SlideShare a Scribd company logo
1 of 39
Advanced Meter Testing
                   Programs

                  Advanced Meter Testing Programs,
                  Traceability, Commission Requirements as
                  part of Site Verification in a Pre and Post
                  AMI World
                  Prepared by Tom Lawton,TESCO

                  for the Fall Southeastern Electricity Metering Association
10/02/2012        Advanced Metering Track
                                Slide 1
                  November 7, 2012                                             1
Session Objectives

•   Understand Types of Meter Testing
•   Review Categories of Meter Testing
•   Review Test Plans for Meters
•   Review Florida Meter Testing Requirements
•   Review Why Statistical Test Plans Are Best
•   Review Changes for ANSI Testing Requirements
•   Review Aspects of Traceability of Meter Test Results



                                                           2
Program Background

Meter Testing for new and in-service meters is specified in
ANSI C12.1-2008, American National Standard for Electric
Meters, Code for Electricity Metering. Most utility
commissions use this Standard a reference or the basis for their
meter testing requirements.

The face of the electric meter population throughout the
country and especially throughout the state of Florida is
changing as are the meter testing requirements. Several AMI
programs have been completed and more have started
throughout the State contributing to these changes.




                                                                   3
Types of Meter Testing
• New meters have many tests specified in ANSI C12.1
  and C12.20, usually performed by the meter vendors.
• With In-service meters, mainly meter consumption
  accuracy
   – Maybe Full Load, Light Load, Weighted Average
     Accuracy
   – In the Meter Shop (periodic in service testing
     requirements)
   – In the Field (customer inquiries & complaints)
• With AMI/Smart Grid, must consider meter device
  functional testing for in-service.
                                                        4
Impact of AMI & AMR


Test an installation and system and not just a meter!


Test programs for AMR & AMI systems need to
involve testing and checking the meter performance
as well as checking and testing the installation. This
more extensive test check list needs to be done
especially for the higher revenue C&I customers.



                                                         5
Impact of AMI Devices

• New concept of what is a meter…includes everything
  under the cover.



• AMI communications modules and
  service disconnect switches.

• Need to applies sampling and testing requirements to
  these devices when part of the AMI meter.

                                                         6
Categories Of Meter Testing

• New Meters
  – Testing in the Meter Shop or Cross Dock


• In Service
  – Testing in the Meter Shop for State periodic requirements
  – Testing in the field for customer inquiries or complaints


• Retirement
  – Testing in the Meter Shop or Cross Dock


                                                                7
Current ANSI C12.1 Performance
         Requirements




                                 8
Test Plans for Meters


Four test plan options available:
    •   Periodic
    •   Variable Interval
    •   Selective
    •   Statistical




                                    9
Periodic Test Plans


• Periodic
  – Varies by State
  – Example provided by ANSI C12.1:
     •   Each Electro Mechanical meter is tested once every 8 years
     •   All other Meters are tested every 16 years
     •   Appendix D provides details for other meters & devices
     •   No guidance for AMI meters
  – Generally, average of 12.5% of population tested per year




                                                                      10
Variable Interval Test Plans

• Variable Interval
  – Formula-based plan where percentage of
    meters to be tested is based on the formula.
    For example:
    Required Percentage = 4 + 0.133 (2X + Y)
     • X is percentage of meters tested > 102% in
       preceding year
     • Y is percentage of meters tested < 98% or >
       102% in preceding year
     • If required percentage reaches 8%, then the
       meter group has to be put on a remedial action
       program.


                                                        11
Selective Test Plans

• Selective Plan
  – Not Specified In ANSI C12.1
  – Complex formula-based plan where the percentage
    of meters to be tested is based on one of four
    formulas depending on the value of X and Y. Fro
    example:
     • X is percentage of meters tested > 102% in preceding
       year
     • Y is percentage of meters tested < 98% or > 102% in
       preceding year
     • Minimum sample for a meter group is either 12.5% of the
       population or 200 meters, whichever is less.



                                                                 12
Statistical Test Plans
                          The Best Approach


   ANSI C12.1-2001 Code for Electricity Metering Guidance

Paragraph 5.1.4.3.3 Statistical sampling plan


“The statistical sampling plan used shall conform to accepted principles of
statistical sampling based on either variables or attributes methods. Meters shall
be divided into homogeneous groups, such as manufacturer and manufacturer’s
type. The groups may be further divided into subdivision within the
manufacturer’s type by major design modifications.”


NOTE - Examples of statistical sampling plans can be found in ANSI/ASQC
Z1.9, the ANSI version of MIL-STD-414 and ANSI/ASQC Z1.4, the ANSI
version of MIL-STD-105.

                                                                                     13
General Meter Testing Requirements

• New Meters
  – Manufacturers tests
  – In-house tests on new shipments
• In-Service Meters
  – Periodic Tests
  – Selective, random, or statistical testing
• Retirement tests and testing of related
  metering equipment

                                                14
In-Service Testing
                      Requirements - Nationally
• Of 51 jurisdictions (50 states and the District of Columbia):

     - 5 states mandate periodic testing and allow no alternative: AL, CO, MS, OR, & TX

     - 3 states allow for periodic testing or variable interval / selective testing but no other
            alternative: HI, NY, & RI

     - Of the remaining 43 jurisdictions, statistical sample testing is possible in all. Specifically:

           ¡ 7 states normally require periodic testing but allow waivers for statistical sample testing
                        programs: CT, DE, MO, NH, NJ, ND, & OK

           ¡ 16 states directly allow for statistical sample testing programs, normally with pre-
                        approval by the commission: AR, FL, IL, IN, IA, KY, ME, MI, NM, NC, PA,
                        SC, TN, UT, WV, and WI

           ¡ 5 states prescribe no specific plan but require an in-service testing plan to be filed with
                        the commission: AK, AZ, MD, WA, & WY

           ¡ 15 jurisdictions have no specific in-service testing requirements. In-service testing plans
                       are simply incorporated into rate or tariff filings or otherwise filed with the     15
                       commission: CA, DC, GA, ID, KS, LA, MA, MN, MT, NE, NV, OH, SD, VT,
                       & VA
In-Service Testing Requirements -
                            Nationally
• Of states allowing for statistical sample testing:


    - 8 specifically reference MIL-STD 414 or ANSI/ASQC Z1.9 as a suitable plan:

         FL, IL, IN, MI, TN, WA, WV, & WI


    - 8 specifically reference ANSI C12.1 or ASA C12 as the guidance for in-service testing plans:

    AZ, AR, CT, IA, NM, OH, PA, & UT


    - One state allows for statistical sample testing but only using ANSI/ASQC Z1.4: MD


    - Of the remaining 26 jurisdictions, no specific guidance is given for the choice of statistical
         sample testing plans:

        AK, CA, DC, DE, GA, ID, KS, KY, LA, ME, MA, MN, MO, MT, NE, NV, NH, NJ, NC,
    ND, OK, SC, SD, VT, VA, & WY

                                                                                                       16
Why Use a Statistical Testing Plan?

• Focuses testing on the proper meters.


• Minimizes number of meters to be tested;
 usually requires less than 30% of what a
 periodic testing plan requires.


• Provides data and analysis tools for use in
 understanding what is happening with installed meters
 or for use in the purchasing of new meters.
                                                     17
Homogeneous Population(s)

• The groups or populations being sampled and tested
  are made up of the same or similar items, items
  which operate in the same way and were made in the
  same manner.

• For electric meters, this has traditionally been
  interpreted as being meters of a specific meter
  type from a manufacturer (i.e. AB1, J5S, MX, etc.).

• AMR & AMI programs have helped to make the
  overall populations more homogenous. This makes a
  utility with AMR & AMI meters better prepared to
  take advantage of a statistical sampling plan.
                                                        18
Suitably Sized Samples


• The sample size for each group must be large enough
  to provide a statistically valid sample or the group’s
  population.
• The larger the group’s population, the greater the
  savings for statistical testing over periodic


           testing and the more statistically reliable the
  testing.
• AMI implementation generally results in larger
  group populations. The larger the population, the
  more suitable for statistical testing.                     19
Random Sample Selection

• Every item within the group or population has
  an equal chance of being selected as part of the
  sample for testing.

• Random sample selection is critical to providing
  for a statistically valid sample.




                                                     20
Population Fits the Statistical Model

• The statistical model being used for the sampling/testing
           plan needs to match the actual distribution of the
  population.
• In most circumstances, one is looking at a normal or
  Gaussian distribution (i.e. a Bell curve).
• This can be checked using a histogram plot and normality
  test. For mechanical and electromechanical meters, a
  normal distribution fits the actual data very well.
• For electronic or solid-state meters, the meters are highly
  accurate and recent analysis shows that the test data may not
  be normal.

                                                                  21
Statistical Testing Plan w/ AMR & AMI

• By definition AMR & AMI meters no longer
  have a pair of human eyes checking the installation
  each month. Statistical testing allows the Utility to
  quickly identify which areas may have a problem.

• Potential problems that could be caught by aggressive
  testing.
   – A faulty batch of meters
   –   Design or premature equipment failures
   –   Poor installation due to a poorly trained crew
   –   Location related failures
   –   Energy Diversion

                                                          22
Statistical Sampling and Revenue
                 Protection

One of the significant benefits to the statistical
sampling of AMR & AMI meters is the
potential to spot energy diversion more readily.
Statistical testing of meters will indicate the
overall health of the meter population.
Coupled with historical revenue information
and meter tamper flags statistical testing can
become a powerful tool for combating energy
diversion.
Utilities will be in a better position than ever to
spot trends toward energy diversion more
readily and on a closer to real time basis.
                                                      23
Statistical Testing with AMI

Statistical testing to monitor AMI programs will
also point out
• design or manufacturing deficiencies
• installation or post-installation problems (some
  of which may or may not be energy diversion).


All should be pursued and the root cause
understood.


                                                     24
Why Do All of this Testing?

Installation of AMI programs move at seemingly breakneck
speeds with all focus on schedule. At the same time,
problems and exceptions seem to be pouring out of the
woodwork. Upper management wants to hear about project
milestones and budgets and not about the problems.
Especially not any publicly embarrassing problems
associated with an AMI installation.




                                                           25
Why Do All of this Testing?

• Statistical testing will allow you to more readily identify
  where the problems are and where there were simply
  anomalies.
• The testing will help differentiate between training and
  equipment problems.
• The testing will also help to identify potential weak areas in
  the system that may bear closer scrutiny as the system goes
  into service
• Putting a good testing system into place during the
  implementation will help to keep you on schedule, on budget,
  and out of trouble during the installation and will ensure that
  there will be a good system in place with the self discipline
  and understanding to administer the system.
                                                                    26
Summary

AMR & AMI provides the Utility with the opportunity to
get even more and better business information from their
installed meter base. Statistical Sampling of these in-
service meters can help to point up deficiencies in the
installed system during installation as well as shortly after
system implementation. The sampling can help to
identify potential energy diversion and can help catch
design inadequacies in the meters. Once a problem is
identified additional statistical testing can help to zero in
on a problem and help to identify potential solutions.
Statistically testing the installed meter population will
allow the utility to more fairly meter the entire population
without unfairly charging any one customer and without
unfairly subsidizing any group of customers.
Statistical sampling plans are also lower cost plans to use
than the traditional periodic plans.
                                                                27
Current ANSI C12.1 Section 5 Issues

• Acceptance testing of new meters is not mentioned.

• Statistical sampling plans are not adequately defined.

• Post deployment or performance monitoring of newly
  certified meters not covered.




                                                           28
Updating ANSI C12.1 Section 5


• Consider new meters

• Consider AMI devices

• Consider new metering device acceptance testing

• Provide definition of Statistical Sampling plans

• Consider performance monitoring of newly certified
  meters
                                                       29
Recommended Changes
           New Meters & Metering Devices


• New meters are covered by sampling and
  testing requirements.

• As-found, as-left, returned to service tests.

• Accuracy classes in C12.20
  (0.2% and 0.5%) referenced.

                                                  30
Recommended Changes
              Statistical Sampling Plans


• In-service statistical sampling plans should be
  developed using:
  – ANSI/ASQ Z1.9 Sampling Procedures and Tables for
    Inspection by Variables
  – ANSI/ASQ Z1.4 Sampling Procedures and Tables for
    Inspection by Attributes
• Provides guidance on how to handle sample
  failures.
• Similar to some State Commission
  requirements.
                                                       31
Recommended Changes
      New Metering Device Acceptance Testing


• Sampling and testing of new meter shipments

• Uses ANSI Z1.4 (attributes) or ANSI Z1.9
  (Variables) for sample size and acceptance
  criteria.

• Specifies an Acceptable Quality
  Limit (AQL) of 1% or less.

                                                32
Recommended Changes
     Performance Monitoring of Newly Certified Meters


• Evaluate newly certified meters after
  installation…. Different than in-service.

• Use statistical sampling plan.




                                                        33
Meter Testing Traceability

•   Test equipment to NIST standards
•   Tracking number of meters to be tested per
    State Commission requirements
•   Tracking meter test data
     •   Meter records
     •   Meter Data Management System (MDMS)




                                                 34
Test Equipment Calibration


  Primary Requirement: Traceable to NIST
                Standards

• Meter Test Boards, Field Test Kits calibrated to a
  known master standard maintained at Meter Shop.

• Master standard calibrated by outside vendor
  traceable to NIST or directly by NIST.




                                                       35
Tracking Meter Records

AMI programs help to update and overhaul
meter record systems. Having the records
for the entire meter population updated
allows for a better chance that test data is
available to answer questions and that any
meter may be selected as part of the sample
for testing.



                                               36
Meter Test Data Tracking

• Need to track test data throughout meter life
   – Certification testing, first article, acceptance testing, in-
      service (field & shop), retirement
• Best time to start to develop the program is before the
  meters are being installed.
• Use installation reports to determine if there is any
  initial concerns about the meters being installed.
• Typical reports that should be available:
    • Failed Meter Report, Project to Date
    • Electric Meters on Network Report
                                                                     37
Meter Test Data Tracking System


• System should track meter test results for ease of
  future reference or for response to public or Utility
  Commission inquiries.

• Maybe part of MDMS or separate system such as
  ADM

• Requires discipline in collecting & entering data,
  especially field tests.



                                                          38
Questions?
Please feel free to call or e-mail any questions


               Tom Lawton
Tom.Lawton@TescoMeterManager.com 215-688-0298 (cell)




             The Eastern Specialty Company             39

More Related Content

What's hot

Plant wide control design based on steady-state combined indexes
Plant wide control design based on steady-state combined indexesPlant wide control design based on steady-state combined indexes
Plant wide control design based on steady-state combined indexesISA Interchange
 
bio statistical tools of process validation
bio statistical tools of process validationbio statistical tools of process validation
bio statistical tools of process validationmounika chowdary
 
Introduction asme pcc3 inspection planning using risk based methods
Introduction asme pcc3 inspection planning using risk based methods Introduction asme pcc3 inspection planning using risk based methods
Introduction asme pcc3 inspection planning using risk based methods johnfletcher1957
 
STATISTICAL PROCESS CONTROL
STATISTICAL PROCESS CONTROLSTATISTICAL PROCESS CONTROL
STATISTICAL PROCESS CONTROLVivek Thorve
 
Statistical control chart
Statistical control chartStatistical control chart
Statistical control chartAshish Chaudhari
 
Welmec 08.10 guide_for_statistical_verification
Welmec 08.10 guide_for_statistical_verificationWelmec 08.10 guide_for_statistical_verification
Welmec 08.10 guide_for_statistical_verificationWilson Pedro Tamega Junior
 
Sslean Validation 20070622
Sslean Validation 20070622Sslean Validation 20070622
Sslean Validation 20070622jancrielaard
 
inspection , test and measurement
inspection , test and measurementinspection , test and measurement
inspection , test and measurementtanvikumbhar
 
Statistical process control
Statistical process controlStatistical process control
Statistical process controlKarishmaFuse
 
Attribute MSA presentation
Attribute MSA presentationAttribute MSA presentation
Attribute MSA presentationPRASHANT KSHIRSAGAR
 
Statstical process control
Statstical process controlStatstical process control
Statstical process controlXenChisti
 
Arrelic Offering | RBI
Arrelic Offering | RBIArrelic Offering | RBI
Arrelic Offering | RBIArrelic
 

What's hot (17)

Plant wide control design based on steady-state combined indexes
Plant wide control design based on steady-state combined indexesPlant wide control design based on steady-state combined indexes
Plant wide control design based on steady-state combined indexes
 
SBP
SBPSBP
SBP
 
bio statistical tools of process validation
bio statistical tools of process validationbio statistical tools of process validation
bio statistical tools of process validation
 
Analytical control strategy 4
Analytical control strategy 4Analytical control strategy 4
Analytical control strategy 4
 
Introduction asme pcc3 inspection planning using risk based methods
Introduction asme pcc3 inspection planning using risk based methods Introduction asme pcc3 inspection planning using risk based methods
Introduction asme pcc3 inspection planning using risk based methods
 
STATISTICAL PROCESS CONTROL
STATISTICAL PROCESS CONTROLSTATISTICAL PROCESS CONTROL
STATISTICAL PROCESS CONTROL
 
Analytical control strategy 1
Analytical control strategy 1Analytical control strategy 1
Analytical control strategy 1
 
Statistical control chart
Statistical control chartStatistical control chart
Statistical control chart
 
Welmec 08.10 guide_for_statistical_verification
Welmec 08.10 guide_for_statistical_verificationWelmec 08.10 guide_for_statistical_verification
Welmec 08.10 guide_for_statistical_verification
 
Sslean Validation 20070622
Sslean Validation 20070622Sslean Validation 20070622
Sslean Validation 20070622
 
Rbi
RbiRbi
Rbi
 
inspection , test and measurement
inspection , test and measurementinspection , test and measurement
inspection , test and measurement
 
Statistical process control
Statistical process controlStatistical process control
Statistical process control
 
Attribute MSA presentation
Attribute MSA presentationAttribute MSA presentation
Attribute MSA presentation
 
Statstical process control
Statstical process controlStatstical process control
Statstical process control
 
Arrelic Offering | RBI
Arrelic Offering | RBIArrelic Offering | RBI
Arrelic Offering | RBI
 
Risk Based Inspection
Risk Based InspectionRisk Based Inspection
Risk Based Inspection
 

Viewers also liked

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentTESCO - The Eastern Specialty Company
 

Viewers also liked (14)

Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
CT Burden Testing
CT Burden TestingCT Burden Testing
CT Burden Testing
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
Customer Perceptions of New AMI Meters
Customer Perceptions of New AMI MetersCustomer Perceptions of New AMI Meters
Customer Perceptions of New AMI Meters
 
Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories Test Switch Operation, Specifications & Accesories
Test Switch Operation, Specifications & Accesories
 
Hot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best PracticesHot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best Practices
 
Meter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter RecordsMeter Inventory Management & Automating Meter Records
Meter Inventory Management & Automating Meter Records
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After Deployment
 

Similar to TESCO Advanced Meter Testing Programs

Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingTESCO - The Eastern Specialty Company
 
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO - The Eastern Specialty Company
 
Global flow measurement consistency
Global flow measurement consistencyGlobal flow measurement consistency
Global flow measurement consistencyErik Smits
 
Validation of lab instruments and quantitative test methods
Validation of lab instruments and quantitative test methods Validation of lab instruments and quantitative test methods
Validation of lab instruments and quantitative test methods Mostafa Mahmoud
 
calibrationintervalspresentation.pdf
calibrationintervalspresentation.pdfcalibrationintervalspresentation.pdf
calibrationintervalspresentation.pdfAbdulSalamSagir1
 

Similar to TESCO Advanced Meter Testing Programs (20)

Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Meter Testing 101.pptx
Meter Testing 101.pptxMeter Testing 101.pptx
Meter Testing 101.pptx
 
Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter Testing
 
Introduction to Self-Contained Metering
Introduction to Self-Contained MeteringIntroduction to Self-Contained Metering
Introduction to Self-Contained Metering
 
Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability
 
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
 
Single Phase Meter Testing Overview
Single Phase Meter Testing OverviewSingle Phase Meter Testing Overview
Single Phase Meter Testing Overview
 
Global flow measurement consistency
Global flow measurement consistencyGlobal flow measurement consistency
Global flow measurement consistency
 
ANSI Standards & Updates
ANSI Standards & UpdatesANSI Standards & Updates
ANSI Standards & Updates
 
AMI Case Studies
AMI Case StudiesAMI Case Studies
AMI Case Studies
 
AMI Lessons Learned
AMI Lessons LearnedAMI Lessons Learned
AMI Lessons Learned
 
AMI Case Studies
AMI Case StudiesAMI Case Studies
AMI Case Studies
 
ANSI Testing
ANSI TestingANSI Testing
ANSI Testing
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
 
Validation of lab instruments and quantitative test methods
Validation of lab instruments and quantitative test methods Validation of lab instruments and quantitative test methods
Validation of lab instruments and quantitative test methods
 
calibrationintervalspresentation.pdf
calibrationintervalspresentation.pdfcalibrationintervalspresentation.pdf
calibrationintervalspresentation.pdf
 
AMI Meter Certification Before, During and After Deployment
AMI Meter Certification Before, During and After DeploymentAMI Meter Certification Before, During and After Deployment
AMI Meter Certification Before, During and After Deployment
 

Recently uploaded

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 

Recently uploaded (20)

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 

TESCO Advanced Meter Testing Programs

  • 1. Advanced Meter Testing Programs Advanced Meter Testing Programs, Traceability, Commission Requirements as part of Site Verification in a Pre and Post AMI World Prepared by Tom Lawton,TESCO for the Fall Southeastern Electricity Metering Association 10/02/2012 Advanced Metering Track Slide 1 November 7, 2012 1
  • 2. Session Objectives • Understand Types of Meter Testing • Review Categories of Meter Testing • Review Test Plans for Meters • Review Florida Meter Testing Requirements • Review Why Statistical Test Plans Are Best • Review Changes for ANSI Testing Requirements • Review Aspects of Traceability of Meter Test Results 2
  • 3. Program Background Meter Testing for new and in-service meters is specified in ANSI C12.1-2008, American National Standard for Electric Meters, Code for Electricity Metering. Most utility commissions use this Standard a reference or the basis for their meter testing requirements. The face of the electric meter population throughout the country and especially throughout the state of Florida is changing as are the meter testing requirements. Several AMI programs have been completed and more have started throughout the State contributing to these changes. 3
  • 4. Types of Meter Testing • New meters have many tests specified in ANSI C12.1 and C12.20, usually performed by the meter vendors. • With In-service meters, mainly meter consumption accuracy – Maybe Full Load, Light Load, Weighted Average Accuracy – In the Meter Shop (periodic in service testing requirements) – In the Field (customer inquiries & complaints) • With AMI/Smart Grid, must consider meter device functional testing for in-service. 4
  • 5. Impact of AMI & AMR Test an installation and system and not just a meter! Test programs for AMR & AMI systems need to involve testing and checking the meter performance as well as checking and testing the installation. This more extensive test check list needs to be done especially for the higher revenue C&I customers. 5
  • 6. Impact of AMI Devices • New concept of what is a meter…includes everything under the cover. • AMI communications modules and service disconnect switches. • Need to applies sampling and testing requirements to these devices when part of the AMI meter. 6
  • 7. Categories Of Meter Testing • New Meters – Testing in the Meter Shop or Cross Dock • In Service – Testing in the Meter Shop for State periodic requirements – Testing in the field for customer inquiries or complaints • Retirement – Testing in the Meter Shop or Cross Dock 7
  • 8. Current ANSI C12.1 Performance Requirements 8
  • 9. Test Plans for Meters Four test plan options available: • Periodic • Variable Interval • Selective • Statistical 9
  • 10. Periodic Test Plans • Periodic – Varies by State – Example provided by ANSI C12.1: • Each Electro Mechanical meter is tested once every 8 years • All other Meters are tested every 16 years • Appendix D provides details for other meters & devices • No guidance for AMI meters – Generally, average of 12.5% of population tested per year 10
  • 11. Variable Interval Test Plans • Variable Interval – Formula-based plan where percentage of meters to be tested is based on the formula. For example: Required Percentage = 4 + 0.133 (2X + Y) • X is percentage of meters tested > 102% in preceding year • Y is percentage of meters tested < 98% or > 102% in preceding year • If required percentage reaches 8%, then the meter group has to be put on a remedial action program. 11
  • 12. Selective Test Plans • Selective Plan – Not Specified In ANSI C12.1 – Complex formula-based plan where the percentage of meters to be tested is based on one of four formulas depending on the value of X and Y. Fro example: • X is percentage of meters tested > 102% in preceding year • Y is percentage of meters tested < 98% or > 102% in preceding year • Minimum sample for a meter group is either 12.5% of the population or 200 meters, whichever is less. 12
  • 13. Statistical Test Plans The Best Approach ANSI C12.1-2001 Code for Electricity Metering Guidance Paragraph 5.1.4.3.3 Statistical sampling plan “The statistical sampling plan used shall conform to accepted principles of statistical sampling based on either variables or attributes methods. Meters shall be divided into homogeneous groups, such as manufacturer and manufacturer’s type. The groups may be further divided into subdivision within the manufacturer’s type by major design modifications.” NOTE - Examples of statistical sampling plans can be found in ANSI/ASQC Z1.9, the ANSI version of MIL-STD-414 and ANSI/ASQC Z1.4, the ANSI version of MIL-STD-105. 13
  • 14. General Meter Testing Requirements • New Meters – Manufacturers tests – In-house tests on new shipments • In-Service Meters – Periodic Tests – Selective, random, or statistical testing • Retirement tests and testing of related metering equipment 14
  • 15. In-Service Testing Requirements - Nationally • Of 51 jurisdictions (50 states and the District of Columbia): - 5 states mandate periodic testing and allow no alternative: AL, CO, MS, OR, & TX - 3 states allow for periodic testing or variable interval / selective testing but no other alternative: HI, NY, & RI - Of the remaining 43 jurisdictions, statistical sample testing is possible in all. Specifically: ¡ 7 states normally require periodic testing but allow waivers for statistical sample testing programs: CT, DE, MO, NH, NJ, ND, & OK ¡ 16 states directly allow for statistical sample testing programs, normally with pre- approval by the commission: AR, FL, IL, IN, IA, KY, ME, MI, NM, NC, PA, SC, TN, UT, WV, and WI ¡ 5 states prescribe no specific plan but require an in-service testing plan to be filed with the commission: AK, AZ, MD, WA, & WY ¡ 15 jurisdictions have no specific in-service testing requirements. In-service testing plans are simply incorporated into rate or tariff filings or otherwise filed with the 15 commission: CA, DC, GA, ID, KS, LA, MA, MN, MT, NE, NV, OH, SD, VT, & VA
  • 16. In-Service Testing Requirements - Nationally • Of states allowing for statistical sample testing: - 8 specifically reference MIL-STD 414 or ANSI/ASQC Z1.9 as a suitable plan: FL, IL, IN, MI, TN, WA, WV, & WI - 8 specifically reference ANSI C12.1 or ASA C12 as the guidance for in-service testing plans: AZ, AR, CT, IA, NM, OH, PA, & UT - One state allows for statistical sample testing but only using ANSI/ASQC Z1.4: MD - Of the remaining 26 jurisdictions, no specific guidance is given for the choice of statistical sample testing plans: AK, CA, DC, DE, GA, ID, KS, KY, LA, ME, MA, MN, MO, MT, NE, NV, NH, NJ, NC, ND, OK, SC, SD, VT, VA, & WY 16
  • 17. Why Use a Statistical Testing Plan? • Focuses testing on the proper meters. • Minimizes number of meters to be tested; usually requires less than 30% of what a periodic testing plan requires. • Provides data and analysis tools for use in understanding what is happening with installed meters or for use in the purchasing of new meters. 17
  • 18. Homogeneous Population(s) • The groups or populations being sampled and tested are made up of the same or similar items, items which operate in the same way and were made in the same manner. • For electric meters, this has traditionally been interpreted as being meters of a specific meter type from a manufacturer (i.e. AB1, J5S, MX, etc.). • AMR & AMI programs have helped to make the overall populations more homogenous. This makes a utility with AMR & AMI meters better prepared to take advantage of a statistical sampling plan. 18
  • 19. Suitably Sized Samples • The sample size for each group must be large enough to provide a statistically valid sample or the group’s population. • The larger the group’s population, the greater the savings for statistical testing over periodic testing and the more statistically reliable the testing. • AMI implementation generally results in larger group populations. The larger the population, the more suitable for statistical testing. 19
  • 20. Random Sample Selection • Every item within the group or population has an equal chance of being selected as part of the sample for testing. • Random sample selection is critical to providing for a statistically valid sample. 20
  • 21. Population Fits the Statistical Model • The statistical model being used for the sampling/testing plan needs to match the actual distribution of the population. • In most circumstances, one is looking at a normal or Gaussian distribution (i.e. a Bell curve). • This can be checked using a histogram plot and normality test. For mechanical and electromechanical meters, a normal distribution fits the actual data very well. • For electronic or solid-state meters, the meters are highly accurate and recent analysis shows that the test data may not be normal. 21
  • 22. Statistical Testing Plan w/ AMR & AMI • By definition AMR & AMI meters no longer have a pair of human eyes checking the installation each month. Statistical testing allows the Utility to quickly identify which areas may have a problem. • Potential problems that could be caught by aggressive testing. – A faulty batch of meters – Design or premature equipment failures – Poor installation due to a poorly trained crew – Location related failures – Energy Diversion 22
  • 23. Statistical Sampling and Revenue Protection One of the significant benefits to the statistical sampling of AMR & AMI meters is the potential to spot energy diversion more readily. Statistical testing of meters will indicate the overall health of the meter population. Coupled with historical revenue information and meter tamper flags statistical testing can become a powerful tool for combating energy diversion. Utilities will be in a better position than ever to spot trends toward energy diversion more readily and on a closer to real time basis. 23
  • 24. Statistical Testing with AMI Statistical testing to monitor AMI programs will also point out • design or manufacturing deficiencies • installation or post-installation problems (some of which may or may not be energy diversion). All should be pursued and the root cause understood. 24
  • 25. Why Do All of this Testing? Installation of AMI programs move at seemingly breakneck speeds with all focus on schedule. At the same time, problems and exceptions seem to be pouring out of the woodwork. Upper management wants to hear about project milestones and budgets and not about the problems. Especially not any publicly embarrassing problems associated with an AMI installation. 25
  • 26. Why Do All of this Testing? • Statistical testing will allow you to more readily identify where the problems are and where there were simply anomalies. • The testing will help differentiate between training and equipment problems. • The testing will also help to identify potential weak areas in the system that may bear closer scrutiny as the system goes into service • Putting a good testing system into place during the implementation will help to keep you on schedule, on budget, and out of trouble during the installation and will ensure that there will be a good system in place with the self discipline and understanding to administer the system. 26
  • 27. Summary AMR & AMI provides the Utility with the opportunity to get even more and better business information from their installed meter base. Statistical Sampling of these in- service meters can help to point up deficiencies in the installed system during installation as well as shortly after system implementation. The sampling can help to identify potential energy diversion and can help catch design inadequacies in the meters. Once a problem is identified additional statistical testing can help to zero in on a problem and help to identify potential solutions. Statistically testing the installed meter population will allow the utility to more fairly meter the entire population without unfairly charging any one customer and without unfairly subsidizing any group of customers. Statistical sampling plans are also lower cost plans to use than the traditional periodic plans. 27
  • 28. Current ANSI C12.1 Section 5 Issues • Acceptance testing of new meters is not mentioned. • Statistical sampling plans are not adequately defined. • Post deployment or performance monitoring of newly certified meters not covered. 28
  • 29. Updating ANSI C12.1 Section 5 • Consider new meters • Consider AMI devices • Consider new metering device acceptance testing • Provide definition of Statistical Sampling plans • Consider performance monitoring of newly certified meters 29
  • 30. Recommended Changes New Meters & Metering Devices • New meters are covered by sampling and testing requirements. • As-found, as-left, returned to service tests. • Accuracy classes in C12.20 (0.2% and 0.5%) referenced. 30
  • 31. Recommended Changes Statistical Sampling Plans • In-service statistical sampling plans should be developed using: – ANSI/ASQ Z1.9 Sampling Procedures and Tables for Inspection by Variables – ANSI/ASQ Z1.4 Sampling Procedures and Tables for Inspection by Attributes • Provides guidance on how to handle sample failures. • Similar to some State Commission requirements. 31
  • 32. Recommended Changes New Metering Device Acceptance Testing • Sampling and testing of new meter shipments • Uses ANSI Z1.4 (attributes) or ANSI Z1.9 (Variables) for sample size and acceptance criteria. • Specifies an Acceptable Quality Limit (AQL) of 1% or less. 32
  • 33. Recommended Changes Performance Monitoring of Newly Certified Meters • Evaluate newly certified meters after installation…. Different than in-service. • Use statistical sampling plan. 33
  • 34. Meter Testing Traceability • Test equipment to NIST standards • Tracking number of meters to be tested per State Commission requirements • Tracking meter test data • Meter records • Meter Data Management System (MDMS) 34
  • 35. Test Equipment Calibration Primary Requirement: Traceable to NIST Standards • Meter Test Boards, Field Test Kits calibrated to a known master standard maintained at Meter Shop. • Master standard calibrated by outside vendor traceable to NIST or directly by NIST. 35
  • 36. Tracking Meter Records AMI programs help to update and overhaul meter record systems. Having the records for the entire meter population updated allows for a better chance that test data is available to answer questions and that any meter may be selected as part of the sample for testing. 36
  • 37. Meter Test Data Tracking • Need to track test data throughout meter life – Certification testing, first article, acceptance testing, in- service (field & shop), retirement • Best time to start to develop the program is before the meters are being installed. • Use installation reports to determine if there is any initial concerns about the meters being installed. • Typical reports that should be available: • Failed Meter Report, Project to Date • Electric Meters on Network Report 37
  • 38. Meter Test Data Tracking System • System should track meter test results for ease of future reference or for response to public or Utility Commission inquiries. • Maybe part of MDMS or separate system such as ADM • Requires discipline in collecting & entering data, especially field tests. 38
  • 39. Questions? Please feel free to call or e-mail any questions Tom Lawton Tom.Lawton@TescoMeterManager.com 215-688-0298 (cell) The Eastern Specialty Company 39

Editor's Notes

  1. UMPIRE is a Universal Meter Programming and Reading System It reads all meters and recorders It can control all manufactures software
  2. How many meters have been programmed wrong. What is the cost to reputation or customer relations. One single interface to learn The interview style format makes umpire easy to operate and you can decide how to limit what choices the operator has.