This document outlines a 10-day construction schedule to build an office block using light weight concrete. It involves site clearance, excavation, pouring the foundation and slab on days 1-3. Formwork is installed on day 4, and walls are poured on day 6. Trusses are installed on day 6 as well. Formwork is removed on day 8 along with roofing, undercoat painting, tiles, windows and doors. Finishing works like lighting, plumbing and finishes are completed on days 9-10.