SlideShare a Scribd company logo
1 of 21
BUILDING PROCESS
Notes 
• The following project schedule is from actual 
project. It was performed August 2014 in North- 
East Zambia, very rural area close to Tanzanian 
border 
• Crew for 14 on-site days consisted 
– 1 Master Engineer / Chief Supervisor (EHS) 
– 1 Project Manager / Supervisor (EHZ) 
– 2 Master Builders (EHZ) 
– 3 Bricklayers 
– 10-15 Workers (depending on day and tasks) 
– 4 women to carry water and gather grass 
– 2 women for support functions
About tools and methods 
• No construction equipment was used 
• The Earth House Crew provided all hand-held 
tools 
• Even gravel was crushed in place using 
small sledges
Rough Timeline 
Week 1 Week 2 Week 3 Week 4 Week 5 
Area cleaning 
Trenches for 
strip foundation 
Interlocking 
brick mfg 
Adobe brick mfg 
Strip foundation 
Interlock & adobe curing 
Steel pre-cut 
Week 6 Week 7 Week 8 Week 9 Week 10 
Procurement 
and pre-staging 
Logistics 
On Site work and delivery
Preparatory work 
• 2 days - area cleaning and baselines for 
strip foundation 
• 1 day to cast and few days to cure
Adobe and clay works 
• 3 days to create 
interlocking bricks for 
plinth 
• 5 days to create 
adobe bricks for in-filling 
• 2-3 weeks to cure the 
bricks
Steel preparation 
and logistics 
• Earth House Systems™ frames are 
manufactured in Lusaka 
• Roof and span structure is subcontracted 
• 4 days (two men) - structural steel cutting 
and tension rod manufacturing 
• All material and tools are pre-staged in 
warehouse and loaded to a single, 7 ton 
truck
Site Day 1 
• Set up work site, perimeter and occupational 
safety 
• Double-check strip foundation dimensions and 
lay up baselines
Site Day 2 
• Create plinth from 
interlocking bricks 
• Start frame assembly
Site Day 3 
• Detail, plaster and finish plinth 
• Continue frame assembly
Site Day 4 
• Cast and finish concrete slab 
• Finish frame assembly
Site Day 5 
• Lay up assembly plates 
• Start steel works
Site Day 6 
• Preparations for clay 
works 
• Finish steel works
Site Day 7 
• Clay works 
starting from the 
lower frames
Site Day 8 
• Finish in filling with 
adobe bricks, 
shaving and 
smoothing of walls 
• First coat 
plastering, lower 
frames 
• Start roof assembly
Site Day 9 
• Attach heavy-duty 
expanded wire to 
exterior walls 
• First coat 
plastering, interior 
walls, upper frames 
• First coat 
plastering, exterior 
walls
Site Day 10 
• Second coat, 
exterior plastering 
• Finishing exterior 
plastering 
• Electrical work 
preparations
Site Day 11 
• Second coat, interior plastering 
• Finishing, interior plastering
Site Day 12 
• Limewashing inside 
and outside 
• Electrical assembly
Site Day 13 
• Door and panel 
mounting 
• Limewash inside 
and outside 
• Cement floor 
casting
Site Day 14 
• Final detailing 
• Handover to customer

More Related Content

What's hot

Affordable Housing 10 days lcm unit
Affordable Housing   10 days lcm unitAffordable Housing   10 days lcm unit
Affordable Housing 10 days lcm unitJohn Masanda, ACIM
 
Portfolio_Hyunjong Choi
Portfolio_Hyunjong ChoiPortfolio_Hyunjong Choi
Portfolio_Hyunjong ChoiHyunjong Choi
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and ProcessWilden How
 
Building Construction process
Building Construction processBuilding Construction process
Building Construction processJoanne Yunn Tze
 
Chris Tom Labourer resume
Chris Tom Labourer resume Chris Tom Labourer resume
Chris Tom Labourer resume Chris Tom
 
Brochure ozr 2 rev1
Brochure ozr 2 rev1Brochure ozr 2 rev1
Brochure ozr 2 rev1hamidahafifi
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report I'mMiss Lily
 
Company Brochure
Company BrochureCompany Brochure
Company BrochureErin Saiki
 
PRESENTATION ON THE INTERNSHIP
 PRESENTATION ON THE INTERNSHIP PRESENTATION ON THE INTERNSHIP
PRESENTATION ON THE INTERNSHIPSufiyanAhmedJeddy
 
Ahli Bank Head Office Building - TimeLine
Ahli Bank Head Office Building - TimeLineAhli Bank Head Office Building - TimeLine
Ahli Bank Head Office Building - TimeLineAnuj Ramdas
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015Joyce HweeMin
 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Hammam El Meseiry
 
Assembling Powerbilt Building
Assembling Powerbilt BuildingAssembling Powerbilt Building
Assembling Powerbilt Buildingpowerbilt
 

What's hot (20)

Affordable Housing 10 days lcm unit
Affordable Housing   10 days lcm unitAffordable Housing   10 days lcm unit
Affordable Housing 10 days lcm unit
 
TOMS RESUME
TOMS RESUMETOMS RESUME
TOMS RESUME
 
Portfolio_Hyunjong Choi
Portfolio_Hyunjong ChoiPortfolio_Hyunjong Choi
Portfolio_Hyunjong Choi
 
ITS Building Project - progress update 5
ITS Building Project - progress update 5ITS Building Project - progress update 5
ITS Building Project - progress update 5
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and Process
 
Building Construction process
Building Construction processBuilding Construction process
Building Construction process
 
Airport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation ProjectAirport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation Project
 
How We Built The St. Bernard Branch Library From the Ground Up
How We Built The St. Bernard Branch Library From the Ground UpHow We Built The St. Bernard Branch Library From the Ground Up
How We Built The St. Bernard Branch Library From the Ground Up
 
Chris Tom Labourer resume
Chris Tom Labourer resume Chris Tom Labourer resume
Chris Tom Labourer resume
 
Payne Elementary School SIT Meeting (June 2, 2016)
Payne Elementary School SIT Meeting (June 2, 2016)Payne Elementary School SIT Meeting (June 2, 2016)
Payne Elementary School SIT Meeting (June 2, 2016)
 
Paul OBrien CV
Paul OBrien CVPaul OBrien CV
Paul OBrien CV
 
Brochure ozr 2 rev1
Brochure ozr 2 rev1Brochure ozr 2 rev1
Brochure ozr 2 rev1
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
Company Brochure
Company BrochureCompany Brochure
Company Brochure
 
PRESENTATION ON THE INTERNSHIP
 PRESENTATION ON THE INTERNSHIP PRESENTATION ON THE INTERNSHIP
PRESENTATION ON THE INTERNSHIP
 
Exercise
ExerciseExercise
Exercise
 
Ahli Bank Head Office Building - TimeLine
Ahli Bank Head Office Building - TimeLineAhli Bank Head Office Building - TimeLine
Ahli Bank Head Office Building - TimeLine
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)
 
Assembling Powerbilt Building
Assembling Powerbilt BuildingAssembling Powerbilt Building
Assembling Powerbilt Building
 

Similar to Earth House Field Building Process

K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionascemiami-dade
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
 
Building maintenance
Building maintenance Building maintenance
Building maintenance Janki Patel
 
siddhant .construction field visit.pptx
siddhant .construction field visit.pptxsiddhant .construction field visit.pptx
siddhant .construction field visit.pptxSiddhantAshokSuryawa
 
lecture 5 - Technical Specifications and MM.pptx
lecture 5 - Technical Specifications and MM.pptxlecture 5 - Technical Specifications and MM.pptx
lecture 5 - Technical Specifications and MM.pptxBossGold
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxSardarMuhammadHashir
 
The National Eco House Oman
The National Eco House OmanThe National Eco House Oman
The National Eco House OmanMECandPMV
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 

Similar to Earth House Field Building Process (20)

K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progression
 
Client Presentation
Client PresentationClient Presentation
Client Presentation
 
Ferrouscementhouse 2
Ferrouscementhouse 2Ferrouscementhouse 2
Ferrouscementhouse 2
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
siddhant .construction field visit.pptx
siddhant .construction field visit.pptxsiddhant .construction field visit.pptx
siddhant .construction field visit.pptx
 
Ryan Arendse
Ryan ArendseRyan Arendse
Ryan Arendse
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 
lecture 5 - Technical Specifications and MM.pptx
lecture 5 - Technical Specifications and MM.pptxlecture 5 - Technical Specifications and MM.pptx
lecture 5 - Technical Specifications and MM.pptx
 
Factory built substation case study
Factory built substation case studyFactory built substation case study
Factory built substation case study
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptx
 
The National Eco House Oman
The National Eco House OmanThe National Eco House Oman
The National Eco House Oman
 
Steel buildings
Steel buildings  Steel buildings
Steel buildings
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Ravi Resume
Ravi ResumeRavi Resume
Ravi Resume
 
Benjamin Weiser Resume
Benjamin Weiser ResumeBenjamin Weiser Resume
Benjamin Weiser Resume
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Earth House Field Building Process

  • 2. Notes • The following project schedule is from actual project. It was performed August 2014 in North- East Zambia, very rural area close to Tanzanian border • Crew for 14 on-site days consisted – 1 Master Engineer / Chief Supervisor (EHS) – 1 Project Manager / Supervisor (EHZ) – 2 Master Builders (EHZ) – 3 Bricklayers – 10-15 Workers (depending on day and tasks) – 4 women to carry water and gather grass – 2 women for support functions
  • 3. About tools and methods • No construction equipment was used • The Earth House Crew provided all hand-held tools • Even gravel was crushed in place using small sledges
  • 4. Rough Timeline Week 1 Week 2 Week 3 Week 4 Week 5 Area cleaning Trenches for strip foundation Interlocking brick mfg Adobe brick mfg Strip foundation Interlock & adobe curing Steel pre-cut Week 6 Week 7 Week 8 Week 9 Week 10 Procurement and pre-staging Logistics On Site work and delivery
  • 5. Preparatory work • 2 days - area cleaning and baselines for strip foundation • 1 day to cast and few days to cure
  • 6. Adobe and clay works • 3 days to create interlocking bricks for plinth • 5 days to create adobe bricks for in-filling • 2-3 weeks to cure the bricks
  • 7. Steel preparation and logistics • Earth House Systems™ frames are manufactured in Lusaka • Roof and span structure is subcontracted • 4 days (two men) - structural steel cutting and tension rod manufacturing • All material and tools are pre-staged in warehouse and loaded to a single, 7 ton truck
  • 8. Site Day 1 • Set up work site, perimeter and occupational safety • Double-check strip foundation dimensions and lay up baselines
  • 9. Site Day 2 • Create plinth from interlocking bricks • Start frame assembly
  • 10. Site Day 3 • Detail, plaster and finish plinth • Continue frame assembly
  • 11. Site Day 4 • Cast and finish concrete slab • Finish frame assembly
  • 12. Site Day 5 • Lay up assembly plates • Start steel works
  • 13. Site Day 6 • Preparations for clay works • Finish steel works
  • 14. Site Day 7 • Clay works starting from the lower frames
  • 15. Site Day 8 • Finish in filling with adobe bricks, shaving and smoothing of walls • First coat plastering, lower frames • Start roof assembly
  • 16. Site Day 9 • Attach heavy-duty expanded wire to exterior walls • First coat plastering, interior walls, upper frames • First coat plastering, exterior walls
  • 17. Site Day 10 • Second coat, exterior plastering • Finishing exterior plastering • Electrical work preparations
  • 18. Site Day 11 • Second coat, interior plastering • Finishing, interior plastering
  • 19. Site Day 12 • Limewashing inside and outside • Electrical assembly
  • 20. Site Day 13 • Door and panel mounting • Limewash inside and outside • Cement floor casting
  • 21. Site Day 14 • Final detailing • Handover to customer