ANSI
American National Standard Institute, Inc.
• Not a government agency
• Standards do not have force of Law
• All compliance is voluntary
• ANSI doesn’t actually generate any standards
• Each standard is controlled by an industry
organization as the “secretariat”
 For C12 NEMA (National Electrical Manufacturer’s
Association) is the secretariat
 Paul Orr has been the NEMA’s secretary assigned to C12 for
over ten years providing continuity to the process
Slide 2
ANSI
American National Standard Institute, Inc.
• NEMA organizes committees to propose and review
standards
• Standards are republished approximately every 5
years
• Standards codify consensus approaches in common
practice
• Generally, they do not break new ground or deal in
controversial issues
 This is changing. Can’t avoid issues any longer.
Slide 3
ANSI C12
C12 Main Committee
• General makeup has expanded slightly over last few
years
• 34 voting members with representation from three
groups:
 12 - Manufacturers: Meter, Socket, Test Equipment, etc.
 13 - Users: Utilities
 9 - General Interest: PUC, UL, IEEE, Consultants, etc.
• Meets twice a year in conjunction with EEI/AEIC Meter
conference.
Slide 4
ANSI C12
C12 Main Committee
• Has final approval for all activities on any C12 family
standard
• Establishes Subcommittees (SC) and Working Groups
(WG) to address various standards and issues
• Sub committees and Working Groups also meet twice
a year in conjunction with EEI Transmission,
Distribution and Metering Conference and also hold
regular or ad hoc conference calls throughout the
year as members put together drafts and other
technical material for consideration at the next face
to face meeting.
Slide 5
ANSI C12
C12 Subcommittees
• Various subcommittees have been organized to
review specific standards
• This is where the work is really done
• Each operates slightly differently
• Each meets on a schedule of its own choosing
• Most meet at EEI Biannual Transmission, Distribution
and Metering Meetings
• Communication WG meets more often and longer
• Various subgroups meet frequently by teleconference
Slide 6
ANSI C12 – Sub-Committees
Sub-Committee Standards
C12 SC1 C12.1, C12.4, C12.5, C12.10
C12 SC15 C12.6, C12.7, C12.8, C12.9, C12.11
C12 SC16 C12.20, C12.24
C12 SC17 C12.18, C12.19, C12.21, C12.22, C12.23, C12.26
C12 SC29 C12.29 Standard for Field Testing of Metering Sites
C12 SC31 C12.31 VA Measurement Standard
C12 SC46
C12.46 American National Standard for Electricity
Meters - 0.1, 0.2 and 0.5 Accuracy Classes for the
Measurement of Active, Apparent and Reactive Power
Slide 7
ANSI C12 SC 1
C12.1– Code for Electricity Metering
• C12.1-2014 published in 2016
• Changes in this Revision
 Vector diagrams for balanced voltages are defined for
common services
 Various definitions have been updated
 Bi-directional metering is added and tests updated to
include bidirectional measurements
 Significant changes were made to the temperature rise
section based on TRINIWOG tests
Slide 8
ANSI C12 SC 1
C12.1 – Code for Electricity Metering
• Changes in this Revision (continued)
 Table 1b on maximum errors for reference standards was
added
• Tightened to 0.05% and 0.02%
 Meter Accuracy Class 0.5 was added to the standard
 A new column was added to all tables with tighter specs for
AC 0.5
 Section 5 on Standards for New and In Service Performance
was completely rewritten
 Appendix D was rewritten and simplified
 A new Appendix F was added
Slide 9
ANSI C12 SC 1
C12.1 – Code for Electricity Metering
• Safety
 Work is under way to move the safety related sections of
C12.1 into C12.10
 C12 is coordinating efforts with UL and its work on Subject
2735
• UL2735C (Canadian) is about to be balloted
• New topics for next revision
 Changes to EMC Testing
 Addition of demand testing
 Revision of Temperature Rise Test based on additional
testing
Slide 10
ANSI C12 SC 1
C12.10 – Physical Aspects of Watthour Meters –
Safety Standards
• Published C12.10 – 2011
• New revision in editorial review
 Will add safety sections from C12.1
 New safety requirements in development
 Working with UL to achieve consistency with UL 2735C
 10 new meter forms with auxiliary power pins
Slide 11
ANSI C12 SC 1
New meter forms with Auxiliary Power
Slide 12
ANSI C12 SC 1
New meter forms with Auxiliary Power
Slide 13
ANSI C12 SC 1
New meter forms with Auxiliary Power
Slide 14
ANSI C12 SC 1
New meter forms with Auxiliary Power
Slide 15
ANSI C12 SC 15
 C12.6 – Marking and Arrangement of Terminals
for Phase-Shifting Devices used in Metering
• About to be reissued without change
 C12.7 – Requirements for Watthour Meter
Sockets
• Published – Feb 2015
Slide 16
ANSI C12 SC 15
 C12.8 – Test Block and Cabinets for Installation
of Self contained “A” Base Watthour Meters
• Published without change Dec 2012
• Will be deprecated once Figure 4 is moved to C12.7
in its next release
Slide 17
ANSI C12 SC 15
Slide 18
 C12.9 – Test Switches and Plugs for Transformer
Rated Meters
 Extensive Revision in last publication
 Specifications for test plugs added
 Published – March 2015
ANSI C12 SC 15
 C12.11– Instrument Transformers for Revenue
Metering, 10 kBIL through 350 kBIL
 Revised to parallel C57.13
 Published – July 2014
 New proposal on the table to revise barcode formats
to allow QR and other more modern codes
Slide 19
ANSI C12 SC16
C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering
• C12.20 -2015 Published May 2017, Errata sheet also
published
• 0.1 Percent Accuracy Class Added
• New column added to all accuracy test tables
• Section 4.6 added to provide specifications for test
outputs
 Type B port specifications were made “informative” due to a
lack of unanimity. No Standard can force a manufacturer or
utility to change their existing practices without their
voluntary consent.
Slide 20
ANSI C12 SC16
C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering
• Tighter performance at reference conditions was
specified
• Table 2 updated to make clear which forms and
applications are Blondel compliant.
• Table 2A added to make clear which forms and
applications are NOT Blondel compliant
 Therefore NOT covered by the standard
Slide 21
ANSI C12 SC16
C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering
• Polyphase loading for accuracy testing is allowed and
details provided
 In next revision polyphase loading is proposed to be
REQUIRED
• Non-Sinusoidal Performance Testing
 Harmonics WG
• Extensive performance testing using non-sinusoidal
waveforms was added
Slide 22
ANSI C12 SC16
Slide 23
C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering
• Areas of activity for next revision
 Auxiliary device influences (requiring accuracy testing with
any communication devices active)
 Disturbances test for memory corruption due to rapid
power cycling such as during dropout/reclosure events
 Extended temperature operating ranges
ANSI C12 SC29
Slide 24
Field Testing of Metering Installations
• Field Testing of Metering Accuracy
 Hope to send for approval after next meeting
 Agreement on single set of acceptability criteria for
testing under all three modes
• Voltage and current supplied by test equipment
• Site voltage, equipment provided current
• Site voltage and current (customer load)
 Final issue is review of “acceptability” values
ANSI C12 SC31
Slide 25
VA and VAR Metering Standard
• Establish a legal definition for VA and VAR
• VA being addressed first in order to “Fast Track” the result.
 Definitions agreed upon
 Initial draft completed
• At this meeting, new quantity “source VA” was proposed by
Landis+Gyr
 Committee agreed to consider during a series of WEB conferences
• Goal is to promote VA and active energy (watts) as the primary
metering quantities.
ANSI C12.46
Sub-Committee to Develop a Replacement for
C12.1 and C12.20
• Adopts the structure of OIML IR-46
• Addresses 0.1, 0.2, and 0.5 Accuracy Classes
• Addresses Active, Reactive, and Apparent Energy
• Will be biggest change to metering standards in 100
years
• Review and editing of draft in process
• Expected Publication 2020
Slide 26
Questions and Discussion
Slide 27
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-688-0298(cell)
215-785-2338 (office)
Tom.Lawton@tescometering.com
This presentation can also be found under Meter Conferences
and Schools on the TESCO website:
www.tescometering.com

More Related Content

What's hot

Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
lizzabel
 

What's hot (15)

Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Gas Transmission Pipelines
 
Seismic Considerations Seminar | Portland, Oregon
Seismic Considerations Seminar | Portland, OregonSeismic Considerations Seminar | Portland, Oregon
Seismic Considerations Seminar | Portland, Oregon
 
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
 
PHMSA Final Rule Gas Gathering Line Regulation
PHMSA Final Rule Gas Gathering Line Regulation PHMSA Final Rule Gas Gathering Line Regulation
PHMSA Final Rule Gas Gathering Line Regulation
 
Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...
 
AMI Meter Certification Before, During and After Deployment
AMI Meter Certification Before, During and After DeploymentAMI Meter Certification Before, During and After Deployment
AMI Meter Certification Before, During and After Deployment
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After Deployment
 
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
 
Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion  Field Testing - Where, When & HowPipeline Operations & Maintenance Corrosion  Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & How
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
 
External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA) External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA)
 
Brij mohan cv
Brij mohan  cvBrij mohan  cv
Brij mohan cv
 
Tab
TabTab
Tab
 
Ratio controller in two conical tank interacting level system
Ratio controller in two conical tank interacting level systemRatio controller in two conical tank interacting level system
Ratio controller in two conical tank interacting level system
 

Similar to ANSI Standards and Recent Updates that Affect Metering

Similar to ANSI Standards and Recent Updates that Affect Metering (20)

ANSI Standards Review
ANSI Standards ReviewANSI Standards Review
ANSI Standards Review
 
ANSI Testing
ANSI TestingANSI Testing
ANSI Testing
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
ANSI Standards & Updates
ANSI Standards & UpdatesANSI Standards & Updates
ANSI Standards & Updates
 
ANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current EventsANSI C12.1 Overview and Current Events
ANSI C12.1 Overview and Current Events
 
ANSI C12.1 Overview
ANSI C12.1 OverviewANSI C12.1 Overview
ANSI C12.1 Overview
 
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
 
ANSI 2014 Update
ANSI 2014 UpdateANSI 2014 Update
ANSI 2014 Update
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
 
Ex des workshops Julian Wilson
Ex des workshops Julian WilsonEx des workshops Julian Wilson
Ex des workshops Julian Wilson
 
MEA 2017 ANSI Standards Update
MEA 2017   ANSI Standards UpdateMEA 2017   ANSI Standards Update
MEA 2017 ANSI Standards Update
 
ECBC Training_02-Scope Admin
ECBC Training_02-Scope AdminECBC Training_02-Scope Admin
ECBC Training_02-Scope Admin
 
UL Listing for Electric Meters
UL Listing for Electric MetersUL Listing for Electric Meters
UL Listing for Electric Meters
 
Baf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomsonBaf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomson
 
New Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy PerformanceNew Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy Performance
 
Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability
 
14 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-014 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-0
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 

Recently uploaded

Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
FIDO Alliance
 
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
panagenda
 

Recently uploaded (20)

Generative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdfGenerative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdf
 
Microsoft CSP Briefing Pre-Engagement - Questionnaire
Microsoft CSP Briefing Pre-Engagement - QuestionnaireMicrosoft CSP Briefing Pre-Engagement - Questionnaire
Microsoft CSP Briefing Pre-Engagement - Questionnaire
 
ADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptx
 
The Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and InsightThe Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and Insight
 
Introduction to FIDO Authentication and Passkeys.pptx
Introduction to FIDO Authentication and Passkeys.pptxIntroduction to FIDO Authentication and Passkeys.pptx
Introduction to FIDO Authentication and Passkeys.pptx
 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps Productivity
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
How we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdfHow we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdf
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
 
Event-Driven Architecture Masterclass: Challenges in Stream Processing
Event-Driven Architecture Masterclass: Challenges in Stream ProcessingEvent-Driven Architecture Masterclass: Challenges in Stream Processing
Event-Driven Architecture Masterclass: Challenges in Stream Processing
 
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
 
Easier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties ReimaginedEasier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties Reimagined
 
WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024
 
Intro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptxIntro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptx
 
Google I/O Extended 2024 Warsaw
Google I/O Extended 2024 WarsawGoogle I/O Extended 2024 Warsaw
Google I/O Extended 2024 Warsaw
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overview
 
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
 
Working together SRE & Platform Engineering
Working together SRE & Platform EngineeringWorking together SRE & Platform Engineering
Working together SRE & Platform Engineering
 
How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cf
 

ANSI Standards and Recent Updates that Affect Metering

  • 1. ANSI Standards and Recent Updates That Affect Metering Prepared by Tom Lawton, TESCO For Southeastern Electricity Metering Association (SEMA) Monday, November 6, 2017 2:15 p.m.
  • 2. ANSI American National Standard Institute, Inc. • Not a government agency • Standards do not have force of Law • All compliance is voluntary • ANSI doesn’t actually generate any standards • Each standard is controlled by an industry organization as the “secretariat”  For C12 NEMA (National Electrical Manufacturer’s Association) is the secretariat  Paul Orr has been the NEMA’s secretary assigned to C12 for over ten years providing continuity to the process Slide 2
  • 3. ANSI American National Standard Institute, Inc. • NEMA organizes committees to propose and review standards • Standards are republished approximately every 5 years • Standards codify consensus approaches in common practice • Generally, they do not break new ground or deal in controversial issues  This is changing. Can’t avoid issues any longer. Slide 3
  • 4. ANSI C12 C12 Main Committee • General makeup has expanded slightly over last few years • 34 voting members with representation from three groups:  12 - Manufacturers: Meter, Socket, Test Equipment, etc.  13 - Users: Utilities  9 - General Interest: PUC, UL, IEEE, Consultants, etc. • Meets twice a year in conjunction with EEI/AEIC Meter conference. Slide 4
  • 5. ANSI C12 C12 Main Committee • Has final approval for all activities on any C12 family standard • Establishes Subcommittees (SC) and Working Groups (WG) to address various standards and issues • Sub committees and Working Groups also meet twice a year in conjunction with EEI Transmission, Distribution and Metering Conference and also hold regular or ad hoc conference calls throughout the year as members put together drafts and other technical material for consideration at the next face to face meeting. Slide 5
  • 6. ANSI C12 C12 Subcommittees • Various subcommittees have been organized to review specific standards • This is where the work is really done • Each operates slightly differently • Each meets on a schedule of its own choosing • Most meet at EEI Biannual Transmission, Distribution and Metering Meetings • Communication WG meets more often and longer • Various subgroups meet frequently by teleconference Slide 6
  • 7. ANSI C12 – Sub-Committees Sub-Committee Standards C12 SC1 C12.1, C12.4, C12.5, C12.10 C12 SC15 C12.6, C12.7, C12.8, C12.9, C12.11 C12 SC16 C12.20, C12.24 C12 SC17 C12.18, C12.19, C12.21, C12.22, C12.23, C12.26 C12 SC29 C12.29 Standard for Field Testing of Metering Sites C12 SC31 C12.31 VA Measurement Standard C12 SC46 C12.46 American National Standard for Electricity Meters - 0.1, 0.2 and 0.5 Accuracy Classes for the Measurement of Active, Apparent and Reactive Power Slide 7
  • 8. ANSI C12 SC 1 C12.1– Code for Electricity Metering • C12.1-2014 published in 2016 • Changes in this Revision  Vector diagrams for balanced voltages are defined for common services  Various definitions have been updated  Bi-directional metering is added and tests updated to include bidirectional measurements  Significant changes were made to the temperature rise section based on TRINIWOG tests Slide 8
  • 9. ANSI C12 SC 1 C12.1 – Code for Electricity Metering • Changes in this Revision (continued)  Table 1b on maximum errors for reference standards was added • Tightened to 0.05% and 0.02%  Meter Accuracy Class 0.5 was added to the standard  A new column was added to all tables with tighter specs for AC 0.5  Section 5 on Standards for New and In Service Performance was completely rewritten  Appendix D was rewritten and simplified  A new Appendix F was added Slide 9
  • 10. ANSI C12 SC 1 C12.1 – Code for Electricity Metering • Safety  Work is under way to move the safety related sections of C12.1 into C12.10  C12 is coordinating efforts with UL and its work on Subject 2735 • UL2735C (Canadian) is about to be balloted • New topics for next revision  Changes to EMC Testing  Addition of demand testing  Revision of Temperature Rise Test based on additional testing Slide 10
  • 11. ANSI C12 SC 1 C12.10 – Physical Aspects of Watthour Meters – Safety Standards • Published C12.10 – 2011 • New revision in editorial review  Will add safety sections from C12.1  New safety requirements in development  Working with UL to achieve consistency with UL 2735C  10 new meter forms with auxiliary power pins Slide 11
  • 12. ANSI C12 SC 1 New meter forms with Auxiliary Power Slide 12
  • 13. ANSI C12 SC 1 New meter forms with Auxiliary Power Slide 13
  • 14. ANSI C12 SC 1 New meter forms with Auxiliary Power Slide 14
  • 15. ANSI C12 SC 1 New meter forms with Auxiliary Power Slide 15
  • 16. ANSI C12 SC 15  C12.6 – Marking and Arrangement of Terminals for Phase-Shifting Devices used in Metering • About to be reissued without change  C12.7 – Requirements for Watthour Meter Sockets • Published – Feb 2015 Slide 16
  • 17. ANSI C12 SC 15  C12.8 – Test Block and Cabinets for Installation of Self contained “A” Base Watthour Meters • Published without change Dec 2012 • Will be deprecated once Figure 4 is moved to C12.7 in its next release Slide 17
  • 18. ANSI C12 SC 15 Slide 18  C12.9 – Test Switches and Plugs for Transformer Rated Meters  Extensive Revision in last publication  Specifications for test plugs added  Published – March 2015
  • 19. ANSI C12 SC 15  C12.11– Instrument Transformers for Revenue Metering, 10 kBIL through 350 kBIL  Revised to parallel C57.13  Published – July 2014  New proposal on the table to revise barcode formats to allow QR and other more modern codes Slide 19
  • 20. ANSI C12 SC16 C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering • C12.20 -2015 Published May 2017, Errata sheet also published • 0.1 Percent Accuracy Class Added • New column added to all accuracy test tables • Section 4.6 added to provide specifications for test outputs  Type B port specifications were made “informative” due to a lack of unanimity. No Standard can force a manufacturer or utility to change their existing practices without their voluntary consent. Slide 20
  • 21. ANSI C12 SC16 C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering • Tighter performance at reference conditions was specified • Table 2 updated to make clear which forms and applications are Blondel compliant. • Table 2A added to make clear which forms and applications are NOT Blondel compliant  Therefore NOT covered by the standard Slide 21
  • 22. ANSI C12 SC16 C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering • Polyphase loading for accuracy testing is allowed and details provided  In next revision polyphase loading is proposed to be REQUIRED • Non-Sinusoidal Performance Testing  Harmonics WG • Extensive performance testing using non-sinusoidal waveforms was added Slide 22
  • 23. ANSI C12 SC16 Slide 23 C12.20 – 0.1, 0.2 and 0.5 Accuracy Class Metering • Areas of activity for next revision  Auxiliary device influences (requiring accuracy testing with any communication devices active)  Disturbances test for memory corruption due to rapid power cycling such as during dropout/reclosure events  Extended temperature operating ranges
  • 24. ANSI C12 SC29 Slide 24 Field Testing of Metering Installations • Field Testing of Metering Accuracy  Hope to send for approval after next meeting  Agreement on single set of acceptability criteria for testing under all three modes • Voltage and current supplied by test equipment • Site voltage, equipment provided current • Site voltage and current (customer load)  Final issue is review of “acceptability” values
  • 25. ANSI C12 SC31 Slide 25 VA and VAR Metering Standard • Establish a legal definition for VA and VAR • VA being addressed first in order to “Fast Track” the result.  Definitions agreed upon  Initial draft completed • At this meeting, new quantity “source VA” was proposed by Landis+Gyr  Committee agreed to consider during a series of WEB conferences • Goal is to promote VA and active energy (watts) as the primary metering quantities.
  • 26. ANSI C12.46 Sub-Committee to Develop a Replacement for C12.1 and C12.20 • Adopts the structure of OIML IR-46 • Addresses 0.1, 0.2, and 0.5 Accuracy Classes • Addresses Active, Reactive, and Apparent Energy • Will be biggest change to metering standards in 100 years • Review and editing of draft in process • Expected Publication 2020 Slide 26
  • 27. Questions and Discussion Slide 27 Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 215-688-0298(cell) 215-785-2338 (office) Tom.Lawton@tescometering.com This presentation can also be found under Meter Conferences and Schools on the TESCO website: www.tescometering.com