10-3 Term Paper Submission QSO-680
Seminar in Project Management
QSO-680
Seminar in Project Management
Southern New Hampshire University
10-3 Term Paper Submission
Tower Replacement Parts Project
Katie M. O’Brien
June 3, 2014
I work for a company that produces super nickel alloy
powder for jet turbine engines. For use in this term paper I will
call this company Metal Powder. I am the continuous
improvement manager at Metal Powder. It was recognized in
early 2011 that our atomization tower cleaning process needed
to be streamlined to speed up cleaning time and decrease
internal process time to be able to produce more powder heats
in a year. The atomization tower is 60 feet tall and 24 feet in
diameter. Metal Powder produces three separate alloys. When
a new alloy is put in the schedule to be made Metal Powder
must tear down the atomization tower and clean every part and
the entire tower to a white glove inspection before beginning
the next alloy.
The tower cleaning is currently taking 3 to 4 days
depending on the amount of buildup of atomized powder on the
parts. As Metal Powders demand increases in the next six years
it is imperative that Metal Powder turn the tower around faster
and faster to gain additional capacity. Through the use of setup
reduction it has been determined that a total of 84 parts at a cost
of around $100,000 can reduce the cleaning time by one eight
hour shift. This is a gain of 3 more “heats” of powder every
clean. There are 10 to 12 cleanings per year which could be a
potential gain of 30 to 36 heats per year.
This application term paper will use the five phases of
project management to implement the use of the new parts and
ensure that the goal of saving one shift will be recognized. A
team was selected of operators, engineers, production
supervisor, continuous improvement, and maintenance
personnel to help manage the project as resources. The
breakdown of roles in the responsibility matrix is in Figure 1.
Figure 1: Responsibility Matrix
The project team created the Project Charter seen in Figure
2.
Figure 2: Project Charter
Project Information
Project Manager
Katie O’Brien
Project Sponsor
General Manager
Project Description
Determine and implement duplicate parts to be swapped out
during atomization tower cleaning to optimize process and
reduce downtime.
Project Scope
Business Purpose, Objectives and Goals:
Metal Powder demand is going to increase two fold by 2020.
To rise to this challenge Metal Powder must reduce downtime
and increase capacity.
Problem/Opportunity Statement:
The problem of
3 to 4 days of downtime during an atomization tower clean
affects
Production and Quality departments and capacity
The impact of which is
Downtime of 30 to 36 days per year to clean the tower
A successful solution would
Be to reduce tower cleaning time by one 8 hour shift to gain 30
to 36 heats per year.
Constraints
Inclusions:
All parts that are not permanently connected to the tower or by
a twisting fixture.
Exclusions:
Parts that are permanently affixed to the tower or are a safety
risk to remove and reinstall.
Key Assumptions:
Parts will be stored on site and cleaned external to the process
by production operations. All parts over 25 pounds will need a
plan for movement.
Project Dependencies:
This project is dependent on engineering and maintenance
support to execute storage locations along with an upgrade to
the 3rd floor airwall and any fixtures needed for transport of
parts of 25 pounds.
Key Risks and Key Issues:
Timing for installation of 3rd floor airwall along with quoting
and receipt of parts for management of storage and swap out of
parts.
Critical Success Factors
Critical Success Factor
Key Success Indicator
Action Steps to Assure Success
Decrease cleaning time by one eight hour shift
Cleaning time reduced to 3 days
Proper storage locations along with robust standard work to
ensure process runs smoothly
Stakeholder and User Description
Key Stakeholder Descriptions:
Key Stakeholder
Function Represented
Production
Cleaning of parts
Quality
Inspection
Maintenance
Repair
User Summary:
End User Types
Impact Description
Stakeholder
Operators
Will perform movement of parts, swap out and external cleaning
Production
Quality Personnel
Will review cleaning at intermediate steps and then at
completion
Quality
Approvals
Documented Project Charter approvals are required from
designated approvers.
Role/Name
Approval Date
Project Sponsor:
Production Manager:
(PROJECTinsight, 2014)
The project team prioritized the project as a must complete in
2014. This project is linked directly to capacity needs for
future demand. The project cost for materials will be $100,000;
additional cost will be in resources. The list of parts for
duplication can be seen in Figure 3.
Figure 3: List of parts to be replaced
The work breakdown structure for implementation of the
new parts and standard work is seen below in Figure 4.
Figure 4: Work Breakdown Structure
1.0
Tower Replacement Parts
1.1
Identify Parts to Replace
1.2
Order Parts
1.3
Determine part storage locations
1.6
Training
1.4
Install Air wall and racks
1.7
Collect
Data
1.8
Evaluate new times compared to previous cleaning times
1.6.1
Equipment
1.6.2
Production
1.6.3
Maintenance
1.8.1
Test & Measure
1.8.2
Support Process
1.1.1
Perform Set Up Reduction
1.2.1
Verify drawings are correct
1.2.2
Quote Parts
1.3.1
Quote & Replace air wall
1.3.2
Determine quality requirements for storage
1.5
Create standard work
Based on the work breakdown structure above the
following resource tasks have been distributed to the following
teams; Maintenance, Operator, Production Manager, Continuous
Improvement and Engineering. All resources were informed of
responsibilities in a project launch meeting. The responsibility
matrix was reviewed and agreed upon by all resources and
stakeholders. In addition, due to the importance of this project
Monday, Wednesday, Friday update meetings will be held at
8am. The frequency of these meetings may increase or decrease
depending on the status of the project. Timing and schedule are
of the utmost importance. Therefore the schedule is to be met
at all costs. The detail of the work breakdown structure is
being used to minimize scope creep along with the use of a
project charter.
The project is to be completed in three months with a
$100,000 already spent toward the replacement parts. Any
additional costs will be in the fabrication of storage racks, the
3rd floor air wall and labor.
Unfortunately due to the size and management structure of
Metal Powder only engineering and continuous improvement
will be working on this project fulltime. Resources from
Maintenance and Production will be pulled in as they are
needed. Due to the phases in the work breakdown structure this
should not create an issue for schedule. When standard work is
to be written and finalized all resources will be needed. All
parties or a representative will be required to be in update
meetings.
The project was launched on January 13, 2014 initial
stages of the project such as evaluation of part drawings and
quoting went well and was on time. As the project approached
the storage location evaluation issues with resources being
available to evaluate and determine these locations was not
available which delayed the determination of locations. The
project was able to execute the quotes and installation of the 3rd
floor air wall with support from maintenance at the same time
issues were developing with storage locations.
As of March 10, 2014 not all storage locations had been
determined. The sequence of tasks shifted slightly to ensure
that the scheduled was met. I met with quality to determine all
the locations for storage that were not acceptable from a quality
perspective. In addition maintenance evaluated all parts over
our 25 lb. lifting limit and created carts and lifting mechanisms
for easy install and transport to the tower and back to the
storage locations.
By March 31, 2014 determination of all storage locations
was complete. The next task for completion was standard work
which took the input of all stakeholders and resources.
Standard work was created not only for the safe swap out of all
parts and reinstallation but also for the cleaning of the parts
external to the tower cleaning process. This standard work
needed to be robust so a dry run of the replacement and
cleaning process was done to document with pictures and
understand the time and movement of parts and personnel that
would affect the success of ensure one shift of time was saved.
This process took longer than expected. The initial thought of a
dry run has not been captured in the project charter or scope.
This created scope creep for the project and a delay in the
schedule. It was however, recognized that this was a must do to
ensure that the parts were swapped our properly, safely and
ensure quality the first time.
Therefore, the schedule was extended on week to April 21,
2014 for completion. This caused an instant miss on the
schedule portion of the project and scope creep. But it was
recognized by all parties that this task could not be rushed.
Once standard work was solidified training of production and
maintenance regarding the standard work and equipment
utilization was performed and completed on time.
Once the standard work and training was completed the
new process was performed during the next turnaround which
was April 14, 2014. Data was collected for times studies and to
ensure that the deliverable of an 8 hour shift savings was
recognized. The tower clean was completed in less than 3 days,
in 69 hours to be exact on April 16, 2014. The project was
completed two days over schedule prior to the scope creep and 3
days ahead of the recalculated schedule.
See the project closure report in Figure 5 for the results of
the project based on deliverables and scope.
Figure 5: Project Closure Report
Project Name
Tower Replacement Parts
Date
April 17, 2014
Executive Sponsor
General Manager
Project Manager
Katie O’Brien
Schedule
Planned Start Date
January 13, 2014
Actual Start Date
January 13, 2014
Planned End Date
April 14, 2014
Actual End Date
April 16, 2014Appropriation History Fiscal Year
Amount
Funding Source(s)
2011
$100,000
Corporate
Scope VerificationRequirements Review
Yes
No
Explanation/Notes
Were the project objectives (expected outcomes) accomplished?
x
x
Were all Deliverables submitted and accepted?
x
x
Have all contracts been closed?
x
x
Have all final payments been made (i.e., invoices paid)
x
x
Has adequate knowledge transfer been completed?
x
x
Phases
Completion Date
Goals/Objectives
ResultsInitiation:
3rd Quarter 2013
Develop Project Charter and Project Management Plan.
Project approved.Planning:
March 2014
Develop storage locations
Slight scope creep during delay in the project sequence of tasks
changed.
March 2014
Change of Scope: Decided to do a dry run of standard work to
ensure process was correct. Not an original part of the plan.
Dry run complete and standard work edited and confirmed for
all stake holders.
Implementation:
April 2014
Fully deployed new standard work and part replacement
process.
Tower cleaning completed in 69 hours.
Closeout:
April 2014
Closeout of project
All standard work complete. Process being used going forward.
Project Sign Off
The signatures below certify that this project has been
completed in accordance to the specified budget, schedule,
scope, and achieved the intended outcome.
Stakeholders
Name: Signature
Date
Project Sponsor
(or Designee)
General Manager
April 20, 2014
Project Manager
Katie O’Brien
April 20, 2014
(State of New Mexico, 2011)
References
Larson & Gray. (2014). Project Management: The Managerial
Process. New York City, NY: McGraw Hill.
PROJECTinsight. (2014). 5 Basic Phases of Project
Management. Retrieved May 16, 2014, from PROJECTinsight:
http://www.projectinsight.net/project-management-basics/basic-
project-management-phases
State of New Mexico. (2011). Project Closure Example.
Retrieved May 28, 2014, from
www.doit.state.nm.us/pcc/docs/.../DoIT%20Project%20Closeout
.doc
1
FloorDescriptionCurrent StateFuture State
42 Piece Liner
4Liner
4Valve
4Valve
4Torit Filters
4Liner
3Liner
Main DeckBowling Ball
Main DeckSealing Door
Main DeckSight Port Pass Throughs
Main DeckSealing Door Cartridges
Main DeckLocking Pins & Cartridges
Main DeckFurnace Cones
Main DeckSealing Door Arm
6
Pressure Port (Hibon
Sensors)
$400
5Valve$500
5Elbow
5Cyclone Top
5Cyclone Body
5Cyclone Cone
5Valve
5Spool
5Can
5Valve$400
5Pressure ReliefStock Room
5
Flange and Hibon Port Sensor
Manifold
$3,000
4Top SectionIncluded in 25K
4Bellows$1,000
4Elbow
4Spacer
4Center Section
4Top Section
4Outlet Elbow
4Rupture DiskStock Room
4Probe$300
4Probe$300
3Pipe$3,600
3Bellows$1,000
3Elbow
3Deflector Cone
3Elbow$1,250
3Elbow$1,250
3Vortex Breaker$4,500
3Vortex Adapter$2,200
36" Pipe$1,700
Main DeckElbow$1,250
Main DeckBellows (2)$700
Main DeckElbow$1,250
Main DeckPipe$1,700
Main DeckBellows$700
Main DeckElbow$1,200
Main DeckTC and Flange$300
Main DeckOutlet Baffle $2,500
Main DeckFront Port Shields (2)$1,000
Main DeckRear Port Shields (3)$1,500
Main DeckLance$1,000
External Part Replacement
$15,000
$25,000
Included in 25K
Task
Production
Supervisor
EngineeringCIMaintenance
Operator
1
Operator
2
Identify Parts to ReplaceRRSSS
Quote all new partsSR
Order new partsSR
Determine storage location for partsRR
Fabricate storage racks for partsSSR
Upgrade 3rd floor airwallSRS
Create standard work for new processSSRSSS
R = Responsible
S = Support
Project Team
Project Charter©
For [Project Name]
ii
Copyright © Method123 Ltd
Document Control
Document Information
©
Information
Document Id
[Document Management System #]
Document Owner
[Owner Name]
Issue Date
[Date]
Last Saved Date
[Date]
File Name
[Name]
Document History
Version
Issue Date
Changes
[1.0]
[Date]
[Section, Page(s) and Text Revised]
Document Approvals
Role
Name
Signature©
Date
Project Sponsor
Project Review Group
Project Manager©
Quality Manager
(if applicable)
Procurement Manager
(if applicable)
Communications Manager
(if applicable)
Project Office Manager
(if applicable)
Table of Contents
Template Guide1
1Executive Summary2
2Project Definition2
2.1Vision2
2.2Objectives2
2.3Scope3
2.4Deliverables3
3Project Organisation4
3.1Customers4
3.2Stakeholders4
3.3Roles5
3.4Responsibilities5
3.5Structure7
4Project Plan8
4.1Approach8
4.2Overall Plan8
4.3Resource Plan9
4.4Financial Plan10
4.5Quality Plan10
5Project Considerations11
5.1Risks11
5.2Issues11
5.3Assumptions12
5.4Constraints12
6Appendix12
6.1Supporting Documentation12
Template Guide
What is a Project Charter?
A Project Charter is a document which outlines the purpose of
the project, the way the project will be structured and how it
will be successfully implemented. It describes the project:
· Vision, objectives, scope and deliverables (i.e. what we have
to achieve)
· Stakeholders, roles and responsibilities (i.e. who will take part
in it)
· Resource, financial and quality plans (i.e. how it will be
undertaken). ©
The Project Charter may also be referred to as a “Terms of
Reference (TOR)” or “Project Definition Report (PDR)”.
When do I use a Project Charter?
The Project Charter is usually presented by Senior Management
within the business to an identified Business Sponsor. It is
completed after the Business Case and Feasibility Study have
been approved but before the Project Team is formally
appointed.
Furthermore:
· The Project Charter defines the boundaries for the project. It
describes in detail the scope of the project, within which all
deliverables must be produced. Activities should be undertaken
outside the defined scope of the project only if a valid ‘change
request form’ has been approved by the Project Sponsor
· The next stage following approval of the Project Charter is the
formal appointment of the project team. ©
How to use this template
This document provides a guide on the topics usually included
in a Project Charter. Sections may be added, removed or
redefined at your leisure to meet your particular business
circumstance. Example tables, diagrams and charts have been
added (where suitable) to provide further guidance on how to
complete each relevant section.
Executive Summary
Sum up each of the sections in this document concisely by
outlining the project:
· Definition
· Organisation and plan
· Risks and issues
· Assumptions and constraints. ©
Project Definition
This section describes what the project sets out to achieve. It
outlines the vision for the project, the key objectives to be met,
the scope of work to be undertaken and the deliverables to be
produced.
Vision
Describe the overall vision of the project. The vision statement
should be short, concise and achievable. Examples of vision
statements include:
· To deliver a robust, scalable financial management system to
the business
· To procure new work premises with adequate capacity and
functional surrounds
· To successfully introduce new customer service processes to
the marketplace. ©
Objectives
List the key objectives of the project. Objectives are statements
which describe in more detail what it is that the project is going
to achieve. All objectives listed should be Specific, Measurable,
Achievable, Realistic and Time-bound (SMART).
Business Objectives
List the business-specific objectives to be achieved. For
example:
· To deliver new accounts payable and receivable and payroll
processes, thereby reducing financial processing timescales by
at least 30%
· To build brand new work premises with 50% more space, 30
more cark parks and 20% fewer operational costs than the
existing premises
· To provide a new customer complaints service to enable
customers to issue complaints on-line and receive a direct
response from the company within 24hrs. ©
Technology Objectives
List the technology-specific objectives to be achieved. For
example:
· To install new accounts payable and receivable and payroll
system modules within the existing accounting system, thereby
achieving 99.5% system up-time
· To relocate existing technology infrastructure at the new
building premises within 2 days elapsed time and with no
impact on customer service delivery
· To build a new website which allows customers to enter and
track complaints through to resolution.
Scope
Define the scope of the project in terms of the business:
· Processes which will change
· Organisationalareas which will be affected
· Locations which will be impacted on
· Data which will be altered
· Applications which will be installed and/or altered
· Technologies which will be deployed and/or
decommissioned©
Where relevant, identify the related business areas which will
not be affected as a result of this project.
Deliverables
Highlight the key project deliverables in the following table
(includes examples):
Item
Components©
Description
New physical premises
· New physical building
· Interior fit-out
· Telecommunications
· 1200 sq m premises near city centre with outdoor facilities,
parking and signage
· Open plan environment with 5 offices, 3 meeting rooms and a
staff games room
· Voice / data telecoms infrastructure and video conference
facilities
New financial system
· Accounts payable module
· Accounts receivable module
· Payroll module
· A new system module which enables staff to quickly enter
accounts payable transactions
· A new system module which enables staff to quickly enter
accounts receivable transactions
· A new system module which enables staff to quickly enter
payroll information
New customer complaints process
· Complaints website
· Complaints resolution process
· Complaints measurement process
· New website with customer complaints forms, a complaint
tracking page and company contact information
· New full-time staff complaints role and process for resolving
complaints made
· New process for assessing complaint characteristics (such as
numbers, business areas and resolution timescales)
Project Organisation
Customers
Describe the customers who will use the deliverables produced
from the project. Customers may be individuals or groups
within or outside of the company. The success of the project
will be primarily based on whether or not the deliverables
produced match the requirements of the customers identified in
this table.
Customer
Representative©
Customer Group
Customer Name
Stakeholders
List the key stakeholders for this project. A ‘stakeholder’ is
simply a person or entity outside of the project who has a key
interest in the project. For instance, a company financial
controller will have an interest in the cost implications of the
project, a CEO will have an interest in whether the project is
conducted in accordance with the vision of the company.
Examples of stakeholders include:
· Company Executives
· Legislative bodies
· Regulatory bodies.
Complete the following table (includes examples):
Stakeholder©
Interested in
CEO
Alignment with company vision and strategy
Financial Controller
Alignment with company budget
Health and Safety Office
Alignment with health and safety standards
Government body
Compliance with legislation
Industry body
Compliance with codes of practice
Roles
Identify the roles required to undertake the project. Examples of
typical roles include project:
· Sponsor
· Review Group
· Manager
· Team Member
For each role identified, list the resource likely to fill each role
and his/her assignment details by completing the following
table:
Role
Organisation©
Resource Name
Assignment Status
Assignment Date
Role
Organisation
Person
Unassigned / Assigned
xx/yy/zz
For larger projects with more than 10 resources, list only the
key roles in the above table. Include a detailed listing and
description of all roles within a separate Resource Plan
document if required.
Responsibilities
List the generic responsibilities for each role identified. A full
list of the responsibilities, performance criteria and skills
required should be documented within a separate Job
Description for each project role.
Project Sponsor
The Project Sponsor is the principal ‘owner’ of the project. Key
responsibilities include:
· Defining the vision and high level objectives for the project
· Approving the requirements, timetable, resources and budget
· Authorising the provision of funds / resources (internal or
external)
· Approving the project plan and quality plan
· Ensuring that major business risks are identified and managed
· Approving any major changes in scope
· Receiving Project Review Group minutes and taking action
accordingly
· Resolving issues escalated by the Project Manager / Project
Review Group
· Ensuring business / operational support arrangements are put
in place
· Ensuring the participation of a business resource (if required)
· Providing final acceptance of the solution upon project
completion. ©
Project Review Group
The Project Review Group may include both business and 3rd
party representatives and is put in place to ensure that the
project is progressing according to plan.
Key responsibilities include:
· Assisting the Project Sponsor with the definition of the project
vision and objectives
· Undertaking Quality Reviews prior to the completion of each
project milestone
· Ensuring that all business risks are identified and managed
accordingly
· Ensuring conformance to the standards and processes
identified in the Quality Plan
· Ensuring that all appropriate client/vendor contractual
documentation is in place prior to the initiation of the project.
©
Project Manager
The Project Manager ensures that the daily activities undertaken
on the project are in accordance with the approved project
plans. The Project Manager is responsible for ensuring that the
project produces the required deliverables on time, within
budgeted cost and at the level of quality outlined within the
Quality Plan.
Key responsibilities include:
· Documenting the detailed Project Plan and Quality Plan
· Ensuring that all required resources are assigned to the project
and clearly tasked
· Managing assigned resources according to the defined scope
of the project
· Implementing the following project processes: time / cost /
quality / change / risk / issue / procurement / communication /
acceptance management
· Monitoring and reporting on project performance (re:
schedule, cost, quality and risk)
· Ensuring compliance with the processes and standards outlined
in the Quality Plan
· Reporting and escalating project risks and issues
· Managing project interdependencies
· Making adjustments to the detailed plan as necessary to
provide a complete picture of the progress of the project at any
time.
Project Team Member
A Project Team member undertakes all tasks necessary to
design, build and implement the final solution.
Key responsibilities include:
· Undertaking all tasks allocated by the Project Manager (as per
the Project Plan)
· Reporting progress of the execution of tasks to the Project
Manager on a frequent basis
· Maintaining all documentation relating to the execution of
allocated tasks
· Escalating risks and issues to be resolved by the Project
Manager. ©
Structure
Depict the reporting lines between each of the key roles
described above within a Project Organisation Chart. An
example follows:
Project PlanApproach
Describe the approach to be taken to implement each of the
phases within the project.
Phase
Approach©
Initiation
Outline the method by which the project will be further defined,
the project team appointed and the Project Office established.
Planning
Define the overall planning process to ensure that the phases,
activities and tasks are undertaken in a co-ordinated fashion.
Execution
Describe the generic phases and activities required to build, test
and implement the deliverables of the project.
Closure
Describe the steps required to release the deliverables to the
business, close the project office, reallocate staff and perform a
Post Implementation Review of the project.Overall Plan
Provide a summarized plan outlining the sequence of each of the
phases listed above.
A more detailed Project Plan will be drawn up during the
“Planning” phase of the project.
Milestones
List the major project milestones and the required delivery
dates. A ‘milestone’ is a significant event or stage to be
completed. Explain why each milestone is critical to the project,
as follows:
Milestone
Date©
Description
Milestone Title
xx/yy/zz
Explain why milestone date is critical to business
Dependencies
List any project activities which:
· Will impact on another activity external to the project
· Will be impacted on by the non/delivery of another activity
external to the project
Project Activity
Impacts on
Impacted on by
Criticality©
Date
Planned Activity
External Activity
External Activity
Low/Medium/High
xx/yy/zz
Resource Plan
Summarize the duration and effort required for each project
team member, as follows:
Role
Start Date
End Date
% Effort
Project Role
xx/yy/zzzz
xx/yy/zzzz
xx/yy/zzzz
A detailed Resource Plan will be drawn up during the
“Planning” phase of this project.
Financial Plan
Summarize the project budget approved (within the Business
Case) as follows:
Category
Cost©
Value
People
· Salaries of project staff
· Contractors and outsourced parties
· Training courses
$ x
$ x
$ x
Physical
· Building premises for project team
· Equipment and materials
· Tools (computers, cabling, phones…)
$ x
$ x
$ x
Marketing
· Advertising / branding
· Promotional materials
· PR and communications
$ x
$ x
$ x
Organisational
· Operational downtime
· Short-term loss in productivity
· Cultural change
$ x
$ x
Describe
A detailed Financial Plan will be drawn up during the
“Planning” phase of this project.
Quality Plan
Briefly describe the various processes to be undertaken to
ensure the success of the project.
Process©
Description
Quality Management
Summary of how the process will be undertaken
Change Management
Risk Management
Issue Management
Configuration Management
Document Management
Acceptance Management
Procurement Management
Financial Management
Timesheet Management
Project Reporting
Project Communications
A detailed Quality Plan will be drawn up during the “Planning”
phase of this project.
Project Considerations
Risks
Summarize the most apparent risks associated with the project.
Risks are defined as “any event which may adversely affect the
ability of the solution to produce the required deliverables”.
Risks may be Strategic, Environmental, Financial, Operational,
Technical, Industrial, Competitive or Customer related.
Complete the following table:
Description
Likelihood
Impact©
Mitigating Actions
Inability to recruit skilled resource
Low
Very High
Outsource project to a company with proven industry experience
and appropriately skilled staff
Technology solution is unable to deliver required results
Medium
High
Complete a pilot project to prove the full technology solution
Additional capital expenditure may be required in addition to
that approved
Medium
Medium
Maintain strict capital expenditure processes during the project
To complete this section thoroughly, it may be necessary to
undertake a formal Risk Assessment (by documenting a Risk
Management Plan). To reduce the likelihood and impact of each
risk's eventuating, clear ‘mitigating actions’ should be defined.
Issues
Summarize the highest priority issues associated with the
project. Issues are defined as“any event which currently
adversely affects the ability of the solution to produce the
required deliverables”. Complete the following table:
Description©
Priority
Resolution Actions
Required capital expenditure funds have not been budgeted
High
Request funding approval as part of this proposal
Required computer software is only at ‘beta’ phase and has not
yet been released live
Medium
Design solution based on current software version and adapt
changes to solution once the final version of the software has
been released
Council approval must be sought to implement the final solution
Low
Initiate the council approval process early so that it does not
delay the final roll-out process.
Assumptions
List the major assumptions identified with the project to date.
Examples include:
· There will be no legislative, business strategy or policy
changes during this project
· Prices of raw materials will not increase during the course of
the project
· Additional human resources will be available from the
business to support the project. ©
Constraints
List the major constraints identified with the project to date.
Examples include:
· The financial budget allocated is fixed and does not allow for
over-spending
· There are limited technical resource available for the project
· The technical solution must be implemented after-hours to
minimize the operational impact on the business.
AppendixSupporting Documentation
Attach any documentation you believe is relevant to the Project
Charter, including:
· Curricula Vitae (CVs) for key project staff
· Approved Business Case
· Approved Feasibility Study
· Research Materials
· External quotes or tenders
· Detailed financial planning spreadsheets
· Other relevant information or correspondence. ©
ID
Task Name
1
INITIATION
2
Develop Business Case
7
Perform Feasibility Study …
13
Establish Terms of Reference
18
Appoint Project Team
22
Set-up Project Office
26
Approval to Proceed
27
28
PLANNING
29
Develop Project Plan
38
Develop Quality Plan
53
Fomulate Supplier Contracts
57
Approval to Proceed
58
59
EXECUTION
60
Build Deliverables
61
Build Project Deliverables
62
Test Project Deliverables
63
Implement Project Deliverables
64
Monitoring and Control
77
Approval to Proceed
78
79
CLOSURE
80
Register Assets in Financial System
81
Perform Customer Signoff
82
Release Documentation & Equipment
83
Release Project Resources
84
Perform Supplier Contract Closure
85
Document Project Closure Report
86
Post Implementation Review
87
Project Closure
20/01
2/02
6/02
17/02
5/01
12/01
19/01
26/01
2/02
9/02
16/02
23/02
1/03
8/03
15/03
22/03
29/03
5/04
ary
February
March
April
RSV Project 12
Running head: Royal Stone Veneer: New Product Development
Project
Royal Stone Veneer: The Application of Project Management
Principles to a New Product Development ProjectQSO-680
Seminar in Project Management
June 8, 2014
Table of Contents
Royal Stone Veneer: The Application of Project Management
Principles to a New Product
Introduction3
Defining3
Goals3
Specifications4
Figure 1: Priority Matrix4
Figure 2: Responsibility Matrix6
Planning8
Schedule8
Budget8
Risk10
Executing10
Works Cited12
Royal Stone Veneer: New Product Development
ProjectIntroduction
In the building products industry there is a great need to supply
the customer with a cheaper alternative to traditional exterior
cladding products (i.e. wood and stone). The Royal Stone
Veneer project is an attempt to penetrate the portion of the
building products market that relates to stone by introducing a
quality, cost competitive, and a less labor intensive product
installation “stone-like” product. The introduction of such a
product will spur growth in our business so that we can continue
to grow and be a profitable organization. DefiningGoals
As a start to defining this project upper management had set a
few goals that the project must meet in order to be viable within
our organization. The first was that this product had to be
innovative. There are other polymeric stone veneer products in
the building products market currently, but this product must be
easily differentiated from other like products currently on the
market. The second goal was to promote sales of our existing
products along with this new product to allow us to sell the new
product along with more of our existing products. The third
goal was that the new product must be one that will allow the
company to make a profit and allow us to take market share
away from our competitors in this product category along with
our existing line of products. As a fourth goal which is actually
a required goal for every project within our organization is that
the project must be completed in a safe and environmentally
friendly manner.Royal Stone Veneer: New Product Development
ProjectSpecifications
In order to ensure that our needs for this project were
clearly defined the project manager wrote a “Scope” document.
This document outlines the requirements for all facets of the
project. The outline defines manufacturing method, internal or
external manufacturing, material type(s), what parts will be
needed to make this product viable to the home exterior
cladding market, market research to be completed, code
compliance testing, and beta testing to be conducted toward the
end of the project.
Another important point in the defining phase was the
development of the priority matrix. The priority matrix gives
the project team an overview of what management will accept in
terms of the project time to completion, the performance or
how closely the project will meet the requirements, and if the
project must be completed within the budget or if a cost overrun
is acceptable. The following represents the priority matrix that
defined the Royal Stone Veneer Project:Figure 1: Priority
Matrix
Time
Performance
Cost
X
Constrain
X
Enhance
X
Accept
Royal Stone Veneer: New Product Development Project
The priority matrix that was developed for this particular
project is one that gives a project team freedom to be creative in
the development process of the product. Under the accept
criteria of the matrix is cost. Since management has indicated
that cost is not constraining this project the team has the ability
to experiment or “ooch” (Heath, 2013) with different designs
that may enhance the look or function of the product and make
this one of a kind product stand out even more than it would
without enhancement. The term “ooch” was used in the last
sentence; ooching is the process of conducting small
experiments to test a given hypothesis (Heath, 2013). In the
case of this project ooching is required to determine the
coloration of the product; this would only be a small portion of
the experimentation that is required for the overall project.
The fact that the project matrix for this project has
performance as the constraint and time as the enhancement
criteria also foster a good project environment for a new
product development project. Time being under the
enhancement criteria grants the team ample time so that the
development of the product is not rushed, but does not give the
team an unlimited amount of time to complete tasks. Time
being the criteria that can be enhanced is management’s way of
saying that the team is given an allotted amount of time to
complete the project, but we would rather have this project to
market sooner than later. This may not be the case in all new
product development projects, but this project must have some
flexibility in the time to completion.
Performance being the constraint of this project is
completely understandable. This product being a new and
unique product makes the need for the product to be made to the
specification of the utmost importance. In this project
specifically there was a fair amount of
Royal Stone Veneer: New Product Development Project
market research completed so that our company could
understand the needs and wants of our customers. Getting the
feedback from the customer and applying what we have heard to
the specifications of the project is important to the success of
the project. Performance as the constraint, especially for this
project, is the best criteria to ensure that the product will meet
the customer’s needs and wants.Figure 2: Responsibility Matrix
Responsibility Matrix For RSV Project
Deliverables
Design
Development
Purchasing
Quality
Testing
Third Party Manufacturer
Project Manager
Panel Design
1
2
3
4
Accessory Design
1
2
3
4
Decoration Development
1
2
4
Automation Specifications
1
2
2
Panel Development
2
1
3
Accessory Development
2
1
3
Tooling Design
1
2
2
Prototyping
2
2
2
3
1
2
Automation Implementation
1
1
2
2
2
Material Procurement
3
3
1
2
1
Responsible
2
Support
3
Consult
4
Approve
Figure 2 shows a modified and truncated version of the
responsibility matrix that was developed for the Royal Stone
Veneer project. I was asked by management not to use the
actual matrix that was developed for this project. The matrix
shows that design and development are responsible for or are in
a support role for each task. This may not be the ideal situation
for a
Royal Stone Veneer: New Product Development Project
project of this size and scope, but other than the third party
manufacturers that are performing work in the project the team
consists of five members. Two engineers, one representative of
quality/ product development, one representative of purchasing,
and the project manager. Having so few team members has
made the decision making process much easier throughout the
project. We don’t have to deal with as many different
personalities which has made any conflict that has arisen very
easy to resolve without ruffling too many feathers in the
process.
The matrix organization structure for this project is a
balanced matrix. The project manager developed the overall
scope and plan for the project while the functional (Engineering
Manager) is making the determination as to how the work will
be completed. For this project this type of structure has worked
well. Since 60% of the team members are direct reports to the
functional manager the project has progressed quite well. The
functional manager in this case has a great interest in seeing
this project to fruition, so the other team members are also on
board with the manager’s goals. Where this has been
disadvantageous is with such a small team that is not totally
dedicated to the project, tasks frequently take a little longer
than they would if there were a larger team with more members
to aid in completing the work. Another disadvantage to the
using the matrix structure in the case of our company is the fact
that resources are shared across projects. This would normally
be a strength, but with a small group that works on projects in
our company we tend to not always be able to dedicate the time
that may be necessary to ensure that the work is being
completed. Most of the team members are working on three or
more projects at one time along with performing their day to
day tasks which explains why tasks may not get completed as
quickly as they normally would if there were a dedicated team
to complete project work.
Royal Stone Veneer: New Product Development
ProjectPlanningSchedule
The schedule for this project is a resource-constrained type
of schedule. The project team has very few members internally
that are performing the design and development tasks with a
third party manufacturing the product. Looking back at figure
1, this is why management has determined that the time is a
priority that cannot be constrained, but if possible could be
enhanced. The schedule for this project is not detailed to the
extent of a traditional project. The ES, LS, LF, and EF are not
defined and the team is unsure of which activities have slack as
an example. After studying the application of the previously
mentioned items in the QSO-680 course I now see that although
the Royal Stone Veneer project is not employing this method,
the use of the methods would likely make the project progress a
little more smoothly.
The schedule for the project is developed in a project
management software called Smartsheet. Similar to Microsoft
Project, Smartsheet allows the user to enter tasks with dates,
predecessors, and resource assignments. MS project has more
features and functionality than Smartsheet, for example, in MS
project the user has the ability to create network diagrams and
perform earned value analysis which is not available in
smartsheet. Having a schedule that outlines the project
activities, completion dates, and resource assignments has
allowed this project to stay on pace to complete on
schedule.Budget
With the development of artist renderings and physical
prototypes of the product we were able to conduct a rather
extensive amount of market research. This research allowed us
to get feedback from contractors, architects, and homeowners as
to what the product needed to be. We
Royal Stone Veneer: New Product Development Project
were able to determine at what price point this product would be
able to be sold at, what types of coloration were needed to
satisfy the needs of the American market, and how the product
must perform in order for it to be viable in the home exterior
cladding market. The market research was the first phase in
planning the project; once the research was completed we now
have the requisite information to develop a plan for the
development and introduction of a product that will be well
received in the market.
Once all of the research information had been collected the
team had to make some determinations as to how this product
would be manufactured. Could it be done via a manual process?
Would automation get the product to the price point we need?
Would automation be too large of an initial investment? Our
scope document was sent to multiple suppliers along with a
request for proposal. Once the proposals were received we were
able to make a determination as to which direction we must go.
The project manager developed a budget consisting of cost of
automation, development costs, tooling costs, man hours, and
code compliance testing. Our company requires that each larger
project go through a stage gate process where the project budget
and plan are reviewed by a committee that consists of mostly
upper management. During this meeting the committee
approves or disapproves the budget for the project. The budget
numbers given in this part of the process are purely budgetary; a
more detailed time-phased
budget is created after the committee gives the go ahead for the
preliminary budget requested. The term time-phased budget is
used loosely when defining the budget for this project. The
budget is broken down by work package but is not as detailed as
how much will be spent per week. The budget is tracked on a
spread sheet that shows the spending per the schedule of
Royal Stone Veneer: New Product Development Project
activities which is like a time-phased budget. We are able to
track our spending per activity and this sheet is viewable by a
select group of senior managers which allows them to see the
progress of the project in terms of spending. This being a
somewhat large capital project there are requirements that the
budgeted dollars must be spent by the scheduled date.Risk
With any project there are risks that could be detrimental
to the project, risks are an inherent part of projects; whether it
is a cost overrun, a delay in the build of a piece of equipment,
or delayed raw material delivery there are many possible risks
related to project tasks. My company has taken a more formal
approach to risk management, meaning that some of the risk
assessment and mitigation procedures are used but the methods
are not followed to the letter of the law. There are contingency
plans in place to allow the project to continue if the first option
is deemed to not be viable or will not allow the product to
achieve the required performance. As a short example the
product that this project is aimed at developing must have
colorant applied to the surface. In our scope there is a section
that calls for an automated decoration machine. As a
contingency plan for the coloration or decoration of the product,
a manual method of decoration can be used in order to achieve
the appropriate level of coloration. We are relying on our
contingency plans as risk mitigation which would not suffice in
an organization that is any level above formal i.e.
institutionalized (QSO-680 "Module Ten Lecture"), but this
method has worked quite well up to this point in the project.
Executing
Currently this project is in the heart of the execution phase. All
planned activities have begun. Although there is a single team
member that has been given the title of project managerRoyal
Stone Veneer: New Product Development Project
RSV Project 11
each team member has taken on the task of keeping everyone
abreast of the status of the project tasks to which they are
assigned. A standard template for status report is used on a bi-
weekly basis. This form includes what activities have been
completed since the last report and what activities will need to
be completed for the next report. Each status report contains a
snapshot from each of the Gantt charts that apply to your tasks
and the amount of dollars spent on the tasks. Once the status
reports are complete the project manager reads them all and
gives the project sponsor (general manager) an overall update of
how the project is progressing. There is also a project sheet
that is visible to all team and the project sponsor that shows the
progression of the project from a capital spending perspective.
Both the status update and the project sheet have been
instrumental in keeping everyone informed as to the status of
the project.
Royal Stone Veneer: New Product Development Project
Works Cited
(n.d.). Retrieved from http://pmstats.dis.arkansas.gov/meth/07-
execution%20phase.pdf
Heath, C. &. (2013). Decisive "How To Make Better
Decisions". New York: Crown Business.
Larson, E. W., & Gray, C. F. (2014). Project Management "The
Manegerial Approach". New York: McGraw-Hill Education.
Olvey, P. (2012). Royal Stone Veneer Project Scope. Columbus,
OH, United States of America.
QSO-680 "Module Ten Lecture". (n.d.). New Hampshire.
10-3 Term Paper Submission                    QSO-680 Seminar in.docx

More Related Content

Similar to 10-3 Term Paper Submission QSO-680 Seminar in.docx

Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Caroline Bilet
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Lean Construction and integrated Project delivery
Lean Construction and integrated Project deliveryLean Construction and integrated Project delivery
Lean Construction and integrated Project deliveryNottingham Trent University
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
Interaction sharing my experience
Interaction   sharing my experienceInteraction   sharing my experience
Interaction sharing my experienceSamir Dave
 
The Renovation and Extension of the Hindustan Shiva Mandir
The Renovation and Extension of the Hindustan Shiva MandirThe Renovation and Extension of the Hindustan Shiva Mandir
The Renovation and Extension of the Hindustan Shiva MandirAdesh Ramharack
 
Updated C.V of water & sewerage
Updated  C.V of water & sewerageUpdated  C.V of water & sewerage
Updated C.V of water & sewerageKhalid Pervez
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2Rodney Taylor
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 
PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015gufron gufron
 
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docxREQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docxheunice
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 

Similar to 10-3 Term Paper Submission QSO-680 Seminar in.docx (20)

Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Lean Construction and integrated Project delivery
Lean Construction and integrated Project deliveryLean Construction and integrated Project delivery
Lean Construction and integrated Project delivery
 
CV-PM
CV-PMCV-PM
CV-PM
 
Project Review Presentation (2)
Project Review Presentation (2)Project Review Presentation (2)
Project Review Presentation (2)
 
CV
CVCV
CV
 
CV-Pon
CV-PonCV-Pon
CV-Pon
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
Student Project
Student ProjectStudent Project
Student Project
 
Interaction sharing my experience
Interaction   sharing my experienceInteraction   sharing my experience
Interaction sharing my experience
 
The Renovation and Extension of the Hindustan Shiva Mandir
The Renovation and Extension of the Hindustan Shiva MandirThe Renovation and Extension of the Hindustan Shiva Mandir
The Renovation and Extension of the Hindustan Shiva Mandir
 
Updated C.V of water & sewerage
Updated  C.V of water & sewerageUpdated  C.V of water & sewerage
Updated C.V of water & sewerage
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2
 
Running head PMPM .docx
Running head PMPM                                          .docxRunning head PMPM                                          .docx
Running head PMPM .docx
 
project management UOC-1
project management UOC-1project management UOC-1
project management UOC-1
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 
PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015PERSONAL EXPERIENCE RECORD-2015
PERSONAL EXPERIENCE RECORD-2015
 
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docxREQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx
REQUIREMENTS MANAGEMENT PLANPurposeThis document defines the s.docx
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Final Project.pptx
Final Project.pptxFinal Project.pptx
Final Project.pptx
 

More from hyacinthshackley2629

Your company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docxYour company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docxhyacinthshackley2629
 
Your Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docxYour Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docxhyacinthshackley2629
 
Your company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docxYour company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docxhyacinthshackley2629
 
Your company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docxYour company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docxhyacinthshackley2629
 
Your company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docxYour company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docxhyacinthshackley2629
 
Your company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docxYour company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docxhyacinthshackley2629
 
your company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docxyour company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docxhyacinthshackley2629
 
Your company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docxYour company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docxhyacinthshackley2629
 
Your company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docxYour company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docxhyacinthshackley2629
 
Your company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docxYour company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docxhyacinthshackley2629
 
Your company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docxYour company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docxhyacinthshackley2629
 
Your company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docxYour company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docxhyacinthshackley2629
 
Your company You are a new Supply Chain Analyst with the ACME.docx
Your company   You are a new Supply Chain Analyst with the ACME.docxYour company   You are a new Supply Chain Analyst with the ACME.docx
Your company You are a new Supply Chain Analyst with the ACME.docxhyacinthshackley2629
 
Your company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docxYour company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docxhyacinthshackley2629
 
Your Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docxYour Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docxhyacinthshackley2629
 
Your community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docxYour community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docxhyacinthshackley2629
 
Your Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docxYour Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docxhyacinthshackley2629
 
Your Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docxYour Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docxhyacinthshackley2629
 
Your Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docxYour Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docxhyacinthshackley2629
 
Your coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docxYour coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docxhyacinthshackley2629
 

More from hyacinthshackley2629 (20)

Your company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docxYour company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docx
 
Your Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docxYour Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docx
 
Your company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docxYour company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docx
 
Your company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docxYour company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docx
 
Your company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docxYour company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docx
 
Your company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docxYour company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docx
 
your company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docxyour company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docx
 
Your company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docxYour company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docx
 
Your company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docxYour company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docx
 
Your company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docxYour company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docx
 
Your company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docxYour company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docx
 
Your company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docxYour company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docx
 
Your company You are a new Supply Chain Analyst with the ACME.docx
Your company   You are a new Supply Chain Analyst with the ACME.docxYour company   You are a new Supply Chain Analyst with the ACME.docx
Your company You are a new Supply Chain Analyst with the ACME.docx
 
Your company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docxYour company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docx
 
Your Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docxYour Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docx
 
Your community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docxYour community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docx
 
Your Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docxYour Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docx
 
Your Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docxYour Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docx
 
Your Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docxYour Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docx
 
Your coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docxYour coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docx
 

Recently uploaded

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

10-3 Term Paper Submission QSO-680 Seminar in.docx

  • 1. 10-3 Term Paper Submission QSO-680 Seminar in Project Management QSO-680 Seminar in Project Management Southern New Hampshire University 10-3 Term Paper Submission Tower Replacement Parts Project Katie M. O’Brien June 3, 2014 I work for a company that produces super nickel alloy powder for jet turbine engines. For use in this term paper I will call this company Metal Powder. I am the continuous improvement manager at Metal Powder. It was recognized in early 2011 that our atomization tower cleaning process needed to be streamlined to speed up cleaning time and decrease internal process time to be able to produce more powder heats in a year. The atomization tower is 60 feet tall and 24 feet in diameter. Metal Powder produces three separate alloys. When
  • 2. a new alloy is put in the schedule to be made Metal Powder must tear down the atomization tower and clean every part and the entire tower to a white glove inspection before beginning the next alloy. The tower cleaning is currently taking 3 to 4 days depending on the amount of buildup of atomized powder on the parts. As Metal Powders demand increases in the next six years it is imperative that Metal Powder turn the tower around faster and faster to gain additional capacity. Through the use of setup reduction it has been determined that a total of 84 parts at a cost of around $100,000 can reduce the cleaning time by one eight hour shift. This is a gain of 3 more “heats” of powder every clean. There are 10 to 12 cleanings per year which could be a potential gain of 30 to 36 heats per year. This application term paper will use the five phases of project management to implement the use of the new parts and ensure that the goal of saving one shift will be recognized. A team was selected of operators, engineers, production supervisor, continuous improvement, and maintenance personnel to help manage the project as resources. The breakdown of roles in the responsibility matrix is in Figure 1. Figure 1: Responsibility Matrix The project team created the Project Charter seen in Figure 2. Figure 2: Project Charter Project Information Project Manager Katie O’Brien Project Sponsor General Manager Project Description Determine and implement duplicate parts to be swapped out during atomization tower cleaning to optimize process and reduce downtime. Project Scope
  • 3. Business Purpose, Objectives and Goals: Metal Powder demand is going to increase two fold by 2020. To rise to this challenge Metal Powder must reduce downtime and increase capacity. Problem/Opportunity Statement: The problem of 3 to 4 days of downtime during an atomization tower clean affects Production and Quality departments and capacity The impact of which is Downtime of 30 to 36 days per year to clean the tower A successful solution would Be to reduce tower cleaning time by one 8 hour shift to gain 30 to 36 heats per year. Constraints Inclusions: All parts that are not permanently connected to the tower or by a twisting fixture. Exclusions: Parts that are permanently affixed to the tower or are a safety risk to remove and reinstall. Key Assumptions: Parts will be stored on site and cleaned external to the process by production operations. All parts over 25 pounds will need a plan for movement. Project Dependencies: This project is dependent on engineering and maintenance support to execute storage locations along with an upgrade to the 3rd floor airwall and any fixtures needed for transport of parts of 25 pounds. Key Risks and Key Issues: Timing for installation of 3rd floor airwall along with quoting and receipt of parts for management of storage and swap out of parts. Critical Success Factors
  • 4. Critical Success Factor Key Success Indicator Action Steps to Assure Success Decrease cleaning time by one eight hour shift Cleaning time reduced to 3 days Proper storage locations along with robust standard work to ensure process runs smoothly Stakeholder and User Description Key Stakeholder Descriptions: Key Stakeholder Function Represented Production Cleaning of parts Quality Inspection Maintenance Repair User Summary: End User Types Impact Description Stakeholder Operators Will perform movement of parts, swap out and external cleaning Production Quality Personnel Will review cleaning at intermediate steps and then at completion Quality Approvals Documented Project Charter approvals are required from designated approvers. Role/Name Approval Date
  • 5. Project Sponsor: Production Manager: (PROJECTinsight, 2014) The project team prioritized the project as a must complete in 2014. This project is linked directly to capacity needs for future demand. The project cost for materials will be $100,000; additional cost will be in resources. The list of parts for duplication can be seen in Figure 3. Figure 3: List of parts to be replaced The work breakdown structure for implementation of the new parts and standard work is seen below in Figure 4. Figure 4: Work Breakdown Structure 1.0 Tower Replacement Parts 1.1 Identify Parts to Replace 1.2 Order Parts 1.3 Determine part storage locations 1.6 Training 1.4 Install Air wall and racks 1.7 Collect Data 1.8 Evaluate new times compared to previous cleaning times
  • 6. 1.6.1 Equipment 1.6.2 Production 1.6.3 Maintenance 1.8.1 Test & Measure 1.8.2 Support Process 1.1.1 Perform Set Up Reduction 1.2.1 Verify drawings are correct 1.2.2 Quote Parts 1.3.1 Quote & Replace air wall 1.3.2 Determine quality requirements for storage 1.5 Create standard work Based on the work breakdown structure above the following resource tasks have been distributed to the following teams; Maintenance, Operator, Production Manager, Continuous Improvement and Engineering. All resources were informed of responsibilities in a project launch meeting. The responsibility matrix was reviewed and agreed upon by all resources and stakeholders. In addition, due to the importance of this project Monday, Wednesday, Friday update meetings will be held at
  • 7. 8am. The frequency of these meetings may increase or decrease depending on the status of the project. Timing and schedule are of the utmost importance. Therefore the schedule is to be met at all costs. The detail of the work breakdown structure is being used to minimize scope creep along with the use of a project charter. The project is to be completed in three months with a $100,000 already spent toward the replacement parts. Any additional costs will be in the fabrication of storage racks, the 3rd floor air wall and labor. Unfortunately due to the size and management structure of Metal Powder only engineering and continuous improvement will be working on this project fulltime. Resources from Maintenance and Production will be pulled in as they are needed. Due to the phases in the work breakdown structure this should not create an issue for schedule. When standard work is to be written and finalized all resources will be needed. All parties or a representative will be required to be in update meetings. The project was launched on January 13, 2014 initial stages of the project such as evaluation of part drawings and quoting went well and was on time. As the project approached the storage location evaluation issues with resources being available to evaluate and determine these locations was not available which delayed the determination of locations. The project was able to execute the quotes and installation of the 3rd floor air wall with support from maintenance at the same time issues were developing with storage locations. As of March 10, 2014 not all storage locations had been determined. The sequence of tasks shifted slightly to ensure that the scheduled was met. I met with quality to determine all the locations for storage that were not acceptable from a quality perspective. In addition maintenance evaluated all parts over our 25 lb. lifting limit and created carts and lifting mechanisms for easy install and transport to the tower and back to the storage locations.
  • 8. By March 31, 2014 determination of all storage locations was complete. The next task for completion was standard work which took the input of all stakeholders and resources. Standard work was created not only for the safe swap out of all parts and reinstallation but also for the cleaning of the parts external to the tower cleaning process. This standard work needed to be robust so a dry run of the replacement and cleaning process was done to document with pictures and understand the time and movement of parts and personnel that would affect the success of ensure one shift of time was saved. This process took longer than expected. The initial thought of a dry run has not been captured in the project charter or scope. This created scope creep for the project and a delay in the schedule. It was however, recognized that this was a must do to ensure that the parts were swapped our properly, safely and ensure quality the first time. Therefore, the schedule was extended on week to April 21, 2014 for completion. This caused an instant miss on the schedule portion of the project and scope creep. But it was recognized by all parties that this task could not be rushed. Once standard work was solidified training of production and maintenance regarding the standard work and equipment utilization was performed and completed on time. Once the standard work and training was completed the new process was performed during the next turnaround which was April 14, 2014. Data was collected for times studies and to ensure that the deliverable of an 8 hour shift savings was recognized. The tower clean was completed in less than 3 days, in 69 hours to be exact on April 16, 2014. The project was completed two days over schedule prior to the scope creep and 3 days ahead of the recalculated schedule. See the project closure report in Figure 5 for the results of the project based on deliverables and scope. Figure 5: Project Closure Report Project Name Tower Replacement Parts
  • 9. Date April 17, 2014 Executive Sponsor General Manager Project Manager Katie O’Brien Schedule Planned Start Date January 13, 2014 Actual Start Date January 13, 2014 Planned End Date April 14, 2014 Actual End Date April 16, 2014Appropriation History Fiscal Year Amount Funding Source(s) 2011 $100,000 Corporate Scope VerificationRequirements Review Yes No Explanation/Notes Were the project objectives (expected outcomes) accomplished? x x Were all Deliverables submitted and accepted?
  • 10. x x Have all contracts been closed? x x Have all final payments been made (i.e., invoices paid) x x Has adequate knowledge transfer been completed? x x Phases Completion Date Goals/Objectives ResultsInitiation: 3rd Quarter 2013 Develop Project Charter and Project Management Plan. Project approved.Planning: March 2014 Develop storage locations Slight scope creep during delay in the project sequence of tasks changed. March 2014 Change of Scope: Decided to do a dry run of standard work to ensure process was correct. Not an original part of the plan. Dry run complete and standard work edited and confirmed for all stake holders. Implementation: April 2014 Fully deployed new standard work and part replacement
  • 11. process. Tower cleaning completed in 69 hours. Closeout: April 2014 Closeout of project All standard work complete. Process being used going forward. Project Sign Off The signatures below certify that this project has been completed in accordance to the specified budget, schedule, scope, and achieved the intended outcome. Stakeholders Name: Signature Date Project Sponsor (or Designee) General Manager April 20, 2014 Project Manager Katie O’Brien April 20, 2014 (State of New Mexico, 2011) References Larson & Gray. (2014). Project Management: The Managerial Process. New York City, NY: McGraw Hill. PROJECTinsight. (2014). 5 Basic Phases of Project Management. Retrieved May 16, 2014, from PROJECTinsight: http://www.projectinsight.net/project-management-basics/basic- project-management-phases State of New Mexico. (2011). Project Closure Example. Retrieved May 28, 2014, from www.doit.state.nm.us/pcc/docs/.../DoIT%20Project%20Closeout
  • 12. .doc 1 FloorDescriptionCurrent StateFuture State 42 Piece Liner 4Liner 4Valve 4Valve 4Torit Filters 4Liner 3Liner Main DeckBowling Ball Main DeckSealing Door Main DeckSight Port Pass Throughs Main DeckSealing Door Cartridges Main DeckLocking Pins & Cartridges Main DeckFurnace Cones Main DeckSealing Door Arm 6 Pressure Port (Hibon Sensors) $400 5Valve$500 5Elbow 5Cyclone Top 5Cyclone Body 5Cyclone Cone 5Valve 5Spool 5Can 5Valve$400 5Pressure ReliefStock Room
  • 13. 5 Flange and Hibon Port Sensor Manifold $3,000 4Top SectionIncluded in 25K 4Bellows$1,000 4Elbow 4Spacer 4Center Section 4Top Section 4Outlet Elbow 4Rupture DiskStock Room 4Probe$300 4Probe$300 3Pipe$3,600 3Bellows$1,000 3Elbow 3Deflector Cone 3Elbow$1,250 3Elbow$1,250 3Vortex Breaker$4,500 3Vortex Adapter$2,200 36" Pipe$1,700 Main DeckElbow$1,250 Main DeckBellows (2)$700 Main DeckElbow$1,250 Main DeckPipe$1,700 Main DeckBellows$700 Main DeckElbow$1,200 Main DeckTC and Flange$300 Main DeckOutlet Baffle $2,500 Main DeckFront Port Shields (2)$1,000 Main DeckRear Port Shields (3)$1,500 Main DeckLance$1,000 External Part Replacement $15,000
  • 14. $25,000 Included in 25K Task Production Supervisor EngineeringCIMaintenance Operator 1 Operator 2 Identify Parts to ReplaceRRSSS Quote all new partsSR Order new partsSR Determine storage location for partsRR Fabricate storage racks for partsSSR Upgrade 3rd floor airwallSRS Create standard work for new processSSRSSS R = Responsible S = Support Project Team
  • 15. Project Charter© For [Project Name] ii Copyright © Method123 Ltd Document Control Document Information © Information Document Id [Document Management System #] Document Owner [Owner Name] Issue Date [Date] Last Saved Date [Date] File Name [Name] Document History Version Issue Date Changes
  • 16. [1.0] [Date] [Section, Page(s) and Text Revised] Document Approvals Role Name Signature© Date Project Sponsor Project Review Group Project Manager©
  • 17. Quality Manager (if applicable) Procurement Manager (if applicable) Communications Manager (if applicable) Project Office Manager (if applicable) Table of Contents Template Guide1 1Executive Summary2 2Project Definition2 2.1Vision2 2.2Objectives2 2.3Scope3 2.4Deliverables3
  • 18. 3Project Organisation4 3.1Customers4 3.2Stakeholders4 3.3Roles5 3.4Responsibilities5 3.5Structure7 4Project Plan8 4.1Approach8 4.2Overall Plan8 4.3Resource Plan9 4.4Financial Plan10 4.5Quality Plan10 5Project Considerations11 5.1Risks11 5.2Issues11 5.3Assumptions12 5.4Constraints12 6Appendix12 6.1Supporting Documentation12 Template Guide What is a Project Charter? A Project Charter is a document which outlines the purpose of the project, the way the project will be structured and how it will be successfully implemented. It describes the project: · Vision, objectives, scope and deliverables (i.e. what we have to achieve) · Stakeholders, roles and responsibilities (i.e. who will take part in it) · Resource, financial and quality plans (i.e. how it will be undertaken). © The Project Charter may also be referred to as a “Terms of Reference (TOR)” or “Project Definition Report (PDR)”.
  • 19. When do I use a Project Charter? The Project Charter is usually presented by Senior Management within the business to an identified Business Sponsor. It is completed after the Business Case and Feasibility Study have been approved but before the Project Team is formally appointed. Furthermore: · The Project Charter defines the boundaries for the project. It describes in detail the scope of the project, within which all deliverables must be produced. Activities should be undertaken outside the defined scope of the project only if a valid ‘change request form’ has been approved by the Project Sponsor · The next stage following approval of the Project Charter is the formal appointment of the project team. © How to use this template This document provides a guide on the topics usually included in a Project Charter. Sections may be added, removed or redefined at your leisure to meet your particular business circumstance. Example tables, diagrams and charts have been added (where suitable) to provide further guidance on how to complete each relevant section. Executive Summary Sum up each of the sections in this document concisely by outlining the project: · Definition · Organisation and plan · Risks and issues
  • 20. · Assumptions and constraints. © Project Definition This section describes what the project sets out to achieve. It outlines the vision for the project, the key objectives to be met, the scope of work to be undertaken and the deliverables to be produced. Vision Describe the overall vision of the project. The vision statement should be short, concise and achievable. Examples of vision statements include: · To deliver a robust, scalable financial management system to the business · To procure new work premises with adequate capacity and functional surrounds · To successfully introduce new customer service processes to the marketplace. © Objectives List the key objectives of the project. Objectives are statements which describe in more detail what it is that the project is going to achieve. All objectives listed should be Specific, Measurable, Achievable, Realistic and Time-bound (SMART). Business Objectives List the business-specific objectives to be achieved. For example: · To deliver new accounts payable and receivable and payroll processes, thereby reducing financial processing timescales by at least 30% · To build brand new work premises with 50% more space, 30 more cark parks and 20% fewer operational costs than the existing premises · To provide a new customer complaints service to enable customers to issue complaints on-line and receive a direct
  • 21. response from the company within 24hrs. © Technology Objectives List the technology-specific objectives to be achieved. For example: · To install new accounts payable and receivable and payroll system modules within the existing accounting system, thereby achieving 99.5% system up-time · To relocate existing technology infrastructure at the new building premises within 2 days elapsed time and with no impact on customer service delivery · To build a new website which allows customers to enter and track complaints through to resolution. Scope Define the scope of the project in terms of the business: · Processes which will change · Organisationalareas which will be affected · Locations which will be impacted on · Data which will be altered · Applications which will be installed and/or altered · Technologies which will be deployed and/or decommissioned© Where relevant, identify the related business areas which will not be affected as a result of this project. Deliverables Highlight the key project deliverables in the following table (includes examples): Item Components© Description New physical premises
  • 22. · New physical building · Interior fit-out · Telecommunications · 1200 sq m premises near city centre with outdoor facilities, parking and signage · Open plan environment with 5 offices, 3 meeting rooms and a staff games room · Voice / data telecoms infrastructure and video conference facilities New financial system · Accounts payable module · Accounts receivable module · Payroll module · A new system module which enables staff to quickly enter accounts payable transactions · A new system module which enables staff to quickly enter accounts receivable transactions · A new system module which enables staff to quickly enter payroll information New customer complaints process · Complaints website · Complaints resolution process · Complaints measurement process · New website with customer complaints forms, a complaint
  • 23. tracking page and company contact information · New full-time staff complaints role and process for resolving complaints made · New process for assessing complaint characteristics (such as numbers, business areas and resolution timescales) Project Organisation Customers Describe the customers who will use the deliverables produced from the project. Customers may be individuals or groups within or outside of the company. The success of the project will be primarily based on whether or not the deliverables produced match the requirements of the customers identified in this table. Customer Representative© Customer Group Customer Name Stakeholders List the key stakeholders for this project. A ‘stakeholder’ is simply a person or entity outside of the project who has a key
  • 24. interest in the project. For instance, a company financial controller will have an interest in the cost implications of the project, a CEO will have an interest in whether the project is conducted in accordance with the vision of the company. Examples of stakeholders include: · Company Executives · Legislative bodies · Regulatory bodies. Complete the following table (includes examples): Stakeholder© Interested in CEO Alignment with company vision and strategy Financial Controller Alignment with company budget Health and Safety Office Alignment with health and safety standards Government body Compliance with legislation Industry body Compliance with codes of practice Roles Identify the roles required to undertake the project. Examples of
  • 25. typical roles include project: · Sponsor · Review Group · Manager · Team Member For each role identified, list the resource likely to fill each role and his/her assignment details by completing the following table: Role Organisation© Resource Name Assignment Status Assignment Date Role Organisation Person Unassigned / Assigned xx/yy/zz For larger projects with more than 10 resources, list only the key roles in the above table. Include a detailed listing and description of all roles within a separate Resource Plan document if required.
  • 26. Responsibilities List the generic responsibilities for each role identified. A full list of the responsibilities, performance criteria and skills required should be documented within a separate Job Description for each project role. Project Sponsor The Project Sponsor is the principal ‘owner’ of the project. Key responsibilities include: · Defining the vision and high level objectives for the project · Approving the requirements, timetable, resources and budget · Authorising the provision of funds / resources (internal or external) · Approving the project plan and quality plan · Ensuring that major business risks are identified and managed · Approving any major changes in scope · Receiving Project Review Group minutes and taking action accordingly · Resolving issues escalated by the Project Manager / Project Review Group · Ensuring business / operational support arrangements are put in place · Ensuring the participation of a business resource (if required) · Providing final acceptance of the solution upon project completion. © Project Review Group The Project Review Group may include both business and 3rd party representatives and is put in place to ensure that the project is progressing according to plan. Key responsibilities include:
  • 27. · Assisting the Project Sponsor with the definition of the project vision and objectives · Undertaking Quality Reviews prior to the completion of each project milestone · Ensuring that all business risks are identified and managed accordingly · Ensuring conformance to the standards and processes identified in the Quality Plan · Ensuring that all appropriate client/vendor contractual documentation is in place prior to the initiation of the project. © Project Manager The Project Manager ensures that the daily activities undertaken on the project are in accordance with the approved project plans. The Project Manager is responsible for ensuring that the project produces the required deliverables on time, within budgeted cost and at the level of quality outlined within the Quality Plan. Key responsibilities include: · Documenting the detailed Project Plan and Quality Plan · Ensuring that all required resources are assigned to the project and clearly tasked · Managing assigned resources according to the defined scope of the project · Implementing the following project processes: time / cost / quality / change / risk / issue / procurement / communication / acceptance management · Monitoring and reporting on project performance (re: schedule, cost, quality and risk) · Ensuring compliance with the processes and standards outlined in the Quality Plan · Reporting and escalating project risks and issues
  • 28. · Managing project interdependencies · Making adjustments to the detailed plan as necessary to provide a complete picture of the progress of the project at any time. Project Team Member A Project Team member undertakes all tasks necessary to design, build and implement the final solution. Key responsibilities include: · Undertaking all tasks allocated by the Project Manager (as per the Project Plan) · Reporting progress of the execution of tasks to the Project Manager on a frequent basis · Maintaining all documentation relating to the execution of allocated tasks · Escalating risks and issues to be resolved by the Project Manager. © Structure Depict the reporting lines between each of the key roles described above within a Project Organisation Chart. An example follows: Project PlanApproach Describe the approach to be taken to implement each of the phases within the project.
  • 29. Phase Approach© Initiation Outline the method by which the project will be further defined, the project team appointed and the Project Office established. Planning Define the overall planning process to ensure that the phases, activities and tasks are undertaken in a co-ordinated fashion. Execution Describe the generic phases and activities required to build, test and implement the deliverables of the project. Closure Describe the steps required to release the deliverables to the business, close the project office, reallocate staff and perform a Post Implementation Review of the project.Overall Plan Provide a summarized plan outlining the sequence of each of the phases listed above. A more detailed Project Plan will be drawn up during the “Planning” phase of the project. Milestones List the major project milestones and the required delivery dates. A ‘milestone’ is a significant event or stage to be completed. Explain why each milestone is critical to the project, as follows: Milestone Date© Description Milestone Title xx/yy/zz Explain why milestone date is critical to business
  • 30. Dependencies List any project activities which: · Will impact on another activity external to the project · Will be impacted on by the non/delivery of another activity external to the project Project Activity Impacts on Impacted on by Criticality© Date Planned Activity External Activity External Activity Low/Medium/High xx/yy/zz
  • 31. Resource Plan Summarize the duration and effort required for each project team member, as follows: Role Start Date End Date % Effort Project Role xx/yy/zzzz xx/yy/zzzz xx/yy/zzzz A detailed Resource Plan will be drawn up during the “Planning” phase of this project. Financial Plan Summarize the project budget approved (within the Business Case) as follows:
  • 32. Category Cost© Value People · Salaries of project staff · Contractors and outsourced parties · Training courses $ x $ x $ x Physical · Building premises for project team · Equipment and materials · Tools (computers, cabling, phones…) $ x $ x $ x Marketing · Advertising / branding · Promotional materials · PR and communications $ x $ x $ x Organisational · Operational downtime · Short-term loss in productivity · Cultural change $ x $ x Describe
  • 33. A detailed Financial Plan will be drawn up during the “Planning” phase of this project. Quality Plan Briefly describe the various processes to be undertaken to ensure the success of the project. Process© Description Quality Management Summary of how the process will be undertaken Change Management Risk Management Issue Management Configuration Management Document Management Acceptance Management Procurement Management Financial Management Timesheet Management
  • 34. Project Reporting Project Communications A detailed Quality Plan will be drawn up during the “Planning” phase of this project. Project Considerations Risks Summarize the most apparent risks associated with the project. Risks are defined as “any event which may adversely affect the ability of the solution to produce the required deliverables”. Risks may be Strategic, Environmental, Financial, Operational, Technical, Industrial, Competitive or Customer related. Complete the following table: Description Likelihood Impact© Mitigating Actions Inability to recruit skilled resource Low Very High Outsource project to a company with proven industry experience and appropriately skilled staff Technology solution is unable to deliver required results Medium High Complete a pilot project to prove the full technology solution Additional capital expenditure may be required in addition to
  • 35. that approved Medium Medium Maintain strict capital expenditure processes during the project To complete this section thoroughly, it may be necessary to undertake a formal Risk Assessment (by documenting a Risk Management Plan). To reduce the likelihood and impact of each risk's eventuating, clear ‘mitigating actions’ should be defined. Issues Summarize the highest priority issues associated with the project. Issues are defined as“any event which currently adversely affects the ability of the solution to produce the required deliverables”. Complete the following table: Description© Priority Resolution Actions Required capital expenditure funds have not been budgeted High Request funding approval as part of this proposal Required computer software is only at ‘beta’ phase and has not yet been released live Medium Design solution based on current software version and adapt changes to solution once the final version of the software has been released Council approval must be sought to implement the final solution
  • 36. Low Initiate the council approval process early so that it does not delay the final roll-out process. Assumptions List the major assumptions identified with the project to date. Examples include: · There will be no legislative, business strategy or policy changes during this project · Prices of raw materials will not increase during the course of the project · Additional human resources will be available from the business to support the project. © Constraints List the major constraints identified with the project to date. Examples include: · The financial budget allocated is fixed and does not allow for over-spending · There are limited technical resource available for the project · The technical solution must be implemented after-hours to minimize the operational impact on the business. AppendixSupporting Documentation Attach any documentation you believe is relevant to the Project Charter, including: · Curricula Vitae (CVs) for key project staff · Approved Business Case
  • 37. · Approved Feasibility Study · Research Materials · External quotes or tenders · Detailed financial planning spreadsheets · Other relevant information or correspondence. © ID Task Name 1 INITIATION 2 Develop Business Case 7 Perform Feasibility Study … 13 Establish Terms of Reference 18 Appoint Project Team 22 Set-up Project Office 26 Approval to Proceed 27 28 PLANNING 29 Develop Project Plan 38 Develop Quality Plan 53 Fomulate Supplier Contracts 57 Approval to Proceed 58 59
  • 38. EXECUTION 60 Build Deliverables 61 Build Project Deliverables 62 Test Project Deliverables 63 Implement Project Deliverables 64 Monitoring and Control 77 Approval to Proceed 78 79 CLOSURE 80 Register Assets in Financial System 81 Perform Customer Signoff 82 Release Documentation & Equipment 83 Release Project Resources 84 Perform Supplier Contract Closure 85 Document Project Closure Report 86 Post Implementation Review 87 Project Closure 20/01 2/02 6/02 17/02
  • 39. 5/01 12/01 19/01 26/01 2/02 9/02 16/02 23/02 1/03 8/03 15/03 22/03 29/03 5/04 ary February March April RSV Project 12 Running head: Royal Stone Veneer: New Product Development Project Royal Stone Veneer: The Application of Project Management Principles to a New Product Development ProjectQSO-680 Seminar in Project Management June 8, 2014
  • 40. Table of Contents Royal Stone Veneer: The Application of Project Management Principles to a New Product Introduction3 Defining3 Goals3 Specifications4 Figure 1: Priority Matrix4 Figure 2: Responsibility Matrix6 Planning8 Schedule8 Budget8 Risk10 Executing10 Works Cited12 Royal Stone Veneer: New Product Development ProjectIntroduction In the building products industry there is a great need to supply the customer with a cheaper alternative to traditional exterior cladding products (i.e. wood and stone). The Royal Stone Veneer project is an attempt to penetrate the portion of the building products market that relates to stone by introducing a quality, cost competitive, and a less labor intensive product installation “stone-like” product. The introduction of such a product will spur growth in our business so that we can continue to grow and be a profitable organization. DefiningGoals As a start to defining this project upper management had set a few goals that the project must meet in order to be viable within our organization. The first was that this product had to be innovative. There are other polymeric stone veneer products in the building products market currently, but this product must be easily differentiated from other like products currently on the market. The second goal was to promote sales of our existing products along with this new product to allow us to sell the new product along with more of our existing products. The third
  • 41. goal was that the new product must be one that will allow the company to make a profit and allow us to take market share away from our competitors in this product category along with our existing line of products. As a fourth goal which is actually a required goal for every project within our organization is that the project must be completed in a safe and environmentally friendly manner.Royal Stone Veneer: New Product Development ProjectSpecifications In order to ensure that our needs for this project were clearly defined the project manager wrote a “Scope” document. This document outlines the requirements for all facets of the project. The outline defines manufacturing method, internal or external manufacturing, material type(s), what parts will be needed to make this product viable to the home exterior cladding market, market research to be completed, code compliance testing, and beta testing to be conducted toward the end of the project. Another important point in the defining phase was the development of the priority matrix. The priority matrix gives the project team an overview of what management will accept in terms of the project time to completion, the performance or how closely the project will meet the requirements, and if the project must be completed within the budget or if a cost overrun is acceptable. The following represents the priority matrix that defined the Royal Stone Veneer Project:Figure 1: Priority Matrix Time Performance Cost X Constrain
  • 43. Royal Stone Veneer: New Product Development Project The priority matrix that was developed for this particular project is one that gives a project team freedom to be creative in the development process of the product. Under the accept criteria of the matrix is cost. Since management has indicated that cost is not constraining this project the team has the ability to experiment or “ooch” (Heath, 2013) with different designs that may enhance the look or function of the product and make this one of a kind product stand out even more than it would without enhancement. The term “ooch” was used in the last sentence; ooching is the process of conducting small experiments to test a given hypothesis (Heath, 2013). In the case of this project ooching is required to determine the coloration of the product; this would only be a small portion of the experimentation that is required for the overall project. The fact that the project matrix for this project has performance as the constraint and time as the enhancement criteria also foster a good project environment for a new product development project. Time being under the enhancement criteria grants the team ample time so that the development of the product is not rushed, but does not give the team an unlimited amount of time to complete tasks. Time being the criteria that can be enhanced is management’s way of saying that the team is given an allotted amount of time to complete the project, but we would rather have this project to market sooner than later. This may not be the case in all new product development projects, but this project must have some flexibility in the time to completion. Performance being the constraint of this project is completely understandable. This product being a new and unique product makes the need for the product to be made to the
  • 44. specification of the utmost importance. In this project specifically there was a fair amount of Royal Stone Veneer: New Product Development Project market research completed so that our company could understand the needs and wants of our customers. Getting the feedback from the customer and applying what we have heard to the specifications of the project is important to the success of the project. Performance as the constraint, especially for this project, is the best criteria to ensure that the product will meet the customer’s needs and wants.Figure 2: Responsibility Matrix Responsibility Matrix For RSV Project Deliverables Design Development Purchasing Quality Testing Third Party Manufacturer Project Manager Panel Design 1 2 3 4 Accessory Design 1 2 3 4
  • 45. Decoration Development 1 2 4 Automation Specifications 1 2 2 Panel Development 2 1 3 Accessory Development 2 1 3 Tooling Design 1 2
  • 47. Figure 2 shows a modified and truncated version of the responsibility matrix that was developed for the Royal Stone Veneer project. I was asked by management not to use the actual matrix that was developed for this project. The matrix shows that design and development are responsible for or are in a support role for each task. This may not be the ideal situation for a Royal Stone Veneer: New Product Development Project project of this size and scope, but other than the third party manufacturers that are performing work in the project the team consists of five members. Two engineers, one representative of quality/ product development, one representative of purchasing, and the project manager. Having so few team members has made the decision making process much easier throughout the project. We don’t have to deal with as many different personalities which has made any conflict that has arisen very easy to resolve without ruffling too many feathers in the process. The matrix organization structure for this project is a balanced matrix. The project manager developed the overall scope and plan for the project while the functional (Engineering Manager) is making the determination as to how the work will be completed. For this project this type of structure has worked well. Since 60% of the team members are direct reports to the functional manager the project has progressed quite well. The functional manager in this case has a great interest in seeing this project to fruition, so the other team members are also on board with the manager’s goals. Where this has been disadvantageous is with such a small team that is not totally dedicated to the project, tasks frequently take a little longer than they would if there were a larger team with more members to aid in completing the work. Another disadvantage to the using the matrix structure in the case of our company is the fact that resources are shared across projects. This would normally be a strength, but with a small group that works on projects in
  • 48. our company we tend to not always be able to dedicate the time that may be necessary to ensure that the work is being completed. Most of the team members are working on three or more projects at one time along with performing their day to day tasks which explains why tasks may not get completed as quickly as they normally would if there were a dedicated team to complete project work. Royal Stone Veneer: New Product Development ProjectPlanningSchedule The schedule for this project is a resource-constrained type of schedule. The project team has very few members internally that are performing the design and development tasks with a third party manufacturing the product. Looking back at figure 1, this is why management has determined that the time is a priority that cannot be constrained, but if possible could be enhanced. The schedule for this project is not detailed to the extent of a traditional project. The ES, LS, LF, and EF are not defined and the team is unsure of which activities have slack as an example. After studying the application of the previously mentioned items in the QSO-680 course I now see that although the Royal Stone Veneer project is not employing this method, the use of the methods would likely make the project progress a little more smoothly. The schedule for the project is developed in a project management software called Smartsheet. Similar to Microsoft Project, Smartsheet allows the user to enter tasks with dates, predecessors, and resource assignments. MS project has more features and functionality than Smartsheet, for example, in MS project the user has the ability to create network diagrams and perform earned value analysis which is not available in smartsheet. Having a schedule that outlines the project activities, completion dates, and resource assignments has allowed this project to stay on pace to complete on schedule.Budget With the development of artist renderings and physical prototypes of the product we were able to conduct a rather
  • 49. extensive amount of market research. This research allowed us to get feedback from contractors, architects, and homeowners as to what the product needed to be. We Royal Stone Veneer: New Product Development Project were able to determine at what price point this product would be able to be sold at, what types of coloration were needed to satisfy the needs of the American market, and how the product must perform in order for it to be viable in the home exterior cladding market. The market research was the first phase in planning the project; once the research was completed we now have the requisite information to develop a plan for the development and introduction of a product that will be well received in the market. Once all of the research information had been collected the team had to make some determinations as to how this product would be manufactured. Could it be done via a manual process? Would automation get the product to the price point we need? Would automation be too large of an initial investment? Our scope document was sent to multiple suppliers along with a request for proposal. Once the proposals were received we were able to make a determination as to which direction we must go. The project manager developed a budget consisting of cost of automation, development costs, tooling costs, man hours, and code compliance testing. Our company requires that each larger project go through a stage gate process where the project budget and plan are reviewed by a committee that consists of mostly upper management. During this meeting the committee approves or disapproves the budget for the project. The budget numbers given in this part of the process are purely budgetary; a more detailed time-phased budget is created after the committee gives the go ahead for the preliminary budget requested. The term time-phased budget is used loosely when defining the budget for this project. The budget is broken down by work package but is not as detailed as how much will be spent per week. The budget is tracked on a spread sheet that shows the spending per the schedule of
  • 50. Royal Stone Veneer: New Product Development Project activities which is like a time-phased budget. We are able to track our spending per activity and this sheet is viewable by a select group of senior managers which allows them to see the progress of the project in terms of spending. This being a somewhat large capital project there are requirements that the budgeted dollars must be spent by the scheduled date.Risk With any project there are risks that could be detrimental to the project, risks are an inherent part of projects; whether it is a cost overrun, a delay in the build of a piece of equipment, or delayed raw material delivery there are many possible risks related to project tasks. My company has taken a more formal approach to risk management, meaning that some of the risk assessment and mitigation procedures are used but the methods are not followed to the letter of the law. There are contingency plans in place to allow the project to continue if the first option is deemed to not be viable or will not allow the product to achieve the required performance. As a short example the product that this project is aimed at developing must have colorant applied to the surface. In our scope there is a section that calls for an automated decoration machine. As a contingency plan for the coloration or decoration of the product, a manual method of decoration can be used in order to achieve the appropriate level of coloration. We are relying on our contingency plans as risk mitigation which would not suffice in an organization that is any level above formal i.e. institutionalized (QSO-680 "Module Ten Lecture"), but this method has worked quite well up to this point in the project. Executing Currently this project is in the heart of the execution phase. All planned activities have begun. Although there is a single team member that has been given the title of project managerRoyal Stone Veneer: New Product Development Project RSV Project 11
  • 51. each team member has taken on the task of keeping everyone abreast of the status of the project tasks to which they are assigned. A standard template for status report is used on a bi- weekly basis. This form includes what activities have been completed since the last report and what activities will need to be completed for the next report. Each status report contains a snapshot from each of the Gantt charts that apply to your tasks and the amount of dollars spent on the tasks. Once the status reports are complete the project manager reads them all and gives the project sponsor (general manager) an overall update of how the project is progressing. There is also a project sheet that is visible to all team and the project sponsor that shows the progression of the project from a capital spending perspective. Both the status update and the project sheet have been instrumental in keeping everyone informed as to the status of the project. Royal Stone Veneer: New Product Development Project Works Cited (n.d.). Retrieved from http://pmstats.dis.arkansas.gov/meth/07- execution%20phase.pdf Heath, C. &. (2013). Decisive "How To Make Better Decisions". New York: Crown Business. Larson, E. W., & Gray, C. F. (2014). Project Management "The Manegerial Approach". New York: McGraw-Hill Education. Olvey, P. (2012). Royal Stone Veneer Project Scope. Columbus, OH, United States of America. QSO-680 "Module Ten Lecture". (n.d.). New Hampshire.