Ministry of Water Resources & Electricity
Dams ImplementatIon UnIt
GENERAL DIRECTORATE OF PROJECTS
DAM COMPLEX OF UPPER
ATBARA PROJECT
Brief Introduction to Contracts& Planning Works
ENG.Awad Hamdan
Contracts & Planning Department
1.Contract
1.1 Definition:
A voluntary, deliberate, and legally binding agreement
between two or more competent parties
Contracts & Planning Department
1.Cotracts
1.2 Contract’s Essentials
• Offer
• Acceptance
• Objective
• Obligations
• Consideration
• Competent Parties
Contracts & Planning Department
2. Project
2.1 Definition
Set of one or more activities that should be
performed within a period of time , budget
and quality.
Contracts & Planning Department
Contracts & Planning Department
Project planning is the process that defines the project
activities and end products that will be performed and
describes how the activities will be accomplished. The
purpose of project planning is to define each major
task, estimate the time and resources required, and
provide a framework for management review and
control.
2. Project
2.3 Project Planning
Contracts & Planning Department
project planning activities Scope:
• To define the specific work to be performed and
goals that define and bind the project.
• to define the Estimates to be documented for
planning, tracking, and controlling the project.
• to define Commitments that are planned,
documented, and agreed to by affected groups.
• Project alternatives, assumptions, and constraints.
2. Project
2. Project
The planning process includes steps to estimate the
size of the project, estimate the technical scope of
the effort, estimate the resources required to
complete the project, produce a schedule, identify
and assess risks, and negotiate commitments.
Contracts & Planning Department
2. Project
Repetition of the previous steps is necessary to
establish the project plan. Typically, several
iterations of the planning process are performed
before a plan is actually completed.
Contracts & Planning Department
3. Construction Projects
3.1 Construction Project Parties
• Client (Employer)
• Consultant (Engineer)
• Contractor
3.2 Contractual Relationship Between Parties
• Employer-Consultant Contract
• Employer-Contractor Contract
Contracts & Planning Department
4. Project’s Constraints
Contracts & Planning Department
• Measurement Contract
• Lump-sum Contract
• Direct Labour Contract
• Cost Plus Contract
•
•
•
•
Based on Price Determination
5. Types of Contracts
Contracts & Planning Department
100%
• Lump-sum Contract
• Measurement Contract
• Cost Plus Contract
• Direct Labour Contract
0% 100%
5. Types of Contracts
0%
Contractor’s RiskType of ContractEmployer’s Risk
Contracts & Planning Department
Contracts & Planning Department
Measurement for payment of drilling holes in any
material will be made per linear metre actually drilled
and when specified per hole drilled for setting up the
drilling machine, shifting it from one borehole to
another, within the site limits, including erection,
dismantling and linking with energy and water sources.
No measurement is made for re-drilling when grouting is
carried-out by progress procedure.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
All boreholes stopped due to fault of the Contractor
before reaching the depth required by the Engineer will
not be considered for payment.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
Measurement for payment of water tests will be the
number of water tests satisfactorily carried-out in 5 m
sections or smaller than 5 m at the Engineer's request.
Measurement for drainage hole will be made on the
same basis as drilling.
Measurement of grouting work will be made per hole
drilled; when specified for handling and setting up the
grouting equipment and the removal of the same per
section grouted, and per kilo of dry material actually
injected.
6. MEASUREMENT AND PAYMENT Of Drilling Works
1. Drawings
2. Specification
3. Bills of Quantities
4. Conditions of Contract
5. Instructions to Tenderers
6. Soil Investigation Report
1.
2.
3.
4.
5.
6.
7. Contract’s Document
4.1
Contracts & Planning Department
4.2
7.
8.
9.
10.
7. Agreement
8. Letter of Acceptance
9. Memorandum of Understanding
10.Contractor’s Schedules
Contracts & Planning Department
7. Contract’s Document
‫ةةةةة‬ ‫ةةةةةةة‬ ‫ةةةة‬ ‫ةةة‬ ‫ةةةةة‬
‫ةةةةةةةة‬
‫ة‬‫ة‬‫ةةة‬
Contracts & Planning Department
Wishing you A Fruitful Training
Period at DCUAP
‫ةةةةةة‬ ‫ةةةة‬ ‫ة‬

More Related Content

What's hot

Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementApril Davies, MA, CAPM
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfilejbonvier
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESShivam Sood
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closuresunnycmui
 
Project End Report - Project Management template
Project End Report - Project Management template Project End Report - Project Management template
Project End Report - Project Management template Simon Misiewicz
 
Civil Supervisor
Civil SupervisorCivil Supervisor
Civil SupervisorShady Eid
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Bo Q Preamble Td2 3 Jan 20
Bo Q Preamble Td2 3  Jan 20Bo Q Preamble Td2 3  Jan 20
Bo Q Preamble Td2 3 Jan 20guest5980d0
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slidesDoreen Yeo
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
project planning of water management
 project planning of water management project planning of water management
project planning of water managementMir Mosharraf Hosain
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contractMaysam Ghaffari
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank Thomas Magatu
 

What's hot (20)

contract procedure
contract procedurecontract procedure
contract procedure
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Project closure
Project closureProject closure
Project closure
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closure
 
Project End Report - Project Management template
Project End Report - Project Management template Project End Report - Project Management template
Project End Report - Project Management template
 
Civil Supervisor
Civil SupervisorCivil Supervisor
Civil Supervisor
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Bo Q Preamble Td2 3 Jan 20
Bo Q Preamble Td2 3  Jan 20Bo Q Preamble Td2 3  Jan 20
Bo Q Preamble Td2 3 Jan 20
 
Coordinated project information (cpi)
Coordinated project information (cpi)Coordinated project information (cpi)
Coordinated project information (cpi)
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
project planning of water management
 project planning of water management project planning of water management
project planning of water management
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contract
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank
 

Similar to Dams Projects Planning Works

Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacksglibson rojer
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aForbes Chanakira
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfYeshiharegAlemu
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case studyFreelancelanders
 

Similar to Dams Projects Planning Works (20)

Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Running head PMPM .docx
Running head PMPM                                          .docxRunning head PMPM                                          .docx
Running head PMPM .docx
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
 
Project management
Project managementProject management
Project management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Dams Projects Planning Works

  • 1. Ministry of Water Resources & Electricity Dams ImplementatIon UnIt GENERAL DIRECTORATE OF PROJECTS DAM COMPLEX OF UPPER ATBARA PROJECT Brief Introduction to Contracts& Planning Works ENG.Awad Hamdan Contracts & Planning Department
  • 2. 1.Contract 1.1 Definition: A voluntary, deliberate, and legally binding agreement between two or more competent parties Contracts & Planning Department
  • 3. 1.Cotracts 1.2 Contract’s Essentials • Offer • Acceptance • Objective • Obligations • Consideration • Competent Parties Contracts & Planning Department
  • 4. 2. Project 2.1 Definition Set of one or more activities that should be performed within a period of time , budget and quality. Contracts & Planning Department
  • 5. Contracts & Planning Department Project planning is the process that defines the project activities and end products that will be performed and describes how the activities will be accomplished. The purpose of project planning is to define each major task, estimate the time and resources required, and provide a framework for management review and control. 2. Project 2.3 Project Planning
  • 6. Contracts & Planning Department project planning activities Scope: • To define the specific work to be performed and goals that define and bind the project. • to define the Estimates to be documented for planning, tracking, and controlling the project. • to define Commitments that are planned, documented, and agreed to by affected groups. • Project alternatives, assumptions, and constraints. 2. Project
  • 7. 2. Project The planning process includes steps to estimate the size of the project, estimate the technical scope of the effort, estimate the resources required to complete the project, produce a schedule, identify and assess risks, and negotiate commitments. Contracts & Planning Department
  • 8. 2. Project Repetition of the previous steps is necessary to establish the project plan. Typically, several iterations of the planning process are performed before a plan is actually completed. Contracts & Planning Department
  • 9. 3. Construction Projects 3.1 Construction Project Parties • Client (Employer) • Consultant (Engineer) • Contractor 3.2 Contractual Relationship Between Parties • Employer-Consultant Contract • Employer-Contractor Contract Contracts & Planning Department
  • 10. 4. Project’s Constraints Contracts & Planning Department
  • 11. • Measurement Contract • Lump-sum Contract • Direct Labour Contract • Cost Plus Contract • • • • Based on Price Determination 5. Types of Contracts Contracts & Planning Department
  • 12. 100% • Lump-sum Contract • Measurement Contract • Cost Plus Contract • Direct Labour Contract 0% 100% 5. Types of Contracts 0% Contractor’s RiskType of ContractEmployer’s Risk Contracts & Planning Department
  • 13. Contracts & Planning Department Measurement for payment of drilling holes in any material will be made per linear metre actually drilled and when specified per hole drilled for setting up the drilling machine, shifting it from one borehole to another, within the site limits, including erection, dismantling and linking with energy and water sources. No measurement is made for re-drilling when grouting is carried-out by progress procedure. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 14. Contracts & Planning Department All boreholes stopped due to fault of the Contractor before reaching the depth required by the Engineer will not be considered for payment. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 15. Contracts & Planning Department Measurement for payment of water tests will be the number of water tests satisfactorily carried-out in 5 m sections or smaller than 5 m at the Engineer's request. Measurement for drainage hole will be made on the same basis as drilling. Measurement of grouting work will be made per hole drilled; when specified for handling and setting up the grouting equipment and the removal of the same per section grouted, and per kilo of dry material actually injected. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 16. 1. Drawings 2. Specification 3. Bills of Quantities 4. Conditions of Contract 5. Instructions to Tenderers 6. Soil Investigation Report 1. 2. 3. 4. 5. 6. 7. Contract’s Document 4.1 Contracts & Planning Department
  • 17. 4.2 7. 8. 9. 10. 7. Agreement 8. Letter of Acceptance 9. Memorandum of Understanding 10.Contractor’s Schedules Contracts & Planning Department 7. Contract’s Document
  • 18. ‫ةةةةة‬ ‫ةةةةةةة‬ ‫ةةةة‬ ‫ةةة‬ ‫ةةةةة‬ ‫ةةةةةةةة‬ ‫ة‬‫ة‬‫ةةة‬ Contracts & Planning Department Wishing you A Fruitful Training Period at DCUAP ‫ةةةةةة‬ ‫ةةةة‬ ‫ة‬