Executive Summary Report
of Whistler Ski project
PJM6025 Project Scheduling & Cost Plan
Instructor: Donald Columbare
Student: Maria Hu (Yue Hu)
College of professional Studies
Northeastern University
Agenda
 Introduction (updated information)
 Revised information
 Revised Project Scope and Objective for Stage 1
 Current Schedule Status and Forecast
 Current Cost Status and Forecast
 Current Issues and Actions
 References
Introduction (Project Status Report)
 Based on stockholders’ and executive board’s requirement, project team of
Whistler Ski stage one decided to change the project plan to satisfy demands,
increase the efficiency of the team and decrease the total cost for next two
stages of the project.
 Project manager set the baseline to 10/20/16
 The Project Status Date is 8/17/17
The original finish date is 10/17/17.
The project just pass one month and 13 tasks was be completed 100 percentage.
The total cost will increase to 541,580 dollars, whereas the original cost is
527,160 dollars.
The schedule will be delay around 9 days due to several task be delayed and the
speed is slower than expected.
The cost risks and delay risks will be increase because below reasons.
Cooperation barriers with different clients
Delay frequently happened in installing, electrical, plumbing activities due
to technical issues
Communication issues in Generator Suppliers.
Revised information
 There is several tasks already be completed (Please see notice for part of completed
tasks).
Revised information
 These incomplete tasks be changed through adjusting the duration
WBS Task Mode Task Name Duration Start Finish Predecessors Resource Names Cost Start Slack % Complete
1.1.1 Auto Scheduled
1.1.1 Publish the
Project Plan
12 days
Mon
4/17/17
Tue 5/2/17 Project manager $5,280.00 0 days 100%
2.1.1 Auto Scheduled
2.1.1 Build the Main
Entrance Road
12 days
Mon
4/24/17
Tue 5/9/17 3SS+5 days
BigDawg Paving Company
for Main Road
[$16,500.00]
$16,500.00 12 days 0%
3.1.3 Auto Scheduled
3.2.1 Clear the sites
for Day lodge
10 days
Wed
5/10/17
Tue
5/23/17
7 Tom $3,200.00 12 days 0%
3.1.4 Auto Scheduled
3.1.3 Construct
Foundation for the Day
Lodge
14 days
Wed
5/24/17
Tue
6/13/17
12,13 Joe's Foundation Company $10,080.00 0 days 86%
3.2.1 Auto Scheduled
3.2.2 Construct the
Main Frame Work for
Day Lodge
24 days
Wed
6/14/17
Tue
7/18/17
14
Ski Lodge Specialty
complete the Day Lodge
mainframe work
[$125,000.00]
$125,000.00 0 days 100%
4.1.4 Auto Scheduled
7.1.3 Build the
Foundation for the
Generator House
12 days
Wed
5/24/17
Fri 6/9/17 14SS Joe's Foundation Company $8,640.00 53 days 0%
4.2.1 Auto Scheduled
7.2.2 Build the Main
Framework for
Generator House
16 days
Mon
6/12/17
Mon 7/3/17 31
Pete and Sons
Co.[$35,000.00]
$35,000.00 53 days 0%
5.1 Auto Scheduled
8.1 Clear the Parking
Lot
14 days
Wed
5/10/17
Tue
5/30/17
7
BigDawg Paving Company
for Parking Lot
[$20,000.00]
$20,000.00 100 days 0%
Revised Project Scope and Objective
for Stage 1
 Whistler Ski Association will construct another Ski Lodge and Ski complex.
 The project deliverables for the revised first stage
 project plan
 roads
 day lodge
 generator house
 parking lot
 The duration of the first stage changes from the original 140 days to 131 days.
 The total cost for the first stage should match 541,580 dollars and below ten-
million dollars.
Current Schedule Status and Forecast
 Based on the calculation through project formulas, the total project is completed 43%. According for the
original plan, the project delay and behind the original plan. The revised finish data is 10/30/17. The revised
estimated number of days is 131 days and delay at least 9 days from the original end date. The planed value
of the work is 200,800 dollars, and 122,161.65 dollars was earned. Earned value schedule variance shows
the difference in cost terms between the current progress and the baseline plan of a task, all assigned tasks
of a resource, or for an assignment up to the status date or today’s date (SV= 78,638.35 dollars).
 Conclusion and Forecast
 The scope creep will happened
 The delay should be happened.
 The total delay of the project should over nice days.
 Reconsider the original schedule for increase the efficiency of each task managers.
 Project team did not do a valuable work as the original expectations.
 Add more supervisors for following up these tasks be completed on time.
 Obtain feedbacks from task managers
 Add additional resources or cut unnecessary works for managing the project schedule.
Current Cost Status and Forecast
 I think that the project cost are over budget, because the earned value cost variance is negative. The
actual costs is 124,276 dollars. Only 122,161.65 dollars earned for current works. The earned value
schedule variances show negative value between plan value and earned value.
 Conclusion and Forecast
 Project manager underestimate the cost of these works at this time.
 The actual costs over the plan cost, which will bring the project into financial difficult.
 Project manager need to re-consider the payment for these resources.
 Project manager also need to focus on important task.
 The quality of the project need to be worried.
 Project manager need to communicate with stakeholders to reduce the future cost in financial budgets.
 Ask for abundant financial supports from stakeholders, executive board and clients.
Current Issues and Actions
Code Issue/Risk Action
1The Critical Path have been changed. There is only two
activities on the Critical Path.
Report the changes to stakholders and notice the delay of the two important activities. Follow up Jerry to make sure he can
complete the task on time. Increase the speed to complete the construct the main frame work for Day Lodge task.
2The Cost of Day Lodge increase due to only 45 % be
completed for installing plumbing for Day Lodge
Add human resources for Jerry to complete the task on time. Reduce the hourly payment as punishment for helping Jerry
to catch up
3The Schedule of install plumbing for Day Lodge delay Ask the reason for the delay. Assign new resource for help. Increase the daily working hours
4The cost of project plan increase due to two days delay Fixed the cost of publish the plan with penalty if the plan be delayed
5The cost of build the main entrance road increase due to 6 day
extra work
Start when the project plan be published without five day delay. Add more valuable company for helps about the extra six
days
6The cost increase for day lodge due to delay in both clear and
construct
Add more human resources for help Tom to clear the sites. Ask Joe's foundation company to add any other company for
cooperation
7The cost increase of Generator house due to the delay of build
the foundation
Add more resouces for help Joe's foundation complete the task in a valuable way.
8The schedule delay of Generator house due to start to start
relationship in construct foundation for the Day lodge
Change the start to start to finish to start to give changes to Joe's foundation company to fouces on quality rather than take
risk to redo
9The delay of construct the main frame work for Day Lodge
bring negative impact on complete final construction for Day
lodge
Ask Ski Lodge specialty for extra work hours per day. Add other company for help.
10Although the duration of build the main framework for
genertor house has been changed, project manager never
change the payment for Pete and Son Co.
Tell Pete and Son Co. what's going on. Increase the payment for the company.
11Although the duration of the clear parking lot is reduced, the
fix cost of the activity never be changed
Tell DigDawg Paving Company for changing the days. Ask for reducation of payment
12Consolidated electrical is overcommitted with other clients
and only 60 % completed
Ask for accelaration of the process. Hiring other company for helps.
13The plumber ran into technical issues and delay the
installation
Ask technical experts for helps. Change the plumber to more sophisticated one.
14Delay of electical and plumbing activities Add more professonal employees. Supervise the quality of these tasks.
15The Delay of Generator house due to suppliers Change the suppliers. Add more suppliers for helps. Reduce the suppliers' payment for the delay.
References
 Institute, P. M. (2011). Practice standard for earned value management (2th
ed.).
 Institute, P. M. (2011). Practice standard for Scheduling (2th ed.).
 Larson, E. W. & Gray, C. F. (2013). Project management: The managerial
process (6th ed.).
 Wk 5 Lecture Earned Value Management Tutorial
 Wk 5 Lecture Baseline, Change Control and Progress Reporting
 Wk 5 Lecture Measuring Performance

More Related Content

Similar to Executive Summarization (Maria Hu)

The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...Association for Project Management
 
Contractor Proposal Template PowerPoint Presentation Slides
Contractor Proposal Template PowerPoint Presentation SlidesContractor Proposal Template PowerPoint Presentation Slides
Contractor Proposal Template PowerPoint Presentation SlidesSlideTeam
 
Real Estate Proposal PowerPoint Presentation Slides
Real Estate Proposal PowerPoint Presentation SlidesReal Estate Proposal PowerPoint Presentation Slides
Real Estate Proposal PowerPoint Presentation SlidesSlideTeam
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
PT2520Statement of Work · History· Scope· Constraints.docx
PT2520Statement of Work · History· Scope· Constraints.docxPT2520Statement of Work · History· Scope· Constraints.docx
PT2520Statement of Work · History· Scope· Constraints.docxamrit47
 
Business Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesBusiness Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesSlideTeam
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsSachin Melwani
 
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxProject ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxbriancrawford30935
 
Material movement in a manufacturing plant
Material movement in a manufacturing plantMaterial movement in a manufacturing plant
Material movement in a manufacturing plantAmit Kumar
 
Business Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation SlidesBusiness Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation SlidesSlideTeam
 
Focused performance
Focused performance Focused performance
Focused performance Lou Russell
 
Multiple Project template.pptx
Multiple Project template.pptxMultiple Project template.pptx
Multiple Project template.pptxAdilPatel34
 
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docxFIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docxRAJU852744
 
BSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docxBSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docxstudywriters
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxRebeccaEdwards88
 
Process Improvement Project official
Process Improvement Project officialProcess Improvement Project official
Process Improvement Project officialPhilip Spottswood
 
HVAC Financing at Penn South - 2013 Presentation
HVAC Financing at Penn South - 2013 PresentationHVAC Financing at Penn South - 2013 Presentation
HVAC Financing at Penn South - 2013 Presentationpennsouthoffice
 

Similar to Executive Summarization (Maria Hu) (20)

The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...
 
Contractor Proposal Template PowerPoint Presentation Slides
Contractor Proposal Template PowerPoint Presentation SlidesContractor Proposal Template PowerPoint Presentation Slides
Contractor Proposal Template PowerPoint Presentation Slides
 
Final Review
Final ReviewFinal Review
Final Review
 
Real Estate Proposal PowerPoint Presentation Slides
Real Estate Proposal PowerPoint Presentation SlidesReal Estate Proposal PowerPoint Presentation Slides
Real Estate Proposal PowerPoint Presentation Slides
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
PT2520Statement of Work · History· Scope· Constraints.docx
PT2520Statement of Work · History· Scope· Constraints.docxPT2520Statement of Work · History· Scope· Constraints.docx
PT2520Statement of Work · History· Scope· Constraints.docx
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
 
Business Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation SlidesBusiness Proposal Powerpoint Presentation Slides
Business Proposal Powerpoint Presentation Slides
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisons
 
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxProject ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
 
Material movement in a manufacturing plant
Material movement in a manufacturing plantMaterial movement in a manufacturing plant
Material movement in a manufacturing plant
 
Business Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation SlidesBusiness Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation Slides
 
Focused performance
Focused performance Focused performance
Focused performance
 
Multiple Project template.pptx
Multiple Project template.pptxMultiple Project template.pptx
Multiple Project template.pptx
 
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docxFIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
 
TEAM LEADERSHIP
TEAM LEADERSHIPTEAM LEADERSHIP
TEAM LEADERSHIP
 
BSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docxBSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docx
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Process Improvement Project official
Process Improvement Project officialProcess Improvement Project official
Process Improvement Project official
 
HVAC Financing at Penn South - 2013 Presentation
HVAC Financing at Penn South - 2013 PresentationHVAC Financing at Penn South - 2013 Presentation
HVAC Financing at Penn South - 2013 Presentation
 

Executive Summarization (Maria Hu)

  • 1. Executive Summary Report of Whistler Ski project PJM6025 Project Scheduling & Cost Plan Instructor: Donald Columbare Student: Maria Hu (Yue Hu) College of professional Studies Northeastern University
  • 2. Agenda  Introduction (updated information)  Revised information  Revised Project Scope and Objective for Stage 1  Current Schedule Status and Forecast  Current Cost Status and Forecast  Current Issues and Actions  References
  • 3. Introduction (Project Status Report)  Based on stockholders’ and executive board’s requirement, project team of Whistler Ski stage one decided to change the project plan to satisfy demands, increase the efficiency of the team and decrease the total cost for next two stages of the project.  Project manager set the baseline to 10/20/16  The Project Status Date is 8/17/17 The original finish date is 10/17/17. The project just pass one month and 13 tasks was be completed 100 percentage. The total cost will increase to 541,580 dollars, whereas the original cost is 527,160 dollars. The schedule will be delay around 9 days due to several task be delayed and the speed is slower than expected. The cost risks and delay risks will be increase because below reasons. Cooperation barriers with different clients Delay frequently happened in installing, electrical, plumbing activities due to technical issues Communication issues in Generator Suppliers.
  • 4. Revised information  There is several tasks already be completed (Please see notice for part of completed tasks).
  • 5. Revised information  These incomplete tasks be changed through adjusting the duration WBS Task Mode Task Name Duration Start Finish Predecessors Resource Names Cost Start Slack % Complete 1.1.1 Auto Scheduled 1.1.1 Publish the Project Plan 12 days Mon 4/17/17 Tue 5/2/17 Project manager $5,280.00 0 days 100% 2.1.1 Auto Scheduled 2.1.1 Build the Main Entrance Road 12 days Mon 4/24/17 Tue 5/9/17 3SS+5 days BigDawg Paving Company for Main Road [$16,500.00] $16,500.00 12 days 0% 3.1.3 Auto Scheduled 3.2.1 Clear the sites for Day lodge 10 days Wed 5/10/17 Tue 5/23/17 7 Tom $3,200.00 12 days 0% 3.1.4 Auto Scheduled 3.1.3 Construct Foundation for the Day Lodge 14 days Wed 5/24/17 Tue 6/13/17 12,13 Joe's Foundation Company $10,080.00 0 days 86% 3.2.1 Auto Scheduled 3.2.2 Construct the Main Frame Work for Day Lodge 24 days Wed 6/14/17 Tue 7/18/17 14 Ski Lodge Specialty complete the Day Lodge mainframe work [$125,000.00] $125,000.00 0 days 100% 4.1.4 Auto Scheduled 7.1.3 Build the Foundation for the Generator House 12 days Wed 5/24/17 Fri 6/9/17 14SS Joe's Foundation Company $8,640.00 53 days 0% 4.2.1 Auto Scheduled 7.2.2 Build the Main Framework for Generator House 16 days Mon 6/12/17 Mon 7/3/17 31 Pete and Sons Co.[$35,000.00] $35,000.00 53 days 0% 5.1 Auto Scheduled 8.1 Clear the Parking Lot 14 days Wed 5/10/17 Tue 5/30/17 7 BigDawg Paving Company for Parking Lot [$20,000.00] $20,000.00 100 days 0%
  • 6. Revised Project Scope and Objective for Stage 1  Whistler Ski Association will construct another Ski Lodge and Ski complex.  The project deliverables for the revised first stage  project plan  roads  day lodge  generator house  parking lot  The duration of the first stage changes from the original 140 days to 131 days.  The total cost for the first stage should match 541,580 dollars and below ten- million dollars.
  • 7. Current Schedule Status and Forecast  Based on the calculation through project formulas, the total project is completed 43%. According for the original plan, the project delay and behind the original plan. The revised finish data is 10/30/17. The revised estimated number of days is 131 days and delay at least 9 days from the original end date. The planed value of the work is 200,800 dollars, and 122,161.65 dollars was earned. Earned value schedule variance shows the difference in cost terms between the current progress and the baseline plan of a task, all assigned tasks of a resource, or for an assignment up to the status date or today’s date (SV= 78,638.35 dollars).  Conclusion and Forecast  The scope creep will happened  The delay should be happened.  The total delay of the project should over nice days.  Reconsider the original schedule for increase the efficiency of each task managers.  Project team did not do a valuable work as the original expectations.  Add more supervisors for following up these tasks be completed on time.  Obtain feedbacks from task managers  Add additional resources or cut unnecessary works for managing the project schedule.
  • 8. Current Cost Status and Forecast  I think that the project cost are over budget, because the earned value cost variance is negative. The actual costs is 124,276 dollars. Only 122,161.65 dollars earned for current works. The earned value schedule variances show negative value between plan value and earned value.  Conclusion and Forecast  Project manager underestimate the cost of these works at this time.  The actual costs over the plan cost, which will bring the project into financial difficult.  Project manager need to re-consider the payment for these resources.  Project manager also need to focus on important task.  The quality of the project need to be worried.  Project manager need to communicate with stakeholders to reduce the future cost in financial budgets.  Ask for abundant financial supports from stakeholders, executive board and clients.
  • 9. Current Issues and Actions Code Issue/Risk Action 1The Critical Path have been changed. There is only two activities on the Critical Path. Report the changes to stakholders and notice the delay of the two important activities. Follow up Jerry to make sure he can complete the task on time. Increase the speed to complete the construct the main frame work for Day Lodge task. 2The Cost of Day Lodge increase due to only 45 % be completed for installing plumbing for Day Lodge Add human resources for Jerry to complete the task on time. Reduce the hourly payment as punishment for helping Jerry to catch up 3The Schedule of install plumbing for Day Lodge delay Ask the reason for the delay. Assign new resource for help. Increase the daily working hours 4The cost of project plan increase due to two days delay Fixed the cost of publish the plan with penalty if the plan be delayed 5The cost of build the main entrance road increase due to 6 day extra work Start when the project plan be published without five day delay. Add more valuable company for helps about the extra six days 6The cost increase for day lodge due to delay in both clear and construct Add more human resources for help Tom to clear the sites. Ask Joe's foundation company to add any other company for cooperation 7The cost increase of Generator house due to the delay of build the foundation Add more resouces for help Joe's foundation complete the task in a valuable way. 8The schedule delay of Generator house due to start to start relationship in construct foundation for the Day lodge Change the start to start to finish to start to give changes to Joe's foundation company to fouces on quality rather than take risk to redo 9The delay of construct the main frame work for Day Lodge bring negative impact on complete final construction for Day lodge Ask Ski Lodge specialty for extra work hours per day. Add other company for help. 10Although the duration of build the main framework for genertor house has been changed, project manager never change the payment for Pete and Son Co. Tell Pete and Son Co. what's going on. Increase the payment for the company. 11Although the duration of the clear parking lot is reduced, the fix cost of the activity never be changed Tell DigDawg Paving Company for changing the days. Ask for reducation of payment 12Consolidated electrical is overcommitted with other clients and only 60 % completed Ask for accelaration of the process. Hiring other company for helps. 13The plumber ran into technical issues and delay the installation Ask technical experts for helps. Change the plumber to more sophisticated one. 14Delay of electical and plumbing activities Add more professonal employees. Supervise the quality of these tasks. 15The Delay of Generator house due to suppliers Change the suppliers. Add more suppliers for helps. Reduce the suppliers' payment for the delay.
  • 10. References  Institute, P. M. (2011). Practice standard for earned value management (2th ed.).  Institute, P. M. (2011). Practice standard for Scheduling (2th ed.).  Larson, E. W. & Gray, C. F. (2013). Project management: The managerial process (6th ed.).  Wk 5 Lecture Earned Value Management Tutorial  Wk 5 Lecture Baseline, Change Control and Progress Reporting  Wk 5 Lecture Measuring Performance

Editor's Notes

  1. The original start date of the project is 4/17/17, while the project already passed one month. The original finish date is 10/17/17. The project already pass four monthes and 13 tasks was be completed 100 percentage. The total cost will increase to 541,580 dollars, whereas the original cost is 527,160 dollars. The schedule will be delay around 9 days due to several task be delayed and the speed is slower than expected. The cost risks and delay risks will be increase because below reasons. Cooperation barriers with different clients Delay frequently happened in installing, electrical, plumbing activities due to technical issues Communication issues in Generator Suppliers. Use bullets / short sentences to convey the project status report for the first paragraph.
  2. Install the electrical wiring for the Day Lodge is 60% completed Install plumbing is 45% completed
  3. The ten-million dollars includes first, second and third stages.
  4. Conclusion and Forecast The scope creep will happened due to these changes put current project in uncertainty situations. The project should be completed over 50 percent, whereas it only be completed 43 percent. The delay should be happened. The total delay of the project should over nice days. The planed value of these works over the actual earned value these works, which mean that the project manager need to reconsider the original schedule for increase the efficiency of each task managers. This is a negative result in schedule variance, which means that we are behind the schedule and we did not do a valuable work as the original expectations. Project manager need to add more supervisors for following up these tasks be completed on time. Project manager also need to obtain feedbacks from task managers to decide to add additional resources or cut unnecessary works for moving forward the project schedule.
  5. Conclusion and Forecast The earned cost value is negative 2,114.35 dollars, which means that project manager underestimate the cost of these works at this time. The actual costs over the plan cost, which will bring the project into financial difficult. Project manager need to re-consider the payment for these resources Project manager also need to focus on important task rather than assigning resources for less important task. The quality of the project need to be worried because that task managers are not valuable than expected. Project manager need to communicate with stakeholders and discuss the most practical ways to reduce the future cost in financial budgets. Ask for abundant financial supports in case of financial crash of the project.