Hutch O'Malley lead design team (including Praxis Architecture, Linesight, Harkin M&E, Coima, Simon Clear and Associates, Owens McCarthy, Adrian Purcell) worked with Nautic construction to deliver 8,500m3 of industrial space with 1 year of a devastating fire on the site outside Nenagh.
Individual part (substructure) of a 3rt semester project of Architectural Technology and Construction Management course; Islands Brygge Terraced Houses, showing process of developing each key junctions and construction of the substructure part.
Individual part (substructure) of a 3rt semester project of Architectural Technology and Construction Management course; Islands Brygge Terraced Houses, showing process of developing each key junctions and construction of the substructure part.
This presentation highlights highway pavement widening practices in the San Angelo District. Please remember to cite this research if the information you find here is used.
Welcome to this second newsletter from the project BRICKER, a four-year initiative to ultimately kick-start large-scale renovation of public non-residential buildings, and thus set an example for future public policy on energy solutions in the built environment.
Land Development Ukraine provides services such as geodesy and landsurvey, site selection and prolongation of land lease contracts, legal audit-due-dilligence, evaluation and approvals for receiving building permit fro real estate objects.
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...Tehmas Saeed
This was my second Graded unit Project, it involved construction of Steel framed Office building, based on HND modules we were advised to devise solution of Steel building which two areas of specialisation in which I chose Sustainability and Frame Structure. This assignment does not have drawings and calculations unfortunately i have lost them, however their is a copy at Former Stow College now Glasgow Kelvin college so students can access from there. For any structural help, I would strongly advise to meet Mr Murdo a very competent lecturer in Kelvin college.
Although its rough guide, we were not heavily using journals at that stage, as we relied mostly on our course material. However some of the Green material which i used was taken from companies publications.
This presentation highlights highway pavement widening practices in the San Angelo District. Please remember to cite this research if the information you find here is used.
Welcome to this second newsletter from the project BRICKER, a four-year initiative to ultimately kick-start large-scale renovation of public non-residential buildings, and thus set an example for future public policy on energy solutions in the built environment.
Land Development Ukraine provides services such as geodesy and landsurvey, site selection and prolongation of land lease contracts, legal audit-due-dilligence, evaluation and approvals for receiving building permit fro real estate objects.
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...Tehmas Saeed
This was my second Graded unit Project, it involved construction of Steel framed Office building, based on HND modules we were advised to devise solution of Steel building which two areas of specialisation in which I chose Sustainability and Frame Structure. This assignment does not have drawings and calculations unfortunately i have lost them, however their is a copy at Former Stow College now Glasgow Kelvin college so students can access from there. For any structural help, I would strongly advise to meet Mr Murdo a very competent lecturer in Kelvin college.
Although its rough guide, we were not heavily using journals at that stage, as we relied mostly on our course material. However some of the Green material which i used was taken from companies publications.
BIM on Project Site - Estella Heights Phase 2 ProjectHung Lam Vu Ngo
This is showing an approach to adopt BIM for Main-contractor on Project site, demonstration of a Mix-used Building Project in Ho Chi Minh City, Vietnam.
Presented by: Hung Lam - BIM Lead
The RIBA Plan of Work 2013 organises the process of briefing, designing, constructing, maintaining, operating and using building projects into eight Work Stages. The plan of work has always been about organising the design process.
What it not is a schedule of services document and it is not intended to be contractual.
However, it does set the scene for any given project
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
2. Background
Hutch O’Malley
Design
● New industrial buildings, housing estates and
large dwellings.
● Inspection and critique of existing buildings
and infrastructure.
● Surface water attenuation systems, potable
water supply design and road design and
analysis.
Consultancy
● Planning strategy, Site acquisition.
● Design team management.
● Technical advice applied to practical situations.
2
6. November 2016 Initial actions
○ Safety
○ Demolition required.
○ Liaise with insurers and QS.
○ Planning history;
○ Implied permission to replace building.
○ Where planning was not granted for
elements these cannot be replaced.
○ Scope of new design and functional
requirements.
○ Re-location (Nenagh)
○ Fire safety concerns to be addressed.
○ Insurance Liaison.
6
7. December 2016 Re-location
● Temporary building acquired
○ Immediate survey and design of industrial
layout.
● New fire safety design required
○ Drawing up and auditing building as fit
out ongoing.
○ Strong liaison with Fire officer.
● Insurance
○ Ensuring certifications issued on an
ongoing basis.
○ Coordination of commissioning and
activation of areas.
7
8. January 2017 Planning
● Local Authority Engagement
○ Outstanding compliance issues.
○ Preference to relocate operations to
industrial estate.
○ Concerns regarding environmental issues.
● Insurance settlement
○ Design replacement building matching
original.
○ Modify and justify application of modern
standards etc.
● Infrastructural & Environmental
○ “Bunded” site required to retain potential
“Fire water”
○ Surface water attenuation required.
8
9. February 2017 Initial Works & Design
● Site levels Assessment
○ Balance cut-fill across entire site.
○ 3D model of roads and floor levels
● Underground Services
○ Balance depth of dig and flow
velocity.
○ Sizing SUDS systems.
● Fire Safety Certificate
● Disabled Access Certificate
● Macro M & E Design commences.
○ Production layouts
○ Meetings with M & E
Contractors/ESB 9
12. March 2017 Refine Design
● Nomination of Piling & Steel
Contractor
● Lighting design
○ Minimum Lux levels in all public areas.
○ Vast LED options.
● Legal Mapping
○ Definition of new legal boundaries
○ Land transfers and agreements 12
13. April 2017: Construction Timeline
2 Acres under the roof.
● 32 Shipping Containers full of flat
packed machines to arrive on site by
Sep. 1st. (ordered 6 months in
advance)
● In Production Target: October 31st,
● Showroom construction to follow.
N.B: 53 WEEKS FROM FIRE.
13
14. May 2017 Grant of planning
● Contractor appointed following
tendering process.
● Preliminary Site Setup begins.
● Commencement Notice lodged.
● Floor Slab Design. 14
15. June 2017-Construction PM
15
● Contractor Detail Signoff.
● Construction Commences above ground.
● “Big Picture” M & E Design continues.
● Office Area design begins.
17. July 2017
● Macro M & E Design continues.
● Production area construction continuing.
● Begin Micro M & E design.
● Timeline is adjusted & Tightens
17
18. August 2017
● Production area nears completion.
● Insurance Company M & E Reqs.
● Machinery Suppliers.
18
19. September 2017
● Machinery Delivery
● Exterior Groundworks
● Office/Showroom design finalisation.
● Rainwater storage system commences.
19
23. November 2017
● Handover of Production area
● Production Startup & issues
resolved.
● Completion of Production area.
● Showroom completion phase. 23
29. 29
Hutch O’Malley
Consulting Civil and Structural Engineers
The Railway Station, Attyflin, Patrickswell, Co Limerick
T: 061 320260
E: admin@hutchomalley.ie
W: www.hutchomalley.ie
L: ihttps://ie.linkedin.com/company/hutch-o%27malley
F: www.facebook.com/hutchomalley
Editor's Notes
David O'Malley
David O'Malley
Mark Quinn
David O'Malley / Simon Clear
Alterations are acceptable where theses are deemed to be required by modern regulations or requirements.
David O'Malley
Dylan Casey
Alterations are acceptable where theses are deemed to be required by modern regulations or requirements.
Define production requirements, machinery, and workflow
Define production zones, segregation, traffic flow, high risk areas
Opportunity to improve production capabilities and output. Machinery, quality
Dylan Casey
Alterations are acceptable where theses are deemed to be required by modern regulations or requirements.
Dylan Casey
Over 100 piles
Infilled site - piles in poor areas
Columns strapped to floor slab everywhere else
Dylan
Richard Leonard
Contractor Detail Signoff.
Finalising Foundation/Floor structure
Signoff of Structural detailing from Suppliers.
Construction Commences above ground.
Ducting/Services layouts completed.
Floor pours commence.
Steel structure follows on with 2 week lead. (Lead for Concrete Strength)
Roof structure follows Steel with 2 week lead. (lead needed for logistics/Space for contractors)
“Big Picture” M & E Design continues.
First meetings with machinery suppliers.
First meetings with Extraction Ducting & Heating suppliers.
Office Area design begins.
Macro M & E Design continues.
More Meetings with Machinery suppliers.
Heating unit supplier finalised.
Production layout changes to suit.
Office Area design internal layouts.
Production area construction continuing.
Construction of project on track.
Begin Micro M & E design.
Broadband & Internal Network layout design.
Meetings with ESB re: network issues.
Fire & Security Design.
Plant Extraction system.
Timeline is adjusted & Tightens
Plant Delivery finalised.
M & E contractors move into phase 1.
Richard Leonard
Production area nears completion.
M & E contractors move in to phase 2.
Construction of Internal Walls.
Production offices construction commences.
Insurance Company M & E Reqs.
Sprinkler system requirements agreed.
Boiler house changes/Sprinkler system design/Storage Tanks locations.
Machinery Suppliers.
LOGISTICS: Micro requirements for machines.
Extraction/Electrical/Lighting/Air/Water/ Network/Heating system layouts & clashes.
Heating system changes.
Richard Leonard.
Machinery Delivery
Logistics issues.
Ducting/Extraction systems commence
Electrical layouts adjusted.
Heating system commences.
Exterior Groundworks
Drainage layouts, ducting runs.
Office/Showroom design finalisation.
Structural analysis & design.
M & E Design
Rainwater storage system commences.
Richard Leonard
M & E installation.
Minor clash issues due to incorrect/extra machinery.
Knock on effects to Prod layout & issues.
Showroom Construction commences.
Design team additions. Lighting design/Interior design.
Structure for “Unique” Feature Stairs & Steel from burnt building.
Prepare for handover of Prod. Area.
Car Park, Retaining walls, Fencing.
External Groundwork completions.
Beginning of construction of the Robotic Stock storage unit. A lot of machines being assembled.
Richard Leonard
Handover of Production area
Logistics/Legal/Insurance issues of handover.
Production Startup & issues involved:
Health & Safety/Inductions etc.
Plant requirement issues.
Training of staff.
Dealing with heating system runup, FUEL
Completion of Production area works.
Showroom ramps into completion phase.