Preface
• This is a PowerPoint file I created in order to
  help me in my studies.

• The material in these slides are a distilled
  version of the literature from 2 books
1. Total Quality Management – 3rd Edition –
   Besterfield, Michna, Besterfield, Sacre.
2. Total Quality Management – Bharat Wakhlu
12/11/2012            Sourabh Jain              2
HOME
             Introduction                    Leadership


              Customer                         Employee
             Satisfaction                    Involvement

        Continuous Process                   Performance
          Improvement                         Measures


                QMS                             SPC



12/11/2012                    Sourabh Jain                 3
Introduction




12/11/2012       Sourabh Jain   4
Quality
• Degree to which a set of                inherent
  characteristics fulfils requirements.

• Q=Performance/Expectations

• TQM; T = Total i.e. company-wide, suppliers,
  customers; M = Management i.e. art of
  directing and controlling
12/11/2012            Sourabh Jain               5
Quality q and Total Quality Q
• Product orientation
• Ensure produced goods are fit for sale
• No prevention, No learning




12/11/2012               Sourabh Jain        6
Quality q and Total Quality Q
• Customer/Process/Product orientation
• Listen to customer, product design, process
  optimized
• Right the first time, every time; Learning; importance
  of internal customers




12/11/2012               Sourabh Jain                  7
Dimensions of Quality
Dimension                    Meaning

Performance                  Primary product characteristics

Features                     Added features

Conformance                  Meeting standards

Reliability                  Consistency of performance

Durability                   Useful life

Service                      Resolution of complaints

Response                     Human to human interface

Aesthetics                   Sensory characteristics

Reputation                   Past performance
12/11/2012            Sourabh Jain                             8
Total Quality
1. Performance Superiority

2. Delight customers

3. Provide value (value=quality/cost)

4. Doing the right things

5. Right the first time

12/11/2012                Sourabh Jain   9
Definition of TQM
• TQM is the art of managing the whole to achieve
  excellence.

• TQM is a philosophy and a set of guiding
  principles that represent the foundation of a
  continually improving firm.

• It is the application of quantitative methods and
  HR to improve all processes within a firm and
  exceed customer needs now and in the future.

12/11/2012             Sourabh Jain               10
6 basic concepts of TQM
1.    Committed and involved management to provide long term- top
      to bottom – organizational support

2.    Unwavering focus on the customer – internal and external

3.    Effective involvement and utilization of entire workforce

4.    Continuous improvement of business and production process

5.    Treat suppliers as partners

6.    Establish performance measures for processes

12/11/2012                          Sourabh Jain                  11
Culture changes for TQM
Quality element    OLD CULTURE                  TQM CULTURE

Definition         Product oriented             Customer oriented

Priorities         Second to service and cost   Equal to service and cost

Decisions          Short term                   Long term

Emphasis           Detection                    Prevention

Errors             Operations                   System

Responsibility     Quality Control              Everyone

Problem Solving    Managers                     Teams

Procurement        Price                        Life cycle costs, Partnership

Manager’s Role     Plan, assign, control,       Delegate, coach, facilitate,
                   enforce                      mentor
12/11/2012                   Sourabh Jain                                   12
Model for TQM

                 Product,
                             Systems
  Outstanding    Services                       People
                               and
  Leadership       and                          power
                            Procedures
                 Process
                                                            MEETING/
                                                           EXCEEDING
                                                           CUSTOMER
                                                          EXPECTATIONS

                      CONTINUOUS               CUSTOMER
  BENCHMARKING         SYSTEMATIC                FOCUS
                     IMPROVEMENT



12/11/2012                      Sourabh Jain                        13
Paradigms of TQM
• Belief that people are a potential source of
  ‘beneficial forces’ will lead to total quality

• Functional and Hierarchical divisions of a firm
  contribute to parochial thinking – not good

• Everyone has to participate in obtaining total
  quality
12/11/2012             Sourabh Jain                 14
Gurus of TQM
• Shewhart
1. Economic Control of Quality of Mfg product
2. Control Chart Theory
3. Assignable and chance causes of variation
4. Rational Subgroups
5. PDSA cycle



12/11/2012          Sourabh Jain                15
Gurus of TQM
• Deming
1. Out of the Crisis
2. Quality, Productivity and Competitive
   Position
3. 14 points to improve q,p,c
4. Taught SPC and quality to Japanese



12/11/2012        Sourabh Jain         16
Gurus of TQM
• Juran
1. Juran’s Quality control Handbook
2. Project Improvements based on ROI
3. Promoted commitment to quality at all levels
4. Juran Trilogy – Planning, Control,
   Improvement



12/11/2012           Sourabh Jain             17
Gurus of TQM
• Feigenbaum
1. Total Quality Control
2. Customer Satisfaction
3. Genuine Management Involvement
4. Employee Involvement
5. Company wide total quality control
6. First line supervision leadership

12/11/2012           Sourabh Jain       18
Gurus of TQM
• Ishikawa
1. SPC texts in Japanese and English
2. Adapted TQC i.e. TQM in Japan
3. Fishbone diagram
4. Quality circles




12/11/2012           Sourabh Jain      19
Gurus of TQM
• Crosby
1. Quality is Free
2. Quality without tears
3. Do it right the first time
4. Zero defects




12/11/2012             Sourabh Jain   20
Gurus of TQM
• Taguchi
1. Loss Function
2. Quality Engineering
3. Robust design of parameters/tolerances




12/11/2012          Sourabh Jain            21
Obstacles to TQM
1.    Lack of management commitment
2.    Inability to change organization culture
3.    Improper planning
4.    Lack of continuous training and education
5.    Incompatible Org structure & isolated
      departments and individuals
6.    Ineffective measurement techniques
7.    Paying inadequate attention to customers
8.    Inadequate use of empowerment and teamwork
9.    Failure to continually improve
12/11/2012             Sourabh Jain            22
Benefits of TQM
•   Improve quality
•   Employee participation and satisfaction
•   Teamwork and Working relationships
•   Customer satisfaction
•   Productivity
•   Communication
•   Profitability and Market Share

12/11/2012             Sourabh Jain           23
Leadership




12/11/2012      Sourabh Jain   24
Leader
• A leader
1. Shapes
2. Promotes
3. Protects
4. Exemplifies
• the organization’s values



12/11/2012            Sourabh Jain   25
Manager vs. Leader
Manager       Leadership for quality (Outstanding leadership)

Plan          EXPOSE limited utility of current approaches

Organize      ENVISION the future

Staff         ENLIST others in the quest

Lead          EMPOWER them to act

Control       ENCOURAGE right effort

Feedback      EXEMPLIFY by personal action

12/11/2012                    Sourabh Jain                      26
Leadership Style


 Leads to time bomb
 situations                                  Best style

             FEARFUL                          WHOLESOME
                            RIGID STYLE
              STYLE                             STYLE




12/11/2012                    Sourabh Jain                27
Characteristics of Quality Leaders
1. Priority attention to internal/external customers

2. Empower, rather than control subordinates

3. Emphasize improvement, rather than maintenance

4. Emphasize prevention

5. Encourage collaboration rather than competition

6. Train and coach, rather than direct and supervise

12/11/2012                  Sourabh Jain               28
Characteristics of Quality Leaders
7. Learn from problems

8. Continually try to improve communications

9. Continually demonstrate their commitment to quality

10. Choose suppliers on basis of quality, not price

11. Establish organizational systems to support quality effort

12. Encourage and Recognize team effort

12/11/2012                   Sourabh Jain                        29
7 habits of highly effective people
1.    Be proactive - don’t let fate control you, you control it

2.    Begin with the end in mind – have a vision and plan

3.    Put first things first – learn to prioritize

4.    Think win-win – seek mutual benefits

5.    Seek first to understand, then be understood

6.    Synergy – teams are better than individuals

7.    Sharpen the saw – renew one’s physical, spiritual, mental and
      emotional dimension


12/11/2012                             Sourabh Jain               30
Deming Philosophy
• Create and publish aims/purpose of firm

• Learn the new philosophy

• Understand purpose of inspection

• Stop awarding business on price alone

• Improve constantly and forever the system

• Institute training

• Teach and institute leadership

12/11/2012                    Sourabh Jain    31
Deming Philosophy
• Drive out fear, create trust and a climate for innovation

• Optimize efforts of teams, groups and staff areas

• Eliminate exhortations for the work force

• Eliminate numerical quotas for workforce and MBO

• Remove barriers that rob people of pride of workmanship

• Encourage education and self-empowerment for everyone

• Take action to accomplish the transformation

12/11/2012                     Sourabh Jain                   32
Customer Satisfaction




12/11/2012           Sourabh Jain    33
Customer Satisfaction Model


                                                Company Offer

                                        Satisfier



                       Customer Needs




12/11/2012               Sourabh Jain                           34
Notes
• Customer – Internal and External is the focus.

• Customer Satisfaction is subjective, hence
  hard to measure

• Customer Satisfaction should not be viewed in
  a vacuum


12/11/2012            Sourabh Jain                 35
Customer feedback
1. To discover customer dissatisfaction

2. Discover relative priorities of Quality

3. Compare performance with competition

4. Identify customer’s needs

5. Determine opportunities for improvement

12/11/2012              Sourabh Jain         36
Modes of feedback
1.    Comment card – Service industry

2.    Customer Questionnaire – mail, telephone

3.    Focus groups – like a GD

4.    Toll free telephone numbers – complaints

5.    Customer visits – B2B

6.    Report card – send to customer every quarter

7.    The internet – blogs

8.    Employee feedback – why problem?

9.    Mass customization – variety at affordable cost
12/11/2012                         Sourabh Jain         37
Customer Complaints
                       Complain to   Action
                       Management                      Shout at Front
                           1%                         Line Employees
                                                            19%




                     Do nothing
                        80%




   Every complaint should be accepted, analyzed and acted upon because those
   who don’t complain might have switched loyalty.
12/11/2012                         Sourabh Jain                                38
Handling complaints
• Accept feedback

• Empower front-line employees to resolve

• More inspection does not solve it; find the root cause

• Communicate complaint to everyone in firm

• Contact complainant and put mind at ease

• Be proactive about customer needs

12/11/2012                 Sourabh Jain                    39
Employee Involvement




12/11/2012           Sourabh Jain   40
Motivation
• Maslow’s Hierarchy of needs
• Herzberg’s 2-factor theory

• What employees want
1. Interesting Work
2. Appreciation
3. Involvement
4. Job Security

12/11/2012          Sourabh Jain   41
Achieving a motivated work force
1.    Know thyself

2.    Know your employees

3.    Establish a +ve attitude

4.    Share goals

5.    Monitor progress

6.    Develop interesting work

7.    Communicate effectively

8.    Celebrate success
12/11/2012                       Sourabh Jain   42
Employee Surveys
1.    Quality Council creates Survey team

2.    Develop instrument (questionnaire).Constructs to be used are
      1.     Personality Characteristics
      2.     Management Styles
      3.     Job attitudes
      4.     The work

3.    Administer survey (confidential and by 3rd party)

4.    Compile and analyze (report is circulated in firm)

5.    Determine areas for improvement


12/11/2012                            Sourabh Jain                   43
Suggestion Systems
• Management must make it easy for employees to
  suggest improvements

1. Be progressive – regularly ask employees

2. Remove fear – focus on the process, not the person

3. Simplify the process

4. Respond quickly - accept/Reject/Refer giving time
   or reason

5. Reward the idea
12/11/2012                Sourabh Jain                  44
Performance Appraisal
• Purpose
1. Tells employee how they are performing
2. Basis for promotions and increments
3. Counseling
4. Opportunities

•     Employee involvement is critical and appraisals
      must be continuous.

•     Types – Ranking, Narrative, Forced, Graphic
12/11/2012                Sourabh Jain              45
Problems with appraisal systems
1. Emphasis on short term performance

2. Individual appraisals destroy teamwork

3. A person is only about 15 % responsible for
   his results

4. Based on subjectivity and immeasurables

12/11/2012           Sourabh Jain            46
Improving the appraisal system
1. Use rating scales with fewer rating categories

2. Equal emphasis to individual and group appraisals

3. More frequent performance reviews with focus on
   improvement

4. Promotion decision to be based on current performance
   AND potential for new post

5. External customer satisfaction a part of the process

6. 360 degree appraisals

7. Evaluation for process improvements
12/11/2012                 Sourabh Jain                   47
Benefits of employee involvement
• Employees
1. Make better decisions using expert knowledge of
   process

2. More likely to implement and support decisions they
   had a part in making/better able to accept changes

3. Better able to spot pinpoint areas for improvement

4. Better able to take immediate corrective action

5. EI increases morale, improves industrial relations
   and increases commitment to unit goals
12/11/2012               Sourabh Jain                   48
Continuous Process
               Improvement




12/11/2012          Sourabh Jain   49
Juran Trilogy – Plan, Control, Improve
• Planning
1. Determine external and internal customers

2. Identify their needs and translate into requirements

3. Develop product/service as per needs of not only
   customer but other stakeholders too

4. Develop processes able to produce product/service

5. Transfer plans to operations ensuring process validity
12/11/2012                Sourabh Jain                      50
Juran Trilogy – Plan, Control, Improve
• Control
1. Determine items to be controlled and their units of
   measure

2. Set goals for controls and determine what sensors are
   needed

3. Measure actual performance

4. Compare it with goals

5. Act on the difference

12/11/2012                 Sourabh Jain               51
Juran Trilogy – Plan, Control, Improve
   • Improvement
   • Quality council identifies improvement areas and establishes project
     teams to work on it

                              Quality Control (during operations)
                50
                              Sporadic Waste
                40
                30
                                             Original Zone of Quality Control
 QUALITY        20
                                                                              New Zone of Quality Control
PLANNING        10           Chronic Waste                          Quality
                                                                    Improvement




                                                                                                     FEEDBACK
                 0
                     0   1       2     3         4           5          6       7       8        9              10
                                                    Time
                                           FEEDBACK
   12/11/2012                          Sourabh Jain                                                        52
                                           Cost of poor Quality
PDSA Cycle

                      Plan


             Act                     Do


                      Study

12/11/2012            Sourabh Jain        53
Problem Solving method
                                               1 Identify
                                              Opportunity


                   7 Plan for                                            2 Analyze
                    Future                                                Process




                  6                                                           3 Develop
             Standardize                                                       Optimal
               solution                                                      Solution (s)




                                5 Study the                      4
                                   results                   Implement
12/11/2012                                    Sourabh Jain                                  54
1 Identify Opportunity
• Identify problem – Pareto
  analysis, Survey, Brainstorm, proposals

• Form team – QC forms a multifunction team if
  required

• Define scope – scope, goals, milestones


12/11/2012            Sourabh Jain           55
2 Analyze Process
• Develop Process Flow diagram

• Define target performance measures

• Relevant Data collection

• Fishbone diagram

12/11/2012           Sourabh Jain      56
3 Develop Optimal Solution (s)
• Brainstorm – create new process/combine
  different process/modify existing process

• Evaluate Test solutions using control charts –
  criteria: feasibility, scope, training and effects




12/11/2012              Sourabh Jain                   57
4 Implement
• Prepare implementation plan

• Obtain approval

• Implement process improvements




12/11/2012          Sourabh Jain   58
5 Study the results
• Monitor and evaluate the change

• Check if fine tuning is needed

• If dissatisfied with results, repeat some phases




12/11/2012            Sourabh Jain               59
6 Standardize solution
• Positrol (Positive control) – ensures important
  variables are kept under control

• Process Certification

• Operator Certification



12/11/2012            Sourabh Jain              60
7 Plan for Future
• Regular reviews of progress by QC

• Knowledge Management System – save
  learnings

• Repeat Phase 1.



12/11/2012           Sourabh Jain      61
Kaizen
• Process of continuous improvement in small
  increments without complex technology or high
  costs making processes better

• Uses concepts like: Value/Non value added
  activities, Mudas, Motion studies, SOP, 5S, Visual
  Management, JIT etc

• 5S – Sort, Simplify, Sweep, Standardize, Sustain

12/11/2012              Sourabh Jain                   62
Six Sigma
• Uses Cp analysis as a way to measure progress


• We should reduce the process variability σ to keep process
  centered on the target μ.


• Process Capability Index = USL-LSL/6 σ

• Process Performance Index Cpk
  = min(USL-X,X-LSL)/3 σ

• Default Cp >1, Cpk =1
12/11/2012                 Sourabh Jain                    63
Performance Measures




12/11/2012           Sourabh Jain   64
Strategy
• QC creates a total system of measures using
  info from stakeholders and firms’ VMG and
  values

• Ex: Quality
• % reduction in nonconformities
• % of certified suppliers


12/11/2012           Sourabh Jain               65
Strategy
• Cost
• % increase in inventory turnover
• % increase in output dollars per employee

• Similarly for innovation (NPD time), reliability (% processes
  having Cp=2), flexibility(setup time) etc.

• Tracked monthly to show trends, identify problems and
  allocate resources

• Depts create mechanisms and authorities to capture this
  data

12/11/2012                  Sourabh Jain                      66
Performance Measure Presentation
1. Time series graph (Time in days, weeks etc)

2. Control charts (R,Xbar)

3. Capability Index

4. Taguchi Loss Function

5. Cost of poor quality

6. Malcolm Balridge National Quality Award
12/11/2012                Sourabh Jain           67
Quality Costs
• Those costs associated with the non-
  achievement of product or service quality as is
  required

• Quality cost programs – quantifies this cost

• Use Pareto analysis to find major cost drivers


12/11/2012            Sourabh Jain                 68
Quality Costs
• Preventive cost: Cost used up in preventing
  recurrence of some failure. Ex: Customer
  surveys, Product testing, Quality audits

• Appraisal cost: Cost of assuring acceptability
  of product. Ex: laboratory support, measuring
  equipment, certifications


12/11/2012            Sourabh Jain                 69
Quality Costs
• Internal Failure Cost: cost to evaluate, dispose
  off, & either correct or replace nonconforming
  products prior to customer delivery. Ex:
  rework       and      scrap,     poor     supply
  materials, internal failure labor loss

• External Failure Cost: After delivery. Ex:
  returned     goods,        updates,        warranty
  claims, penalties, lost sales, liabilities, goodwill

12/11/2012              Sourabh Jain                70
Malcolm Balridge National Quality
                   Award
•   Leadership                       110
•   Strategic Planning                80
•   Customer and Market focus         80
•   Information and Analysis          80
•   HR Focus                         100
•   Process Management               100
•   Business Results                 450

12/11/2012            Sourabh Jain         71
Quality Management System




12/11/2012              Sourabh Jain     72
QMS
• Registration under ISO involves assessment and
  periodic surveillance audit of the adequacy of a
  supplier’s quality system by a 3rd party

• Benefits of ISO
1. Customers are demanding compliance
2. To improve processes/systems
3. Global deployment of products
4. Snowball effect

12/11/2012            Sourabh Jain               73
ISO 9000
•   Generic in nature
•   It has 3 standards
•   ISO 9000:2000 QMS fundamentals/vocabulary
•   ISO 9000:2000 QMS requirements
•   ISO 9000:2000 QMS guidelines for
    performance improvement



12/11/2012           Sourabh Jain           74
ISO 9001 requirements
1.    Scope
2.    Normative reference
3.    Terms and Definitions
4.    QMS – General Reqs and Documents
5.    Management Responsibility
6.    Resource Management
7.    Product Realization
8.    Measurement, Analysis and Improvement

12/11/2012            Sourabh Jain            75
Process based QMS

                                      5
                                 Management
                                 Responsibility




                                  4 QMS
                                                        8
                    6 Resource   Continual        Measurement                Customer
                   Management    Improve           Analysis and             Satisfaction
                                                  Improvement
                                   ment



                                  7 Product
              Input               Realization
             Require                                              Output
              ments                                               Product

12/11/2012                        Sourabh Jain                                    76
Implementation
1. Top management commitment
2. Appoint management representative
3. Awareness
4. Appoint implementation team
5. Training
6. Time Schedule
7. Select element owners
8. Review present system
9. Write the documents
10. Install the new system
11. Internal audit
12. Management review
13. Preassessment
14. Registration
12/11/2012                 Sourabh Jain   77
Documentation
                                  What will be done and why ?
                   Policy


                Procedures             Who, When, Where


                                                 How
             Work Instructions

                  Proof
12/11/2012         Sourabh Jain                                 78
Statistical Process Control




12/11/2012              Sourabh Jain       79
Introduction
• SPC is a technical tool for improving product
  and service quality.

•   Pareto Diagram
•   Process Flow Diagram
•   Cause and Effect Diagram
•   Check Sheets
•   Histogram

12/11/2012            Sourabh Jain                80
Pareto Diagram
• Vital few and the useful many
• Ranks data classifications in descending order




12/11/2012            Sourabh Jain                 81
Pareto Diagram
• Solving 50 % of vital few is better and easier
  than 50 % of useful many

• Never ending process




12/11/2012            Sourabh Jain                 82
Process Flow Diagram




12/11/2012           Sourabh Jain   83
Cause and Effect Diagram
• Brainstorming essential. 4 or more likely
  causes determined by voting




12/11/2012             Sourabh Jain           84
Cause and Effect Diagram
• Wide scope for application

• Encourages participation and contribution by
  everyone

• Diagrams posted in key locations to stimulate
  continued reference


12/11/2012             Sourabh Jain               85
Check Sheets
• For ease of data collection
• Customized for situation




12/11/2012            Sourabh Jain   86
Histograms
• Graphically estimates Cp, relationships to
  specifications and target, shape of population
  and gaps in data

• Graphical and analytical

• Ungrouped and Grouped data (for large data)


12/11/2012            Sourabh Jain                 87
12/11/2012   Sourabh Jain   88
Normal curve
• Larger the Std Dev, flatter the curve (less data)




12/11/2012             Sourabh Jain               89
Types and Causes of variation
• Types
1. Within piece
2. Piece to piece
3. Time to time

• Causes
1. Equipment
2. Material
3. Environment
4. Operator

12/11/2012           Sourabh Jain        90
Variable Control Charts




12/11/2012            Sourabh Jain     91
Process Capability
• σ = Rbar/d2

• Cp = (USL-LSL)/6 σ

• USL-LSL=tolerance

• X

• X

• Cpk = min{(USL-Xbar) or (Xbar-LSL)}/3 σ

12/11/2012                 Sourabh Jain     92
Cp and Cpk
1. Cp value does not change as process center
   changes
2. Cp=Cpk process is centered
3. Cpk<=Cp
4. Cpk>1 process conforms to specifications
5. Cpk<1 process not conforms to specifications
6. Cp<1 process not capable
7. Cpk=0 average =USL or LSL
8. Cpk <0 average outside specifications
12/11/2012           Sourabh Jain             93
Scatter diagrams
• For correlations




12/11/2012           Sourabh Jain   94
BLUE OCEAN STRATEGY




12/11/2012           Sourabh Jain   95
12/11/2012   Sourabh Jain   96

Tqm

  • 1.
    By Sourabh Jain MBA 2010 - 2012 National Institute of Technology Karnataka, Surathkal, India 12/11/2012 Sourabh Jain 1
  • 2.
    Preface • This isa PowerPoint file I created in order to help me in my studies. • The material in these slides are a distilled version of the literature from 2 books 1. Total Quality Management – 3rd Edition – Besterfield, Michna, Besterfield, Sacre. 2. Total Quality Management – Bharat Wakhlu 12/11/2012 Sourabh Jain 2
  • 3.
    HOME Introduction Leadership Customer Employee Satisfaction Involvement Continuous Process Performance Improvement Measures QMS SPC 12/11/2012 Sourabh Jain 3
  • 4.
  • 5.
    Quality • Degree towhich a set of inherent characteristics fulfils requirements. • Q=Performance/Expectations • TQM; T = Total i.e. company-wide, suppliers, customers; M = Management i.e. art of directing and controlling 12/11/2012 Sourabh Jain 5
  • 6.
    Quality q andTotal Quality Q • Product orientation • Ensure produced goods are fit for sale • No prevention, No learning 12/11/2012 Sourabh Jain 6
  • 7.
    Quality q andTotal Quality Q • Customer/Process/Product orientation • Listen to customer, product design, process optimized • Right the first time, every time; Learning; importance of internal customers 12/11/2012 Sourabh Jain 7
  • 8.
    Dimensions of Quality Dimension Meaning Performance Primary product characteristics Features Added features Conformance Meeting standards Reliability Consistency of performance Durability Useful life Service Resolution of complaints Response Human to human interface Aesthetics Sensory characteristics Reputation Past performance 12/11/2012 Sourabh Jain 8
  • 9.
    Total Quality 1. PerformanceSuperiority 2. Delight customers 3. Provide value (value=quality/cost) 4. Doing the right things 5. Right the first time 12/11/2012 Sourabh Jain 9
  • 10.
    Definition of TQM •TQM is the art of managing the whole to achieve excellence. • TQM is a philosophy and a set of guiding principles that represent the foundation of a continually improving firm. • It is the application of quantitative methods and HR to improve all processes within a firm and exceed customer needs now and in the future. 12/11/2012 Sourabh Jain 10
  • 11.
    6 basic conceptsof TQM 1. Committed and involved management to provide long term- top to bottom – organizational support 2. Unwavering focus on the customer – internal and external 3. Effective involvement and utilization of entire workforce 4. Continuous improvement of business and production process 5. Treat suppliers as partners 6. Establish performance measures for processes 12/11/2012 Sourabh Jain 11
  • 12.
    Culture changes forTQM Quality element OLD CULTURE TQM CULTURE Definition Product oriented Customer oriented Priorities Second to service and cost Equal to service and cost Decisions Short term Long term Emphasis Detection Prevention Errors Operations System Responsibility Quality Control Everyone Problem Solving Managers Teams Procurement Price Life cycle costs, Partnership Manager’s Role Plan, assign, control, Delegate, coach, facilitate, enforce mentor 12/11/2012 Sourabh Jain 12
  • 13.
    Model for TQM Product, Systems Outstanding Services People and Leadership and power Procedures Process MEETING/ EXCEEDING CUSTOMER EXPECTATIONS CONTINUOUS CUSTOMER BENCHMARKING SYSTEMATIC FOCUS IMPROVEMENT 12/11/2012 Sourabh Jain 13
  • 14.
    Paradigms of TQM •Belief that people are a potential source of ‘beneficial forces’ will lead to total quality • Functional and Hierarchical divisions of a firm contribute to parochial thinking – not good • Everyone has to participate in obtaining total quality 12/11/2012 Sourabh Jain 14
  • 15.
    Gurus of TQM •Shewhart 1. Economic Control of Quality of Mfg product 2. Control Chart Theory 3. Assignable and chance causes of variation 4. Rational Subgroups 5. PDSA cycle 12/11/2012 Sourabh Jain 15
  • 16.
    Gurus of TQM •Deming 1. Out of the Crisis 2. Quality, Productivity and Competitive Position 3. 14 points to improve q,p,c 4. Taught SPC and quality to Japanese 12/11/2012 Sourabh Jain 16
  • 17.
    Gurus of TQM •Juran 1. Juran’s Quality control Handbook 2. Project Improvements based on ROI 3. Promoted commitment to quality at all levels 4. Juran Trilogy – Planning, Control, Improvement 12/11/2012 Sourabh Jain 17
  • 18.
    Gurus of TQM •Feigenbaum 1. Total Quality Control 2. Customer Satisfaction 3. Genuine Management Involvement 4. Employee Involvement 5. Company wide total quality control 6. First line supervision leadership 12/11/2012 Sourabh Jain 18
  • 19.
    Gurus of TQM •Ishikawa 1. SPC texts in Japanese and English 2. Adapted TQC i.e. TQM in Japan 3. Fishbone diagram 4. Quality circles 12/11/2012 Sourabh Jain 19
  • 20.
    Gurus of TQM •Crosby 1. Quality is Free 2. Quality without tears 3. Do it right the first time 4. Zero defects 12/11/2012 Sourabh Jain 20
  • 21.
    Gurus of TQM •Taguchi 1. Loss Function 2. Quality Engineering 3. Robust design of parameters/tolerances 12/11/2012 Sourabh Jain 21
  • 22.
    Obstacles to TQM 1. Lack of management commitment 2. Inability to change organization culture 3. Improper planning 4. Lack of continuous training and education 5. Incompatible Org structure & isolated departments and individuals 6. Ineffective measurement techniques 7. Paying inadequate attention to customers 8. Inadequate use of empowerment and teamwork 9. Failure to continually improve 12/11/2012 Sourabh Jain 22
  • 23.
    Benefits of TQM • Improve quality • Employee participation and satisfaction • Teamwork and Working relationships • Customer satisfaction • Productivity • Communication • Profitability and Market Share 12/11/2012 Sourabh Jain 23
  • 24.
    Leadership 12/11/2012 Sourabh Jain 24
  • 25.
    Leader • A leader 1.Shapes 2. Promotes 3. Protects 4. Exemplifies • the organization’s values 12/11/2012 Sourabh Jain 25
  • 26.
    Manager vs. Leader Manager Leadership for quality (Outstanding leadership) Plan EXPOSE limited utility of current approaches Organize ENVISION the future Staff ENLIST others in the quest Lead EMPOWER them to act Control ENCOURAGE right effort Feedback EXEMPLIFY by personal action 12/11/2012 Sourabh Jain 26
  • 27.
    Leadership Style Leadsto time bomb situations Best style FEARFUL WHOLESOME RIGID STYLE STYLE STYLE 12/11/2012 Sourabh Jain 27
  • 28.
    Characteristics of QualityLeaders 1. Priority attention to internal/external customers 2. Empower, rather than control subordinates 3. Emphasize improvement, rather than maintenance 4. Emphasize prevention 5. Encourage collaboration rather than competition 6. Train and coach, rather than direct and supervise 12/11/2012 Sourabh Jain 28
  • 29.
    Characteristics of QualityLeaders 7. Learn from problems 8. Continually try to improve communications 9. Continually demonstrate their commitment to quality 10. Choose suppliers on basis of quality, not price 11. Establish organizational systems to support quality effort 12. Encourage and Recognize team effort 12/11/2012 Sourabh Jain 29
  • 30.
    7 habits ofhighly effective people 1. Be proactive - don’t let fate control you, you control it 2. Begin with the end in mind – have a vision and plan 3. Put first things first – learn to prioritize 4. Think win-win – seek mutual benefits 5. Seek first to understand, then be understood 6. Synergy – teams are better than individuals 7. Sharpen the saw – renew one’s physical, spiritual, mental and emotional dimension 12/11/2012 Sourabh Jain 30
  • 31.
    Deming Philosophy • Createand publish aims/purpose of firm • Learn the new philosophy • Understand purpose of inspection • Stop awarding business on price alone • Improve constantly and forever the system • Institute training • Teach and institute leadership 12/11/2012 Sourabh Jain 31
  • 32.
    Deming Philosophy • Driveout fear, create trust and a climate for innovation • Optimize efforts of teams, groups and staff areas • Eliminate exhortations for the work force • Eliminate numerical quotas for workforce and MBO • Remove barriers that rob people of pride of workmanship • Encourage education and self-empowerment for everyone • Take action to accomplish the transformation 12/11/2012 Sourabh Jain 32
  • 33.
  • 34.
    Customer Satisfaction Model Company Offer Satisfier Customer Needs 12/11/2012 Sourabh Jain 34
  • 35.
    Notes • Customer –Internal and External is the focus. • Customer Satisfaction is subjective, hence hard to measure • Customer Satisfaction should not be viewed in a vacuum 12/11/2012 Sourabh Jain 35
  • 36.
    Customer feedback 1. Todiscover customer dissatisfaction 2. Discover relative priorities of Quality 3. Compare performance with competition 4. Identify customer’s needs 5. Determine opportunities for improvement 12/11/2012 Sourabh Jain 36
  • 37.
    Modes of feedback 1. Comment card – Service industry 2. Customer Questionnaire – mail, telephone 3. Focus groups – like a GD 4. Toll free telephone numbers – complaints 5. Customer visits – B2B 6. Report card – send to customer every quarter 7. The internet – blogs 8. Employee feedback – why problem? 9. Mass customization – variety at affordable cost 12/11/2012 Sourabh Jain 37
  • 38.
    Customer Complaints Complain to Action Management Shout at Front 1% Line Employees 19% Do nothing 80% Every complaint should be accepted, analyzed and acted upon because those who don’t complain might have switched loyalty. 12/11/2012 Sourabh Jain 38
  • 39.
    Handling complaints • Acceptfeedback • Empower front-line employees to resolve • More inspection does not solve it; find the root cause • Communicate complaint to everyone in firm • Contact complainant and put mind at ease • Be proactive about customer needs 12/11/2012 Sourabh Jain 39
  • 40.
  • 41.
    Motivation • Maslow’s Hierarchyof needs • Herzberg’s 2-factor theory • What employees want 1. Interesting Work 2. Appreciation 3. Involvement 4. Job Security 12/11/2012 Sourabh Jain 41
  • 42.
    Achieving a motivatedwork force 1. Know thyself 2. Know your employees 3. Establish a +ve attitude 4. Share goals 5. Monitor progress 6. Develop interesting work 7. Communicate effectively 8. Celebrate success 12/11/2012 Sourabh Jain 42
  • 43.
    Employee Surveys 1. Quality Council creates Survey team 2. Develop instrument (questionnaire).Constructs to be used are 1. Personality Characteristics 2. Management Styles 3. Job attitudes 4. The work 3. Administer survey (confidential and by 3rd party) 4. Compile and analyze (report is circulated in firm) 5. Determine areas for improvement 12/11/2012 Sourabh Jain 43
  • 44.
    Suggestion Systems • Managementmust make it easy for employees to suggest improvements 1. Be progressive – regularly ask employees 2. Remove fear – focus on the process, not the person 3. Simplify the process 4. Respond quickly - accept/Reject/Refer giving time or reason 5. Reward the idea 12/11/2012 Sourabh Jain 44
  • 45.
    Performance Appraisal • Purpose 1.Tells employee how they are performing 2. Basis for promotions and increments 3. Counseling 4. Opportunities • Employee involvement is critical and appraisals must be continuous. • Types – Ranking, Narrative, Forced, Graphic 12/11/2012 Sourabh Jain 45
  • 46.
    Problems with appraisalsystems 1. Emphasis on short term performance 2. Individual appraisals destroy teamwork 3. A person is only about 15 % responsible for his results 4. Based on subjectivity and immeasurables 12/11/2012 Sourabh Jain 46
  • 47.
    Improving the appraisalsystem 1. Use rating scales with fewer rating categories 2. Equal emphasis to individual and group appraisals 3. More frequent performance reviews with focus on improvement 4. Promotion decision to be based on current performance AND potential for new post 5. External customer satisfaction a part of the process 6. 360 degree appraisals 7. Evaluation for process improvements 12/11/2012 Sourabh Jain 47
  • 48.
    Benefits of employeeinvolvement • Employees 1. Make better decisions using expert knowledge of process 2. More likely to implement and support decisions they had a part in making/better able to accept changes 3. Better able to spot pinpoint areas for improvement 4. Better able to take immediate corrective action 5. EI increases morale, improves industrial relations and increases commitment to unit goals 12/11/2012 Sourabh Jain 48
  • 49.
    Continuous Process Improvement 12/11/2012 Sourabh Jain 49
  • 50.
    Juran Trilogy –Plan, Control, Improve • Planning 1. Determine external and internal customers 2. Identify their needs and translate into requirements 3. Develop product/service as per needs of not only customer but other stakeholders too 4. Develop processes able to produce product/service 5. Transfer plans to operations ensuring process validity 12/11/2012 Sourabh Jain 50
  • 51.
    Juran Trilogy –Plan, Control, Improve • Control 1. Determine items to be controlled and their units of measure 2. Set goals for controls and determine what sensors are needed 3. Measure actual performance 4. Compare it with goals 5. Act on the difference 12/11/2012 Sourabh Jain 51
  • 52.
    Juran Trilogy –Plan, Control, Improve • Improvement • Quality council identifies improvement areas and establishes project teams to work on it Quality Control (during operations) 50 Sporadic Waste 40 30 Original Zone of Quality Control QUALITY 20 New Zone of Quality Control PLANNING 10 Chronic Waste Quality Improvement FEEDBACK 0 0 1 2 3 4 5 6 7 8 9 10 Time FEEDBACK 12/11/2012 Sourabh Jain 52 Cost of poor Quality
  • 53.
    PDSA Cycle Plan Act Do Study 12/11/2012 Sourabh Jain 53
  • 54.
    Problem Solving method 1 Identify Opportunity 7 Plan for 2 Analyze Future Process 6 3 Develop Standardize Optimal solution Solution (s) 5 Study the 4 results Implement 12/11/2012 Sourabh Jain 54
  • 55.
    1 Identify Opportunity •Identify problem – Pareto analysis, Survey, Brainstorm, proposals • Form team – QC forms a multifunction team if required • Define scope – scope, goals, milestones 12/11/2012 Sourabh Jain 55
  • 56.
    2 Analyze Process •Develop Process Flow diagram • Define target performance measures • Relevant Data collection • Fishbone diagram 12/11/2012 Sourabh Jain 56
  • 57.
    3 Develop OptimalSolution (s) • Brainstorm – create new process/combine different process/modify existing process • Evaluate Test solutions using control charts – criteria: feasibility, scope, training and effects 12/11/2012 Sourabh Jain 57
  • 58.
    4 Implement • Prepareimplementation plan • Obtain approval • Implement process improvements 12/11/2012 Sourabh Jain 58
  • 59.
    5 Study theresults • Monitor and evaluate the change • Check if fine tuning is needed • If dissatisfied with results, repeat some phases 12/11/2012 Sourabh Jain 59
  • 60.
    6 Standardize solution •Positrol (Positive control) – ensures important variables are kept under control • Process Certification • Operator Certification 12/11/2012 Sourabh Jain 60
  • 61.
    7 Plan forFuture • Regular reviews of progress by QC • Knowledge Management System – save learnings • Repeat Phase 1. 12/11/2012 Sourabh Jain 61
  • 62.
    Kaizen • Process ofcontinuous improvement in small increments without complex technology or high costs making processes better • Uses concepts like: Value/Non value added activities, Mudas, Motion studies, SOP, 5S, Visual Management, JIT etc • 5S – Sort, Simplify, Sweep, Standardize, Sustain 12/11/2012 Sourabh Jain 62
  • 63.
    Six Sigma • UsesCp analysis as a way to measure progress • We should reduce the process variability σ to keep process centered on the target μ. • Process Capability Index = USL-LSL/6 σ • Process Performance Index Cpk = min(USL-X,X-LSL)/3 σ • Default Cp >1, Cpk =1 12/11/2012 Sourabh Jain 63
  • 64.
  • 65.
    Strategy • QC createsa total system of measures using info from stakeholders and firms’ VMG and values • Ex: Quality • % reduction in nonconformities • % of certified suppliers 12/11/2012 Sourabh Jain 65
  • 66.
    Strategy • Cost • %increase in inventory turnover • % increase in output dollars per employee • Similarly for innovation (NPD time), reliability (% processes having Cp=2), flexibility(setup time) etc. • Tracked monthly to show trends, identify problems and allocate resources • Depts create mechanisms and authorities to capture this data 12/11/2012 Sourabh Jain 66
  • 67.
    Performance Measure Presentation 1.Time series graph (Time in days, weeks etc) 2. Control charts (R,Xbar) 3. Capability Index 4. Taguchi Loss Function 5. Cost of poor quality 6. Malcolm Balridge National Quality Award 12/11/2012 Sourabh Jain 67
  • 68.
    Quality Costs • Thosecosts associated with the non- achievement of product or service quality as is required • Quality cost programs – quantifies this cost • Use Pareto analysis to find major cost drivers 12/11/2012 Sourabh Jain 68
  • 69.
    Quality Costs • Preventivecost: Cost used up in preventing recurrence of some failure. Ex: Customer surveys, Product testing, Quality audits • Appraisal cost: Cost of assuring acceptability of product. Ex: laboratory support, measuring equipment, certifications 12/11/2012 Sourabh Jain 69
  • 70.
    Quality Costs • InternalFailure Cost: cost to evaluate, dispose off, & either correct or replace nonconforming products prior to customer delivery. Ex: rework and scrap, poor supply materials, internal failure labor loss • External Failure Cost: After delivery. Ex: returned goods, updates, warranty claims, penalties, lost sales, liabilities, goodwill 12/11/2012 Sourabh Jain 70
  • 71.
    Malcolm Balridge NationalQuality Award • Leadership 110 • Strategic Planning 80 • Customer and Market focus 80 • Information and Analysis 80 • HR Focus 100 • Process Management 100 • Business Results 450 12/11/2012 Sourabh Jain 71
  • 72.
  • 73.
    QMS • Registration underISO involves assessment and periodic surveillance audit of the adequacy of a supplier’s quality system by a 3rd party • Benefits of ISO 1. Customers are demanding compliance 2. To improve processes/systems 3. Global deployment of products 4. Snowball effect 12/11/2012 Sourabh Jain 73
  • 74.
    ISO 9000 • Generic in nature • It has 3 standards • ISO 9000:2000 QMS fundamentals/vocabulary • ISO 9000:2000 QMS requirements • ISO 9000:2000 QMS guidelines for performance improvement 12/11/2012 Sourabh Jain 74
  • 75.
    ISO 9001 requirements 1. Scope 2. Normative reference 3. Terms and Definitions 4. QMS – General Reqs and Documents 5. Management Responsibility 6. Resource Management 7. Product Realization 8. Measurement, Analysis and Improvement 12/11/2012 Sourabh Jain 75
  • 76.
    Process based QMS 5 Management Responsibility 4 QMS 8 6 Resource Continual Measurement Customer Management Improve Analysis and Satisfaction Improvement ment 7 Product Input Realization Require Output ments Product 12/11/2012 Sourabh Jain 76
  • 77.
    Implementation 1. Top managementcommitment 2. Appoint management representative 3. Awareness 4. Appoint implementation team 5. Training 6. Time Schedule 7. Select element owners 8. Review present system 9. Write the documents 10. Install the new system 11. Internal audit 12. Management review 13. Preassessment 14. Registration 12/11/2012 Sourabh Jain 77
  • 78.
    Documentation What will be done and why ? Policy Procedures Who, When, Where How Work Instructions Proof 12/11/2012 Sourabh Jain 78
  • 79.
  • 80.
    Introduction • SPC isa technical tool for improving product and service quality. • Pareto Diagram • Process Flow Diagram • Cause and Effect Diagram • Check Sheets • Histogram 12/11/2012 Sourabh Jain 80
  • 81.
    Pareto Diagram • Vitalfew and the useful many • Ranks data classifications in descending order 12/11/2012 Sourabh Jain 81
  • 82.
    Pareto Diagram • Solving50 % of vital few is better and easier than 50 % of useful many • Never ending process 12/11/2012 Sourabh Jain 82
  • 83.
  • 84.
    Cause and EffectDiagram • Brainstorming essential. 4 or more likely causes determined by voting 12/11/2012 Sourabh Jain 84
  • 85.
    Cause and EffectDiagram • Wide scope for application • Encourages participation and contribution by everyone • Diagrams posted in key locations to stimulate continued reference 12/11/2012 Sourabh Jain 85
  • 86.
    Check Sheets • Forease of data collection • Customized for situation 12/11/2012 Sourabh Jain 86
  • 87.
    Histograms • Graphically estimatesCp, relationships to specifications and target, shape of population and gaps in data • Graphical and analytical • Ungrouped and Grouped data (for large data) 12/11/2012 Sourabh Jain 87
  • 88.
    12/11/2012 Sourabh Jain 88
  • 89.
    Normal curve • Largerthe Std Dev, flatter the curve (less data) 12/11/2012 Sourabh Jain 89
  • 90.
    Types and Causesof variation • Types 1. Within piece 2. Piece to piece 3. Time to time • Causes 1. Equipment 2. Material 3. Environment 4. Operator 12/11/2012 Sourabh Jain 90
  • 91.
  • 92.
    Process Capability • σ= Rbar/d2 • Cp = (USL-LSL)/6 σ • USL-LSL=tolerance • X • X • Cpk = min{(USL-Xbar) or (Xbar-LSL)}/3 σ 12/11/2012 Sourabh Jain 92
  • 93.
    Cp and Cpk 1.Cp value does not change as process center changes 2. Cp=Cpk process is centered 3. Cpk<=Cp 4. Cpk>1 process conforms to specifications 5. Cpk<1 process not conforms to specifications 6. Cp<1 process not capable 7. Cpk=0 average =USL or LSL 8. Cpk <0 average outside specifications 12/11/2012 Sourabh Jain 93
  • 94.
    Scatter diagrams • Forcorrelations 12/11/2012 Sourabh Jain 94
  • 95.
  • 96.
    12/11/2012 Sourabh Jain 96