SlideShare a Scribd company logo
1 of 22
10/02/2012 Slide 1
Standards - Accuracy,
Precision and Traceability
Notes from the Field
Prepared by Tom Lawton,TESCO
for the 2016 Southeastern Meter School and Conference
Discuss and gain an understanding about;
•What is ANSI C12.1 and why do we care
•What is suitable traceability according to the law
•The need for Meter Standards and traceability in electric metering
•The definition of metrology and the application of this science in electric
metering
•The difference between accuracy and precision and why both are important
•The use of Standards in the test lab
•The use of portable Standards in the field
Session Objectives
ANSI C12.1-2015 is the current American National Standard for
Electric Meters, Code for Electricity Metering. Most utility
commissions use this Standard as a reference or the basis for their
regulatory requirements for electric metering within their state.
ANSI C12.20-2010, American National Standard for Electricity
Meters, 0.2 and 0.5 Accuracy Classes, provides different test
tolerances and a few different or modified tests for higher accuracy
meters.
ANSI develops voluntary Standards that are updated approximately
every seven years by a volunteer group of users (utilities),
manufacturers (manufacturers of meters and related metering
equipment) and interested parties (metering professionals).
ANSI C12.1
• Electric Utilities in the United States are regulated by Utility
Commissions within their individual State.
• Commission rulings and regulations are quite literally – THE LAW.
• Most commissions defer to ANSI C12.1 and codify part or all of this
Standard as part of their individual state law regulating electric
utilities.
• ANSI C12.1 is the Law for electric utilities. Every Electric Utility in
the United States maintains traceability of their meter accuracy back
to NIST (the accepted National Metrology Institute) as per ANSI
C12.1 guidelines.
ANSI C12.1 – Why do we care?
• ANSI C12.20 establishes aspects
and acceptable performance criteria
for 0.2 and 0.5 percent accuracy
class meters meeting Blondel’s
Theorem. All other meters are
covered under ANSI C12.1.
• Where there are differences between
C12.20 and C12.1, ANSI Standard
C12.20 takes precedence for meters
covered by C12.20.
• Anything not covered under C12.20
reverts to ANSI C12.1 for meters
covered by C12.20.
ANSI C12.1 and C12.20 Requirements for
accuracy, precision and traceability
Current ANSI C12.1 Testing Requirements –
there are others besides Accuracy
Current ANSI C12.20 Testing Requirements
Every Utility Commission in the United States wants to ensure two
fundamental things regarding the billing of customers within their State;
•That no one customer is being unfairly billed
•That no subset of customers is being unfairly subsidized by the rest of
the rate payers
Correctly Billing the Customer – a Regulator’s
View
• Today we will focus strictly on the traceability for accuracy testing.
Once a meter passes the ANSI tests listed on the previous two
slides there is no regulatory requirement to re-certify a meter in any
way other than for accuracy.
• Electric Utilities are now finding that the functional testing of a meter
must also be done every time a meter is returned to the shop and
for higher end meters full site verifications must also be done
periodically in the field to ensure accurate and reliable metering of
customer energy usage. We will return to these two points briefly at
the end of the presentation.
• This presentation will focus on accuracy and the traceability of this
testing back to the International System of Units (SI).
Accuracy vs. Functional Testing
Accuracy vs Precision
Metrology is defined by the International Bureau of Weights and
Measures (BIPM) as “the science of measurement, embracing both
experimental and theoretical determinations at any level of
uncertainty in any field of science and technology”.
How do we apply this in metering?
.
Metrology and why this word matters to us
3 Standards and standardizing equipment
3.1 General
The purpose of this section is to outline an appropriate chain
of intermediate steps between the national standards and watthour
meters.
3.2 Traceability paths to the International System of Units, SI
It is the responsibility of the utility to establish and maintain
the traceability of the watthour standard to the SI. This traceability
plan shall document the relationship between the revenue meter and
the SI. Described below are some common methods for establishing
this traceability.
ANSI C12.1 Meter Standard Definition and
Requirements
3.2.1 Direct transfer
A watthour transport standard is sent directly to a National Metrology
Institute (NMI) for comparison with the representation of electrical
energy maintained at the NMI. The NMI must be a signatory to the
CIPM Mutual Recognition Arrangement * and be listed in the BIPM
Key Comparison Database (KCDB) indicating Calibration and
Measurement Capabilities (CMC) for AC Power.
3.2.1.2 Independent laboratory
An independent standards laboratory able to document traceability
to the SI may be used by a utility that does not carry out the entire
chain of sequential measurements between the national standards
and the local energy standard. An independent laboratory may
include another utility with a qualified laboratory.
ANSI C12.1 Meter Standard Definition and
Requirements (cont)
3.5.2 Transport standards
•Transport standards are standards of the same nominal accuracy class as the basic reference
standards of a laboratory. Such standards are regularly intercompared with the basic reference
standards to maintain a history of their behavior. The main purpose of the transport standard is to
establish traceability from outside the utility and transfer traceability within the utility.
3.6 Periodic verification of reference standards
•Watthour meters used as reference standards to maintain the unit of energy shall be intercompared
at appropriate intervals.
Every Utility handles their Transfer Standards in a way that suits their operation , their
budget, and the equipment that they have available
– Radian 703’s or their equivalents from Fluke or other manufacturers
– Portable Transfer Standards
– Outside contractors
Transfer/Transport Standards
3.2.1.3 Meter laboratory transport standard comparison to a NMI
The utility selects a transport standard which is sent to the NMI or an
independent laboratory for intercomparison to the national standard.
When the transport standard is returned to the utility, it is
intercompared with the basic reference standards to provide
traceability to the SI.
ANSI C12.1 Meter Standard Definition and
Requirements (cont)
3.3 Meter laboratory
The meter laboratory is concerned with two functions:
a) Maintaining standards whose calibration values are traceable to national standards.
b) Assigning calibration values (correction factors) to working standards.
It may be equipped and staffed to make calibration tests at some or all of the sequential steps
intermediate between the national standards of resistance, EMF, and time interval, and a local
reference standard of energy measurement (such as a group of watthour meters).
3.5 Laboratory standards
Laboratory standards are those standard meters that are used to verify the accuracy of working
standards. The standards in the laboratory are the basic reference standards and the transport
standards.
3.5.1 Basic reference standards
Basic reference standards are those standards with which the accuracy of the watthour is maintained in the
laboratory. Ideally, the basic reference standards of a laboratory should be maintained in groups of three or
more separate individual units that can be intercompared readily. Three standards are the minimum for which a
change in one can be both detected and located by intercomparison.
Meter Labs
3.7 Portable/field/working standard watthour meters
Portable/field/working standards are commonly used interchangeably. These standard
watthour meters are in constant use and accuracy should be verified at least annually.
3.8 Performance records
Historical records should be kept of the performance of each standard. Where this
record shows excessive variation between tests, the standard should then be subjected
to special investigation to determine the cause of the variation. If the cause cannot be
determined and corrected, use of the standard shall be discontinued.
Working Standards
3.4 Meter shop
The meter shop is concerned with the routine testing, repair, and calibration of meters, auxiliary
devices and equipment essential to the metering of electric energy and power.
•Watthour Test Boards are used to test electric meters in traditional meter shops.
•These boards must be “calibrated”.
•What is meter test board calibration and how frequently must this be done
•Best practices and “golden meters”
•How do we maintain traceability for new meters?
Meter Shop Testing
• How is this covered in ANSI C12.1 and ANSI C12.20?
• How do we maintain traceability for these tests?
• How do we ensure the overall accuracy of all of the meters installed on our system?
Field Testing
Is Accuracy testing alone good enough?
ANSI C12.29 will establish recommended
field testing for metering devices and should
eventually be referenced in C12.1 and C12.20.
The new standard is expected to have three
Sections:
• Meter Testing
• Instrument Transformer Testing
• Site Wiring and Auxiliary Devices
New ANSI C12.29 for Field Testing
Metering Devices
Discuss and gain an understanding about;
•What is ANSI C12.1 and why do we care
•What is suitable traceability according to the law
•The need for Meter Standards and traceability in electric metering
•The definition of metrology and the application of this science in electric
metering
•The difference between accuracy and precision and why both are important
•The use of Standards in the test lab
•The use of portable Standards in the field
Session Objectives
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-688-0298 (cell) · 1-800-762-8211
Tom.Lawton@tescometering.com
This presentation can also be found under Meter Conferences
and Schools on the TESCO web site: www.tesco-advent.com

More Related Content

What's hot

Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingTESCO - The Eastern Specialty Company
 
Zigbee based water quality monitoring system using solar power
Zigbee based water quality monitoring system using solar powerZigbee based water quality monitoring system using solar power
Zigbee based water quality monitoring system using solar powereSAT Journals
 
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...Power System Operation
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...TESCO - The Eastern Specialty Company
 

What's hot (20)

Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter Testing
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Introduction to Self-Contained Metering
Introduction to Self-Contained MeteringIntroduction to Self-Contained Metering
Introduction to Self-Contained Metering
 
ANSI Standards & Updates
ANSI Standards & UpdatesANSI Standards & Updates
ANSI Standards & Updates
 
Site Verification for Newer Employees
Site Verification for Newer EmployeesSite Verification for Newer Employees
Site Verification for Newer Employees
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
CALIBRATION INSTRUMENTS
CALIBRATION INSTRUMENTSCALIBRATION INSTRUMENTS
CALIBRATION INSTRUMENTS
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
Zigbee based water quality monitoring system using solar power
Zigbee based water quality monitoring system using solar powerZigbee based water quality monitoring system using solar power
Zigbee based water quality monitoring system using solar power
 
ANSI Testing
ANSI TestingANSI Testing
ANSI Testing
 
Emm unit i
Emm unit   iEmm unit   i
Emm unit i
 
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...
Transmission Line Conductor Asset Health Assessment with Non-Contact Monitori...
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
 
Hands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter TestingHands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter Testing
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Field Testing
Field TestingField Testing
Field Testing
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
DC Metering and Traceability
DC Metering and TraceabilityDC Metering and Traceability
DC Metering and Traceability
 

Viewers also liked

AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Functional Testing - How to Cope With Ever Changing Needs & Requirements
Functional Testing - How to Cope With Ever Changing Needs & RequirementsFunctional Testing - How to Cope With Ever Changing Needs & Requirements
Functional Testing - How to Cope With Ever Changing Needs & RequirementsTESCO - The Eastern Specialty Company
 

Viewers also liked (20)

TESCO New Product Updates
TESCO New Product UpdatesTESCO New Product Updates
TESCO New Product Updates
 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
 
New TESCO Product Update
New TESCO Product UpdateNew TESCO Product Update
New TESCO Product Update
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
Managing Vendor Issues on AMI Design
Managing Vendor Issues on AMI DesignManaging Vendor Issues on AMI Design
Managing Vendor Issues on AMI Design
 
Customer Perceptions of New AMI Meters
Customer Perceptions of New AMI MetersCustomer Perceptions of New AMI Meters
Customer Perceptions of New AMI Meters
 
Functional Testing - How to Cope With Ever Changing Needs & Requirements
Functional Testing - How to Cope With Ever Changing Needs & RequirementsFunctional Testing - How to Cope With Ever Changing Needs & Requirements
Functional Testing - How to Cope With Ever Changing Needs & Requirements
 
History of Electric Metering
History of Electric MeteringHistory of Electric Metering
History of Electric Metering
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni'sMeter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni's
 
Electric Vehicle Service Equipment (EVSE)
Electric Vehicle Service Equipment (EVSE)Electric Vehicle Service Equipment (EVSE)
Electric Vehicle Service Equipment (EVSE)
 
Sema 2016- Managing Vendor Issues on AMI Design
Sema 2016- Managing Vendor Issues on AMI DesignSema 2016- Managing Vendor Issues on AMI Design
Sema 2016- Managing Vendor Issues on AMI Design
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
 
SEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After DeploymentSEMA 2016 - AMI Certification Before, During and After Deployment
SEMA 2016 - AMI Certification Before, During and After Deployment
 
SEMA 2016 - Introduction to Transformer Rated Metering
SEMA 2016 -  Introduction to Transformer Rated MeteringSEMA 2016 -  Introduction to Transformer Rated Metering
SEMA 2016 - Introduction to Transformer Rated Metering
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Keeping the Customer Safe
Keeping the Customer SafeKeeping the Customer Safe
Keeping the Customer Safe
 
SEMA - 2016 Meter Farms, New Tools for AMR and AMI Meters
SEMA - 2016 Meter Farms, New Tools for AMR and AMI MetersSEMA - 2016 Meter Farms, New Tools for AMR and AMI Meters
SEMA - 2016 Meter Farms, New Tools for AMR and AMI Meters
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 
History of Electric Metering
History of Electric MeteringHistory of Electric Metering
History of Electric Metering
 

Similar to Standards - Accuracy, Precision & Traceability

Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...TESCO - The Eastern Specialty Company
 
TRANSDUCERS_chap_1-n.ppt
TRANSDUCERS_chap_1-n.pptTRANSDUCERS_chap_1-n.ppt
TRANSDUCERS_chap_1-n.pptSatishGaur3
 
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO - The Eastern Specialty Company
 
Technical Paper Presentation- ERC Forum
Technical Paper Presentation- ERC ForumTechnical Paper Presentation- ERC Forum
Technical Paper Presentation- ERC ForumRazmi Marzook
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationTESCO - The Eastern Specialty Company
 

Similar to Standards - Accuracy, Precision & Traceability (20)

Single Phase Meter Testing Overview
Single Phase Meter Testing OverviewSingle Phase Meter Testing Overview
Single Phase Meter Testing Overview
 
Customer Request Field Meter Testing Programs
Customer Request Field Meter Testing ProgramsCustomer Request Field Meter Testing Programs
Customer Request Field Meter Testing Programs
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Meter Testing 101.pptx
Meter Testing 101.pptxMeter Testing 101.pptx
Meter Testing 101.pptx
 
Meter Testing Programs & Traceability
Meter Testing Programs & TraceabilityMeter Testing Programs & Traceability
Meter Testing Programs & Traceability
 
ANSI 2014 Update
ANSI 2014 UpdateANSI 2014 Update
ANSI 2014 Update
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
TRANSDUCERS_chap_1-n.ppt
TRANSDUCERS_chap_1-n.pptTRANSDUCERS_chap_1-n.ppt
TRANSDUCERS_chap_1-n.ppt
 
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service PerformanceTESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
TESCO Recommendations for New ANSI C12-1 Standards for In-Service Performance
 
Technical Paper Presentation- ERC Forum
Technical Paper Presentation- ERC ForumTechnical Paper Presentation- ERC Forum
Technical Paper Presentation- ERC Forum
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
 
In-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI DeploymentIn-Service Meter Test Programs After AMI Deployment
In-Service Meter Test Programs After AMI Deployment
 
Power Quality Standards
Power Quality StandardsPower Quality Standards
Power Quality Standards
 
Calibration
CalibrationCalibration
Calibration
 
TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs TESCO Advanced Meter Testing Programs
TESCO Advanced Meter Testing Programs
 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
Unit 6 power quality
Unit 6 power qualityUnit 6 power quality
Unit 6 power quality
 
City & guilds 2392
City & guilds 2392City & guilds 2392
City & guilds 2392
 

Recently uploaded

Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 

Recently uploaded (20)

Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 

Standards - Accuracy, Precision & Traceability

  • 1. 10/02/2012 Slide 1 Standards - Accuracy, Precision and Traceability Notes from the Field Prepared by Tom Lawton,TESCO for the 2016 Southeastern Meter School and Conference
  • 2. Discuss and gain an understanding about; •What is ANSI C12.1 and why do we care •What is suitable traceability according to the law •The need for Meter Standards and traceability in electric metering •The definition of metrology and the application of this science in electric metering •The difference between accuracy and precision and why both are important •The use of Standards in the test lab •The use of portable Standards in the field Session Objectives
  • 3. ANSI C12.1-2015 is the current American National Standard for Electric Meters, Code for Electricity Metering. Most utility commissions use this Standard as a reference or the basis for their regulatory requirements for electric metering within their state. ANSI C12.20-2010, American National Standard for Electricity Meters, 0.2 and 0.5 Accuracy Classes, provides different test tolerances and a few different or modified tests for higher accuracy meters. ANSI develops voluntary Standards that are updated approximately every seven years by a volunteer group of users (utilities), manufacturers (manufacturers of meters and related metering equipment) and interested parties (metering professionals). ANSI C12.1
  • 4. • Electric Utilities in the United States are regulated by Utility Commissions within their individual State. • Commission rulings and regulations are quite literally – THE LAW. • Most commissions defer to ANSI C12.1 and codify part or all of this Standard as part of their individual state law regulating electric utilities. • ANSI C12.1 is the Law for electric utilities. Every Electric Utility in the United States maintains traceability of their meter accuracy back to NIST (the accepted National Metrology Institute) as per ANSI C12.1 guidelines. ANSI C12.1 – Why do we care?
  • 5. • ANSI C12.20 establishes aspects and acceptable performance criteria for 0.2 and 0.5 percent accuracy class meters meeting Blondel’s Theorem. All other meters are covered under ANSI C12.1. • Where there are differences between C12.20 and C12.1, ANSI Standard C12.20 takes precedence for meters covered by C12.20. • Anything not covered under C12.20 reverts to ANSI C12.1 for meters covered by C12.20. ANSI C12.1 and C12.20 Requirements for accuracy, precision and traceability
  • 6. Current ANSI C12.1 Testing Requirements – there are others besides Accuracy
  • 7. Current ANSI C12.20 Testing Requirements
  • 8. Every Utility Commission in the United States wants to ensure two fundamental things regarding the billing of customers within their State; •That no one customer is being unfairly billed •That no subset of customers is being unfairly subsidized by the rest of the rate payers Correctly Billing the Customer – a Regulator’s View
  • 9. • Today we will focus strictly on the traceability for accuracy testing. Once a meter passes the ANSI tests listed on the previous two slides there is no regulatory requirement to re-certify a meter in any way other than for accuracy. • Electric Utilities are now finding that the functional testing of a meter must also be done every time a meter is returned to the shop and for higher end meters full site verifications must also be done periodically in the field to ensure accurate and reliable metering of customer energy usage. We will return to these two points briefly at the end of the presentation. • This presentation will focus on accuracy and the traceability of this testing back to the International System of Units (SI). Accuracy vs. Functional Testing
  • 11. Metrology is defined by the International Bureau of Weights and Measures (BIPM) as “the science of measurement, embracing both experimental and theoretical determinations at any level of uncertainty in any field of science and technology”. How do we apply this in metering? . Metrology and why this word matters to us
  • 12. 3 Standards and standardizing equipment 3.1 General The purpose of this section is to outline an appropriate chain of intermediate steps between the national standards and watthour meters. 3.2 Traceability paths to the International System of Units, SI It is the responsibility of the utility to establish and maintain the traceability of the watthour standard to the SI. This traceability plan shall document the relationship between the revenue meter and the SI. Described below are some common methods for establishing this traceability. ANSI C12.1 Meter Standard Definition and Requirements
  • 13. 3.2.1 Direct transfer A watthour transport standard is sent directly to a National Metrology Institute (NMI) for comparison with the representation of electrical energy maintained at the NMI. The NMI must be a signatory to the CIPM Mutual Recognition Arrangement * and be listed in the BIPM Key Comparison Database (KCDB) indicating Calibration and Measurement Capabilities (CMC) for AC Power. 3.2.1.2 Independent laboratory An independent standards laboratory able to document traceability to the SI may be used by a utility that does not carry out the entire chain of sequential measurements between the national standards and the local energy standard. An independent laboratory may include another utility with a qualified laboratory. ANSI C12.1 Meter Standard Definition and Requirements (cont)
  • 14. 3.5.2 Transport standards •Transport standards are standards of the same nominal accuracy class as the basic reference standards of a laboratory. Such standards are regularly intercompared with the basic reference standards to maintain a history of their behavior. The main purpose of the transport standard is to establish traceability from outside the utility and transfer traceability within the utility. 3.6 Periodic verification of reference standards •Watthour meters used as reference standards to maintain the unit of energy shall be intercompared at appropriate intervals. Every Utility handles their Transfer Standards in a way that suits their operation , their budget, and the equipment that they have available – Radian 703’s or their equivalents from Fluke or other manufacturers – Portable Transfer Standards – Outside contractors Transfer/Transport Standards
  • 15. 3.2.1.3 Meter laboratory transport standard comparison to a NMI The utility selects a transport standard which is sent to the NMI or an independent laboratory for intercomparison to the national standard. When the transport standard is returned to the utility, it is intercompared with the basic reference standards to provide traceability to the SI. ANSI C12.1 Meter Standard Definition and Requirements (cont)
  • 16. 3.3 Meter laboratory The meter laboratory is concerned with two functions: a) Maintaining standards whose calibration values are traceable to national standards. b) Assigning calibration values (correction factors) to working standards. It may be equipped and staffed to make calibration tests at some or all of the sequential steps intermediate between the national standards of resistance, EMF, and time interval, and a local reference standard of energy measurement (such as a group of watthour meters). 3.5 Laboratory standards Laboratory standards are those standard meters that are used to verify the accuracy of working standards. The standards in the laboratory are the basic reference standards and the transport standards. 3.5.1 Basic reference standards Basic reference standards are those standards with which the accuracy of the watthour is maintained in the laboratory. Ideally, the basic reference standards of a laboratory should be maintained in groups of three or more separate individual units that can be intercompared readily. Three standards are the minimum for which a change in one can be both detected and located by intercomparison. Meter Labs
  • 17. 3.7 Portable/field/working standard watthour meters Portable/field/working standards are commonly used interchangeably. These standard watthour meters are in constant use and accuracy should be verified at least annually. 3.8 Performance records Historical records should be kept of the performance of each standard. Where this record shows excessive variation between tests, the standard should then be subjected to special investigation to determine the cause of the variation. If the cause cannot be determined and corrected, use of the standard shall be discontinued. Working Standards
  • 18. 3.4 Meter shop The meter shop is concerned with the routine testing, repair, and calibration of meters, auxiliary devices and equipment essential to the metering of electric energy and power. •Watthour Test Boards are used to test electric meters in traditional meter shops. •These boards must be “calibrated”. •What is meter test board calibration and how frequently must this be done •Best practices and “golden meters” •How do we maintain traceability for new meters? Meter Shop Testing
  • 19. • How is this covered in ANSI C12.1 and ANSI C12.20? • How do we maintain traceability for these tests? • How do we ensure the overall accuracy of all of the meters installed on our system? Field Testing
  • 20. Is Accuracy testing alone good enough? ANSI C12.29 will establish recommended field testing for metering devices and should eventually be referenced in C12.1 and C12.20. The new standard is expected to have three Sections: • Meter Testing • Instrument Transformer Testing • Site Wiring and Auxiliary Devices New ANSI C12.29 for Field Testing Metering Devices
  • 21. Discuss and gain an understanding about; •What is ANSI C12.1 and why do we care •What is suitable traceability according to the law •The need for Meter Standards and traceability in electric metering •The definition of metrology and the application of this science in electric metering •The difference between accuracy and precision and why both are important •The use of Standards in the test lab •The use of portable Standards in the field Session Objectives
  • 22. Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 215-688-0298 (cell) · 1-800-762-8211 Tom.Lawton@tescometering.com This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com

Editor's Notes

  1. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.
  2. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.
  3. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.
  4. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.
  5. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.
  6. Blondel's theorem, named after its discoverer, French electrical engineer André Blondel, is the result of his attempt to simplify both the measurement of electrical energy and the validation of such measurements. The result is a simple rule that specifies the minimum number of watt-hour meters required to measure the consumption of energy in any system of electrical conductors. The theorem states that the power provided to a system of N conductors is equal to the algebraic sum of the power measured by N watt-meters. The N watt-meters are separately connected such that each one measures the current level in one of the N conductors and the potential level between that conductor and a common point. In a further simplification, if that common point is located on one of the conductors, that conductor's meter can be removed and only N-1 meters are required. An electrical energy meter is a watt-meter whose measurements are integrated over time, thus the theorem applies to watt-hour meters as well.[1] Blondel wrote a paper on his results that was delivered to the International Electric Congress held in Chicago in 1893. Although he was not present at the Congress, his paper is included in the published Proceedings.[2] Instead of using N-1 separate meters, the meters are combined into a single housing for commercial purposes such as measuring energy delivered to homes and businesses. Each pairing of a current measuring unit plus a potential measuring unit is then termed a stator or element. Thus, for example, a meter for a four wire service will include three elements. Blondel's Theorem simplifies the work of an electrical utility worker by specifying that an N wire service will be correctly measured by a N-1 element meter. Unfortunately, confusion arises for such workers due to the existence of meters that don't contain tidy pairings of single potential measuring units with single current measuring units. For example, a meter was previously used for four wire services containing two potential coils and three current coils and called a 2.5 element meter. Blondel Noncompliance [edit]Electric energy meters that meet the requirement of N-1 elements for an N wire service are often said to be Blondel Compliant. This label identifies the meter as one that will measure correctly under all conditions when correctly installed. However, a meter doesn't have to be Blondel compliant in order to provide suitably accurate measurements and industry practice often includes the use of such non compliant meters. The form 2S meter is extensively used in the metering of residential three wire services, despite being non compliant in such services. This common residential service consists of two 120 volt wires and one neutral wire. A Blondel compliant meter for such a service would need two elements (and a five jaw socket to accept such a meter), but the 2S meter is a single element meter. The 2S meter includes one potential measuring device (a coil or a voltmeter) and two current measuring devices. The current measuring devices provide a measurement equal to one half of the actual current value. The combination of a single potential coil and two so called half coils provides highly accurate metering under most conditions. The meter has been used since the early days of the electrical industry. The advantages were the lower cost of a single potential coil and the avoidance of interference between two elements driving a single disc in an induction meter. For line to line loads, the meter is Blondel compliant. Such loads are two wire loads and a single element meter suffices. The non compliance of the meter occurs in measuring line to neutral loads. The meter design approximates a two element measurement by combining a half current value with the potential value of the line to line connection. The line to line potential is exactly twice the line to neutral connection if the two line to neutral connections are exactly balanced. Twice the potential times half the current then approximates the actual power value with equality under balanced potential. In the case of line to line loads, two times the half current value times the potential value equals the actual power. Error is introduced if the two line to line potentials are not balanced and if the line to neutral loads are not equally distributed. That error is given by 0.5(V1-V2)(I1-I2) where V1 and I1 are the potential and current connected between one line and neutral and V2 and I2 are those connected between the other line and neutral.[1] Since the industry typically maintains five percent accuracy in potential, the error will be acceptably low if the loads aren't heavily unbalanced. This same meter has been modified or installed in modified sockets and used for two wire, 120 volt services (relabeled as 2W on the meter face). The modification places the two half coils in series such that a full coil is created. In such installations, the single element meter is Blondel compliant. There is also a three wire 240/480 volt version that is not Blondel compliant. Also in use are three phase meters that are not Blondel compliant, such as forms 14S and 15S, but they can be easily replaced by modern meters and can be considered obsolete.