SlideShare a Scribd company logo
1 of 4
CURRICULUM VITAE
Page 1 of 4
UMA MAHESWARARAO ROUTHU
Email:routhuumamahesh@gmail.com
Mobile: 09985808028
Pass PortNo: M4839184
Career Objective
To sustain an excellent and challenging career in the field of Instrumentation by exposing to the cutting edge
technologies in a systematic manner and work dynamically towards thegoals of the organization.
Professional Experience
3.10 years of working experience in the Power sector as an Erection & Commissioning engineer in which gained
rich knowledge in Instrumentation Engineering principles and expertisein various operations.
Current Employer:-
Organization : Wonder Cement Ltd.
Designation : Sr. Engineer (INSTRUMENTATION)
Project : CPP (1x40MW)
Location : Nimbahera,Chittorgarh (Rajasthan)
 Currently involve in 1X40MW Power Plant maintenance and carried out following activities for the CPP project
includingB.H.E.L Make Steam Turbine, Thermax 1 X 160 TPH CFBC Boiler,WTP&ETP,BOP
 1x 40 MW Steam Turbine erection and commissioning
 The Steam turbine master control device of Governing console board erection and commissioning it is a Steam
Turbine speed,pressure,load controller by using Electronic Governer,Electrohydraulic Converter(1800) and Con-
trol Valve Actuator(1910)
 Turbine supervisory instruments like: vibration probes, Magnetic pickup units(MPU),Speed probes, Axial dis-
placement Probes, Key pharos Probes Installation and commissioning work for The Turbine safety and reliable
runningof the Steam Turbine
 Erection & commissioning of Air Cooled condenser including Field instruments, Profibus PA devices e.g. Transmit-
ters, Control valves,Cabletrays,Junction boxes, Cablelying.
 1 x 160 TPH CFBC Boiler instruments erection , commissioningand maintenance
 Involved in erection & commissioning of 5 nos. of PLC Siemens SIMATIC S71200 for Water treatment plant, Efflu-
ent treatment plant& Sewage treatment plant.
 Erection and commissioning of WTP, ETP & STP field instruments, analyzers, totalizers, cable trays, junction boxes,
PLC panels.
 Emerson makes Forbes marshal make PH analyzers and conductivity & ORP and Turbidity analyzers Erection
Commissioning & calibration and maintains.
 Steam and Water Analysis system Erection and commissioning and Maintains Including With PH and Conductivity
analyzers calibration
 ABB ACS800 up to 1250 KW VFD Erection,commissioning and Troubleshooting
 Siemens G120 VFD up to 7.5 KW Erection,commissioning maintenanceand Trouble shooting
 Coal and Lime handlingplantinstruments erection,commissioningand maintenance
Job Profile
 Erection & commissioningof field instruments.
 Planning,schedulingof Projectprogramfor erection, Testing & commissioning.
 Partof commissioningof TSI monitoringRack Bently Nevada
CURRICULUM VITAE
Page 2 of 4
 Partof commissioningWoodward governor WWG-505
 Steam Turbine Controller Valve actuator commissioning through WWG-505, Steam Turbine Controller Valve actu-
ator commissioningthrough I/H converter From Field and WWG 505
 Commissioningof governing consoleBoard.
 Temperature Transmitters installation atPRDS and Primary super heater, secondary super heater.
 RTDs installation for turbine General bearings, Turbine front pedestal Non-Active, Active Bearings, Generator
Winding,Core, Tooth, HOT, COLD, Gear Box Rtds.
 Proximity Sensors Like; Vibration, Speed, Magnetic Pick-Up(MPU), Axial displacement & Key Phaser installation at
Turbine front, Turbine rear,Genarator front,rear,Gear Box for Turbine Safety and Reliable and trouble free run-
ningrunning.
 ABB ACS 800, Siemens G120 VFD drives Maintenance
 Calibration, maintenance and checking of transmitters, gauges, switches, pneumatic control valves, MOVs, pneu-
matic power cylinders.
 Troubleshootingof all the problems regardingerection and commissioningfrominstrumentation prospect.
 Planningfor daily manpower engagement.
 Level transmitter installation in dearator, hotwell and coolingtower, HP heater, LP Heater, Condensate tank.
 Pressure transmitter installation in Lube Oil, Jacking Oil, HP heater, LP Heater, Main steam, PRDS, Turbine extrac-
tions,Dearator, Hotwel, Boiler flue has path, Boiler steam path, Plantinletsteam path.
 Flow transmitter installation from boiler to high pressure header, hp header –turbine, feed water from dearator
to steam drum (orificeand venture tube).
 Installation and commissioningof RTD (PT-100) in turbine and thermocouple (k-type) in boiler area.
 SPM, SOX,NOX,O2 Analyzers erection,commissioning,and maintenance
 Materials (Instruments with proper data, Equipment with proper specifications) selection to purchase and negoti-
ation with the material provider
 Indent of materials and there certification
 Maintain spareparts of all section of power plantinstruments.
 Experienced in preparing documents, reports regarding maintenance, history cards and recording observations
over equipment performance
 Monitor day-to-day work carried outby Contractors.
 Ensure availability of material atrighttime to enable them to complete C&I erection jobs in time.
 Project commissioningjob.
 Store related work issuing the material,instrument code opening with full specification in ERP,PR generate, follow
up the material offered material technical specification checking & giving Clearance to purchase the material.
Maintenance, troubleshooting,faultanalyzing,rectification,interlock checkingof E&I system
Previous Employer:
Organization : INTEQ AUTOMATION SERVICES PVT LTD.
Designation : C&I Engineer
Project : 1. LANCO POWER PROJECT 2. MYHOME INDUSTRIES LIMITED
Location : Vijayawada,Kondapalli Kodhada,Mellachervu
Capacity : 2X371 MW Combined cycle CPP-2(1x60MW)
CURRICULUM VITAE
Page 3 of 4
Professional summary:
• Responsible for complete calibration, Cold loop and Hot loop checking, Installation & cabling of all field instru-
ments of Gas turbine, Fuel gas conditioning system, GT Exhaust system, and equipment cooling water system and
turbine control panel
• Calibration and servicing of process sensors, Transmitters (SMART), Electronic, Pneumatic instruments, MOV and
Pneumatic Control valves.
• Studying of P & I, Control loop, wiringDiagrams and Cablescheduling.
• Have knowledge in Hook up drawings.
• Knowledge on turbine, boiler commissioning,start-up and testingprocedures.
Handling Equipment’s of Instrumentation Kits:
Calibrator ( Nag man PPC-20,Dead Weight Tester,Nagman Digital Calibrator), HART 475 Field communicator, CTP,
Temperature Bath, Source Meter, Loop Calibrator, Fluke RMS Digital multimeter,Fluke 710 series RTD/Thermocouple
Calibrator,Megger,DC Voltage Regulator, Rheostat.
Educational Qualifications
• Bachelor of Technology in Electrical & electronics Engineering from SBCE,Khammam,JNTU with 65.38% in 2011
• Intermediate (MPC) from Board of Intermediate Education,Andhra Pradesh with 73.4% in 2007.
• Secondary School Certificate (SSC) from Secondary School Education,Andhra Pradesh with 77% in 2005
Technical SkillS:
Core knowledge : Power Systems, electrical machines
Operatingsystems : Windows XP,Windows 7
Packages : MS-Office 2007,2010,MicrosoftDynamic AX, ERP
Personal details:
Full Name : Umamaheswara Rao Routhu
Father Name : KrishnamNaidu
Date of Birth : 5th August, 1990
Nationality : Indian.
Marital status : Single.
Languages Known : Telugu, English,and Hindi.
Current CTC : 3.8 Lacks + Parks
Address : D.N0-1-32/1 kattula kaviti,Veeraghattam
Srikakulam(Dist.) Andhra Pradesh – 532 460
Present Address : Qtr.no: E1/14, R.K.Nagar, Wonder Cement LTD, Rasool Pura Nimbahera, chittorgarh
(Dist.), Rajasthan,Pin:312601
Place:Nimbahera, Rajasthan (Umamaheswara Rao Routhu)
CURRICULUM VITAE
Page 4 of 4
Date:

More Related Content

What's hot

1 CV for Sr instrument technician in 8 years exp
1 CV for Sr instrument technician in 8 years exp1 CV for Sr instrument technician in 8 years exp
1 CV for Sr instrument technician in 8 years expParthsarathy vijayan
 
Instrument Technician for Maintenance new
Instrument Technician  for Maintenance newInstrument Technician  for Maintenance new
Instrument Technician for Maintenance newNoel Roque
 
Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Jr. Vacaro
 
DARIUS RODRIGUEZ ANGELES 2016 resume
DARIUS RODRIGUEZ ANGELES 2016 resumeDARIUS RODRIGUEZ ANGELES 2016 resume
DARIUS RODRIGUEZ ANGELES 2016 resumeDarius Angeles
 
Resume srivenkatesh instrumentation engineer
Resume srivenkatesh instrumentation engineerResume srivenkatesh instrumentation engineer
Resume srivenkatesh instrumentation engineerSrivenkatesh Padmanaban
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame
 
INSTRUMENT - TECHNICIAN – PROCESS CONTROL & INSTRUMENTATION
INSTRUMENT - TECHNICIAN  – PROCESS CONTROL & INSTRUMENTATION  INSTRUMENT - TECHNICIAN  – PROCESS CONTROL & INSTRUMENTATION
INSTRUMENT - TECHNICIAN – PROCESS CONTROL & INSTRUMENTATION umesh patel
 
Iprofessional
IprofessionalIprofessional
Iprofessionalkaraguppi
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler okBunk Bonk
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer
 
CV of Control and Instrumentation Engr
CV of Control and Instrumentation EngrCV of Control and Instrumentation Engr
CV of Control and Instrumentation EngrGovinda Raman
 
sayed bessat cv last rev (2)
sayed bessat cv last rev (2)sayed bessat cv last rev (2)
sayed bessat cv last rev (2)Sayed Bessat
 

What's hot (20)

1 CV for Sr instrument technician in 8 years exp
1 CV for Sr instrument technician in 8 years exp1 CV for Sr instrument technician in 8 years exp
1 CV for Sr instrument technician in 8 years exp
 
Instrument Technician for Maintenance new
Instrument Technician  for Maintenance newInstrument Technician  for Maintenance new
Instrument Technician for Maintenance new
 
Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)
 
Instrument Technician
Instrument  TechnicianInstrument  Technician
Instrument Technician
 
DARIUS RODRIGUEZ ANGELES 2016 resume
DARIUS RODRIGUEZ ANGELES 2016 resumeDARIUS RODRIGUEZ ANGELES 2016 resume
DARIUS RODRIGUEZ ANGELES 2016 resume
 
Instrument Supervisor CV
Instrument Supervisor CVInstrument Supervisor CV
Instrument Supervisor CV
 
Resume srivenkatesh instrumentation engineer
Resume srivenkatesh instrumentation engineerResume srivenkatesh instrumentation engineer
Resume srivenkatesh instrumentation engineer
 
SUDHEESH CV .
SUDHEESH CV .SUDHEESH CV .
SUDHEESH CV .
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CV
 
cv Instrument Commissioning Engineer
cv Instrument Commissioning Engineercv Instrument Commissioning Engineer
cv Instrument Commissioning Engineer
 
INSTRUMENT - TECHNICIAN – PROCESS CONTROL & INSTRUMENTATION
INSTRUMENT - TECHNICIAN  – PROCESS CONTROL & INSTRUMENTATION  INSTRUMENT - TECHNICIAN  – PROCESS CONTROL & INSTRUMENTATION
INSTRUMENT - TECHNICIAN – PROCESS CONTROL & INSTRUMENTATION
 
Matt Instr CV
Matt Instr CVMatt Instr CV
Matt Instr CV
 
Iprofessional
IprofessionalIprofessional
Iprofessional
 
Sandeep Singh
Sandeep SinghSandeep Singh
Sandeep Singh
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015
 
Lingeswaran CVe
Lingeswaran CVeLingeswaran CVe
Lingeswaran CVe
 
CV of Control and Instrumentation Engr
CV of Control and Instrumentation EngrCV of Control and Instrumentation Engr
CV of Control and Instrumentation Engr
 
CV Elect
CV ElectCV Elect
CV Elect
 
sayed bessat cv last rev (2)
sayed bessat cv last rev (2)sayed bessat cv last rev (2)
sayed bessat cv last rev (2)
 

Viewers also liked

CV - Jurie Botha
CV - Jurie BothaCV - Jurie Botha
CV - Jurie BothaJurie Botha
 
Resume - Vusile Mabongo_ 5 April 2016
Resume  - Vusile Mabongo_ 5 April 2016Resume  - Vusile Mabongo_ 5 April 2016
Resume - Vusile Mabongo_ 5 April 2016Vusile Mabongo
 
RESUME - Cas Scheepers 1 Rev
RESUME - Cas Scheepers 1 RevRESUME - Cas Scheepers 1 Rev
RESUME - Cas Scheepers 1 RevCas Scheepers
 
SOMC Company Presentation
SOMC Company PresentationSOMC Company Presentation
SOMC Company Presentationtimothybo
 
HEMANT UPDATED CV-4Dec.16
HEMANT UPDATED CV-4Dec.16HEMANT UPDATED CV-4Dec.16
HEMANT UPDATED CV-4Dec.16Hemant Chavan
 
Piping Engineer CV -Sandip Karmakar
Piping Engineer CV -Sandip KarmakarPiping Engineer CV -Sandip Karmakar
Piping Engineer CV -Sandip KarmakarSandip Karmakar
 
Power plant desk operation engineer(Boiler, turbine, HVAC)
Power plant desk operation engineer(Boiler, turbine, HVAC)Power plant desk operation engineer(Boiler, turbine, HVAC)
Power plant desk operation engineer(Boiler, turbine, HVAC)Sachin Pyasi
 
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)Abhishek Chaudhary
 

Viewers also liked (20)

khiva resume
khiva resumekhiva resume
khiva resume
 
CV - Jurie Botha
CV - Jurie BothaCV - Jurie Botha
CV - Jurie Botha
 
Sudeshna Resume
Sudeshna ResumeSudeshna Resume
Sudeshna Resume
 
Resume - Vusile Mabongo_ 5 April 2016
Resume  - Vusile Mabongo_ 5 April 2016Resume  - Vusile Mabongo_ 5 April 2016
Resume - Vusile Mabongo_ 5 April 2016
 
Jestin - Resume
Jestin - ResumeJestin - Resume
Jestin - Resume
 
RESUME - Cas Scheepers 1 Rev
RESUME - Cas Scheepers 1 RevRESUME - Cas Scheepers 1 Rev
RESUME - Cas Scheepers 1 Rev
 
GAURANG-CV
GAURANG-CVGAURANG-CV
GAURANG-CV
 
Ravi Resume
Ravi ResumeRavi Resume
Ravi Resume
 
SOMC Company Presentation
SOMC Company PresentationSOMC Company Presentation
SOMC Company Presentation
 
AMITAVA RESUME (2)
AMITAVA RESUME (2)AMITAVA RESUME (2)
AMITAVA RESUME (2)
 
HEMANT UPDATED CV-4Dec.16
HEMANT UPDATED CV-4Dec.16HEMANT UPDATED CV-4Dec.16
HEMANT UPDATED CV-4Dec.16
 
vijay resume QEC
vijay resume  QECvijay resume  QEC
vijay resume QEC
 
RESUME
RESUMERESUME
RESUME
 
Piping Engineer CV -Sandip Karmakar
Piping Engineer CV -Sandip KarmakarPiping Engineer CV -Sandip Karmakar
Piping Engineer CV -Sandip Karmakar
 
Resume Vinoth
Resume VinothResume Vinoth
Resume Vinoth
 
vijayan - resume
vijayan - resumevijayan - resume
vijayan - resume
 
Power plant desk operation engineer(Boiler, turbine, HVAC)
Power plant desk operation engineer(Boiler, turbine, HVAC)Power plant desk operation engineer(Boiler, turbine, HVAC)
Power plant desk operation engineer(Boiler, turbine, HVAC)
 
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
 
Monika, resume
Monika, resumeMonika, resume
Monika, resume
 
RESUME PIPING SUPERVISOR
RESUME PIPING SUPERVISORRESUME PIPING SUPERVISOR
RESUME PIPING SUPERVISOR
 

Similar to Uma mahesh Resume (20)

Cv
CvCv
Cv
 
Basheervs C&I Engineer
Basheervs C&I EngineerBasheervs C&I Engineer
Basheervs C&I Engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
updated_ashishmalhotra
updated_ashishmalhotraupdated_ashishmalhotra
updated_ashishmalhotra
 
Sr.Inst Tech
Sr.Inst TechSr.Inst Tech
Sr.Inst Tech
 
pronay CV 08052016
pronay CV 08052016pronay CV 08052016
pronay CV 08052016
 
NAVNATH UPDATED CV
NAVNATH UPDATED CVNAVNATH UPDATED CV
NAVNATH UPDATED CV
 
Inst Sr.Tech new
Inst Sr.Tech newInst Sr.Tech new
Inst Sr.Tech new
 
electrician
electricianelectrician
electrician
 
resume
resumeresume
resume
 
ExxonMobil Job Scop
ExxonMobil Job ScopExxonMobil Job Scop
ExxonMobil Job Scop
 
VETRI CV
VETRI CVVETRI CV
VETRI CV
 
Tahir Mahmood Butt
Tahir Mahmood ButtTahir Mahmood Butt
Tahir Mahmood Butt
 
Resume E&I Engineer
Resume E&I EngineerResume E&I Engineer
Resume E&I Engineer
 
Vijay cv
Vijay cvVijay cv
Vijay cv
 
Raghu Resume
Raghu Resume Raghu Resume
Raghu Resume
 
new_
new_new_
new_
 
Palanikumar Resume
Palanikumar ResumePalanikumar Resume
Palanikumar Resume
 
Cv tapan kumar prusty updated
Cv tapan kumar prusty updatedCv tapan kumar prusty updated
Cv tapan kumar prusty updated
 

Uma mahesh Resume

  • 1. CURRICULUM VITAE Page 1 of 4 UMA MAHESWARARAO ROUTHU Email:routhuumamahesh@gmail.com Mobile: 09985808028 Pass PortNo: M4839184 Career Objective To sustain an excellent and challenging career in the field of Instrumentation by exposing to the cutting edge technologies in a systematic manner and work dynamically towards thegoals of the organization. Professional Experience 3.10 years of working experience in the Power sector as an Erection & Commissioning engineer in which gained rich knowledge in Instrumentation Engineering principles and expertisein various operations. Current Employer:- Organization : Wonder Cement Ltd. Designation : Sr. Engineer (INSTRUMENTATION) Project : CPP (1x40MW) Location : Nimbahera,Chittorgarh (Rajasthan)  Currently involve in 1X40MW Power Plant maintenance and carried out following activities for the CPP project includingB.H.E.L Make Steam Turbine, Thermax 1 X 160 TPH CFBC Boiler,WTP&ETP,BOP  1x 40 MW Steam Turbine erection and commissioning  The Steam turbine master control device of Governing console board erection and commissioning it is a Steam Turbine speed,pressure,load controller by using Electronic Governer,Electrohydraulic Converter(1800) and Con- trol Valve Actuator(1910)  Turbine supervisory instruments like: vibration probes, Magnetic pickup units(MPU),Speed probes, Axial dis- placement Probes, Key pharos Probes Installation and commissioning work for The Turbine safety and reliable runningof the Steam Turbine  Erection & commissioning of Air Cooled condenser including Field instruments, Profibus PA devices e.g. Transmit- ters, Control valves,Cabletrays,Junction boxes, Cablelying.  1 x 160 TPH CFBC Boiler instruments erection , commissioningand maintenance  Involved in erection & commissioning of 5 nos. of PLC Siemens SIMATIC S71200 for Water treatment plant, Efflu- ent treatment plant& Sewage treatment plant.  Erection and commissioning of WTP, ETP & STP field instruments, analyzers, totalizers, cable trays, junction boxes, PLC panels.  Emerson makes Forbes marshal make PH analyzers and conductivity & ORP and Turbidity analyzers Erection Commissioning & calibration and maintains.  Steam and Water Analysis system Erection and commissioning and Maintains Including With PH and Conductivity analyzers calibration  ABB ACS800 up to 1250 KW VFD Erection,commissioning and Troubleshooting  Siemens G120 VFD up to 7.5 KW Erection,commissioning maintenanceand Trouble shooting  Coal and Lime handlingplantinstruments erection,commissioningand maintenance Job Profile  Erection & commissioningof field instruments.  Planning,schedulingof Projectprogramfor erection, Testing & commissioning.  Partof commissioningof TSI monitoringRack Bently Nevada
  • 2. CURRICULUM VITAE Page 2 of 4  Partof commissioningWoodward governor WWG-505  Steam Turbine Controller Valve actuator commissioning through WWG-505, Steam Turbine Controller Valve actu- ator commissioningthrough I/H converter From Field and WWG 505  Commissioningof governing consoleBoard.  Temperature Transmitters installation atPRDS and Primary super heater, secondary super heater.  RTDs installation for turbine General bearings, Turbine front pedestal Non-Active, Active Bearings, Generator Winding,Core, Tooth, HOT, COLD, Gear Box Rtds.  Proximity Sensors Like; Vibration, Speed, Magnetic Pick-Up(MPU), Axial displacement & Key Phaser installation at Turbine front, Turbine rear,Genarator front,rear,Gear Box for Turbine Safety and Reliable and trouble free run- ningrunning.  ABB ACS 800, Siemens G120 VFD drives Maintenance  Calibration, maintenance and checking of transmitters, gauges, switches, pneumatic control valves, MOVs, pneu- matic power cylinders.  Troubleshootingof all the problems regardingerection and commissioningfrominstrumentation prospect.  Planningfor daily manpower engagement.  Level transmitter installation in dearator, hotwell and coolingtower, HP heater, LP Heater, Condensate tank.  Pressure transmitter installation in Lube Oil, Jacking Oil, HP heater, LP Heater, Main steam, PRDS, Turbine extrac- tions,Dearator, Hotwel, Boiler flue has path, Boiler steam path, Plantinletsteam path.  Flow transmitter installation from boiler to high pressure header, hp header –turbine, feed water from dearator to steam drum (orificeand venture tube).  Installation and commissioningof RTD (PT-100) in turbine and thermocouple (k-type) in boiler area.  SPM, SOX,NOX,O2 Analyzers erection,commissioning,and maintenance  Materials (Instruments with proper data, Equipment with proper specifications) selection to purchase and negoti- ation with the material provider  Indent of materials and there certification  Maintain spareparts of all section of power plantinstruments.  Experienced in preparing documents, reports regarding maintenance, history cards and recording observations over equipment performance  Monitor day-to-day work carried outby Contractors.  Ensure availability of material atrighttime to enable them to complete C&I erection jobs in time.  Project commissioningjob.  Store related work issuing the material,instrument code opening with full specification in ERP,PR generate, follow up the material offered material technical specification checking & giving Clearance to purchase the material. Maintenance, troubleshooting,faultanalyzing,rectification,interlock checkingof E&I system Previous Employer: Organization : INTEQ AUTOMATION SERVICES PVT LTD. Designation : C&I Engineer Project : 1. LANCO POWER PROJECT 2. MYHOME INDUSTRIES LIMITED Location : Vijayawada,Kondapalli Kodhada,Mellachervu Capacity : 2X371 MW Combined cycle CPP-2(1x60MW)
  • 3. CURRICULUM VITAE Page 3 of 4 Professional summary: • Responsible for complete calibration, Cold loop and Hot loop checking, Installation & cabling of all field instru- ments of Gas turbine, Fuel gas conditioning system, GT Exhaust system, and equipment cooling water system and turbine control panel • Calibration and servicing of process sensors, Transmitters (SMART), Electronic, Pneumatic instruments, MOV and Pneumatic Control valves. • Studying of P & I, Control loop, wiringDiagrams and Cablescheduling. • Have knowledge in Hook up drawings. • Knowledge on turbine, boiler commissioning,start-up and testingprocedures. Handling Equipment’s of Instrumentation Kits: Calibrator ( Nag man PPC-20,Dead Weight Tester,Nagman Digital Calibrator), HART 475 Field communicator, CTP, Temperature Bath, Source Meter, Loop Calibrator, Fluke RMS Digital multimeter,Fluke 710 series RTD/Thermocouple Calibrator,Megger,DC Voltage Regulator, Rheostat. Educational Qualifications • Bachelor of Technology in Electrical & electronics Engineering from SBCE,Khammam,JNTU with 65.38% in 2011 • Intermediate (MPC) from Board of Intermediate Education,Andhra Pradesh with 73.4% in 2007. • Secondary School Certificate (SSC) from Secondary School Education,Andhra Pradesh with 77% in 2005 Technical SkillS: Core knowledge : Power Systems, electrical machines Operatingsystems : Windows XP,Windows 7 Packages : MS-Office 2007,2010,MicrosoftDynamic AX, ERP Personal details: Full Name : Umamaheswara Rao Routhu Father Name : KrishnamNaidu Date of Birth : 5th August, 1990 Nationality : Indian. Marital status : Single. Languages Known : Telugu, English,and Hindi. Current CTC : 3.8 Lacks + Parks Address : D.N0-1-32/1 kattula kaviti,Veeraghattam Srikakulam(Dist.) Andhra Pradesh – 532 460 Present Address : Qtr.no: E1/14, R.K.Nagar, Wonder Cement LTD, Rasool Pura Nimbahera, chittorgarh (Dist.), Rajasthan,Pin:312601 Place:Nimbahera, Rajasthan (Umamaheswara Rao Routhu)