SlideShare a Scribd company logo
1 of 36
Power SystemPower System
ProtectionProtection
1
ContentsContents
Introduction
Functions of Equipment Protection
Functions of Protective Relays
Required Information for Protective Setting
Protection Settings Process
Functional Elements of Protective Relays
Operating Characteristics of Protective Relays
Over current and Directional Protection
Elements
Distance Protection Function
2
Protection Settings: IntroductionProtection Settings: Introduction
A power system is composed of a number of
sections (equipment) such as generator,
transformer, bus bar and transmission line.
These sections are protected by protective
relaying systems comprising of instrument
transformers (ITs), protective relays, circuit
breakers (CBs) and communication equipment.
In case of a fault occurring on a section, its
associated protective relays should detect the
fault and issue trip signals to open their
associated CBs to isolate the faulted section
from the rest of the power system, in order to
avoid further damage to the power system.
3
4
Below Fig. 1 is an typical example of power system sections with their
protection systems. Where:
G1 is a generator. T1 is a transformer. B1,...,B5 are bus bars. L45 is
a transmission line (TL).
RG is a generator protective relay. RT is a transformer protective
relay. RB is a bus protective relay. RL-4,...,RL-9 are TL protective
relays. C1,..., C9 are CBs.
Protection Settings: Introduction
Protection Settings: IntroductionProtection Settings: Introduction
Maximum fault clearance times are usually
specified by the regulating bodies and
network service providers.
The clearing times are given for local and
remote CBs and depend on the voltage level
and are determined primarily to meet
stability requirements and minimize plant
damage.
The maximum clearance times of the backup
protection are also specified.
e.g. the clearing times for faults on the lines
specified by one network service provider in
Australia are presented in Table I (next
slide).
5
Table I: Fault clearance timesTable I: Fault clearance times
Voltage
level [kV]
CB operate correctly
[ms]
CB fail [ms]
Local Remote Local Remote
500 80 100 175 175
330 100 120 250 250
275 100 120 250 250
220 120 140 430 430
132 120 160 430 430
110 120 160 430 430
66 120 160 430 430
≤ 33 1160 - 1500 -
6
Functions of Equipment ProtectionFunctions of Equipment Protection
Protection schemes are generally divided into
equipment protection and system protection.
The main function of equipment protection is to
selectively and rapidly detect and disconnect a fault
on the protected circuit to:
◦ ensure optimal power quality to customers;
◦ minimize damage to the primary plant;
◦ prevent damage to healthy equipment that
conducts fault current during faults;
◦ restore supply over the remaining healthy
network;
◦ sustain stability and integrity of the power system;
◦ limit safety hazard to the power utility personnel
and the public.
7
Functions of Protective RelaysFunctions of Protective Relays
 The protection functions are considered adequate when
the protection relays perform correctly in terms of:
 Dependability: The probability of not having a failure to
operate under given conditions for a given time interval.
 Security: The probability of not having an unwanted
operation under given conditions for a given time interval.
 Speed of Operation: The clearance of faults in the
shortest time is a fundamental requirement (transmission
system), but this must be seen in conjunction with the
associated cost implications and the performance
requirements for a specific application.
8
……Functions of Protective RelaysFunctions of Protective Relays
 Selectivity (Discrimination):
The ability to detect a fault within a specified zone of
a network and to trip the appropriate CB(s) to clear
this fault with a minimum disturbance to the rest of
that network.
 Single failure criterion:
A protection design criterion whereby a protection
system must not fail to operate even after one
component fails to operate.
With respect to the protection relay, the single
failure criterion caters primarily for a failed or
defective relay, and not a failure to operate as a
result of a performance deficiency inherent within
the design of the relay.
9
……Functions of Protective RelaysFunctions of Protective Relays
The setting of protection relays is not a
definite science.
Depending on local conditions and
requirements, setting of each protective
function has to be optimized to achieve
the best balance between reliability,
security and speed of operation.
Protection settings should therefore be
calculated by protection engineers with
vast experience in protective relaying,
power system operation and
performance and quality of supply.
10
required information for Protective Settingrequired information for Protective Setting
Line Parameters:
 For a new line: final total line length as well as the
lengths, conductor sizes and tower types of each
section where different tower types or conductors
have been used.
 This information is used to calculate the parameters
(positive and zero sequence resistance, reactance and
susceptance) for each section.
 Maximum load current or apparent power (MVA)
corresponding to the emergency line which can be
obtained from the table of standard conductor rating
(available in each utility).
 The number of conductors in a bundle has to be taken
into consideration.
11
……required information for Protective Settingrequired information for Protective Setting
Transformer Parameters:
◦ The manufacturer's positive and zero sequence
impedance test values have to be obtained.
◦ The transformer nameplate normally provides the
manufacturer's positive sequence impedance values
only.
Terminal Equipment Rating:
◦ The rating of terminal equipment (CB, CT, line trap,
links) of the circuit may limit its transfer capability
therefore the rating of each device has to be
known.
◦ Data can be obtained from the single line diagrams.
12
……required information for Protectiverequired information for Protective
SettingSetting
Fault Studies
◦ Results of fault studies must be provided.
◦ The developed settings should be checked on future
cases modelled with the system changes that will
take place in the future (e.g. within 5 years).
◦ Use a maximum fault current case.
CT & VT Ratios:
◦ Obtain the CT ratios as indicated on the protection
diagrams.
◦ For existing circuits, it is possible to verify the ratios
indicated on the diagrams by measuring the load
currents on site and comparing with a known ratio.
•
13
……required information for Protective Settingrequired information for Protective Setting
Checking For CT Saturation:
◦ Protection systems are adversely affected by CT saturation.
It is the responsibility of protection engineers to establish for
which forms of protection and under what conditions the CT
should not saturate.
CTs for Transformer Differential
Protection:
◦ MV, HV and LV CTs must be matched as far as possible
taking into consideration the transformer vector group, tap
changer influence and the connection of CTs.
CTs for Transformer Restricted Earth
Fault (REF) Protection:
◦ All CT ratios must be the same (as with the bus
zone protection), except if the relay can internally
correct unmatched ratios.
14
PROTECTION SETTINGS PROCESSPROTECTION SETTINGS PROCESS
 The Protection Settings team obtains all the
information necessary for correct setting calculations.
 The settings are then calculated according to the
latest philosophy, using sound engineering principles.
Pre-written programs may be used as a guide.
 After calculation of the settings, it is important that
another competent person checks them.
 The persons who calculate and who check the
settings both sign the formal settings document.
 The flowchart in Fig. 2 indicates information flow
during protection setting preparation for
commissioning of new Transmission plant.
15
16
Project leader of the Protection
Settings team determines scope
of work and target dates
Summary and comparison of inputs
IED manufacturers provide bay
specific IED details
Engineering team provides bay
specific proformas and drawings
Corrective actions and re-issue of
drawings
Study new protection and create
necessary setting templates in
liaison with engineering team and
IED manufactureres
OK Not OK
Calculation and verification of settings
Settings stored in central database
and formal document issued
Implementation date and responsible
field person stored in the central
database -> implementation action
Implementation sheet completed
by field staff and returned to
Protection Settings team
Interface with the Expansion Planing
team and IED manufacturers to obtain
relevant equipment parameters for
correct system modelling
Centralised Settings Management
System sends the action documents
to the field staff
Corrective actions required to
ensure implementation
Fig. 2 Information flow during
protection settings preparation
FUNCTIONAL ELEMENTS OF PROTECTIVEFUNCTIONAL ELEMENTS OF PROTECTIVE
RELAYSRELAYS
 To achieve maximum flexibility, relays is designed using the
concept of functional elements which include protection
elements, control elements, input and output contacts etc.
 The protection elements are arranged to detect the system
condition, make a decision if the observed variables are
over/under the acceptable limit, and take proper action if
acceptable limits are crossed.
 Protection element measures system quantities such as
voltages and currents, and compares these quantities or
their combination against a threshold setting (pickup
values).
 If this comparison indicates that the thresholds are crossed,
a decision element is triggered.
 This may involve a timing element, to determine if the
condition is permanent or temporary. If all checks are
satisfied, the relay (action element) operates.
17
18
Fault
Pickup of
protection element
Operation of
protection element
Assertion of relay
trip logic signal
Action of relay
trip contact
Circuit breaker
opening
Fault cleared
Sequence of protection operation initiated by a fault is
shown in Fig. 3.
OPERATING CHARACTERISTICS OFOPERATING CHARACTERISTICS OF
PROTECTIVE RELAYSPROTECTIVE RELAYS
 Protective relays respond and operate according to
defined operating characteristic and applied settings.
 Each type of protective relay has distinctive operating
characteristic to achieve implementation objective:
sensitivity, selectivity, reliability and adequate speed
of operation.
 Basic operating characteristics of protective elements
is as follows:
 Overcurrent protection function: the overcurrent
element operates or picks up when its input current
exceeds a predetermined value.
 Directional function: an element picks up for faults
in one direction, and remains stable for faults in the
other direction.
19
……OPERATING CHARACTERISTICS OF PROTECTIVEOPERATING CHARACTERISTICS OF PROTECTIVE
RELAYSRELAYS
Distance protection function: an element
used for protection of transmission lines whose
response is a function of the measured electrical
distance between the relay location and the fault
point.
Differential protection function: it senses a
difference between incoming and outgoing
currents flowing through the protected
apparatus.
Communications-Assisted Tripping
Schemes: a form of the transmission line
protection that uses a communication between
distance relays at opposite line ends resulting in
selective clearing of all line faults without time
delay.
20
OVERCURRENT AND DIRECTIONALOVERCURRENT AND DIRECTIONAL
PROTECTION ELEMENTSPROTECTION ELEMENTS
 An over current condition occurs when the
maximum continuous load current permissible for a
particular piece of equipment is exceeded.
 A phase overcurrent protection element
continuously monitors the phase current being
conducted in the system and issue a trip command
to a CB when the measured current exceeds a
predefined setting.
 The biggest area of concern for over-current
protection is how to achieve selectivity.
 Some possible solutions have been developed,
including monitoring current levels (current
grading), introducing time delays (time grading) or
combining the two as well as including a directional
element to detect the direction of current flow.
21
Current gradingCurrent grading
Current grading will achieve selectivity by
determine the location of a fault using purely
magnitude of current.
It is difficult to implement this in practice
unless feeder sections have sufficient
differences in impedance to cause noticeable
variations in fault current.
In a network where there are several
sections of line connected in series, without
significant impedances at their junctions
there will be little difference in currents, so
discrimination or selectivity cannot be
achieved using current grading.
22
time delaystime delays
 An alternate means of grading is introducing time delays
between subsequent relays.
 Time delays are set so that the appropriate relay has
sufficient time to open its breaker and clear the fault on its
section of line before the relay associated with the adjacent
section acts.
 Hence, the relay at the remote end is set up to have the
shortest time delay and each successive relay back toward
the source has an increasingly longer time delay.
 This eliminates some of the problems with current grading
and achieves a system where the minimum amount of
equipment is isolated during a fault.
 However, there is one main problem which arises due to the
fact that timing is based solely on position, not fault current
level.
 So, faults nearer to the source, which carry the highest
current, will take longer to clear, which is very contradictory
and can prove to be quite costly.
23
directional elementsdirectional elements
 Selectivity can be achieved by using directional elements
in conjunction with instantaneous or definite-time
overcurrent elements.
 Directional overcurrent protection schemes respond to
faults in only one direction which allows the relay to be
set in coordination with other relays downstream from the
relay location.
 This is explained using example in Fig. 4.
24
directional elementsdirectional elements
 By providing directional
elements at the remote ends
of this system, which would
only operate for fault
currents flowing in one
direction we can maintain
redundancy during a fault.
 This is in line with one of the
main outcomes of ensuring
selectivity, which is to
minimize amount of circuitry
that is isolated in order to
clear a fault.
25
Fig. 4: Use of direction element
example
direction of current flowdirection of current flow
 In AC systems, it is difficult to determine the direction of
current flow and the only way to achieve this is to perform
measurements with reference to another alternating
quantity, namely voltage. The main principle of how
directional elements operate is based on the following
equations for torque:
 If current is in the forward direction, then the sign of the
torque equation will be positive and as soon as the direction
of current flow reverses, the sign of the torque equation
becomes negative. These calculations are constantly being
performed internally inside directional element.
26
)cos( ABCABCA IVIVT ∠−∠••=
)cos( BCABCAB IVIVT ∠−∠••=
)cos( CABCABC IVIVT ∠−∠••=
DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION
A distance protection element measures the
quotient V/I (impedance), considering the
phase angle between the voltage V and the
current I.
In the event of a fault, sudden changes
occur in measured voltage and current,
causing a variation in the measured
impedance.
The measured impedance is then compared
against the set value.
Distance element will trip the relay (a trip
command will be issued to the CB associated
with the relay) if the measured value of the
impedance is less then the value set.
27
……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION
We can see that the impedance value of a
fault loop increases from zero for a short
circuit at the source end A, up to some finite
value at the remote end B. We can use this
principle to set up zones of distance
protection as well as to provide feedback
about where a fault occurred (distance to
fault).
Operating characteristics of distance
protection elements are usually represented
using R-X diagrams.
Fig. 6 shows an example of Mho R-X
operating characteristic. The relay is
considered to be at the origin.
28
……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION
29
Region of
operation
Zone 1
Region of
non-operation
outside the circle
Load
region
R
X
Zone 2
A
B
80%
120%
Line P
Line Q
Fig. 6 Mho positive-sequence R-X operating
characteristic of a distance element.
……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION
The need for zones shown in Fig. 6 arises
from the need of selective protection; i.e.
the distance element should only trip faulty
section.
We can set the distance element to only
trigger a trip signal for faults within a
certain distance from the relay, which is
called the distance element reach.
The setting impedance is represented by
, where ZL is the line impedance.
The distance element will only trip when
the measured impedance ZR is less than or
equal to the setting impedance hsZL.
30
RS s LZ h Z=
……DISTANCE PROTECTIONDISTANCE PROTECTION
FUNCTIONFUNCTION
 Typically hs is set to protect 80% of the line between
two buses and this forms protection Zone 1.
 Errors in the VTs and CTs, modeled transmission line
data, and fault study data do not permit setting Zone 1
for 100% of the transmission line.
 If we set Zone 1 for 100% of the transmission line,
unwanted tripping could occur for faults just beyond
the remote end of the line.
31
……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION
Zone 2 is set to protect 120% of the line,
hence making it over-reaching, because it
extends into the section of line protected by
the relay at point B. To avoid nuisance
tripping, any fault occurring in Zone 1 is
cleared instantaneously, while faults which
occur in Zone 2 are cleared after a time delay
in order to allow relay B to clear that fault
first.
This provides redundancy in the protection
system (backup), whilst maintaining
selectivity.
32
ABOUT SYSTEM PROTECTIONABOUT SYSTEM PROTECTION
33
RELAY TESTING SERVICESRELAY TESTING SERVICES
34
Click Here ForClick Here For
Power System ProtectionPower System Protection
35
THANK YOUTHANK YOU
FOR MORE INFORMATIONFOR MORE INFORMATION
VISIT OUR WEBSITE ....VISIT OUR WEBSITE ....
36

More Related Content

What's hot

ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
J. FR
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
moiz89
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
jbpatel7290
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
michaeljmack
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
Priten Vasa
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
ashwin fcc
 

What's hot (20)

Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
220kv substation
220kv substation220kv substation
220kv substation
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
Bus Bar Protection
Bus Bar ProtectionBus Bar Protection
Bus Bar Protection
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Protective relay
Protective relay Protective relay
Protective relay
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zones
 

Viewers also liked

POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.BhideFundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Sourabh Ghosh
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
Binit Das
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power System
vkmalik
 
Numerical protection 2
Numerical protection 2Numerical protection 2
Numerical protection 2
angila95
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
farazrafi87
 

Viewers also liked (20)

POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.BhideFundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
protection and relay scheme
protection and relay schemeprotection and relay scheme
protection and relay scheme
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power System
 
protection for power system
protection for power systemprotection for power system
protection for power system
 
Types of relay
Types of relayTypes of relay
Types of relay
 
Distance Relay:->Mho relay
Distance Relay:->Mho relayDistance Relay:->Mho relay
Distance Relay:->Mho relay
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protection
 
Numerical protection 2
Numerical protection 2Numerical protection 2
Numerical protection 2
 
distance relay
distance relaydistance relay
distance relay
 
Protective Relay by Shamim Reza
Protective Relay  by Shamim RezaProtective Relay  by Shamim Reza
Protective Relay by Shamim Reza
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
Installation
InstallationInstallation
Installation
 

Similar to Power system Protection Services in India

protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
Thien Phan Bản
 
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Oktay Yaman
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectio
Aminu Bugaje
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
Power System Operation
 

Similar to Power system Protection Services in India (20)

protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
 
H15 POWER SYSTEM PROTECTION EMERSON EDUARDO RODRIGUES.pdf
H15 POWER SYSTEM PROTECTION EMERSON EDUARDO RODRIGUES.pdfH15 POWER SYSTEM PROTECTION EMERSON EDUARDO RODRIGUES.pdf
H15 POWER SYSTEM PROTECTION EMERSON EDUARDO RODRIGUES.pdf
 
Protective relaying
Protective relayingProtective relaying
Protective relaying
 
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
Implementation of Transformer Protection by Intelligent Electronic Device for...
Implementation of Transformer Protection by Intelligent Electronic Device for...Implementation of Transformer Protection by Intelligent Electronic Device for...
Implementation of Transformer Protection by Intelligent Electronic Device for...
 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectio
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
Modelling and Implementation of Microprocessor Based Numerical Relay for Prot...
Modelling and Implementation of Microprocessor Based Numerical Relay for Prot...Modelling and Implementation of Microprocessor Based Numerical Relay for Prot...
Modelling and Implementation of Microprocessor Based Numerical Relay for Prot...
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
 
E011123541
E011123541E011123541
E011123541
 
Transformer Protection using PLC
Transformer Protection using PLCTransformer Protection using PLC
Transformer Protection using PLC
 
Sistem Tenaga Listrik
Sistem Tenaga Listrik Sistem Tenaga Listrik
Sistem Tenaga Listrik
 
Review on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power TransformerReview on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power Transformer
 
Electrical network protection guide schneider electric
Electrical network protection guide schneider electricElectrical network protection guide schneider electric
Electrical network protection guide schneider electric
 
128 electrical power-protection_guide
128 electrical power-protection_guide128 electrical power-protection_guide
128 electrical power-protection_guide
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 

More from System Protection

More from System Protection (20)

Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54
 
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your AssetsMastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
 
AC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System ProtectionAC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System Protection
 
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System ProtectionDigital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
 
DIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System ProtectionDIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System Protection
 
Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711
 
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp TestingEarth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
 
Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016
 
Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)
 
Case Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenueCase Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenue
 
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber MatHONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
 
Salisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over ShoesSalisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over Shoes
 
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kVSalisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
 
LOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System ProtectionLOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System Protection
 
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System ProtectionPORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
 
RCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System ProtectionRCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System Protection
 
Case Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-downCase Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-down
 
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
 
Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...
 
Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 

Power system Protection Services in India

  • 2. ContentsContents Introduction Functions of Equipment Protection Functions of Protective Relays Required Information for Protective Setting Protection Settings Process Functional Elements of Protective Relays Operating Characteristics of Protective Relays Over current and Directional Protection Elements Distance Protection Function 2
  • 3. Protection Settings: IntroductionProtection Settings: Introduction A power system is composed of a number of sections (equipment) such as generator, transformer, bus bar and transmission line. These sections are protected by protective relaying systems comprising of instrument transformers (ITs), protective relays, circuit breakers (CBs) and communication equipment. In case of a fault occurring on a section, its associated protective relays should detect the fault and issue trip signals to open their associated CBs to isolate the faulted section from the rest of the power system, in order to avoid further damage to the power system. 3
  • 4. 4 Below Fig. 1 is an typical example of power system sections with their protection systems. Where: G1 is a generator. T1 is a transformer. B1,...,B5 are bus bars. L45 is a transmission line (TL). RG is a generator protective relay. RT is a transformer protective relay. RB is a bus protective relay. RL-4,...,RL-9 are TL protective relays. C1,..., C9 are CBs. Protection Settings: Introduction
  • 5. Protection Settings: IntroductionProtection Settings: Introduction Maximum fault clearance times are usually specified by the regulating bodies and network service providers. The clearing times are given for local and remote CBs and depend on the voltage level and are determined primarily to meet stability requirements and minimize plant damage. The maximum clearance times of the backup protection are also specified. e.g. the clearing times for faults on the lines specified by one network service provider in Australia are presented in Table I (next slide). 5
  • 6. Table I: Fault clearance timesTable I: Fault clearance times Voltage level [kV] CB operate correctly [ms] CB fail [ms] Local Remote Local Remote 500 80 100 175 175 330 100 120 250 250 275 100 120 250 250 220 120 140 430 430 132 120 160 430 430 110 120 160 430 430 66 120 160 430 430 ≤ 33 1160 - 1500 - 6
  • 7. Functions of Equipment ProtectionFunctions of Equipment Protection Protection schemes are generally divided into equipment protection and system protection. The main function of equipment protection is to selectively and rapidly detect and disconnect a fault on the protected circuit to: ◦ ensure optimal power quality to customers; ◦ minimize damage to the primary plant; ◦ prevent damage to healthy equipment that conducts fault current during faults; ◦ restore supply over the remaining healthy network; ◦ sustain stability and integrity of the power system; ◦ limit safety hazard to the power utility personnel and the public. 7
  • 8. Functions of Protective RelaysFunctions of Protective Relays  The protection functions are considered adequate when the protection relays perform correctly in terms of:  Dependability: The probability of not having a failure to operate under given conditions for a given time interval.  Security: The probability of not having an unwanted operation under given conditions for a given time interval.  Speed of Operation: The clearance of faults in the shortest time is a fundamental requirement (transmission system), but this must be seen in conjunction with the associated cost implications and the performance requirements for a specific application. 8
  • 9. ……Functions of Protective RelaysFunctions of Protective Relays  Selectivity (Discrimination): The ability to detect a fault within a specified zone of a network and to trip the appropriate CB(s) to clear this fault with a minimum disturbance to the rest of that network.  Single failure criterion: A protection design criterion whereby a protection system must not fail to operate even after one component fails to operate. With respect to the protection relay, the single failure criterion caters primarily for a failed or defective relay, and not a failure to operate as a result of a performance deficiency inherent within the design of the relay. 9
  • 10. ……Functions of Protective RelaysFunctions of Protective Relays The setting of protection relays is not a definite science. Depending on local conditions and requirements, setting of each protective function has to be optimized to achieve the best balance between reliability, security and speed of operation. Protection settings should therefore be calculated by protection engineers with vast experience in protective relaying, power system operation and performance and quality of supply. 10
  • 11. required information for Protective Settingrequired information for Protective Setting Line Parameters:  For a new line: final total line length as well as the lengths, conductor sizes and tower types of each section where different tower types or conductors have been used.  This information is used to calculate the parameters (positive and zero sequence resistance, reactance and susceptance) for each section.  Maximum load current or apparent power (MVA) corresponding to the emergency line which can be obtained from the table of standard conductor rating (available in each utility).  The number of conductors in a bundle has to be taken into consideration. 11
  • 12. ……required information for Protective Settingrequired information for Protective Setting Transformer Parameters: ◦ The manufacturer's positive and zero sequence impedance test values have to be obtained. ◦ The transformer nameplate normally provides the manufacturer's positive sequence impedance values only. Terminal Equipment Rating: ◦ The rating of terminal equipment (CB, CT, line trap, links) of the circuit may limit its transfer capability therefore the rating of each device has to be known. ◦ Data can be obtained from the single line diagrams. 12
  • 13. ……required information for Protectiverequired information for Protective SettingSetting Fault Studies ◦ Results of fault studies must be provided. ◦ The developed settings should be checked on future cases modelled with the system changes that will take place in the future (e.g. within 5 years). ◦ Use a maximum fault current case. CT & VT Ratios: ◦ Obtain the CT ratios as indicated on the protection diagrams. ◦ For existing circuits, it is possible to verify the ratios indicated on the diagrams by measuring the load currents on site and comparing with a known ratio. • 13
  • 14. ……required information for Protective Settingrequired information for Protective Setting Checking For CT Saturation: ◦ Protection systems are adversely affected by CT saturation. It is the responsibility of protection engineers to establish for which forms of protection and under what conditions the CT should not saturate. CTs for Transformer Differential Protection: ◦ MV, HV and LV CTs must be matched as far as possible taking into consideration the transformer vector group, tap changer influence and the connection of CTs. CTs for Transformer Restricted Earth Fault (REF) Protection: ◦ All CT ratios must be the same (as with the bus zone protection), except if the relay can internally correct unmatched ratios. 14
  • 15. PROTECTION SETTINGS PROCESSPROTECTION SETTINGS PROCESS  The Protection Settings team obtains all the information necessary for correct setting calculations.  The settings are then calculated according to the latest philosophy, using sound engineering principles. Pre-written programs may be used as a guide.  After calculation of the settings, it is important that another competent person checks them.  The persons who calculate and who check the settings both sign the formal settings document.  The flowchart in Fig. 2 indicates information flow during protection setting preparation for commissioning of new Transmission plant. 15
  • 16. 16 Project leader of the Protection Settings team determines scope of work and target dates Summary and comparison of inputs IED manufacturers provide bay specific IED details Engineering team provides bay specific proformas and drawings Corrective actions and re-issue of drawings Study new protection and create necessary setting templates in liaison with engineering team and IED manufactureres OK Not OK Calculation and verification of settings Settings stored in central database and formal document issued Implementation date and responsible field person stored in the central database -> implementation action Implementation sheet completed by field staff and returned to Protection Settings team Interface with the Expansion Planing team and IED manufacturers to obtain relevant equipment parameters for correct system modelling Centralised Settings Management System sends the action documents to the field staff Corrective actions required to ensure implementation Fig. 2 Information flow during protection settings preparation
  • 17. FUNCTIONAL ELEMENTS OF PROTECTIVEFUNCTIONAL ELEMENTS OF PROTECTIVE RELAYSRELAYS  To achieve maximum flexibility, relays is designed using the concept of functional elements which include protection elements, control elements, input and output contacts etc.  The protection elements are arranged to detect the system condition, make a decision if the observed variables are over/under the acceptable limit, and take proper action if acceptable limits are crossed.  Protection element measures system quantities such as voltages and currents, and compares these quantities or their combination against a threshold setting (pickup values).  If this comparison indicates that the thresholds are crossed, a decision element is triggered.  This may involve a timing element, to determine if the condition is permanent or temporary. If all checks are satisfied, the relay (action element) operates. 17
  • 18. 18 Fault Pickup of protection element Operation of protection element Assertion of relay trip logic signal Action of relay trip contact Circuit breaker opening Fault cleared Sequence of protection operation initiated by a fault is shown in Fig. 3.
  • 19. OPERATING CHARACTERISTICS OFOPERATING CHARACTERISTICS OF PROTECTIVE RELAYSPROTECTIVE RELAYS  Protective relays respond and operate according to defined operating characteristic and applied settings.  Each type of protective relay has distinctive operating characteristic to achieve implementation objective: sensitivity, selectivity, reliability and adequate speed of operation.  Basic operating characteristics of protective elements is as follows:  Overcurrent protection function: the overcurrent element operates or picks up when its input current exceeds a predetermined value.  Directional function: an element picks up for faults in one direction, and remains stable for faults in the other direction. 19
  • 20. ……OPERATING CHARACTERISTICS OF PROTECTIVEOPERATING CHARACTERISTICS OF PROTECTIVE RELAYSRELAYS Distance protection function: an element used for protection of transmission lines whose response is a function of the measured electrical distance between the relay location and the fault point. Differential protection function: it senses a difference between incoming and outgoing currents flowing through the protected apparatus. Communications-Assisted Tripping Schemes: a form of the transmission line protection that uses a communication between distance relays at opposite line ends resulting in selective clearing of all line faults without time delay. 20
  • 21. OVERCURRENT AND DIRECTIONALOVERCURRENT AND DIRECTIONAL PROTECTION ELEMENTSPROTECTION ELEMENTS  An over current condition occurs when the maximum continuous load current permissible for a particular piece of equipment is exceeded.  A phase overcurrent protection element continuously monitors the phase current being conducted in the system and issue a trip command to a CB when the measured current exceeds a predefined setting.  The biggest area of concern for over-current protection is how to achieve selectivity.  Some possible solutions have been developed, including monitoring current levels (current grading), introducing time delays (time grading) or combining the two as well as including a directional element to detect the direction of current flow. 21
  • 22. Current gradingCurrent grading Current grading will achieve selectivity by determine the location of a fault using purely magnitude of current. It is difficult to implement this in practice unless feeder sections have sufficient differences in impedance to cause noticeable variations in fault current. In a network where there are several sections of line connected in series, without significant impedances at their junctions there will be little difference in currents, so discrimination or selectivity cannot be achieved using current grading. 22
  • 23. time delaystime delays  An alternate means of grading is introducing time delays between subsequent relays.  Time delays are set so that the appropriate relay has sufficient time to open its breaker and clear the fault on its section of line before the relay associated with the adjacent section acts.  Hence, the relay at the remote end is set up to have the shortest time delay and each successive relay back toward the source has an increasingly longer time delay.  This eliminates some of the problems with current grading and achieves a system where the minimum amount of equipment is isolated during a fault.  However, there is one main problem which arises due to the fact that timing is based solely on position, not fault current level.  So, faults nearer to the source, which carry the highest current, will take longer to clear, which is very contradictory and can prove to be quite costly. 23
  • 24. directional elementsdirectional elements  Selectivity can be achieved by using directional elements in conjunction with instantaneous or definite-time overcurrent elements.  Directional overcurrent protection schemes respond to faults in only one direction which allows the relay to be set in coordination with other relays downstream from the relay location.  This is explained using example in Fig. 4. 24
  • 25. directional elementsdirectional elements  By providing directional elements at the remote ends of this system, which would only operate for fault currents flowing in one direction we can maintain redundancy during a fault.  This is in line with one of the main outcomes of ensuring selectivity, which is to minimize amount of circuitry that is isolated in order to clear a fault. 25 Fig. 4: Use of direction element example
  • 26. direction of current flowdirection of current flow  In AC systems, it is difficult to determine the direction of current flow and the only way to achieve this is to perform measurements with reference to another alternating quantity, namely voltage. The main principle of how directional elements operate is based on the following equations for torque:  If current is in the forward direction, then the sign of the torque equation will be positive and as soon as the direction of current flow reverses, the sign of the torque equation becomes negative. These calculations are constantly being performed internally inside directional element. 26 )cos( ABCABCA IVIVT ∠−∠••= )cos( BCABCAB IVIVT ∠−∠••= )cos( CABCABC IVIVT ∠−∠••=
  • 27. DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION A distance protection element measures the quotient V/I (impedance), considering the phase angle between the voltage V and the current I. In the event of a fault, sudden changes occur in measured voltage and current, causing a variation in the measured impedance. The measured impedance is then compared against the set value. Distance element will trip the relay (a trip command will be issued to the CB associated with the relay) if the measured value of the impedance is less then the value set. 27
  • 28. ……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION We can see that the impedance value of a fault loop increases from zero for a short circuit at the source end A, up to some finite value at the remote end B. We can use this principle to set up zones of distance protection as well as to provide feedback about where a fault occurred (distance to fault). Operating characteristics of distance protection elements are usually represented using R-X diagrams. Fig. 6 shows an example of Mho R-X operating characteristic. The relay is considered to be at the origin. 28
  • 29. ……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION 29 Region of operation Zone 1 Region of non-operation outside the circle Load region R X Zone 2 A B 80% 120% Line P Line Q Fig. 6 Mho positive-sequence R-X operating characteristic of a distance element.
  • 30. ……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION The need for zones shown in Fig. 6 arises from the need of selective protection; i.e. the distance element should only trip faulty section. We can set the distance element to only trigger a trip signal for faults within a certain distance from the relay, which is called the distance element reach. The setting impedance is represented by , where ZL is the line impedance. The distance element will only trip when the measured impedance ZR is less than or equal to the setting impedance hsZL. 30 RS s LZ h Z=
  • 31. ……DISTANCE PROTECTIONDISTANCE PROTECTION FUNCTIONFUNCTION  Typically hs is set to protect 80% of the line between two buses and this forms protection Zone 1.  Errors in the VTs and CTs, modeled transmission line data, and fault study data do not permit setting Zone 1 for 100% of the transmission line.  If we set Zone 1 for 100% of the transmission line, unwanted tripping could occur for faults just beyond the remote end of the line. 31
  • 32. ……DISTANCE PROTECTION FUNCTIONDISTANCE PROTECTION FUNCTION Zone 2 is set to protect 120% of the line, hence making it over-reaching, because it extends into the section of line protected by the relay at point B. To avoid nuisance tripping, any fault occurring in Zone 1 is cleared instantaneously, while faults which occur in Zone 2 are cleared after a time delay in order to allow relay B to clear that fault first. This provides redundancy in the protection system (backup), whilst maintaining selectivity. 32
  • 33. ABOUT SYSTEM PROTECTIONABOUT SYSTEM PROTECTION 33
  • 34. RELAY TESTING SERVICESRELAY TESTING SERVICES 34
  • 35. Click Here ForClick Here For Power System ProtectionPower System Protection 35
  • 36. THANK YOUTHANK YOU FOR MORE INFORMATIONFOR MORE INFORMATION VISIT OUR WEBSITE ....VISIT OUR WEBSITE .... 36