14 weeks it would result in the majority of variations being dealt with at the end of
the project. I discussed this issue with the Contractor, who agreed to undertake my site
instructions once I had given them in writing.
Case Study
Issue Date: August 2006 Page 14 Grahame John Landers
Chairing meetings not only gave me the experience of co-ordinating all parties involved with
the project but also further developed my interpersonal skills. I recognised the importance of
preparing meeting minutes to keep interested parties and client informed of events taking
placing on site and to clearly communicate any action points to the relevant parties.
Monitoring costs throughout the course of the project enabled me to decide if additional
costs were accommodated within the project costs. It also allowed me to regularly advise the
client on remaining contingency funds, additional costs and the project final account.
Through monitoring the progress of the works, I gained experience of assessing a contractor
programme and acquired practical knowledge of the length of time certain construction tasks
may take. This has assisted me when advising the client as estimated construction time the
project.
5.5 Contractual Issues
With the refurbishment and the new extension not being completed to programme, I
acquired an understanding of the importance of closely monitoring a contractor’s progress
and performance. From this, I recognise the importance of gaining a detailed explanation of
the reason(s) why a contractor is not meeting the programme and analysing the events in the
Critical path would necessitate the need to hold a review meeting.
5.6 Health & Safety / CDM
Due to the revised start date, being at the start of the teaching calendar, the H&S of the staff
and children became paramount. Through undertaking a Risk Assessment, I was able to
identify the hazards and what best options to nullify or reduce the risk. This exercise has
increased my awareness of H&S issues.
In complying with Regulation 14 of CDM, and providing Risk Assessments has enabled
further understanding of how my design could be built with health and safety problems.
Through, analysing potential risk has further improved my design abilities,
Case Study
Issue Date: August 2006 Page 15 Grahame John Landers
5.7 Overarching Analysis - Project Manager
The assistance of M&E designer; Structural Engineer; in-house Quantity Surveyor and
Planning Supervisor has been invaluable in ensuring the project during the pre and post
contract phases, meet the project objectives and aims. My proactive management approach
of the project team (including the Contractor and Building Control) and co-ordination of all
their information was therefore successful.
Working within the education sector has enabled me to gain a fundamental understanding
and experience of DfES guidelines and criteria in providing nursery facilities, suitable for
children’s usage and educational development.
Case Study
Issue Date: August 2006 Page 16 Grahame John Landers
6.0 CONCLUSION
This case study (including appraisal and analysis) has focused upon my involvement during
the three construction phases to refurbish and improve the existing nursery facilities.
Experience gained throughout this project has enabled me to further develop my
understanding and knowledge of statutory, technical and construction matters. For example
the planning issues and unexpected poor thermal performance of the existing building
construction that both involved extra costs and posed risks to the project programme.
When situations arose I would research the options from various sources of information (e.g.
legislation, textbooks, line management, etc.) to determine the best course of action. My
proactive approach in resolving site issues quickly prevented undue delay and cost to the
programme where possible.
The refurbishment and improvement met with the Client’s expectations and aim by meeting
current guidelines; standards; legislation and appearance.
The project is currently in the Post Construction Phase which includes the 12 months defects
liability period.
Case Study
Issue Date: August 2006 Appendix A Grahame John Landers
APPENDIX A
DRAWINGS
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
APPENDIX B
BEFORE & AFTER PHOTOGRAPHS
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 2: Front elevation and step access at Feasibility
PHOTO 3: Front elevation and ramp access at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 4: Toilets at Feasibility
PHOTO 5: Refurbished toilets at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 6: Food preparation located in toilet area at Feasibility
PHOTO 7: Ambulant disabled toilet located in former food preparation area at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 8: Store room at Feasibility
PHOTO 9: New kitchen located in former store room area at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 10: Conservatory / classroom partition and step at Feasibility
PHOTO 11: Removed conservatory / classroom partition and step at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 12: Existing roof covering at Feasibility
PHOTO 13: New roof coverings at Practical Completion
Case Study
Issue Date: August 2006 Appendix B Grahame John Landers
PHOTO 14: Existing hard & soft landscaping at Feasibility
PHOTO 15: Remodelled hard & soft landscaping at Practical Completion

More Related Content

What's hot

Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
Devry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newDevry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newuopassignment
 
NYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance ProgramNYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance Programjsmithwick0926
 
Revised recovery programme preparation practical guide rev.00
Revised recovery programme preparation practical guide rev.00Revised recovery programme preparation practical guide rev.00
Revised recovery programme preparation practical guide rev.00ElHusseinAllam
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guidelineZuzi Evangelista
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2TBC Corporation
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comRoelofMerwe131
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comagathachristie149
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-StatementJeremy Heady
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comvenkat60045
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planningawad suliman
 

What's hot (18)

Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Richard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett ResumeRichard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett Resume
 
Devry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 newDevry proj 586 final exam set 1 new
Devry proj 586 final exam set 1 new
 
NYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance ProgramNYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance Program
 
Revised recovery programme preparation practical guide rev.00
Revised recovery programme preparation practical guide rev.00Revised recovery programme preparation practical guide rev.00
Revised recovery programme preparation practical guide rev.00
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Job Order Contracting 101
Job Order Contracting 101Job Order Contracting 101
Job Order Contracting 101
 
Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2
 
Claims
ClaimsClaims
Claims
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.com
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-Statement
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planning
 

Viewers also liked

Social Science-Conscious Analysis Case Study: The Cost of Public School
Social Science-Conscious Analysis Case Study: The Cost of Public SchoolSocial Science-Conscious Analysis Case Study: The Cost of Public School
Social Science-Conscious Analysis Case Study: The Cost of Public SchoolRiley H.
 
Ttt Learning Instruction Mment Mary
Ttt  Learning Instruction Mment MaryTtt  Learning Instruction Mment Mary
Ttt Learning Instruction Mment MaryAlbert Boekhorst
 
Site conditions-analysis
Site conditions-analysis Site conditions-analysis
Site conditions-analysis blankbox
 
Working Condition of Wal-Mart. Abdul Motaleb
Working Condition of Wal-Mart. Abdul MotalebWorking Condition of Wal-Mart. Abdul Motaleb
Working Condition of Wal-Mart. Abdul MotalebAbdul Motaleb
 
Types of instructional materials
Types of instructional materialsTypes of instructional materials
Types of instructional materialsJulienne Abenoja
 
Gropu 3 management of instruction
Gropu 3 management of instructionGropu 3 management of instruction
Gropu 3 management of instructionJason Calonzo
 
Types of Instructional Materials
Types of Instructional MaterialsTypes of Instructional Materials
Types of Instructional MaterialsQueenie Santos
 
Objective-Related Principles of Teaching
Objective-Related Principles of TeachingObjective-Related Principles of Teaching
Objective-Related Principles of Teachingjoy santos
 
Types and Characteristics of Instructional Materials
Types and Characteristics of Instructional MaterialsTypes and Characteristics of Instructional Materials
Types and Characteristics of Instructional MaterialsMarianne Beltran
 
USING AND EVALUATING INSTRUCTIONAL MATERIALS
USING AND EVALUATING INSTRUCTIONAL MATERIALSUSING AND EVALUATING INSTRUCTIONAL MATERIALS
USING AND EVALUATING INSTRUCTIONAL MATERIALSjanehbasto
 
Ed. Tech. I Lesson 6:Using and Evaluating Instructional Materials
Ed. Tech. I Lesson 6:Using and Evaluating Instructional MaterialsEd. Tech. I Lesson 6:Using and Evaluating Instructional Materials
Ed. Tech. I Lesson 6:Using and Evaluating Instructional MaterialsRisha Cajilig
 
Management of instruction
Management of instructionManagement of instruction
Management of instructionRed Soriano
 
Instructional Materials in Mathematics
Instructional Materials in MathematicsInstructional Materials in Mathematics
Instructional Materials in MathematicsBlenda Sotto
 
Instructional Materials in Mathematics
Instructional Materials in MathematicsInstructional Materials in Mathematics
Instructional Materials in MathematicsMary Caryl Yaun
 
Commonly used materials in the classroom
Commonly used materials in the classroomCommonly used materials in the classroom
Commonly used materials in the classroomAda Marie Tayao
 
Preparation and evaluation of instructional materials
Preparation and evaluation of instructional materialsPreparation and evaluation of instructional materials
Preparation and evaluation of instructional materialsJhun Ar Ar Ramos
 
Selecting and Use of Instructional Materials
Selecting and Use of Instructional MaterialsSelecting and Use of Instructional Materials
Selecting and Use of Instructional MaterialsKristine Ann de Jesus
 

Viewers also liked (20)

Social Science-Conscious Analysis Case Study: The Cost of Public School
Social Science-Conscious Analysis Case Study: The Cost of Public SchoolSocial Science-Conscious Analysis Case Study: The Cost of Public School
Social Science-Conscious Analysis Case Study: The Cost of Public School
 
Ttt Learning Instruction Mment Mary
Ttt  Learning Instruction Mment MaryTtt  Learning Instruction Mment Mary
Ttt Learning Instruction Mment Mary
 
Site conditions-analysis
Site conditions-analysis Site conditions-analysis
Site conditions-analysis
 
Working Condition of Wal-Mart. Abdul Motaleb
Working Condition of Wal-Mart. Abdul MotalebWorking Condition of Wal-Mart. Abdul Motaleb
Working Condition of Wal-Mart. Abdul Motaleb
 
TYPES OF INSTRUCTIONAL MATERIALS
TYPES OF INSTRUCTIONAL MATERIALSTYPES OF INSTRUCTIONAL MATERIALS
TYPES OF INSTRUCTIONAL MATERIALS
 
Types of instructional materials
Types of instructional materialsTypes of instructional materials
Types of instructional materials
 
Gropu 3 management of instruction
Gropu 3 management of instructionGropu 3 management of instruction
Gropu 3 management of instruction
 
Types of Instructional Materials
Types of Instructional MaterialsTypes of Instructional Materials
Types of Instructional Materials
 
Objective-Related Principles of Teaching
Objective-Related Principles of TeachingObjective-Related Principles of Teaching
Objective-Related Principles of Teaching
 
Types and Characteristics of Instructional Materials
Types and Characteristics of Instructional MaterialsTypes and Characteristics of Instructional Materials
Types and Characteristics of Instructional Materials
 
USING AND EVALUATING INSTRUCTIONAL MATERIALS
USING AND EVALUATING INSTRUCTIONAL MATERIALSUSING AND EVALUATING INSTRUCTIONAL MATERIALS
USING AND EVALUATING INSTRUCTIONAL MATERIALS
 
Ed. Tech. I Lesson 6:Using and Evaluating Instructional Materials
Ed. Tech. I Lesson 6:Using and Evaluating Instructional MaterialsEd. Tech. I Lesson 6:Using and Evaluating Instructional Materials
Ed. Tech. I Lesson 6:Using and Evaluating Instructional Materials
 
Management of instruction
Management of instructionManagement of instruction
Management of instruction
 
Instructional Materials in Mathematics
Instructional Materials in MathematicsInstructional Materials in Mathematics
Instructional Materials in Mathematics
 
Instructional Materials in Mathematics
Instructional Materials in MathematicsInstructional Materials in Mathematics
Instructional Materials in Mathematics
 
Commonly used materials in the classroom
Commonly used materials in the classroomCommonly used materials in the classroom
Commonly used materials in the classroom
 
Preparation and evaluation of instructional materials
Preparation and evaluation of instructional materialsPreparation and evaluation of instructional materials
Preparation and evaluation of instructional materials
 
Selecting and Use of Instructional Materials
Selecting and Use of Instructional MaterialsSelecting and Use of Instructional Materials
Selecting and Use of Instructional Materials
 
Instructional materials
Instructional materialsInstructional materials
Instructional materials
 
Strategic Planning Workshop
Strategic Planning WorkshopStrategic Planning Workshop
Strategic Planning Workshop
 

Similar to Surrey education case study

Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Managementgrahamelanders
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash PoolPick_Everard
 
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxDepartment X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxsalmonpybus
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxlesleyryder69361
 
Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxZiyad Zaidi
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementakashdhewale87
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectAllen Green
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability EngineerAngela Lopez
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCruzIbarra161
 

Similar to Surrey education case study (20)

Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Management
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Pmp4
Pmp4Pmp4
Pmp4
 
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxDepartment X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docx
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project management
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final Project
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated Projec
 

Recently uploaded

Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 

Recently uploaded (20)

Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 

Surrey education case study

  • 1. CASE STUDY (INC: PROJECT DISCUSSION AND ANALYSIS) School Nursery Refurbishment & Extension Author: GRAHAME LANDERS BSc(Hons) Building Surveyor Project Manager Issued: 26th August 2006
  • 2. Case Study Contents Author: Grahame Landers Building Surveyor Project Manager CONTENTS 1.0 INTRODUCTION 1 1.1 Property Description 1 1.2 Clients Brief 1 1.3 Contract Particulars 2 2.0 PRE CONSTRUCTION PHASE 3 2.1 Statutory Requirements and Application 3 2.2 Specification Preparation 4 2.3 Construction (Design & Management) Regulations 1994 4 3.0 CONSTRUCTION PHASE 5 3.1 Site Monitoring and Progress Meetings 5 3.2 Interim Payments and Compensation Events 5 3.3 Practical Completion 5 4.0 PROJECT MANAGEMENT APPRAISALS & SOLUTIONS THROUGHOUT 7 4.1 Planning Issues and Programme 7 4.2 Working in the School Term / Health & Safety Considerations 8 4.3 Existing Roof 9 4.4 Contract Administration / Contractual Issues 10 5.0 APPRAISAL AND ANALYSIS AT COMPLETION 12 5.1 Planning Issues 12 5.2 Building Control Issues 12 5.3 Form of Contract 13 5.4 Administering the NEC 13 5.5 Contractual Issues 14 5.6 Health & Safety / CDM 15 5.7 Overarching Analysis – Project Manager 15 6.0 CONCLUSION 16 APPENDIX A: Drawings APPENDIX B: Before & After Photographs
  • 3. Case Study Issue Date: August 2006 Page 1 Grahame John Landers 1.0 INTRODUCTION 1.1 Property Description The detached single storey nursery is located in a residential area of Surrey, and was constructed circa 1975. The nursery consists of WC, food preparation area, conservatory, store room and large and small teaching rooms. The building is of load bearing masonry construction with inner blockwork and external facing brickwork cavity wall. The floor is a reinforced cast in-situ concrete. The roof is flat. 1.2 Client’s Brief The Client was required to improve and update nursery facilities by complying with DfES Guidelines; DDA legislation and food preparation hygiene standards. Our brief was to assess and make recommendations on the Client’s requirement and to provide a cost appraisal of the proposed works. A Feasibility Report produced by another in- house Department recommended the following works: • New extension, to provide a ‘quiet room’. • Internal structural alterations to create an open plan main classroom. • Levelling of the internal floor for disabled usage and insert a new disabled WC. • External hard landscape remodelling for disabled access. • Separate food preparation area away from the children’s WC, for hygienic purposes. • General refurbishment and modernisation.
  • 4. Case Study Issue Date: August 2006 Page 2 Grahame John Landers 1.3 Contract Particulars • Contract Value: £200,000.00 • Contract: New Engineering Contract 2005, with: - • Core Clauses. • Strategy Option A: (Contractor prices for undefined work) • Secondary Options: - o X12 (Partnering). o X16 (Retention) • Actual Construction Period: 14 weeks • Actual Lead-in (2weeks): 22nd August 2005 – 3rd September 2005 • Actual Start On-site Date: 5th September 2005 • Actual Finish Date: 9th December 2005
  • 5. Case Study Issue Date: August 2006 Page 3 Grahame John Landers 2.0 PRE CONSTRUCTION PHASE 2.1 Statutory Requirements and Applications 2.1.1 Planning Requirements I prepared a Full Planning Application including existing and proposed AutoCAD drawings, for the new extension and remodelling of the external hard and soft landscaping. Following submission, I displayed site notices, for Public information. An objection to the development was raised by the adjacent neighbour. Consequently I was advised by Planning: - 1. Remodelling of the new extension footprint was required, to ensure the four meter buffer zone, which was imposed in the original Planning Approval Conditions, when the existing nursery was built in 1975, was respected. This 1975 condition was not known at prior to submitting the application. 2. The application would be determined at a public Committee meeting. Waiting a lengthy time period for the next Committee meeting, delayed the start on-site date. 2.1.2 Building Regulations Application I prepared, Full Building Regulation Plans Application, including existing and proposed CAD drawings. Key considerations were: - • DDA and internal disabled provisions. • Internal structural demolitions and alterations. • Thermal performance. • New extension including new rainwater drainage. • Fire Strategy (new fire/smoke alarm system, emergency lighting, escape routes).
  • 6. Case Study Issue Date: August 2006 Page 4 Grahame John Landers 3.2 Specification Preparation As the Client appointed a Partnering Contractor, without formal Tender procedures, production of Tender Documents was not necessary. Instead, I produced a specification that included Materials and Workmanship clauses and a Schedule of Works. 2.3 Construction (Design & Management) Regulations 1994 As lead designer, I advised the Client that the project came under the remit of the CDM Regulations 1994, as: - • The project would exceed 30 working days. • More than five people would be on site at any one time. • The works entailed demolition. The Client appointed a competent person to undertake Planning Supervision duties. To aid the PS in the production of the Plan I forwarded all project information. The PS requirements were included in the Plan Prelims - the works would only be ‘Practically Complete’ once all H&S File information had been received.
  • 7. Case Study Issue Date: August 2006 Page 5 Grahame John Landers 3.0 CONSTRUCTION PHASE 3.1 Site Meetings and Monitoring Progress I chaired monthly site meetings throughout the course of the programme. During these meetings, I dealt with all technical queries, contractual issues, compensation events, etc. I used the Contractor’s programme, when monitoring progress, by comparing the actual completed site works against the programmes, activity time durations. Also during the monitoring meetings I assessed and advised on the quality of workmanship. 3.2 Interim Payments and Compensation Events The Contractor submitted monthly valuations for works undertaken to date of submission, which I checked and produced certificates. Due to the time taken to confirm my site instructions, through Compensation Events, which under the NEC can take up to 13 weeks (if a revised quote was not asked for), proved impractical for the original 12 week programme. Through trust and partnering (NEC X12), the Contractor immediately undertook my site instructions. 3.3 Practical Completion 3.3.1 Health & Safety File, Handover and Practical Completion Certification Prior to programme completion date, I contacted the PS to discuss the information that the Contractor would need to supply, for the H&S File. The PS’s request included: - • List of all sub-Contractors and their specialist applications. • List of all specialist materials supplied. • Certificates, warranties and guarantees. During the formal handover meeting, with the Client in attendance, I undertook a final snag inspection and on being satisfied with the quality of workmanship and there being zero defects, I advised the Client and PS that all works were complete.
  • 8. Case Study Issue Date: August 2006 Page 6 Grahame John Landers After reviewing the H&S File contents with the PS and being satisfied with the contents, I prepared the Practical Completion Certificate, which included the 12-months defects liability period expiry date. 3.3.2 Final Account On agreement of the Final Account, the Contractor issued an invoice for payment to the Client. Half of the 5% retention which was kept during the course of the contract was released, and added to the Final Account. The other 2.5% of the total cost of the works was withheld for the defects liability period.
  • 9. Case Study Issue Date: August 2006 Page 7 Grahame John Landers 4.0 PROJECT MANAGEMENT APPRAISALS & SOLUTIONS THROUGHOUT The following section identifies particular key issues which I was involved. In each case I have looked at the reasons for the course of action selected and why I dismissed alternatives. 4.1 Planning Issues and Programme As the adjacent neighbour objected to the development, the Planning decision had to be held in public, by Committee. As next Committee meeting was 4 weeks into the programme along with the Contractors lead-in time meant that works would not start at the beginning of the summer holidays and house the nursery in the hall for four weeks as originally planned but at the commencement of the new term. Consequently the nursery services would not have accommodation, throughout the works duration. To have all the project duration in term time was too long for the Nursery to be without adequate facilities. Options available and choice made 1. Postpone the Project until 2006 Summer Holidays. This option meant the works would not be undertaken during the teaching year and they could continue using the existing nersury facilities. However, it would pose problems to the Client’s funding arrangements and the costs would incur interest. 2. Look for Alternative Accommodation within the Vicinity of the School (i.e. Church Hall). To avoid financial issues associated with option 1 and to prevent postponement, moving the nursery services into a suitable alternative accommodation would allow the nursery to function to DfES guidelines. The nursery would be detached from the school and costs would be incurred from renting a suitable building for the works duration. 3. Provide a Temporary Modular Unit, with Associated Services, Located on the Nursery Site. This option meant the nursery would remain on its existing site, function to DfES guidelines and not be detached from the school. However, costs would be incurred costs from the hire and fit out to DfES criteria and Planning approval. I recommended option 3, to which the Client agreed.
  • 10. Case Study Issue Date: August 2006 Page 8 Grahame John Landers 4.2 Working in School Term Time / Health & Safety Considerations In addition to the disruption to school and nursery teaching, caused by noisy works and site operations, I also identified the following major H&S issues: - • An access path and the playground abutted the nursery building. • The Contractor would be in partial occupation of the nursery site, with the nursery (housed within the modular unit) occupying the other side. • A designated Contractor’s storage area was to the other side to the only school / nursery entrance. Options available and choice made 1. Postpone the Project until 2006 Summer Holidays: This avoided H&S risk to the children and disruption to teaching, but costs would gain interest and cause problems to the Client’s annual funding. 2. Out of Hours Working. To avoid problems associated with option 1, the Contractor working weekends, before and after school hours would mean no disruptions to teaching, the children could use the tarmac playground during winter and transporting materials across the only school / nursery entrance would not prevent access, especially during the children’s drop off and pick up times. However, working out of hours would gain additional costs, possible neighbour disputes and gaining tradesmen. 3. Provide a Perimeter Barriers and Ensure Deliveries and Noisy Works are Undertaken Out of Hours: In providing a high metal gate across the access path with a lock, hoardings between the modular unit and the nursery building, having a zoned hoarded perimeter area in the playground and enforcing out of school hours of deliveries, noisy works and transportation of materials would prevent teaching disruptions. However, this option needed careful programming by the Contractor. I recommended option 3, to which the Client agreed. I requested method statements and risk assessments from the Contractor.
  • 11. Case Study Issue Date: August 2006 Page 9 Grahame John Landers 4.3 Existing Roof Works to the existing roof was not originally included in the feasibility works. In reviewing the requirement of thermal performance and ventilation it became known by Client that replacement of the existing roof covering was planned to be undertaken in the near future. I therefore put a number of option appraisals, to the Client. Options available and choice made 1. Cold Roof Construction: Provide a 25mm diameter ventilation gaps to the soffits and 200mm thick insulation quilt to the void. However, the advantages of saving money from using the elevation scaffold access to the roof during these works would be lost and further disruption to the nursery would occur in the near future. 2. Warm Roof Construction: Remove the covering and provide new tapered insulation above the deck with a new covering. This option, took advantage of the scaffolding, the replacement covering would have the same life span and 20 year warranty as the new extension covering. The tapered insulation would provide good falls to gutters through its service life, thus preventing ponding and no future planned works. However, the existing roof and the new extension cold roof would be of a different construction and the existing upstands would need to be built-up to accommodate the tapered insulation. 3. Cold Roof Construction and New Roof Covering: In consideration of the limited Client’s additional funds, keeping the new and existing roof constructions the same (cold) and the near future planned covering replacement, this third option, was a comprise between options 1 and 2, by providing 25mm diameter ventilation gap, 200mm thick insulation quilt and covering replacement. Discussions with the Contractor to establish timelines of undertaking the each of the above options on-site, along with Building Control decision time was added to my calculated design time. Each option timeline was determined and also put forward to the Client. I recommended option 3, to which the Client agreed to the timeline and provided additional monies for the works along. My additional specification and design was approved by Building Control.
  • 12. Case Study Issue Date: August 2006 Page 10 Grahame John Landers 4.4 Contract Administration / Contractual Issues Over the course of the project a 6 week delay occurred to the programme. I needed to evaluate the amount of extension of time, I could grant to the Contractor. Options available and choice made Risks to the original programme included - 1. Neighbours’ Objection to the Development: This caused my Planning Application to be decided by the Planning Committee, held in public. As the next Committee meeting was four weeks into the programme, the start on-site date was delayed. Total delay of 4 weeks. 2. Breach of Structural Engineers Foundation Design. The Contractor in undertaking the new extension foundation excavations did not adhere to the Structural Engineer’s design, as more of the existing in-situ reinforced foundation, was removed. The design allowed for the new foundations to be supported and joined to the existing. The Structural Engineer need to check / revise his design and for Building Control acceptance, caused a total delay of 2 weeks for the new quiet room extension works. 3. Additional Works: The works to upgrade the existing roof to include new insulation, new cross internal ventilation, new roof covering, caused an on-site total delay of 2 weeks. Impact from Delays upon the Programme and Resulting Extension of Time • The critical path was affected by adjacent neighbour objecting to my Planning application. It meant the application needed to be decided upon by the Planning Committee, whose next meeting was four weeks in to the original programme. This delayed the original date for the Contractor’s lead-in time by 4 weeks. I advised the Contractor early enough to prevent any programme delays and delay costs from being occurred. The Contractor did not raise an ‘early warning’ notice.
  • 13. Case Study Issue Date: August 2006 Page 11 Grahame John Landers • The Contractor’s error in removing more existing foundation did not affect the critical path. The critical path at that stage was undertaking the internal strip out and not the building extension works. The Contractor did not raise an ‘early warning’ notice. • The additional works to upgrade the roof did affect the critical path. The site works added an extra 2 weeks on to the construction phase programme. The Contractor did raise an ‘early warning’ notice. I therefore decided that the 2 week delay resulting from the additional on-site roofing works was not the Contractor’s fault and an extension of time, could be granted. The Client agreed. I issued a ‘Compensation Event’. The original programme was delayed by a total 6 weeks, due to the Planning Application objection by the neighbour and from the additional roofing works.
  • 14. Case Study Issue Date: August 2006 Page 12 Grahame John Landers 5.0 APPRAISAL AND ANALYSIS AT COMPLETION The following section is a critical analysis of my project involvement. Where appropriate I have identified lessons learnt, reflective learning and professional development. 5.1 Planning Issues I gained additional Planning experience when the neighbour objected to the development. The original extension layout was unknowingly in breach of the original 1975 planning consent condition as it did not maintain a four meter buffer zone. This experience was in the way objections were dealt with at Committee level. Although, remodelling of the new extension to be 4 meters away from the neighbour’s boundary was an easy AutoCAD exercise, the objection caused a four delay to the start date and caused disruption to nursery and school. Forward and flexible thinking was important to minimise major problems, especially advising the Client that a temporary modular unit was a solution. 5.2 Building Control Issues I had to ensure that all proposed works met the requirements of the Building Regulations and in addition the unforeseen works. This exposure to in achieving compliance increased my knowledge of the Building Regulations, but also how Building Control Officers operate and how they administer the Building Regulations. I also learnt that by establishing a close relationship with Building Control Officers limits delays. In providing option appraisals for undertaking replacement of the existing roof covering, I demonstrated to the Client the advantages of bringing forward the replacement works and incorporating them within the project. In formulating recommendations, I learnt how to communicate effectively in writing.
  • 15. Case Study Issue Date: August 2006 Page 13 Grahame John Landers 5.3 Form of Contract In using the NEC, I realised that there were many advantages to this Contract as oppose to the traditional contracts, as ‘Early Warning’ highlighted problems to time, quality and finances at an early stage, ‘Compensation Events’ provide final account figure during the works and the X12 (Partnering) drives parties to mutually achieve the project aim and goals. Although I was not involved in the recommendation for the NEC, which is a contract suited for most major Engineering and Building works, I have since reflected reflect upon the importance of advising the Client on a Contract that is best suited to a project’s scope, budget, complexity and programme. A suitable contract for this project, is the JCT, Intermediate Form of Contract 1998, as guidance given in the Practice Note 5, (Series 2), states the IFC is usable where: - • Value of the works up to £375,000.00 (2003 prices). • Contract period does not exceed 12 months. • Works are not complex or requiring complex trades. Normal NEC practices require the need of multiple staff. Whilst acting as Project Manager (under delegated powers); Designer, Building Surveyor, AutoCAD Technician, Administrator of the Contract, co-ordinator of the Structural Engineer and M&E Consultations, it became very onerous. I soon learnt that managing staff and information is essential, to ensure smooth running of an NEC project. 5.4 Administering the NEC I identified a major problem during the course of the works that it can take up to 13 week to confirm my site instruction through a Compensation Event. As the actual works on-site lasted for 14 weeks it would result in the majority of variations being dealt with at the end of the project. I discussed this issue with the Contractor, who agreed to undertake my site instructions once I had given them in writing.
  • 16. Case Study Issue Date: August 2006 Page 14 Grahame John Landers Chairing meetings not only gave me the experience of co-ordinating all parties involved with the project but also further developed my interpersonal skills. I recognised the importance of preparing meeting minutes to keep interested parties and client informed of events taking placing on site and to clearly communicate any action points to the relevant parties. Monitoring costs throughout the course of the project enabled me to decide if additional costs were accommodated within the project costs. It also allowed me to regularly advise the client on remaining contingency funds, additional costs and the project final account. Through monitoring the progress of the works, I gained experience of assessing a contractor programme and acquired practical knowledge of the length of time certain construction tasks may take. This has assisted me when advising the client as estimated construction time the project. 5.5 Contractual Issues With the refurbishment and the new extension not being completed to programme, I acquired an understanding of the importance of closely monitoring a contractor’s progress and performance. From this, I recognise the importance of gaining a detailed explanation of the reason(s) why a contractor is not meeting the programme and analysing the events in the Critical path would necessitate the need to hold a review meeting. 5.6 Health & Safety / CDM Due to the revised start date, being at the start of the teaching calendar, the H&S of the staff and children became paramount. Through undertaking a Risk Assessment, I was able to identify the hazards and what best options to nullify or reduce the risk. This exercise has increased my awareness of H&S issues. In complying with Regulation 14 of CDM, and providing Risk Assessments has enabled further understanding of how my design could be built with health and safety problems. Through, analysing potential risk has further improved my design abilities,
  • 17. Case Study Issue Date: August 2006 Page 15 Grahame John Landers 5.7 Overarching Analysis - Project Manager The assistance of M&E designer; Structural Engineer; in-house Quantity Surveyor and Planning Supervisor has been invaluable in ensuring the project during the pre and post contract phases, meet the project objectives and aims. My proactive management approach of the project team (including the Contractor and Building Control) and co-ordination of all their information was therefore successful. Working within the education sector has enabled me to gain a fundamental understanding and experience of DfES guidelines and criteria in providing nursery facilities, suitable for children’s usage and educational development.
  • 18. Case Study Issue Date: August 2006 Page 16 Grahame John Landers 6.0 CONCLUSION This case study (including appraisal and analysis) has focused upon my involvement during the three construction phases to refurbish and improve the existing nursery facilities. Experience gained throughout this project has enabled me to further develop my understanding and knowledge of statutory, technical and construction matters. For example the planning issues and unexpected poor thermal performance of the existing building construction that both involved extra costs and posed risks to the project programme. When situations arose I would research the options from various sources of information (e.g. legislation, textbooks, line management, etc.) to determine the best course of action. My proactive approach in resolving site issues quickly prevented undue delay and cost to the programme where possible. The refurbishment and improvement met with the Client’s expectations and aim by meeting current guidelines; standards; legislation and appearance. The project is currently in the Post Construction Phase which includes the 12 months defects liability period.
  • 19. Case Study Issue Date: August 2006 Appendix A Grahame John Landers APPENDIX A DRAWINGS
  • 20.
  • 21.
  • 22. Case Study Issue Date: August 2006 Appendix B Grahame John Landers APPENDIX B BEFORE & AFTER PHOTOGRAPHS
  • 23. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 2: Front elevation and step access at Feasibility PHOTO 3: Front elevation and ramp access at Practical Completion
  • 24. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 4: Toilets at Feasibility PHOTO 5: Refurbished toilets at Practical Completion
  • 25. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 6: Food preparation located in toilet area at Feasibility PHOTO 7: Ambulant disabled toilet located in former food preparation area at Practical Completion
  • 26. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 8: Store room at Feasibility PHOTO 9: New kitchen located in former store room area at Practical Completion
  • 27. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 10: Conservatory / classroom partition and step at Feasibility PHOTO 11: Removed conservatory / classroom partition and step at Practical Completion
  • 28. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 12: Existing roof covering at Feasibility PHOTO 13: New roof coverings at Practical Completion
  • 29. Case Study Issue Date: August 2006 Appendix B Grahame John Landers PHOTO 14: Existing hard & soft landscaping at Feasibility PHOTO 15: Remodelled hard & soft landscaping at Practical Completion