SlideShare a Scribd company logo
1 of 19
Site Verification –
Protocols & Tools for
Complex Metering Installations
November 6, 2013

Notes from the Field
Prepared by Tom Lawton,TESCO
10/02/2012

for the Southeastern Electricity Metering Association (SEMA)
Slide 1
Premise
• Over much of the 20th century, utilities, regulators and customers each
relied upon lab and field meter testing efforts which were primarily focused
upon the accuracy of the watt-hour meter and demand register.
• This focus is now changing with overwhelming deployment of electronic
meters and significant deployment of AMR and AMI meters throughout the
installed base in North America.
• The focus has now shifted to the metering installation as a whole and not
the accuracy of the meter.
Field Testing
Common Features and Common Sources of Concern
Electro Mechanical meters were
subject to registration errors caused
by mechanical issues with moving
parts resulting in either the loss of
revenue to the utility or over billing
for the customer. Some of the more
common problems were:
•
•
•
•

Friction wear
Gear mesh misalignment
Retarding magnet failure
Timing motors
Electronic Meters – new failure modes require new testing
and inspection methods
Electronic meters fail as do electro mechanical meters but differently
• Their overall life expectancy is not nearly the same
• Failure modes include drift (unexpected)
• Failure modes include catastrophic (expected)
• Failure modes include non-catastrophic but significant measurement error
modes
• Failure modes can include non-measurement issues which render the meter
ineffective or inaccurate for billing purposes.
Traditional Non-Meter Related problems

Any metering site has always had a number of issues that could also cause metering inaccuracies,
billing inaccuracies, safety concerns or some combination of all three.
Residential metering sites;
•

Traditionally utilities trained their meter readers to look for any abnormal conditions that might
reflect a failing or failed meter, cut seals, tampering, or a dangerous condition. Some meter
readers were better than others, but most were excellent lines of defense against bad metering
and unsafe conditions.

•

Second line of traditional defense were trouble calls to the residence.

•

In an AMI environment we are going to have to rely on trouble calls, information gleaned from the
data gathered (or not gathered) and the Random Sample program used by the utility – regardless
of whether the testing is being done in the shop or the field.
Traditional Non-Meter Related problems (cont)

Issues at Transformer Rated sites;
•

The monthly meter read and if there was a demand, the demand reset allowed the
utility to see these sites every month.

•

The resources used for this are traditionally better trained and more likely to note an
issue.

•

Utilities also tended to have an annual or periodic inspection program already in
place.

•

As personnel cut backs became rampant in the industry many of these programs were
cut back (less frequent) or eliminated, or just chronically behind.
Best Practices
• Residential vs Commercial
• Self-Contained vs Transformer Rated
• Follow the money and be as proactive as possible
Data Base, Protocols, and Field Tool for
Performing these checks
•
•
•
•
•
•
•
•
•

Data Base tool must be able to record all data from the field.
This tool must be easy to use with a variety of platforms
This tool must be updateable by meter operations
Site verification protocols should be a living set of documents
Different protocols should be developed for different types of meters and
different types of metering sites.
All data about the site should be available for the operator in the field
All new data should be recorded without over writing pre-existing data (as
expected, as found, as left)
Protocols should also be check lists. Pull down menus are preferred
Data can come back to system of record either live or in batch mode
Potential Site Check List
• Verify the meter number
• Record the GPS location of the site or verify the location
• Take a picture of the site
• Verify Access information and add any new information as
required
• Verify protocol to be used for this site
Potential Site Check List (cont)

• Perform a visual safety inspection of the
site.
– utility equipment
– Customer equipment
Potential Site Check List (cont)

• Things to look for include
– intact down ground on pole
– properly attached enclosure
– unwanted voltage on enclosure
– proper trimming and site tidiness (absence
of discarded seals, etc.)
Potential Site Check List (cont)

• Visually inspect for energy diversions (intentional
and not). This includes broken or missing wires,
jumpers, open test switch, unconnected wires and
foreign objects on meters or other metering
equipment. Broken or missing wires can seriously
cause the under measurement of energy. A simple
broken wire on a CT or VT can cause the loss of 1/3
to 1/2 of the registration on either 3 element or 2
element metering, respectively.
Potential Site Check List (cont)

• Perform and record the test result
• Visually check lightning arrestors and transformers for
damage or leaks.
• Check for proper grounding and bonding of metering
equipment. Poor grounding and bonding practices may
result in inaccurate measurements that go undetected
for long periods of time. Implementing a single point
ground policy and practice can reduce or eliminate this
type of issue.
Potential Site Check List (cont)
• Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage.
• Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires,
loose connections, etc.
• Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross
wired. Be sure CTs are grounded in one location (test switch) only.
• Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify
amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet
(voltage).
• Check rotation by closing in one phase at a time at the test switch and observing the phase meter
for forward rotation. If forward rotation is not observed measurements may be significantly impacted
as the phases are most likely cancelling each other out.
• Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing
compensation (line and/or transformer losses) the compensation should be verified either through
direct testing at the is generally a very small percentage of
• Loss compensation site or by examining recorded pulse data.
the overall measurement and would not be caught under
utilities normal high/low checks. However, the small
percentages when applied to large loads or generation can
really add up over time. Billing adjustments can easily be in
the $million range if not caught early.
Potential Site Check List (cont)
•

Verify metering vectors. Traditionally this has been done using instruments such as a circuit
analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many of these desired values are
programmed into the meters Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in determining if unbalanced loads are
present and if CTs are sized properly. The vendor software generally has the ability to capture
both diagnostic and vector information electronically. These electronic records should be kept in
the meter shop for future comparisons.

•

If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for
totalization they also should be verified vs. the known load on the meter.

•

Verify meter information including meter multiplier (rework it), serial number, dials/decimals, Mp,
Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact
on measured/reported values.

•

Verify CT shunts are all opened.
Potential Site Check List (cont)

• Burden test CTs and voltage check PTs.
• Ratio Test the CT’s and PT’s
• Record results. Review previous results and perform a
review all the way back through the billing.
Shop Testing
•

Accuracy Testing

•

Meter Communications
Performance

•

Software & Firmware
Verification

•

Setting Verification

•

Functional Testing

•

Disconnect/Reconnect
Functionality
and as left setting
Testing Frequency & Cost
•
•
•
•
•
•
•

Tools (hardware and software)
Personnel
Frequency
Test
Report
Analyze
Learn, Share, Adapt
Questions and Discussion

Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-688-0298 (cell)
1-800-762-8211
This presentation can also be found under Meter
Conferences and Schools on the TESCO web site:
www.tesco-advent.com

More Related Content

What's hot

Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingTESCO - The Eastern Specialty Company
 
Leading Indicator Program OverView Rev A
Leading  Indicator Program OverView Rev ALeading  Indicator Program OverView Rev A
Leading Indicator Program OverView Rev APhil Rochette
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...TESCO - The Eastern Specialty Company
 
Emerging diagnostic technologies
Emerging diagnostic technologiesEmerging diagnostic technologies
Emerging diagnostic technologiesRich Wurzbach
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingTESCO - The Eastern Specialty Company
 
Wind turbine condition monitoring sqi rev
Wind turbine condition monitoring sqi revWind turbine condition monitoring sqi rev
Wind turbine condition monitoring sqi revSpectra Quest Inc
 
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCE
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCEELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCE
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCEEBRAHIM KHALIL
 
Fluke How To Improve Your Maintenance Program Video
Fluke How To Improve Your Maintenance Program VideoFluke How To Improve Your Maintenance Program Video
Fluke How To Improve Your Maintenance Program VideoTranscat
 
Goodman Final Presentation_French_Jeremy
Goodman Final Presentation_French_JeremyGoodman Final Presentation_French_Jeremy
Goodman Final Presentation_French_JeremyJeremy French
 
Fault diagnosis & fault tolerance in wind turbines
Fault diagnosis & fault tolerance in wind turbinesFault diagnosis & fault tolerance in wind turbines
Fault diagnosis & fault tolerance in wind turbinesNitin Goyal
 
Chandan_Electrical Engineer
Chandan_Electrical EngineerChandan_Electrical Engineer
Chandan_Electrical EngineerChandan Nag
 
V-Map G3 A3 Flyer (Final Rev 0)
V-Map G3 A3 Flyer (Final Rev 0)V-Map G3 A3 Flyer (Final Rev 0)
V-Map G3 A3 Flyer (Final Rev 0)shangothetammy
 
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...Schneider Electric
 

What's hot (20)

Self-Contained Fundamentals
Self-Contained FundamentalsSelf-Contained Fundamentals
Self-Contained Fundamentals
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
 
Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter Testing
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 
Leading Indicator Program OverView Rev A
Leading  Indicator Program OverView Rev ALeading  Indicator Program OverView Rev A
Leading Indicator Program OverView Rev A
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
Emerging diagnostic technologies
Emerging diagnostic technologiesEmerging diagnostic technologies
Emerging diagnostic technologies
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
 
Wind turbine condition monitoring sqi rev
Wind turbine condition monitoring sqi revWind turbine condition monitoring sqi rev
Wind turbine condition monitoring sqi rev
 
Tesco's AMI Specific Products and Services
Tesco's AMI Specific Products and ServicesTesco's AMI Specific Products and Services
Tesco's AMI Specific Products and Services
 
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCE
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCEELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCE
ELECTRICAL ENGINEER WITH 13 YEARS OF EXPERIENCE
 
Fluke How To Improve Your Maintenance Program Video
Fluke How To Improve Your Maintenance Program VideoFluke How To Improve Your Maintenance Program Video
Fluke How To Improve Your Maintenance Program Video
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
 
Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability
 
Goodman Final Presentation_French_Jeremy
Goodman Final Presentation_French_JeremyGoodman Final Presentation_French_Jeremy
Goodman Final Presentation_French_Jeremy
 
Fault diagnosis & fault tolerance in wind turbines
Fault diagnosis & fault tolerance in wind turbinesFault diagnosis & fault tolerance in wind turbines
Fault diagnosis & fault tolerance in wind turbines
 
Chandan_Electrical Engineer
Chandan_Electrical EngineerChandan_Electrical Engineer
Chandan_Electrical Engineer
 
V-Map G3 A3 Flyer (Final Rev 0)
V-Map G3 A3 Flyer (Final Rev 0)V-Map G3 A3 Flyer (Final Rev 0)
V-Map G3 A3 Flyer (Final Rev 0)
 
Automation 1.4x
Automation 1.4xAutomation 1.4x
Automation 1.4x
 
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
 

Viewers also liked

Viewers also liked (15)

Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter RecordsMeter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter Records
 
TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
CT Burden Testing
CT Burden TestingCT Burden Testing
CT Burden Testing
 
Customer Perceptions of New AMI Meters
Customer Perceptions of New AMI MetersCustomer Perceptions of New AMI Meters
Customer Perceptions of New AMI Meters
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Hot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best PracticesHot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best Practices
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
In-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI DeploymentIn-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI Deployment
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After Deployment
 

Similar to Site Verification - Protocols & Tools for Complex Metering Installations

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationTESCO - The Eastern Specialty Company
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationTESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023TESCO - The Eastern Specialty Company
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018TESCO - The Eastern Specialty Company
 

Similar to Site Verification - Protocols & Tools for Complex Metering Installations (20)

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
 
Site Verification for Newer Employees
Site Verification for Newer EmployeesSite Verification for Newer Employees
Site Verification for Newer Employees
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
 
Customer Request Field Meter Testing Programs
Customer Request Field Meter Testing ProgramsCustomer Request Field Meter Testing Programs
Customer Request Field Meter Testing Programs
 
Single Phase Meter Testing Overview
Single Phase Meter Testing OverviewSingle Phase Meter Testing Overview
Single Phase Meter Testing Overview
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Introduction to Self-Contained Metering
Introduction to Self-Contained MeteringIntroduction to Self-Contained Metering
Introduction to Self-Contained Metering
 
Meter Testing 101.pptx
Meter Testing 101.pptxMeter Testing 101.pptx
Meter Testing 101.pptx
 
New Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO SolutionsNew Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO Solutions
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
Meter Shops of the Future
Meter Shops of the FutureMeter Shops of the Future
Meter Shops of the Future
 

Recently uploaded

Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilV3cube
 

Recently uploaded (20)

Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of Brazil
 

Site Verification - Protocols & Tools for Complex Metering Installations

  • 1. Site Verification – Protocols & Tools for Complex Metering Installations November 6, 2013 Notes from the Field Prepared by Tom Lawton,TESCO 10/02/2012 for the Southeastern Electricity Metering Association (SEMA) Slide 1
  • 2. Premise • Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. • This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America. • The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
  • 3. Field Testing Common Features and Common Sources of Concern Electro Mechanical meters were subject to registration errors caused by mechanical issues with moving parts resulting in either the loss of revenue to the utility or over billing for the customer. Some of the more common problems were: • • • • Friction wear Gear mesh misalignment Retarding magnet failure Timing motors
  • 4. Electronic Meters – new failure modes require new testing and inspection methods Electronic meters fail as do electro mechanical meters but differently • Their overall life expectancy is not nearly the same • Failure modes include drift (unexpected) • Failure modes include catastrophic (expected) • Failure modes include non-catastrophic but significant measurement error modes • Failure modes can include non-measurement issues which render the meter ineffective or inaccurate for billing purposes.
  • 5. Traditional Non-Meter Related problems Any metering site has always had a number of issues that could also cause metering inaccuracies, billing inaccuracies, safety concerns or some combination of all three. Residential metering sites; • Traditionally utilities trained their meter readers to look for any abnormal conditions that might reflect a failing or failed meter, cut seals, tampering, or a dangerous condition. Some meter readers were better than others, but most were excellent lines of defense against bad metering and unsafe conditions. • Second line of traditional defense were trouble calls to the residence. • In an AMI environment we are going to have to rely on trouble calls, information gleaned from the data gathered (or not gathered) and the Random Sample program used by the utility – regardless of whether the testing is being done in the shop or the field.
  • 6. Traditional Non-Meter Related problems (cont) Issues at Transformer Rated sites; • The monthly meter read and if there was a demand, the demand reset allowed the utility to see these sites every month. • The resources used for this are traditionally better trained and more likely to note an issue. • Utilities also tended to have an annual or periodic inspection program already in place. • As personnel cut backs became rampant in the industry many of these programs were cut back (less frequent) or eliminated, or just chronically behind.
  • 7. Best Practices • Residential vs Commercial • Self-Contained vs Transformer Rated • Follow the money and be as proactive as possible
  • 8. Data Base, Protocols, and Field Tool for Performing these checks • • • • • • • • • Data Base tool must be able to record all data from the field. This tool must be easy to use with a variety of platforms This tool must be updateable by meter operations Site verification protocols should be a living set of documents Different protocols should be developed for different types of meters and different types of metering sites. All data about the site should be available for the operator in the field All new data should be recorded without over writing pre-existing data (as expected, as found, as left) Protocols should also be check lists. Pull down menus are preferred Data can come back to system of record either live or in batch mode
  • 9. Potential Site Check List • Verify the meter number • Record the GPS location of the site or verify the location • Take a picture of the site • Verify Access information and add any new information as required • Verify protocol to be used for this site
  • 10. Potential Site Check List (cont) • Perform a visual safety inspection of the site. – utility equipment – Customer equipment
  • 11. Potential Site Check List (cont) • Things to look for include – intact down ground on pole – properly attached enclosure – unwanted voltage on enclosure – proper trimming and site tidiness (absence of discarded seals, etc.)
  • 12. Potential Site Check List (cont) • Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively.
  • 13. Potential Site Check List (cont) • Perform and record the test result • Visually check lightning arrestors and transformers for damage or leaks. • Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue.
  • 14. Potential Site Check List (cont) • Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage. • Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. • Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross wired. Be sure CTs are grounded in one location (test switch) only. • Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). • Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. • Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the is generally a very small percentage of • Loss compensation site or by examining recorded pulse data. the overall measurement and would not be caught under utilities normal high/low checks. However, the small percentages when applied to large loads or generation can really add up over time. Billing adjustments can easily be in the $million range if not caught early.
  • 15. Potential Site Check List (cont) • Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. • If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. • Verify meter information including meter multiplier (rework it), serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values. • Verify CT shunts are all opened.
  • 16. Potential Site Check List (cont) • Burden test CTs and voltage check PTs. • Ratio Test the CT’s and PT’s • Record results. Review previous results and perform a review all the way back through the billing.
  • 17. Shop Testing • Accuracy Testing • Meter Communications Performance • Software & Firmware Verification • Setting Verification • Functional Testing • Disconnect/Reconnect Functionality and as left setting
  • 18. Testing Frequency & Cost • • • • • • • Tools (hardware and software) Personnel Frequency Test Report Analyze Learn, Share, Adapt
  • 19. Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 215-688-0298 (cell) 1-800-762-8211 This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com