SlideShare a Scribd company logo
1 of 21
89.7
94.7
93.0
95.6
86.7
95.6
86.7
Month
Sept. 21
Oct.21
Nov.21
Dec.21
Jan.22
Feb.22
PQI
%
Month
PQI Trend(Sept21-Mar.22)
Overall Construction
Construction
Overall Mar.21 Cumulative
Target: > 94.0 %
97.5
94.8
96.9
95.5
97.5
93.3
96.8
99
89.7
94.7
93
95.6
94.3
84
86
88
90
92
94
96
98
100
PQI
%
Month
Monthly PQI Trend
PQI Linear (PQI)
86.7
90.1 90.1
84
85
86
87
88
89
90
91
Jan.22 Feb.22 Cumulative
PQI
%
Month
Monthly PQI Trend
PQI Linear (PQI)
4
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
PQI IMPACT
3
Drawing &
technical
douments
Controlled
QC
personnel
assigned as
per Sch Q
Handling
storage &
preservatio
n
E & I work
acceptance
Mechanical
Work
Acceptance
Skipping of
ITP activity
Document
Rejections
Civil Work
Acceptance
Jun.21 0.6 2.2 2.6 0.2 1 2.3 0.6 0.2
Jul.21 1.9 0 1.9 0.5 0.9 0.6 1.1 1
Aug. 21 1.9 0 1.9 0.5 1.2 0.6 1.2 1
Sept.21 4.6 2.5 2.3 2 1.7 1.3 0 0
Oct.21 0.7 1.6 4.2 1.7 2.9 0.7
0.7
1.6
4.2
1.7
2.9
0.7
4.6 2.5
2.3
2
1.7
1.3
0 0
1.9
0
1.9
0.5
1.2
0.6
1.2 1
1.9
0
1.9
0.5
0.9
0.6
1.1 1
0.6
2.2
2.6
0.2
1
2.3
0.6
0.2
0
2
4
6
8
10
12
14
Rejection
%
PQI Element
PQI Impact Month wise
5
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Quality Statistics
PQI Analysis For October 2021
PQI
Item
Description
Impact
%
Remarks
2.7 Handling, Storage &
preservation
4.2% SANCR # 500017033, INCR:6600019725.
3.3 Mechanical Work
acceptance
2.9% SALBE:4500237550/4500237877/4500239436/450024027
6/4500243409/4500244649/4500244662
3.5 E & I Work Acceptance 1.7% SALBE:4500238120/4500243460
2.3 Quality Personnel
assigned as per Sch. Q
1.6% Shortage of MCCL QC Personnel & Rotating QC Inspector
for Contractor.
2.2 Drawings & Technical
Documents Controlled
0.7% LBE:4500243751
2.6 Material Receiving
Inspection
0.7% LBE:4500244835
2.1 Skipping of ITP Activity 0.7% LBE:4500242003
6
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
RCA for SANCR 500017033
Description: Preservation failure of storage and handling Material
Main Contractor ENPPI and Sub-Contractors Petrojet failure to maintain proper material preservation at Brown Field and
Green Field Laydown Area of STG Project at SHEDGUM Gas Plant.
Root Cause:
Lack of Communication and provision of required resources, in addition to supervision discrepancies in maintaining the
material with proper demarcation and implementing the requirements of preservation procedures.
Root Cause Analysis:
Meeting arranged with all parties including Project Management, Warehouse, Sub-Contractors and Site Quality Team in order
to discuss the preservation issue:
 Lack of provision of required resources (Space constraint, designated manpower, Protective materials) to ensure that
warehouse can be properly laid out to accommodate all the material as per the requirements of preservation procedures.
Sufficient manpower is not provided to comply with the preservation requirements even after providing required awareness
regarding handling storage and preservation. The issues highlighted through weekly preservation walkthrough were also not
getting proper attention due to lack of resources in addition to the improper maintaining of material with suitable
demarcation (Under inspection, released for construction, quarantined material and storage as per discipline) resulted
misuse of storage area. Additional area provided for storage was also not utilized properly by providing designated areas.
 Shortage of Contractors QC personnel specially the piping QC Inspector resulted lack of attention for Receiving Inspection
of valves and preservation at Contractors location in addition to Sub-Contractor negligence of the preservation procedures
requirements and failed in maintaining piping and tested Valves preservation.
 So, additional precautions became evident to ensure proper implantation of handling and preservation requirements and to
ensure compliance to COMPANY requirements, necessary actions were concluded as follows:
- Investigation and unveiling of root causes.
- Evaluating the current condition and identifying the gaps.
- Assignment of adequate resources, including personnel and protective materials
- Assignment of responsibility regarding proper implementation of preservation and handling requirements
7
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Correction Plan
Sr. No Action Item Responsibility Actions taken
Target
Date
Remarks
1
Meeting arranged with all parties including Project
Management, Warehouse, Sub-Contractors and Site Quality
Team in order to discuss the preservation issue QA
Meeting was conducted to
identify the root cause and
agreed actions for moving
forward. Completed
2
Conducted preservation walkthrough participated by
COMPANY, QC, warehouse in charge and construction
personnel to identify issues and take suggestions and to list
items.
QC/Shahid
Butt
Conducted on 29th Sept.
21 and comments shared
with Client. Completed
3
A repeated walkthrough was conducted headed by QC
Manager on 5th of October 2021 joined by Warehouse and
Construction personnel to attend the issues identified. QC/Shahid
Butt
Issues identified are being
attended Ongoing
To be reviewed on regular
basis
4
Inspection status was updated for all major items and for
better traceability, inclusion of items descriptions on the
Inspection status board.
-
QC/Shahid
Butt
Action Completed and
concurred by Client Completed
To be maintained for all
new Material
5
Tested valves that are not preserved properly to be
identified for re-testing.
PTJ/ENPPI QCS
List of Valves with poor
preservation is shared with
PTJ. Ongoing
To be reviewed on regular
basis during walkthrough.
6
Area for Demolished material will be identified and kept
separately out side warehouse.
Warehouse I/C
All the Material removed
form warehouse Ongoing
To be maintained and
monitored as an ongoing
action.
7
All pipes and fitting with dirt inside to be cleaned by air
and end protection shall be provided and stored as per
preservation requirement.
Warehouse I/C Attended Ongoing
To be maintained and
monitored as an ongoing
action.
8
Housekeeping and removing the unwanted material
dumped in warehouse . The material shall be moved to the
designated areas.
Warehouse I/C
Completed for major part
of the warehouse. Ongoing
To be reviewed on regular
basis
9
Items requiring proper cover at open storage Area shall be
covered by requirement.
Warehouse I/C
Completed for major part
of the warehouse. Ongoing
To be reviewed on regular
basis
10
Material stored in new yard shall be segregated, with
proper sign boards and the layout shall be provided
including Area for quarantine material.
Warehouse I/C
To be maintained and
monitored as an ongoing
action. Ongoing
This activity to be
maintained throughout
the project phase
8
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Corrective Action
Preservation walkthrough will be performed by preservation committee on
every Wednesday. COMPANY will be invited to participate in the
walkthrough.
Communication group (Construction/QC teams) was created to follow-up
the preservation works on spot and on daily basis through dedicated QC
Supervisors/inspectors per each discipline. All the issues identified shall be
rectified on the spot by the committee with the support of warehouse in
charge and their warehouse team
The issues requiring longer lead time for action are to be recorded and to be
closed within next walkthrough. All such items are to be communicated
within through committee communication group and implementation shall be
carried out under direct monitoring of CM/PM upon closure.
After the walkthrough the outcome to be discussed with SAPID Supervisor
explaining resolution action plan.
The open items not closed on time as agreed to be brought to the Notice of
Project Manager.
9
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Corrective Action
New warehouse area shall be laid out properly to ensure proper
demarcation and the layout shall be created.
Team leader from construction is assigned to liaise with warehouse for
immediate actions on deviations and obtain concurrence from QC for action
taken.
Additional piping QC will be assigned to provide focused attention on Material
receiving inspection and to monitor preservation at warehouse and Sub-
Contractors area so that the issues can be promptly highlighted for the major
items such as piping and valves.
10
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Preventive Action
Awareness training on preservation procedure shall be repeated to all
concerned.
Additional Awareness training shall be conducted for warehouse team
regarding handling and storage as per designated layout for the new arrived
material, identification of inspected and quarantine material and repacking
and preservation maintenance of the remaining material after partial
shipment for installation.
Monitor preservation of major equipment’s, valves and pipes etc. through
weekly preservation RFI’s.
Stock of preservation material to be constantly maintained in order to avoid
lapses in maintenance of preservation.
warehouse in charge in liaison with material Receiving QC shall Monitor and
report preservation status on daily basis.
Close Monitoring from CONTRACTOR and SUBCONTRACTOR QC Teams shall be
exerted to ensure that this violation will not be repeated.
11
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Preservation Walkthrough Committee
Committee
Members
Discipline Contractor/Sub-
Contractor
Whattsapp. No. Remarks
Salah Gaber/
Seoudi
Mohammed
Mechanical ENPPI Preservation of Mechanical equipment's
Saqib Javed Piping/Welding ENPPI Piping, Fittings, Valves- Ware house, PTJ yard & site
Manuroop Instrumentation ENPPI Instrumentation- Warehouse and site
Mujeeb Electrical ENPPI Electrical- warehouse, Site
Juan Civil ENPPI MCCL yard, site
Mohammad
Hamdi
Coating ENPPI PTJ yard, Site
Mohammed Al-
Sultan
RTR/HVAC Warehouse, site
Abdul Aziz Warehouse in
charge
ENPPI Will participate in Walkthrough with yard helpers with all
resources to resolve the issues on the spot in ENPPI Yard
and plant area.
Mohamed Ismail All Disciplines Petrojet
Abd Elaziz Adnan All Disciplines Petrojet Will participate in Walkthrough with yard helpers with all
resources to resolve the issues on the spot in PTJ Yard and
plant area.
Rajendran
Moorthi
Civil MCCL Will participate in Walkthrough with yard helpers with all
resources to resolve the issues on the spot in MCCL Yard
and plant area.
Nidhin Mohan Structural MCCL MCCL yard, site
Said Madhshiru RTR/HVAC MCCL Warehouse, site
12
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Mechanical Work Acceptance
LBE Description SALBE# 4500237550 –Contractor and Sub contractor not reviewed properly the Package as
per hold point of SATIP-A-004 Activity no 1.2
Root Cause Sub-Contractor and Contractor QC neglected to verify the packages prior to Client submission.
Corrective action Provided awareness to the QC on the requirement. Punch items list is introduced in the
packages. This issue will be included as a miner risk in the risk register to avoid recurrence in
future.
LBE Description SALBE # 4500237877- installation and assembly of 2-inch CPVC drinking water line at PCR
East area was crossed to the existing sewer PVC line not complying the 300 mm vertical
distance clearance requirement violating SAES-S-010 and SAES-S-040.
Root Cause Subcontractor executed CPVC 2inch Drinking water line as per Isometric drawings no BB 827954
Rev-0 that was not complying standard requirement.
Corrective action Engineering is in liaison with SAPMT for getting a alternate solution to address the issue, Since
the clashing with existing sewage line. Prior to site activities it is required to review the existing
drawing Contractor Engineering. The line is re-routed as per recommendation.
13
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Mechanical Work Acceptance
LBE Description SALBE# 4500239436 –Contractor and Subcontractor failed to notify the company regarding
absence and failed to maintain required coverage of piping inspector at SITE as per schedule
Q.
Root Cause Shortage of Piping QC with Contractor. During the fit-up Sub-Contractor Piping QC was on work
location. After the fit-up activity released for welding and Piping QC came back to TCF for
documentations.
Corrective action Fit-up RFI# 1401504545 raised in system and accepted prior to release for welding. CV for
additional piping QC submitted for approval.
LBE Description SALBE # 4500240276- Line Number 3”-W-0105-1CGOU and 3”W-0103-ICG0U Attached with
the Equipment Air Receiver R44-D-4436-A and B nozzles are out side the OWS.As per
piping and Instrument drawing BA-826364 line to be in the center of OWS.
Root Cause Mismatch between the actual site condition and the drawings for U/G & A/G piping layout.
Corrective action Redline drawing for A/G line shall be prepared to the actual site condition. For future
construction engineering to validate the drawings for proper matching.
14
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Mechanical Work Acceptance
LBE Description SALBE# 4500243409 –Welding activity with SMAW process low hydrogen electrode E-7018
without recording in welding consumable issuance report SATR-W-2010.
Root Cause Lack of Supervision for procedure Implementation
Corrective action Electrodes shall be registered for maintain the proper record prior issued to welders. Awareness
training is provided.
LBE Description SALBE # 4500244649- Contractors Welding QC was demobilized on the mentioned date
without any email or EPM notification of demobilization or vacation.
Root Cause Contractor misinterpreted the EPM remark made by SAPID hence due to human error notification
was for demobilization was not send assuming that notification is already available.
Corrective action It has been agreed that for any future demobilization advance notification shall be provided
irrespective of previous notifications as per the requirements of Schedule Q. Review QC
Requirement regularly as a part of weekly communication meeting and update client before
making any demobilization
LBE Description SALBE # 4500244662-Contractor Rotating Equipment QC went on an emergency leave.
contractor company did not provide an approved reliever till date
Root Cause As Rotating QC Inspectors mother expired he had to proceed on emergency leave even before
approval or any feedback.
Corrective action Contractor has proposed Fahad Al Helal as alternate QC for covering the role of Rotating QC.
Hence CV is provided for SAP generation for CBT and interview.
15
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
E& I Work Acceptance
LBE Description SALBE # 4500238120- Contractor ENPPI have carried out RGS Conduit installation for
armored instrument cables from instrument to Junction box R44-2000-AJB-0006.SAES-J-902
para 13.1.1.2 states clearly that armored instrumentation cables shall be routed in cable
trays and the cable tray installation shall be as per SAES-J-902 para 9.8.
Root Cause Contractor follow the SAES-J-902, Section 13 Para- 13.1.
Corrective action As per SAES-J-902, Section 13 Para- 13.1 state that, the Above ground Routing Instrumentation
Secondary cables may be run on a conduit or in a cable tray as detailed below.
1- Cable between field instruments and junction box shall be routed above ground utilizing one
of the following options either SAES-J-902, Para-13.1.1.1 Conduit or SAES-J-902, Para-13.1.1.2
Tray. In addition.
2- As per SAES-J-902, Para- 13.1.1.1 Single twisted pair/triad cables (Secondary instrumentation
cables), as per Table 2, shall be installed in steel conduits from the field instruments to the field
junction boxes.
LBE Description SALBE # 4500243460- Two qualified cable splicers started to perform the cable splicing for
PC- R45-1000-PC-0001 without having Job Clearance Card – JCC from Inspection Department
which is required prior to the commencement of work.
Root Cause Lack of communication.
Corrective action The issue has been highlighted to SAPMT to make necessary arrangement to issue the JCC and
agreed the JCC will be issued after complete witness for one splice by POD & ITD as Contractor
performed the mock up on actual job instead of sample.
16
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Lack of QC Manpower
Contactor has reviewed the current manpower situation with MCCL and Contractor will provide QC coverage
for Civil & Structural activities through Contractors QC by retaining QC manpower. This provision is will be
retained as a contingency Plan for inspection coverage.
For MCCL Structural welding QC CV is submitted under Main Contractor for approval. Contractor has reviewed the
existing MCCL QC staff which can cover the inspection activities with the addition of Welding QC.
CV of Rotating QC is submitted for Client for SAP issue so that candidate can complete CBT and for scheduling
interview
CV for additional Piping QC to cover additional activities and backlog of receiving inspection is submitted for
approval. The Piping inspector has the approval of Mechanical Inspector and will support QCS.
17
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Drawings & Technical Documents Controlled
LBE Description SALBE:4500243751- Wrong drawing was used for redlining by E&I. Additionally updated red
line log was not available as per approved format.
Root Cause Due to lack of oversight Construction selected the J Index drawing for redlining. In the absence
of redline log for E&I readily available log shared by Construction with SAPID.
Corrective action For additional supports redline markup which is done in J drawing SAPID requested to reflect it
steel structure M Index drawing, the markup was done and signed from civil engineer and SAPMT.
Log for redline is corrected as per approved format and shared with SAPID. For clamps all the
issues are rectified and SAPID signed the RFI after modified the clamp resting and overlapping.
Drawing redlining shall be performed by site team in consultation with Engineering to avoid
lapses. Log shall be maintained to reflect real time changes.
18
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Material Receiving Inspection
LBE Description SALBE:4500244835- Low Voltage Motors, 250HP at ACC Area, it was observed the following
comments: 1- Ten (10) low voltage motors were already installed without offering material
receiving inspection.
2- There is no electrical IFC Drawings for motors installation. 3- For similar motors, INCR
#6600019725 was issued on 25-Sep-21 for having incorrect service factor on the LV motor
name plate. 4- Space heater has not been energized for 19 motors while the humidity goes
above 60% as per Manufacturer Recommendation.
Root Cause Because of the service factor not matching with the 17-SAMSS-503 and data sheet contractor QC
issued INCR no: #6600019725 and awaiting vendor reply, and hold the material receiving activity.
But sub-Contractor failed to follow the company standards and installed the motors.
Corrective action Contractor awaiting vendor reply for the mismatch in service factor and then contractor will
offer the material receiving inspection. 2. Space heater is required only if the humidity exceeds
60% as per the vendor confirmation. Contractor regularly monitoring humidity and maintaining
record.
Vendor to follow the company standards and 17-SAMSS-503 for the LV motors. 2.Subcontarctor is
advised for the Energization of space heaters prior to install the motors to avoid the recurrence
of violations
19
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Skipping of ITP activity
LBE Description SALBE # 4500242003- Contractor started the cable puling of DC Power Cable Conductor 120
mm2 from circuit breaker no. R44-P1-CB(A)-004 to battery bank no. R44-P1-SB-003 without
offering the inspection of material receiving for DC cable conductor which is required as per
SATIP-P-103-02.
Root Cause Supplier failed to follow the Standard requirements during manufacturing.
Corrective action Supplier has been notified for making the proper correction at their end and provide actions for
correcting the issue at site. Also the supplier is advised to follow the Standard requirements in
the future designs by identifying the risk in their QMS.
20
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use
Corrective actions- Summary
0
Actions Taken to
improve
Construction PQI
Preservation walkthrough committee formed to perform weekly
walkthrough, attend issues real time and report pending issues to Project
Manager
MCCL QC manpower issue is addressed by arranging coverage by
Contractors QC to avoid lapses in QC coverage.
Vendors(Siemens, EEIC & Caravan) are Notified to provide advance
notification for site activities to be performed at site through
Construction. Awareness on SATIP activities was provided to Vendor. This
action shall be applied all Vendors planned for site activity.
Ensure only CBT passed CV’s are submitted for future requirements
Warehouse area is extended with proper storage layout.
Additional Piping QC with Mechanical background is submitted for approval
Red line drawing log is updated and being maintained.
21
Saudi Aramco: Company General Use
Saudi Aramco: Company General Use

More Related Content

What's hot

[Partial Preview:] Waste-finding Checklists for Manufacturing Companies
[Partial Preview:] Waste-finding Checklists for Manufacturing Companies[Partial Preview:] Waste-finding Checklists for Manufacturing Companies
[Partial Preview:] Waste-finding Checklists for Manufacturing CompaniesOperational Excellence Consulting
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
Restriction of Hazardous Substances(RoHS) and REACH
Restriction of Hazardous Substances(RoHS) and REACHRestriction of Hazardous Substances(RoHS) and REACH
Restriction of Hazardous Substances(RoHS) and REACHAmit Ghai
 
Solving Manufacturing Problems
Solving Manufacturing ProblemsSolving Manufacturing Problems
Solving Manufacturing ProblemsRonald Shewchuk
 
Kaizen & Small Group Activities
Kaizen & Small Group ActivitiesKaizen & Small Group Activities
Kaizen & Small Group ActivitiesDEEPAK SAHOO
 
Summarized presentation VDA 6.3 2016 (development)
Summarized presentation VDA 6.3 2016 (development)Summarized presentation VDA 6.3 2016 (development)
Summarized presentation VDA 6.3 2016 (development)Kiran Walimbe
 

What's hot (20)

IATF 16949:2016 Clause Modification & Add
IATF 16949:2016 Clause Modification & AddIATF 16949:2016 Clause Modification & Add
IATF 16949:2016 Clause Modification & Add
 
[Partial Preview:] Waste-finding Checklists for Manufacturing Companies
[Partial Preview:] Waste-finding Checklists for Manufacturing Companies[Partial Preview:] Waste-finding Checklists for Manufacturing Companies
[Partial Preview:] Waste-finding Checklists for Manufacturing Companies
 
Internal rejection
Internal rejectionInternal rejection
Internal rejection
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
 
5 s basics
5 s basics5 s basics
5 s basics
 
OFFICE TPM PPT
OFFICE TPM PPTOFFICE TPM PPT
OFFICE TPM PPT
 
Restriction of Hazardous Substances(RoHS) and REACH
Restriction of Hazardous Substances(RoHS) and REACHRestriction of Hazardous Substances(RoHS) and REACH
Restriction of Hazardous Substances(RoHS) and REACH
 
TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)
 
Solving Manufacturing Problems
Solving Manufacturing ProblemsSolving Manufacturing Problems
Solving Manufacturing Problems
 
VDA 6.3 - Process Audit Innovator
VDA 6.3 - Process Audit InnovatorVDA 6.3 - Process Audit Innovator
VDA 6.3 - Process Audit Innovator
 
5 s & Safety
5 s & Safety5 s & Safety
5 s & Safety
 
Error Proofing.ppt
Error Proofing.pptError Proofing.ppt
Error Proofing.ppt
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 
5 s TQM
5 s   TQM5 s   TQM
5 s TQM
 
Kaizen & Small Group Activities
Kaizen & Small Group ActivitiesKaizen & Small Group Activities
Kaizen & Small Group Activities
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
 
DFMA
DFMADFMA
DFMA
 
Summarized presentation VDA 6.3 2016 (development)
Summarized presentation VDA 6.3 2016 (development)Summarized presentation VDA 6.3 2016 (development)
Summarized presentation VDA 6.3 2016 (development)
 
SMED overview
SMED overviewSMED overview
SMED overview
 
Solar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'tsSolar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'ts
 

Similar to PQI Trend Analysis Sept 2021-Mar 2022

Precast Plant Quality System Documentation Set
Precast Plant Quality System Documentation SetPrecast Plant Quality System Documentation Set
Precast Plant Quality System Documentation Setsjlines
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015Arun Jothilingam
 
Pg og sms 018 procedimento de integridade mecânica eng
Pg og sms 018   procedimento de integridade mecânica engPg og sms 018   procedimento de integridade mecânica eng
Pg og sms 018 procedimento de integridade mecânica engFernanda Lopes
 
Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample MemoChad Colton
 
Pharmaceutical plant layout
Pharmaceutical plant layoutPharmaceutical plant layout
Pharmaceutical plant layoutArchana Chavhan
 
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...Shashi Kumar
 
Ajai K. Asthana CV
Ajai K. Asthana CVAjai K. Asthana CV
Ajai K. Asthana CVAjay Asthana
 
Luxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectLuxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectStevelind
 
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...sailorizzhere
 
2015 Resume Cary B. Dela Cruz.pdf
2015 Resume Cary B. Dela Cruz.pdf2015 Resume Cary B. Dela Cruz.pdf
2015 Resume Cary B. Dela Cruz.pdfCary Dela Cruz
 
Safety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.pptSafety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.pptBimal Chandra Das
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validationAJAYKUMAR4872
 
Substantive Procedures - AUDITING STUDY NOTES
Substantive Procedures - AUDITING STUDY NOTES Substantive Procedures - AUDITING STUDY NOTES
Substantive Procedures - AUDITING STUDY NOTES MUHAMMAD HUZAIFA CHAUDHARY
 

Similar to PQI Trend Analysis Sept 2021-Mar 2022 (20)

Hesham_cv
Hesham_cvHesham_cv
Hesham_cv
 
Precast Plant Quality System Documentation Set
Precast Plant Quality System Documentation SetPrecast Plant Quality System Documentation Set
Precast Plant Quality System Documentation Set
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
EL-SAYES_CV
EL-SAYES_CV EL-SAYES_CV
EL-SAYES_CV
 
CV A H K Niazi
CV A H K  NiaziCV A H K  Niazi
CV A H K Niazi
 
Audit exercise no. 1
Audit exercise no. 1Audit exercise no. 1
Audit exercise no. 1
 
Pg og sms 018 procedimento de integridade mecânica eng
Pg og sms 018   procedimento de integridade mecânica engPg og sms 018   procedimento de integridade mecânica eng
Pg og sms 018 procedimento de integridade mecânica eng
 
Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample Memo
 
Pharmaceutical plant layout
Pharmaceutical plant layoutPharmaceutical plant layout
Pharmaceutical plant layout
 
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...
Outcomes of FDA Audit. Brief about how FDA audit was conducted and the observ...
 
Ajai K. Asthana CV
Ajai K. Asthana CVAjai K. Asthana CV
Ajai K. Asthana CV
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Luxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectLuxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area Project
 
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
CE oral Q&A .pdf which give oral preparation QA for MCA chief engineer oral e...
 
CV
CVCV
CV
 
CV TemplateREV [1]
CV TemplateREV [1]CV TemplateREV [1]
CV TemplateREV [1]
 
2015 Resume Cary B. Dela Cruz.pdf
2015 Resume Cary B. Dela Cruz.pdf2015 Resume Cary B. Dela Cruz.pdf
2015 Resume Cary B. Dela Cruz.pdf
 
Safety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.pptSafety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.ppt
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
 
Substantive Procedures - AUDITING STUDY NOTES
Substantive Procedures - AUDITING STUDY NOTES Substantive Procedures - AUDITING STUDY NOTES
Substantive Procedures - AUDITING STUDY NOTES
 

Recently uploaded

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

PQI Trend Analysis Sept 2021-Mar 2022

  • 3. 86.7 90.1 90.1 84 85 86 87 88 89 90 91 Jan.22 Feb.22 Cumulative PQI % Month Monthly PQI Trend PQI Linear (PQI)
  • 4. 4 Saudi Aramco: Company General Use Saudi Aramco: Company General Use PQI IMPACT 3 Drawing & technical douments Controlled QC personnel assigned as per Sch Q Handling storage & preservatio n E & I work acceptance Mechanical Work Acceptance Skipping of ITP activity Document Rejections Civil Work Acceptance Jun.21 0.6 2.2 2.6 0.2 1 2.3 0.6 0.2 Jul.21 1.9 0 1.9 0.5 0.9 0.6 1.1 1 Aug. 21 1.9 0 1.9 0.5 1.2 0.6 1.2 1 Sept.21 4.6 2.5 2.3 2 1.7 1.3 0 0 Oct.21 0.7 1.6 4.2 1.7 2.9 0.7 0.7 1.6 4.2 1.7 2.9 0.7 4.6 2.5 2.3 2 1.7 1.3 0 0 1.9 0 1.9 0.5 1.2 0.6 1.2 1 1.9 0 1.9 0.5 0.9 0.6 1.1 1 0.6 2.2 2.6 0.2 1 2.3 0.6 0.2 0 2 4 6 8 10 12 14 Rejection % PQI Element PQI Impact Month wise
  • 5. 5 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Quality Statistics PQI Analysis For October 2021 PQI Item Description Impact % Remarks 2.7 Handling, Storage & preservation 4.2% SANCR # 500017033, INCR:6600019725. 3.3 Mechanical Work acceptance 2.9% SALBE:4500237550/4500237877/4500239436/450024027 6/4500243409/4500244649/4500244662 3.5 E & I Work Acceptance 1.7% SALBE:4500238120/4500243460 2.3 Quality Personnel assigned as per Sch. Q 1.6% Shortage of MCCL QC Personnel & Rotating QC Inspector for Contractor. 2.2 Drawings & Technical Documents Controlled 0.7% LBE:4500243751 2.6 Material Receiving Inspection 0.7% LBE:4500244835 2.1 Skipping of ITP Activity 0.7% LBE:4500242003
  • 6. 6 Saudi Aramco: Company General Use Saudi Aramco: Company General Use RCA for SANCR 500017033 Description: Preservation failure of storage and handling Material Main Contractor ENPPI and Sub-Contractors Petrojet failure to maintain proper material preservation at Brown Field and Green Field Laydown Area of STG Project at SHEDGUM Gas Plant. Root Cause: Lack of Communication and provision of required resources, in addition to supervision discrepancies in maintaining the material with proper demarcation and implementing the requirements of preservation procedures. Root Cause Analysis: Meeting arranged with all parties including Project Management, Warehouse, Sub-Contractors and Site Quality Team in order to discuss the preservation issue:  Lack of provision of required resources (Space constraint, designated manpower, Protective materials) to ensure that warehouse can be properly laid out to accommodate all the material as per the requirements of preservation procedures. Sufficient manpower is not provided to comply with the preservation requirements even after providing required awareness regarding handling storage and preservation. The issues highlighted through weekly preservation walkthrough were also not getting proper attention due to lack of resources in addition to the improper maintaining of material with suitable demarcation (Under inspection, released for construction, quarantined material and storage as per discipline) resulted misuse of storage area. Additional area provided for storage was also not utilized properly by providing designated areas.  Shortage of Contractors QC personnel specially the piping QC Inspector resulted lack of attention for Receiving Inspection of valves and preservation at Contractors location in addition to Sub-Contractor negligence of the preservation procedures requirements and failed in maintaining piping and tested Valves preservation.  So, additional precautions became evident to ensure proper implantation of handling and preservation requirements and to ensure compliance to COMPANY requirements, necessary actions were concluded as follows: - Investigation and unveiling of root causes. - Evaluating the current condition and identifying the gaps. - Assignment of adequate resources, including personnel and protective materials - Assignment of responsibility regarding proper implementation of preservation and handling requirements
  • 7. 7 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Correction Plan Sr. No Action Item Responsibility Actions taken Target Date Remarks 1 Meeting arranged with all parties including Project Management, Warehouse, Sub-Contractors and Site Quality Team in order to discuss the preservation issue QA Meeting was conducted to identify the root cause and agreed actions for moving forward. Completed 2 Conducted preservation walkthrough participated by COMPANY, QC, warehouse in charge and construction personnel to identify issues and take suggestions and to list items. QC/Shahid Butt Conducted on 29th Sept. 21 and comments shared with Client. Completed 3 A repeated walkthrough was conducted headed by QC Manager on 5th of October 2021 joined by Warehouse and Construction personnel to attend the issues identified. QC/Shahid Butt Issues identified are being attended Ongoing To be reviewed on regular basis 4 Inspection status was updated for all major items and for better traceability, inclusion of items descriptions on the Inspection status board. - QC/Shahid Butt Action Completed and concurred by Client Completed To be maintained for all new Material 5 Tested valves that are not preserved properly to be identified for re-testing. PTJ/ENPPI QCS List of Valves with poor preservation is shared with PTJ. Ongoing To be reviewed on regular basis during walkthrough. 6 Area for Demolished material will be identified and kept separately out side warehouse. Warehouse I/C All the Material removed form warehouse Ongoing To be maintained and monitored as an ongoing action. 7 All pipes and fitting with dirt inside to be cleaned by air and end protection shall be provided and stored as per preservation requirement. Warehouse I/C Attended Ongoing To be maintained and monitored as an ongoing action. 8 Housekeeping and removing the unwanted material dumped in warehouse . The material shall be moved to the designated areas. Warehouse I/C Completed for major part of the warehouse. Ongoing To be reviewed on regular basis 9 Items requiring proper cover at open storage Area shall be covered by requirement. Warehouse I/C Completed for major part of the warehouse. Ongoing To be reviewed on regular basis 10 Material stored in new yard shall be segregated, with proper sign boards and the layout shall be provided including Area for quarantine material. Warehouse I/C To be maintained and monitored as an ongoing action. Ongoing This activity to be maintained throughout the project phase
  • 8. 8 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Corrective Action Preservation walkthrough will be performed by preservation committee on every Wednesday. COMPANY will be invited to participate in the walkthrough. Communication group (Construction/QC teams) was created to follow-up the preservation works on spot and on daily basis through dedicated QC Supervisors/inspectors per each discipline. All the issues identified shall be rectified on the spot by the committee with the support of warehouse in charge and their warehouse team The issues requiring longer lead time for action are to be recorded and to be closed within next walkthrough. All such items are to be communicated within through committee communication group and implementation shall be carried out under direct monitoring of CM/PM upon closure. After the walkthrough the outcome to be discussed with SAPID Supervisor explaining resolution action plan. The open items not closed on time as agreed to be brought to the Notice of Project Manager.
  • 9. 9 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Corrective Action New warehouse area shall be laid out properly to ensure proper demarcation and the layout shall be created. Team leader from construction is assigned to liaise with warehouse for immediate actions on deviations and obtain concurrence from QC for action taken. Additional piping QC will be assigned to provide focused attention on Material receiving inspection and to monitor preservation at warehouse and Sub- Contractors area so that the issues can be promptly highlighted for the major items such as piping and valves.
  • 10. 10 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Preventive Action Awareness training on preservation procedure shall be repeated to all concerned. Additional Awareness training shall be conducted for warehouse team regarding handling and storage as per designated layout for the new arrived material, identification of inspected and quarantine material and repacking and preservation maintenance of the remaining material after partial shipment for installation. Monitor preservation of major equipment’s, valves and pipes etc. through weekly preservation RFI’s. Stock of preservation material to be constantly maintained in order to avoid lapses in maintenance of preservation. warehouse in charge in liaison with material Receiving QC shall Monitor and report preservation status on daily basis. Close Monitoring from CONTRACTOR and SUBCONTRACTOR QC Teams shall be exerted to ensure that this violation will not be repeated.
  • 11. 11 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Preservation Walkthrough Committee Committee Members Discipline Contractor/Sub- Contractor Whattsapp. No. Remarks Salah Gaber/ Seoudi Mohammed Mechanical ENPPI Preservation of Mechanical equipment's Saqib Javed Piping/Welding ENPPI Piping, Fittings, Valves- Ware house, PTJ yard & site Manuroop Instrumentation ENPPI Instrumentation- Warehouse and site Mujeeb Electrical ENPPI Electrical- warehouse, Site Juan Civil ENPPI MCCL yard, site Mohammad Hamdi Coating ENPPI PTJ yard, Site Mohammed Al- Sultan RTR/HVAC Warehouse, site Abdul Aziz Warehouse in charge ENPPI Will participate in Walkthrough with yard helpers with all resources to resolve the issues on the spot in ENPPI Yard and plant area. Mohamed Ismail All Disciplines Petrojet Abd Elaziz Adnan All Disciplines Petrojet Will participate in Walkthrough with yard helpers with all resources to resolve the issues on the spot in PTJ Yard and plant area. Rajendran Moorthi Civil MCCL Will participate in Walkthrough with yard helpers with all resources to resolve the issues on the spot in MCCL Yard and plant area. Nidhin Mohan Structural MCCL MCCL yard, site Said Madhshiru RTR/HVAC MCCL Warehouse, site
  • 12. 12 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Mechanical Work Acceptance LBE Description SALBE# 4500237550 –Contractor and Sub contractor not reviewed properly the Package as per hold point of SATIP-A-004 Activity no 1.2 Root Cause Sub-Contractor and Contractor QC neglected to verify the packages prior to Client submission. Corrective action Provided awareness to the QC on the requirement. Punch items list is introduced in the packages. This issue will be included as a miner risk in the risk register to avoid recurrence in future. LBE Description SALBE # 4500237877- installation and assembly of 2-inch CPVC drinking water line at PCR East area was crossed to the existing sewer PVC line not complying the 300 mm vertical distance clearance requirement violating SAES-S-010 and SAES-S-040. Root Cause Subcontractor executed CPVC 2inch Drinking water line as per Isometric drawings no BB 827954 Rev-0 that was not complying standard requirement. Corrective action Engineering is in liaison with SAPMT for getting a alternate solution to address the issue, Since the clashing with existing sewage line. Prior to site activities it is required to review the existing drawing Contractor Engineering. The line is re-routed as per recommendation.
  • 13. 13 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Mechanical Work Acceptance LBE Description SALBE# 4500239436 –Contractor and Subcontractor failed to notify the company regarding absence and failed to maintain required coverage of piping inspector at SITE as per schedule Q. Root Cause Shortage of Piping QC with Contractor. During the fit-up Sub-Contractor Piping QC was on work location. After the fit-up activity released for welding and Piping QC came back to TCF for documentations. Corrective action Fit-up RFI# 1401504545 raised in system and accepted prior to release for welding. CV for additional piping QC submitted for approval. LBE Description SALBE # 4500240276- Line Number 3”-W-0105-1CGOU and 3”W-0103-ICG0U Attached with the Equipment Air Receiver R44-D-4436-A and B nozzles are out side the OWS.As per piping and Instrument drawing BA-826364 line to be in the center of OWS. Root Cause Mismatch between the actual site condition and the drawings for U/G & A/G piping layout. Corrective action Redline drawing for A/G line shall be prepared to the actual site condition. For future construction engineering to validate the drawings for proper matching.
  • 14. 14 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Mechanical Work Acceptance LBE Description SALBE# 4500243409 –Welding activity with SMAW process low hydrogen electrode E-7018 without recording in welding consumable issuance report SATR-W-2010. Root Cause Lack of Supervision for procedure Implementation Corrective action Electrodes shall be registered for maintain the proper record prior issued to welders. Awareness training is provided. LBE Description SALBE # 4500244649- Contractors Welding QC was demobilized on the mentioned date without any email or EPM notification of demobilization or vacation. Root Cause Contractor misinterpreted the EPM remark made by SAPID hence due to human error notification was for demobilization was not send assuming that notification is already available. Corrective action It has been agreed that for any future demobilization advance notification shall be provided irrespective of previous notifications as per the requirements of Schedule Q. Review QC Requirement regularly as a part of weekly communication meeting and update client before making any demobilization LBE Description SALBE # 4500244662-Contractor Rotating Equipment QC went on an emergency leave. contractor company did not provide an approved reliever till date Root Cause As Rotating QC Inspectors mother expired he had to proceed on emergency leave even before approval or any feedback. Corrective action Contractor has proposed Fahad Al Helal as alternate QC for covering the role of Rotating QC. Hence CV is provided for SAP generation for CBT and interview.
  • 15. 15 Saudi Aramco: Company General Use Saudi Aramco: Company General Use E& I Work Acceptance LBE Description SALBE # 4500238120- Contractor ENPPI have carried out RGS Conduit installation for armored instrument cables from instrument to Junction box R44-2000-AJB-0006.SAES-J-902 para 13.1.1.2 states clearly that armored instrumentation cables shall be routed in cable trays and the cable tray installation shall be as per SAES-J-902 para 9.8. Root Cause Contractor follow the SAES-J-902, Section 13 Para- 13.1. Corrective action As per SAES-J-902, Section 13 Para- 13.1 state that, the Above ground Routing Instrumentation Secondary cables may be run on a conduit or in a cable tray as detailed below. 1- Cable between field instruments and junction box shall be routed above ground utilizing one of the following options either SAES-J-902, Para-13.1.1.1 Conduit or SAES-J-902, Para-13.1.1.2 Tray. In addition. 2- As per SAES-J-902, Para- 13.1.1.1 Single twisted pair/triad cables (Secondary instrumentation cables), as per Table 2, shall be installed in steel conduits from the field instruments to the field junction boxes. LBE Description SALBE # 4500243460- Two qualified cable splicers started to perform the cable splicing for PC- R45-1000-PC-0001 without having Job Clearance Card – JCC from Inspection Department which is required prior to the commencement of work. Root Cause Lack of communication. Corrective action The issue has been highlighted to SAPMT to make necessary arrangement to issue the JCC and agreed the JCC will be issued after complete witness for one splice by POD & ITD as Contractor performed the mock up on actual job instead of sample.
  • 16. 16 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Lack of QC Manpower Contactor has reviewed the current manpower situation with MCCL and Contractor will provide QC coverage for Civil & Structural activities through Contractors QC by retaining QC manpower. This provision is will be retained as a contingency Plan for inspection coverage. For MCCL Structural welding QC CV is submitted under Main Contractor for approval. Contractor has reviewed the existing MCCL QC staff which can cover the inspection activities with the addition of Welding QC. CV of Rotating QC is submitted for Client for SAP issue so that candidate can complete CBT and for scheduling interview CV for additional Piping QC to cover additional activities and backlog of receiving inspection is submitted for approval. The Piping inspector has the approval of Mechanical Inspector and will support QCS.
  • 17. 17 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Drawings & Technical Documents Controlled LBE Description SALBE:4500243751- Wrong drawing was used for redlining by E&I. Additionally updated red line log was not available as per approved format. Root Cause Due to lack of oversight Construction selected the J Index drawing for redlining. In the absence of redline log for E&I readily available log shared by Construction with SAPID. Corrective action For additional supports redline markup which is done in J drawing SAPID requested to reflect it steel structure M Index drawing, the markup was done and signed from civil engineer and SAPMT. Log for redline is corrected as per approved format and shared with SAPID. For clamps all the issues are rectified and SAPID signed the RFI after modified the clamp resting and overlapping. Drawing redlining shall be performed by site team in consultation with Engineering to avoid lapses. Log shall be maintained to reflect real time changes.
  • 18. 18 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Material Receiving Inspection LBE Description SALBE:4500244835- Low Voltage Motors, 250HP at ACC Area, it was observed the following comments: 1- Ten (10) low voltage motors were already installed without offering material receiving inspection. 2- There is no electrical IFC Drawings for motors installation. 3- For similar motors, INCR #6600019725 was issued on 25-Sep-21 for having incorrect service factor on the LV motor name plate. 4- Space heater has not been energized for 19 motors while the humidity goes above 60% as per Manufacturer Recommendation. Root Cause Because of the service factor not matching with the 17-SAMSS-503 and data sheet contractor QC issued INCR no: #6600019725 and awaiting vendor reply, and hold the material receiving activity. But sub-Contractor failed to follow the company standards and installed the motors. Corrective action Contractor awaiting vendor reply for the mismatch in service factor and then contractor will offer the material receiving inspection. 2. Space heater is required only if the humidity exceeds 60% as per the vendor confirmation. Contractor regularly monitoring humidity and maintaining record. Vendor to follow the company standards and 17-SAMSS-503 for the LV motors. 2.Subcontarctor is advised for the Energization of space heaters prior to install the motors to avoid the recurrence of violations
  • 19. 19 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Skipping of ITP activity LBE Description SALBE # 4500242003- Contractor started the cable puling of DC Power Cable Conductor 120 mm2 from circuit breaker no. R44-P1-CB(A)-004 to battery bank no. R44-P1-SB-003 without offering the inspection of material receiving for DC cable conductor which is required as per SATIP-P-103-02. Root Cause Supplier failed to follow the Standard requirements during manufacturing. Corrective action Supplier has been notified for making the proper correction at their end and provide actions for correcting the issue at site. Also the supplier is advised to follow the Standard requirements in the future designs by identifying the risk in their QMS.
  • 20. 20 Saudi Aramco: Company General Use Saudi Aramco: Company General Use Corrective actions- Summary 0 Actions Taken to improve Construction PQI Preservation walkthrough committee formed to perform weekly walkthrough, attend issues real time and report pending issues to Project Manager MCCL QC manpower issue is addressed by arranging coverage by Contractors QC to avoid lapses in QC coverage. Vendors(Siemens, EEIC & Caravan) are Notified to provide advance notification for site activities to be performed at site through Construction. Awareness on SATIP activities was provided to Vendor. This action shall be applied all Vendors planned for site activity. Ensure only CBT passed CV’s are submitted for future requirements Warehouse area is extended with proper storage layout. Additional Piping QC with Mechanical background is submitted for approval Red line drawing log is updated and being maintained.
  • 21. 21 Saudi Aramco: Company General Use Saudi Aramco: Company General Use

Editor's Notes

  1. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  2. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  3. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  4. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  5. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  6. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  7. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  8. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  9. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  10. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  11. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  12. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  13. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  14. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  15. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  16. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  17. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.
  18. 2. Quality Notifications For the program level Quality notifications, there are a total of 82 Non Conformance reports, 6 worksheets, and 20 EDRs that were issued since the beginning of the project. Meanwhile, we have only 1 open NCR which are under resolutions with no major impact on the construction activities. In terms of the 20 EDRs that were issued, there are only 2 EDRs are still open under improvement by the respective Saudi Aramco inspection offices with manufacturers to bridge any gaps for future purchase orders. None of them is considered major.   This concludes the quality brief of FGP.