SlideShare a Scribd company logo
1 of 21
10/02/2012 Slide 1
Fusing Metering
Voltages for High
Capacity Circuits
Notes from the Field
Prepared by Tom Lawton,TESCO
for the Spring ECNE Engineering & Operations Conference 2015
• Fused test switches have been around for many years.
• Fused potentials have been around for many years.
• However over the past twenty years they have boomed in popularity and
boomed in usage.
• In the same time period fused test leads on field meter testing equipment
have gone from a once in a blue moon request to a standard request.
What is the Issue?
• With the advent of auto-ranging meters Utilities
started to recognize that VT’s were no longer
necessary on every service.
• And this is true. But…….
What has changed?
• The voltage transformer is designed to connect in parallel with the line to transform the line voltage to 115 or 120
volts suitable for the meter or relay. To keep the voltage at the meters and relays at a safe value, the secondary
circuit must be grounded. Source ABB
• The name instrument transformer is a general classification applied to current and voltage devices used to
change currents and voltages from one magnitude to another or to perform an isolating function, that is, to isolate
the utilization current or voltage from the supply voltage for safety to both the operator and the end device in use.
Instrument transformers are designed specifically for use with electrical equipment falling into the broad category
of devices commonly called instruments such as voltmeters, ammeters, wattmeters, watt-hour meters, protection
relays, etc. Source GE
• VT’s not only step down the voltage to 120v for metering purposes, but they provide a safety feature to the circuit.
The VT is a current limiting component in the circuit.
• The fault current for a VT is typically the same or less than the fault amps of the meter (typ. 10,000 amps).
Voltage Transformers as Safety Devices?
• Within recent years, auto-ranging meters have been
introduced.
• VT’s have been eliminated for many applications.
• This means the field technician is now dealing with the
primary voltage.
Autoranging meters
A little about Fault Currents
• A fuse or breaker designed to
interrupt the largest potential
short-circuit currents can be
helpful on some days.
Short Circuit Current > Interrupt Rating =
• Overcurrent protective devices must be selected for the proper
– Voltage
– Current
– Interrupt rating
• This last one is the one most typically overlooked. This is also the one most
people do not understand how to plan for or calculate.
• Current limiting is a type of over current protection
• An overcurrent protective device must be able to withstand the destructive
energy of short-circuit currents.
A little about Fault Currents
Short-Circuit Currents & Interrupting Rating
Short-Circuit Currents & Interrupting Rating
• SCCR’s represent the maximum level of short-circuit current that the component or
equipment can withstand under fault conditions .
• This is used for determining compliance with NEC® 110.10.
• This rating can be marked on individual components or assemblies.
• Assembly ratings take into account all components contained within the equipment
rather than just the main overcurrent protective device.
• A common mistake is to assume that the interrupting rating of the overcurrent
protective device protecting the circuit represents the SCCR for the entire circuit.
Interrupting ratings, used for compliance with NEC® 110.9, apply solely to the
overcurrent protective device. It is the characteristics of the overcurrent protective
device (e.g. opening time, let-through energy) that need to be used in determining
compliance with NEC® 110.10, not the interrupting rating.
• NOTE: Short-circuit current ratings (SCCRs) are different than interrupting ratings
marked on overcurrent protective devices.
What is a Short-Circuit Current Rating
(SCCR) ?
• For meter disconnect switches, this withstand
level (SCCR), is often determined by product
testing. For assemblies, the marking can be
determined through product listing or by an
approved method.
• Any valid method uses the “weakest link”
approach. The marking should represent the
limits of the assembly for a safe installation.
How is SCCR Determined?
Point-to-Point Method of Short-Circuit
Calculations
• Some have added fused potentials in line or at the test switch
for transformer rated services.
What have utilities changed as a result of losing
the isolation and current limiting features of a
voltage transformer?
• Some have gone to fused test leads for their field technicians.
Fusing The Test Switch
Meter Test Switch Configurations
• Layout
• Handle Colors
• Reversed vs. Normal Potentials
• Current Links
• Base Sizing
• Barrier Locations
NOTE: On installations that contain Test Switches, test leads terminated
with a test switch safety test probe (test plug) should be used for CT
testing. This provides a “make-before-break” connection to prevent
accidental opening of the current transformer secondary loop.
Fitting into a Pre-Wired Transformer Rated
Enclosure?
• Move items around
• Small nipple box with
four pole switch base
and fusing
• Some have gone to cold sequencing for self contained
services.
Cold Sequencing
• Some rely on better PPE for their Meter Techs
PPE
• Some have not changed their metering practices at all.
• Utilities are not required to fuse the circuits.
• Do we really need to do anything?
None of the Above!
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
Tom.Lawton@tescometermanager.com
Cell: 215-688-0298
This presentation can also be found under Meter Conferences
and Schools on the TESCO web site: www.tesco-advent.com

More Related Content

What's hot

Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protectionChetan Patil
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisPower System Operation
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONMd Sarowar Alam
 
Practical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansPractical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansLiving Online
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordinationmichaeljmack
 
Electro Mechanical v/s Numerical Relay
Electro Mechanical v/s Numerical RelayElectro Mechanical v/s Numerical Relay
Electro Mechanical v/s Numerical RelaySWAPNIL GHAISAS
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordinationmichaeljmack
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devicesPrakash_13209
 
Er rahul sharma feeder protection
Er rahul sharma feeder protectionEr rahul sharma feeder protection
Er rahul sharma feeder protectionRahul Ruddra
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basicsRajan Singh Tanwar
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear StandardsBryan Johnson
 

What's hot (20)

Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash Analysis
 
Protection basic
Protection basicProtection basic
Protection basic
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
7SR10 Overcurrent Relay
7SR10 Overcurrent Relay7SR10 Overcurrent Relay
7SR10 Overcurrent Relay
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATION
 
Practical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansPractical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and Technicians
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
Electro Mechanical v/s Numerical Relay
Electro Mechanical v/s Numerical RelayElectro Mechanical v/s Numerical Relay
Electro Mechanical v/s Numerical Relay
 
auto-reclosure
auto-reclosureauto-reclosure
auto-reclosure
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
 
7SR11 Overcurrent Relay
7SR11 Overcurrent Relay7SR11 Overcurrent Relay
7SR11 Overcurrent Relay
 
Er rahul sharma feeder protection
Er rahul sharma feeder protectionEr rahul sharma feeder protection
Er rahul sharma feeder protection
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
relay-distance relay basics
relay-distance relay basicsrelay-distance relay basics
relay-distance relay basics
 

Viewers also liked

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 

Viewers also liked (15)

Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
 
CT Burden Testing
CT Burden TestingCT Burden Testing
CT Burden Testing
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
In-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI DeploymentIn-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI Deployment
 
Customer Perceptions of New AMI Meters
Customer Perceptions of New AMI MetersCustomer Perceptions of New AMI Meters
Customer Perceptions of New AMI Meters
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs
 
Hot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best PracticesHot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best Practices
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter RecordsMeter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter Records
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After Deployment
 

Similar to Fusing Metering Voltages for High Capacity Circuits

Lecture 2-intro-to-switchgear
Lecture 2-intro-to-switchgearLecture 2-intro-to-switchgear
Lecture 2-intro-to-switchgearAliRaza1718
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSatish Pydimarla
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxDrNiveditaSingh3
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNadir Baloch
 
Current and Voltage Transformers _23_10_2021.pptx
Current and Voltage Transformers _23_10_2021.pptxCurrent and Voltage Transformers _23_10_2021.pptx
Current and Voltage Transformers _23_10_2021.pptxrohith650557
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfYogeshGairola2
 
A Comparison of Contemporary Electrical Distribution Equipment Standards
A Comparison of Contemporary Electrical Distribution Equipment StandardsA Comparison of Contemporary Electrical Distribution Equipment Standards
A Comparison of Contemporary Electrical Distribution Equipment Standardsmichaeljmack
 
Electrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.pptElectrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.pptBrijeshKumar33410
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................hiiarindam
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipmentsEman Dacanay
 
powersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfpowersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfMonalPandey1
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTRAJPRASAD RS
 
Substation presentation by ram
Substation presentation by ramSubstation presentation by ram
Substation presentation by ramGRBabu Naidu
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Living Online
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERRitesh Kumawat
 

Similar to Fusing Metering Voltages for High Capacity Circuits (20)

ET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptxET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptx
 
Lecture 2-intro-to-switchgear
Lecture 2-intro-to-switchgearLecture 2-intro-to-switchgear
Lecture 2-intro-to-switchgear
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Test Switch Operation, Specification & Accessories
Test Switch Operation, Specification & AccessoriesTest Switch Operation, Specification & Accessories
Test Switch Operation, Specification & Accessories
 
Current and Voltage Transformers _23_10_2021.pptx
Current and Voltage Transformers _23_10_2021.pptxCurrent and Voltage Transformers _23_10_2021.pptx
Current and Voltage Transformers _23_10_2021.pptx
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdf
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 
A Comparison of Contemporary Electrical Distribution Equipment Standards
A Comparison of Contemporary Electrical Distribution Equipment StandardsA Comparison of Contemporary Electrical Distribution Equipment Standards
A Comparison of Contemporary Electrical Distribution Equipment Standards
 
Electrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.pptElectrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.ppt
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipments
 
powersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfpowersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdf
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
Substation presentation by ram
Substation presentation by ramSubstation presentation by ram
Substation presentation by ram
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
 

Recently uploaded

My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 

Recently uploaded (20)

My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 

Fusing Metering Voltages for High Capacity Circuits

  • 1. 10/02/2012 Slide 1 Fusing Metering Voltages for High Capacity Circuits Notes from the Field Prepared by Tom Lawton,TESCO for the Spring ECNE Engineering & Operations Conference 2015
  • 2. • Fused test switches have been around for many years. • Fused potentials have been around for many years. • However over the past twenty years they have boomed in popularity and boomed in usage. • In the same time period fused test leads on field meter testing equipment have gone from a once in a blue moon request to a standard request. What is the Issue?
  • 3. • With the advent of auto-ranging meters Utilities started to recognize that VT’s were no longer necessary on every service. • And this is true. But……. What has changed?
  • 4. • The voltage transformer is designed to connect in parallel with the line to transform the line voltage to 115 or 120 volts suitable for the meter or relay. To keep the voltage at the meters and relays at a safe value, the secondary circuit must be grounded. Source ABB • The name instrument transformer is a general classification applied to current and voltage devices used to change currents and voltages from one magnitude to another or to perform an isolating function, that is, to isolate the utilization current or voltage from the supply voltage for safety to both the operator and the end device in use. Instrument transformers are designed specifically for use with electrical equipment falling into the broad category of devices commonly called instruments such as voltmeters, ammeters, wattmeters, watt-hour meters, protection relays, etc. Source GE • VT’s not only step down the voltage to 120v for metering purposes, but they provide a safety feature to the circuit. The VT is a current limiting component in the circuit. • The fault current for a VT is typically the same or less than the fault amps of the meter (typ. 10,000 amps). Voltage Transformers as Safety Devices?
  • 5. • Within recent years, auto-ranging meters have been introduced. • VT’s have been eliminated for many applications. • This means the field technician is now dealing with the primary voltage. Autoranging meters
  • 6. A little about Fault Currents
  • 7. • A fuse or breaker designed to interrupt the largest potential short-circuit currents can be helpful on some days. Short Circuit Current > Interrupt Rating =
  • 8. • Overcurrent protective devices must be selected for the proper – Voltage – Current – Interrupt rating • This last one is the one most typically overlooked. This is also the one most people do not understand how to plan for or calculate. • Current limiting is a type of over current protection • An overcurrent protective device must be able to withstand the destructive energy of short-circuit currents. A little about Fault Currents
  • 9. Short-Circuit Currents & Interrupting Rating
  • 10. Short-Circuit Currents & Interrupting Rating
  • 11. • SCCR’s represent the maximum level of short-circuit current that the component or equipment can withstand under fault conditions . • This is used for determining compliance with NEC® 110.10. • This rating can be marked on individual components or assemblies. • Assembly ratings take into account all components contained within the equipment rather than just the main overcurrent protective device. • A common mistake is to assume that the interrupting rating of the overcurrent protective device protecting the circuit represents the SCCR for the entire circuit. Interrupting ratings, used for compliance with NEC® 110.9, apply solely to the overcurrent protective device. It is the characteristics of the overcurrent protective device (e.g. opening time, let-through energy) that need to be used in determining compliance with NEC® 110.10, not the interrupting rating. • NOTE: Short-circuit current ratings (SCCRs) are different than interrupting ratings marked on overcurrent protective devices. What is a Short-Circuit Current Rating (SCCR) ?
  • 12. • For meter disconnect switches, this withstand level (SCCR), is often determined by product testing. For assemblies, the marking can be determined through product listing or by an approved method. • Any valid method uses the “weakest link” approach. The marking should represent the limits of the assembly for a safe installation. How is SCCR Determined?
  • 13. Point-to-Point Method of Short-Circuit Calculations
  • 14. • Some have added fused potentials in line or at the test switch for transformer rated services. What have utilities changed as a result of losing the isolation and current limiting features of a voltage transformer?
  • 15. • Some have gone to fused test leads for their field technicians. Fusing The Test Switch
  • 16. Meter Test Switch Configurations • Layout • Handle Colors • Reversed vs. Normal Potentials • Current Links • Base Sizing • Barrier Locations NOTE: On installations that contain Test Switches, test leads terminated with a test switch safety test probe (test plug) should be used for CT testing. This provides a “make-before-break” connection to prevent accidental opening of the current transformer secondary loop.
  • 17. Fitting into a Pre-Wired Transformer Rated Enclosure? • Move items around • Small nipple box with four pole switch base and fusing
  • 18. • Some have gone to cold sequencing for self contained services. Cold Sequencing
  • 19. • Some rely on better PPE for their Meter Techs PPE
  • 20. • Some have not changed their metering practices at all. • Utilities are not required to fuse the circuits. • Do we really need to do anything? None of the Above!
  • 21. Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA Tom.Lawton@tescometermanager.com Cell: 215-688-0298 This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com