Head Office Building
Muscat, Sultanate of Oman

TimeLine
2011 - 2014

Compiled by
Anuj Ramdas, Resident Engineer
Engineeri...
Project Details
Plot No.

107/2

Plot Area

10,736 sq. m.

Location

Al Wattayah

Type of Building

Commercial

Area Calcu...
Background

Client

Architect

Consultant

Main Contractor
August

2011

Site Enabling Works
September

2011

Site Enabling Works
13th December

2011

Stone Laying Ceremony
13th December

2011

Stone Laying Ceremony
13th December

2011

Stone Laying Ceremony
December

2011

Site Mobilization
December

2011

First concrete pour at site!
December

2011

First concrete pour at site!
December

2011

First concrete pour at site!
December

2011

Blinding for footings
January

2012

Basement Raft Excavation
January

2012

Basement Raft Blinding
January

2012

Curing Basement Blinding
January

2012

Blinding Waterproofing
January

2012

Footing Reinforcement Works
January

2012

Basement Waterproofing
January

2012

Basement Raft Blinding
January

2012

Blinding Bitumen Coat Application
January

2012

Concreting Footing
January

2012

Raft Reinforcement Works
January

2012

Footing Bitumen Coat Application
January

2012

Raft Reinforcement Works
January

2012

Raft Reinforcement Works
January

2012

Raft Reinforcement Works
February

2012

Raft Concreting
February

2012

Column Reinforcement
February

2012

Column & Retaining Wall Reinforcement
February

2012

Isolated Footings
February

2012

Isolated Footings
February

2012

Compaction Tests
February

2012

Basement Wall Waterproofing
February

2012

Isolated Footings & Earth Compaction
February

2012

Basement Columns
February

2012

Basement Passenger Lift
March

2012

Earth Filling
March

2012

Ground Floor slab shuttering
March

2012

Earth Filling
March

2012

Earth Filling
March

2012

Post Tension (PT) Strand Marking
March

2012

Plinth Beam Works
April

2012

Ground Floor PT Slab Concreting
April

2012

Staircase Concreting
April

2012

Grade Slab Concreting
April

2012

Ground Floor
April

2012

First Floor Slab Shuttering
April

2012

First Floor Slab Shuttering
May

2012

First Floor Slab Reinforcement & PT Strands
May

2012

First Floor Slab Reinforcement & PT Strands
May

2012

First Floor Concreting
May

2012

First Floor Concreting in progress next day
May

2012

Elevation Work Progress
May

2012

Elevation Work Progress
May

2012

Elevation Work Progress
May

2012

Second Floor Slab Reinforcement & PT Strands
May

2012

Second Floor Slab Reinforcement & PT Strands
May

2012

Second Floor Curing
May

2012

Second Floor Curing
May

2012

Third Floor Slab Shuttering
May

2012

Elevation View
May

2012

Third Floor Slab Shuttering
June

2012

Basement Block work
June

2012

Elevation View
July

2012

Third Floor Slab Reinforcement & PT Strands
July

2012

Third Floor Slab Reinforcement & PT Strands
July

2012

Third Floor Slab Reinforcement & PT Strands
July

2012

Staircase Block work
July

2012

Elevation Block work
July

2012

Entrance Structure
July

2012

Bridge Scaffolding
July

2012

Internal Elevations
July

2012

Internal Elevations
July

2012

External Elevation
July

2012

Entrance Elevation
July

2012

Internal Elevation
July

2012

Internal Elevation
July

2012

Internal Elevation
July

2012

External Elevation
July

2012

External Elevation
July

2012

External Elevation
July

2012

Internal Elevation
July

2012

Internal Elevation
July

2012

Internal View
July

2012

External View
July

2012

External View
August

2012

Lift Top Slab Concreting
September

2012

Bitumen Application
September

2012

Internal Floor light weight concreting
September

2012

Atrium Space
September

2012

Elevation View
September

2012

Curtainwall work begins
October

2012

Extension Building Excavation work begins
October

2012

Stone Cladding
October

2012

Skylight Metal Works
October

2012

Elevation View
October

2012

Stone Cladding
October

2012

Stone Cladding
November

2012

Internal Finishes
December

2012

Atrium Works
December

2012

Elevation Works
December

2012

Skylight Metal Works
December

2012

Extension Building Foundation Works
December

2012

Elevation Works
December

2012

Elevation Works
December

2012

Elevation Works
December

2012

Elevation Works
January

2013

Elevation Works
January

2013

Elevation Works
January

2013

Extension Building Compaction Works
January

2013

Elevation Works
January

2013

Water Feature Works
January

2013

Elevation Works
January

2013

Extension Plinth Works
January

2013

Internal Finishes
January

2013

External Elevation
January

2013

Extension Fist Floor PT Slab
January

2013

Service Building Works
January

2013

Internal Services
January

2013

Internal Works
January

2013

Internal Works
January

2013

Internal Works
January

2013

Skylight Aluminium Works
January

2013

Extension Building Slab Curing
January

2013

Rear View
January

2013

Elevation View
January

2013

Elevation View
February

2013

Water Feature Works
February

2013

Atrium Works
February

2013

Elevation Views
February

2013

Internal Elevation Views
February

2013

Internal Elevation Views
February

2013

Internal Elevation Views
February

2013

Internal Elevation Views
February

2013

Internal Elevation Views
February

2013

Internal Elevation Views
February

2013

Extension Building Elevation
February

2013

Internal Elevation Views
February

2013

Rear Views
February

2013

Water Feature Concrete Works
February

2013

Extension Building Elevation
February

2013

Atrium Services
February

2013

External Irrigation Works
March

2013

Internal Services
March

2013

Atrium View
March

2013

External Elevation
March

2013

Atrium Hanging Staircase
March

2013

Atrium Metal Works
March

2013

Extension Building Block Works
March

2013

Atrium Finishes
March

2013

Atrium Finishes
March

2013

Extension Works
March

2013

Elevation View
March

2013

Extension View
April

2013

Atrium Works
April

2013

Office Area
April

2013

External Elevation
April

2013

External Bitumen Application
April

2013

External Works
April

2013

External Works
April

2013

External Works
April

2013

External Works
April

2013

Skylight Metal Works
April

2013

Extension Elevation
April

2013

Skylight Glazing Works
May

2013

Atrium Ducting Works
May

2013

Water Feature Works
May

2013

Water Feature Works
May

2013

Extension Building Cladding Works
May

2013

Atrium Curtainwall Erection
May

2013

Extension Building Curtainwall Works
May

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Elevation View
June

2013

Office Area
June

2013

Elevation View
June

2013

Atrium Curtainwall Works
June

2013

Irrigation Works
June

2013

Extension View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
June

2013

Atrium View
August

2013

Basement Cafeteria
August

2013

Auditorium
August

2013

Office Area
August

2013

Elevation View
August

2013

Elevation View
August

2013

Atrium Curtainwall
August

2013

Elevation View
August

2013

Atrium View
August

2013

Hanging Staircase View
September

2013

Elevation View
September

2013

Elevation View
September

2013

Elevation View
September

2013

Elevation View
September

2013

Atrium View
September

2013

Atrium View
September

2013

Atrium View
September

2013

Atrium View
October

2013

Elevation View
October

2013

Atrium View
October

2013

Atrium View
October

2013

Executive Area
October

2013

Elevation View
October

2013

Elevation View
October

2013

Elevation View
November

2013

Executive Area
November

2013

Executive Area
November

2013

Islamic Banking Area
November

2013

Panoramic Lift
November

2013

National Day Elevation View
December

2013

Atrium View
January

2014

Reception Desk
January

2014

Customer Waiting Area
January

2014

Atrium View
January

2014

Atrium View
January

2014

Elevation View
January

2014

Elevation View
January

2014
January

2014
Upcoming SlideShare
Loading in …5
×

Ahli Bank Head Office Building - TimeLine

1,407 views

Published on

Construction Time Line of Head Office Building

Published in: Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,407
On SlideShare
0
From Embeds
0
Number of Embeds
3
Actions
Shares
0
Downloads
7
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Ahli Bank Head Office Building - TimeLine

  1. 1. Head Office Building Muscat, Sultanate of Oman TimeLine 2011 - 2014 Compiled by Anuj Ramdas, Resident Engineer Engineering Innovation Design & Consulting LLC
  2. 2. Project Details Plot No. 107/2 Plot Area 10,736 sq. m. Location Al Wattayah Type of Building Commercial Area Calculations Basement Floor Phase 1A Phase 1B 907.04 sq. m. Ground Floor 1,370.43 sq. m. 312.54 sq. m. First Floor 1,263.46 sq. m. 309.67 sq. m. Second Floor 1,264.18 sq. m. 311.33 sq. m. Third Floor 1,722.79 sq. m. 411.97 sq. m. Built Up 6,527.90 sq. m. 1,345.61 sq. m. Total Built Up Area 7,873.51 sq. m.
  3. 3. Background Client Architect Consultant Main Contractor
  4. 4. August 2011 Site Enabling Works
  5. 5. September 2011 Site Enabling Works
  6. 6. 13th December 2011 Stone Laying Ceremony
  7. 7. 13th December 2011 Stone Laying Ceremony
  8. 8. 13th December 2011 Stone Laying Ceremony
  9. 9. December 2011 Site Mobilization
  10. 10. December 2011 First concrete pour at site!
  11. 11. December 2011 First concrete pour at site!
  12. 12. December 2011 First concrete pour at site!
  13. 13. December 2011 Blinding for footings
  14. 14. January 2012 Basement Raft Excavation
  15. 15. January 2012 Basement Raft Blinding
  16. 16. January 2012 Curing Basement Blinding
  17. 17. January 2012 Blinding Waterproofing
  18. 18. January 2012 Footing Reinforcement Works
  19. 19. January 2012 Basement Waterproofing
  20. 20. January 2012 Basement Raft Blinding
  21. 21. January 2012 Blinding Bitumen Coat Application
  22. 22. January 2012 Concreting Footing
  23. 23. January 2012 Raft Reinforcement Works
  24. 24. January 2012 Footing Bitumen Coat Application
  25. 25. January 2012 Raft Reinforcement Works
  26. 26. January 2012 Raft Reinforcement Works
  27. 27. January 2012 Raft Reinforcement Works
  28. 28. February 2012 Raft Concreting
  29. 29. February 2012 Column Reinforcement
  30. 30. February 2012 Column & Retaining Wall Reinforcement
  31. 31. February 2012 Isolated Footings
  32. 32. February 2012 Isolated Footings
  33. 33. February 2012 Compaction Tests
  34. 34. February 2012 Basement Wall Waterproofing
  35. 35. February 2012 Isolated Footings & Earth Compaction
  36. 36. February 2012 Basement Columns
  37. 37. February 2012 Basement Passenger Lift
  38. 38. March 2012 Earth Filling
  39. 39. March 2012 Ground Floor slab shuttering
  40. 40. March 2012 Earth Filling
  41. 41. March 2012 Earth Filling
  42. 42. March 2012 Post Tension (PT) Strand Marking
  43. 43. March 2012 Plinth Beam Works
  44. 44. April 2012 Ground Floor PT Slab Concreting
  45. 45. April 2012 Staircase Concreting
  46. 46. April 2012 Grade Slab Concreting
  47. 47. April 2012 Ground Floor
  48. 48. April 2012 First Floor Slab Shuttering
  49. 49. April 2012 First Floor Slab Shuttering
  50. 50. May 2012 First Floor Slab Reinforcement & PT Strands
  51. 51. May 2012 First Floor Slab Reinforcement & PT Strands
  52. 52. May 2012 First Floor Concreting
  53. 53. May 2012 First Floor Concreting in progress next day
  54. 54. May 2012 Elevation Work Progress
  55. 55. May 2012 Elevation Work Progress
  56. 56. May 2012 Elevation Work Progress
  57. 57. May 2012 Second Floor Slab Reinforcement & PT Strands
  58. 58. May 2012 Second Floor Slab Reinforcement & PT Strands
  59. 59. May 2012 Second Floor Curing
  60. 60. May 2012 Second Floor Curing
  61. 61. May 2012 Third Floor Slab Shuttering
  62. 62. May 2012 Elevation View
  63. 63. May 2012 Third Floor Slab Shuttering
  64. 64. June 2012 Basement Block work
  65. 65. June 2012 Elevation View
  66. 66. July 2012 Third Floor Slab Reinforcement & PT Strands
  67. 67. July 2012 Third Floor Slab Reinforcement & PT Strands
  68. 68. July 2012 Third Floor Slab Reinforcement & PT Strands
  69. 69. July 2012 Staircase Block work
  70. 70. July 2012 Elevation Block work
  71. 71. July 2012 Entrance Structure
  72. 72. July 2012 Bridge Scaffolding
  73. 73. July 2012 Internal Elevations
  74. 74. July 2012 Internal Elevations
  75. 75. July 2012 External Elevation
  76. 76. July 2012 Entrance Elevation
  77. 77. July 2012 Internal Elevation
  78. 78. July 2012 Internal Elevation
  79. 79. July 2012 Internal Elevation
  80. 80. July 2012 External Elevation
  81. 81. July 2012 External Elevation
  82. 82. July 2012 External Elevation
  83. 83. July 2012 Internal Elevation
  84. 84. July 2012 Internal Elevation
  85. 85. July 2012 Internal View
  86. 86. July 2012 External View
  87. 87. July 2012 External View
  88. 88. August 2012 Lift Top Slab Concreting
  89. 89. September 2012 Bitumen Application
  90. 90. September 2012 Internal Floor light weight concreting
  91. 91. September 2012 Atrium Space
  92. 92. September 2012 Elevation View
  93. 93. September 2012 Curtainwall work begins
  94. 94. October 2012 Extension Building Excavation work begins
  95. 95. October 2012 Stone Cladding
  96. 96. October 2012 Skylight Metal Works
  97. 97. October 2012 Elevation View
  98. 98. October 2012 Stone Cladding
  99. 99. October 2012 Stone Cladding
  100. 100. November 2012 Internal Finishes
  101. 101. December 2012 Atrium Works
  102. 102. December 2012 Elevation Works
  103. 103. December 2012 Skylight Metal Works
  104. 104. December 2012 Extension Building Foundation Works
  105. 105. December 2012 Elevation Works
  106. 106. December 2012 Elevation Works
  107. 107. December 2012 Elevation Works
  108. 108. December 2012 Elevation Works
  109. 109. January 2013 Elevation Works
  110. 110. January 2013 Elevation Works
  111. 111. January 2013 Extension Building Compaction Works
  112. 112. January 2013 Elevation Works
  113. 113. January 2013 Water Feature Works
  114. 114. January 2013 Elevation Works
  115. 115. January 2013 Extension Plinth Works
  116. 116. January 2013 Internal Finishes
  117. 117. January 2013 External Elevation
  118. 118. January 2013 Extension Fist Floor PT Slab
  119. 119. January 2013 Service Building Works
  120. 120. January 2013 Internal Services
  121. 121. January 2013 Internal Works
  122. 122. January 2013 Internal Works
  123. 123. January 2013 Internal Works
  124. 124. January 2013 Skylight Aluminium Works
  125. 125. January 2013 Extension Building Slab Curing
  126. 126. January 2013 Rear View
  127. 127. January 2013 Elevation View
  128. 128. January 2013 Elevation View
  129. 129. February 2013 Water Feature Works
  130. 130. February 2013 Atrium Works
  131. 131. February 2013 Elevation Views
  132. 132. February 2013 Internal Elevation Views
  133. 133. February 2013 Internal Elevation Views
  134. 134. February 2013 Internal Elevation Views
  135. 135. February 2013 Internal Elevation Views
  136. 136. February 2013 Internal Elevation Views
  137. 137. February 2013 Internal Elevation Views
  138. 138. February 2013 Extension Building Elevation
  139. 139. February 2013 Internal Elevation Views
  140. 140. February 2013 Rear Views
  141. 141. February 2013 Water Feature Concrete Works
  142. 142. February 2013 Extension Building Elevation
  143. 143. February 2013 Atrium Services
  144. 144. February 2013 External Irrigation Works
  145. 145. March 2013 Internal Services
  146. 146. March 2013 Atrium View
  147. 147. March 2013 External Elevation
  148. 148. March 2013 Atrium Hanging Staircase
  149. 149. March 2013 Atrium Metal Works
  150. 150. March 2013 Extension Building Block Works
  151. 151. March 2013 Atrium Finishes
  152. 152. March 2013 Atrium Finishes
  153. 153. March 2013 Extension Works
  154. 154. March 2013 Elevation View
  155. 155. March 2013 Extension View
  156. 156. April 2013 Atrium Works
  157. 157. April 2013 Office Area
  158. 158. April 2013 External Elevation
  159. 159. April 2013 External Bitumen Application
  160. 160. April 2013 External Works
  161. 161. April 2013 External Works
  162. 162. April 2013 External Works
  163. 163. April 2013 External Works
  164. 164. April 2013 Skylight Metal Works
  165. 165. April 2013 Extension Elevation
  166. 166. April 2013 Skylight Glazing Works
  167. 167. May 2013 Atrium Ducting Works
  168. 168. May 2013 Water Feature Works
  169. 169. May 2013 Water Feature Works
  170. 170. May 2013 Extension Building Cladding Works
  171. 171. May 2013 Atrium Curtainwall Erection
  172. 172. May 2013 Extension Building Curtainwall Works
  173. 173. May 2013 Atrium View
  174. 174. June 2013 Atrium View
  175. 175. June 2013 Atrium View
  176. 176. June 2013 Atrium View
  177. 177. June 2013 Elevation View
  178. 178. June 2013 Office Area
  179. 179. June 2013 Elevation View
  180. 180. June 2013 Atrium Curtainwall Works
  181. 181. June 2013 Irrigation Works
  182. 182. June 2013 Extension View
  183. 183. June 2013 Atrium View
  184. 184. June 2013 Atrium View
  185. 185. June 2013 Atrium View
  186. 186. June 2013 Atrium View
  187. 187. June 2013 Atrium View
  188. 188. June 2013 Atrium View
  189. 189. August 2013 Basement Cafeteria
  190. 190. August 2013 Auditorium
  191. 191. August 2013 Office Area
  192. 192. August 2013 Elevation View
  193. 193. August 2013 Elevation View
  194. 194. August 2013 Atrium Curtainwall
  195. 195. August 2013 Elevation View
  196. 196. August 2013 Atrium View
  197. 197. August 2013 Hanging Staircase View
  198. 198. September 2013 Elevation View
  199. 199. September 2013 Elevation View
  200. 200. September 2013 Elevation View
  201. 201. September 2013 Elevation View
  202. 202. September 2013 Atrium View
  203. 203. September 2013 Atrium View
  204. 204. September 2013 Atrium View
  205. 205. September 2013 Atrium View
  206. 206. October 2013 Elevation View
  207. 207. October 2013 Atrium View
  208. 208. October 2013 Atrium View
  209. 209. October 2013 Executive Area
  210. 210. October 2013 Elevation View
  211. 211. October 2013 Elevation View
  212. 212. October 2013 Elevation View
  213. 213. November 2013 Executive Area
  214. 214. November 2013 Executive Area
  215. 215. November 2013 Islamic Banking Area
  216. 216. November 2013 Panoramic Lift
  217. 217. November 2013 National Day Elevation View
  218. 218. December 2013 Atrium View
  219. 219. January 2014 Reception Desk
  220. 220. January 2014 Customer Waiting Area
  221. 221. January 2014 Atrium View
  222. 222. January 2014 Atrium View
  223. 223. January 2014 Elevation View
  224. 224. January 2014 Elevation View
  225. 225. January 2014
  226. 226. January 2014

×