SlideShare a Scribd company logo
1 of 51
Download to read offline
State of the art in Firefighting
on Oil Terminals
Carsten Zilmer Holbæk, Terminal Manager
Inter Terminals SGOT Aps
Mobile: +45 24 66 34 84
Carsten.Holbaek@interterminals.com
2
The Beginning! 50 Years with Oil in Stigsnaes
3
Evolution
4
State of the art in Firefighting
5
Upgrade of old firefighting equipment
1. The project
1. All Tanks to be covered: 20.000 K€
2. Only 11 Tanks to be covered 7.000 K€
2. Building the Foam system
3. Testing the system
• Rim-seal fire: Fully Automated
Start fire fighting by PC
• Tankfarm fire: Semi Automated
Start fire fighting
• Set up Foam guns manually 2 trailers with 4 guns and 2 km
hose each
• Start the pumps by PC.
6
The project
• The Danish authorities increased in January 2010 the requirements for fire protection of
Terminals witch are storing flammable liquids, see BEK28 on technical regulations for
flammable liquids.
• According to the technical regulations tanks with capacity greater than 10,000 storage units
for liquids of Class I and II and tank farms should be fitted with foam system.
• Furthermore, tanks that store Class III liquids, and which is less than 50 meters from Class I or
II tanks should be fitted with irrigation.
• In the spring of 2010 the English company Resource Protection International ( RPI) made a
fire protection study for SGOT, and as a result of high costs to meet future requirements for
fire safety in all tanks, a restriction of freedom was decided to retain liquids Class II and III.
Inter Terminals - liquids Class II :
JET FUEL flash point > 38 ° C
Cutter Light cycle oil with a flash point > 51 º C
Inter Terminals - liquids Class III :
GAS OIL flash point > 55 ° C
Biodiesel (max. 30%) with a flash point < 100 ° C.
7
• Tanks with a total volume of approx. 409,000 m³, was equipped with permanently installed foam
system for any storage of Class II and III liquids.
• Tanks for storage of Class III liquids closer than 50 meters from the tanks with storage of Class II
liquids was provided with irrigation systems .
8
Risk Assessment
9
Application and Approval
• The Application was sent to the authorities on 10 November 2010.
• DEMA (Danish Emergency Management Agency) permission was granted on 22 December
2011 on the basis of the Agency's terms for authorization of 12 December 2011.
10
Approval and terms
• Most significant terms:
The authorities approved the use of mobile plant or mobile equipment for foam
extinguishing of tank farm fires.
Foam extinguishing system response for tank farm fires, should have a capacity of
approx. 92 m³ foam concentrate liquid and approx. 14,500 liters/Minute
Develop a risk assessment and contingency planning for foam preparedness for tank
farm fires, which has to be approved by Emergency Management and other authorities.
Foam plants for extinguishing the RIM seal and full-surface fires will be established in
accordance with the requirements of TFBV and NFPA 11
Foam facilities for foam cover at tank farms to be established based on the requirements
of TFBV and NFPA 11 with a foam concentrate needs 91 m³.
Irrigation networks for cooling the tanks are carried out according to the requirements in
TFBV and IP 19.
Fire water system is performed with a "reserve" of 4,500 liters. minute for fire and
rescue services at the request of DEMA
ABA systems and CCTV systems will be established in agreement with DEMA.
11
The Building process
• Foam system:
• To meet the requirements for capabilities of foam systems and hydrants used 2 pcs existing
diesel fire pumps each with the following data:
• Q flow 1000 m3/h (16,667 liters / min)
• H lifting height 102 meters head.
• Fire water will be seawater intake through 2 pcs. DN 600 intake pipes fitted with filters at
inlet.
• Existing underground steel pipes for pumps will, where necessary, be replaced with plastic
pipes in material PE in dimension DN 400 (ø400 x 23.7 mm) to meet the requirement of a
sufficient min. pressure of 40 meters head at the tanks foam generators and irrigation
nozzles.
• Operator must under current regulations provide that the diesel tank is filled up by alarm and
when the tank is full alarm will be disabled. The minimum tank capacity of 2500 l meaning
that one fire pump can be kept in continuous operation for approx. 30 hours before the tank
is empty.
• There wil be installed 2 pcs. 100% foam pumps which are driven by water turbine with a
partial flow from the diesel fire pumps each with a capacity of
Q 30 m3/hour flow (500 l / min)
H lifting height 110 meters head.
12
Layout-plan
13
Layout-plan
14
• Tank Coverage
• All tanks with fixed roofs, which is scheduled Cl. II and Cl. III products is designed for full
surface coverage with a specific foam capacity of 4.1 l/min/m2.
Foam coverage made with permanently installed equipment.
• All valves for water and foam to foam systems and valves for irrigation is remote controlled
with electric drive. The valves are normally closed and can only be activated for testing and
active fire fighting.
• Upon activation of the fire switch or alarm fire detection system will diesel pumps
automatically start up at a lower speed of approx. 700 rpm as soon as possible to get the
pipes filled with water. Bleeding the piping is done using mechanical ventilation valves or
valves with electric drive.
• When a fire is detected, a start signal for the tank for active fire fighting and will automatically
place the following:
• Foam system water valve opens automatically using its electric drive
• The pipe system to the current tank is vented and fire pumps operate automatically to the
normal discharge pressure of approx. 9.5 bar. This procedure will prevent damage of piping
systems as a result of uncontrolled water hammer
• While the pumps running up to normal speed will foam valve automatically open using
electric drive and the active fire fighting is in operation and can be started.
• After the fire fighting or testing both water and foam pipe will be drained.
15
Layout-plan
16
Layout-plan
17
• The system does not consists of fixed foam cover equipment of tanks farms, but with mobile/portable
devices.
• It will be possible to have both fire pumps and two foam plants in operation simultaneously with
consequent increased foam cover. The enhanced foam cover will depend on the equipment and the
distance from the pump construction as a result of the pressure drop in the equipment and piping.
• Foam extinguishing installations equipped with standard approved foam generators for equal distribution
of foam on the tanks.
• Floating roof tanks, the foam generators being situated higher than the tanks shroud edge whereby it is
physically not possible to products that can penetrate into the foam pipe and generators.
• At fixed roof tanks will be established a lyre ranked higher than the tanks shell edge thus physically not
possible that there may penetrate products upstream of foam pipe.
• Above ground piping will be made of hot galvanized steel for fire protection. Under-ground pipelines and
pipelines in the pump housing to be built in plastic in quality PE.
• The type of foam to be 3% AFFF-LF Low Freeze Class B for hydrocarbon fuels.
Accredited to EN 1568 Part 3 (3%)
• The total design fire quantity of water is 1000 m3/hr (16,667 liters / min.).
• Foam Liquid will be stored in a storage tank of stainless steel or fiberglass insulated and the trace and
placed under an overhang.
• Foam Pump and valve placed frost-free in the same room as fire pumps.
18
P&I Plans
19
CE-Certificate
20
Layout-plan
21
22
Components
23
Fire Detection system
• Fire Detection system:
• Fire detection system performed by DBI Guideline 232 "Automatic fire alarm systems",
including testing and component standards in DS/EN54 "Fire detection and fire alarm
systems.”
• Fire detection is carried out by means of heat-sensitive cables. For floating roof tanks
mounted cables on the floating roof foam barrier and for tanks with fixed roof mounted
cables at all vents.
• From the stand placed a fire-safe two-wire cable to the top of the tank where it is connected
to the heat sensitive cable. As the heat sensitive cable is proposed a digital two-wire type,
which at the exceeding of a predetermined temperature (at least 79 ° C / max. Of 95 ° C) of> 5
sec. establish a short circuit in the cable and thereby gives an alarm at the control panel. The
cable is a two-wire with an outer diameter of <5 mm.
• After a fire, the area of the cable which have been exposed to direct flame or heat above 79 °
C changed.
• In floating roof tanks the heat cable is fitted in the middle of Rim Seal.
• On tanks with fixed roofs kept the heat cable around the tank roof and over all vents.
• Visual monitoring of the terminal is done by 8 pcs video cameras. In Port Office control
stations and terminal fire station installed 40" flat screens for viewing surveillance images.
24
Surveillance
25
Visual surveillance systems
• Establish a visual surveillance systems where both under normal visibility in the dark / fog can
identify and observe any fire from the terminal's own operational security, the fire
department of fire services. The system can also be extended so that monitoring can be
remotely displayed.
• The cameras will be installed on 4 pieces 30 m high masts, each with 2 video cameras, 1 day /
night camera and 1 thermo graphic camera. Each camera is encased in a weatherproof
camera housing equipped with heating and sprinkler / wiper. Below each mast is located 2
pcs. 25 liters sprinkler tank with sprinkler pump.
• The server and hard disk recorder is installed in the port office. This can store recordings for
min. 14 days.
26
27
28
Heat-sensitive cables
9 km of cable
29
30
Commissioning
31
32
Trailer:
• 1 pcs. Waterwall
• 2 pcs. Hosebaskets w. 2x15 mtr.
• 93 pcs. A-hoses 15 mtr.
33
34
35
Logistics
Where to place the hoses!!
36
37
38
39
Fire Station 2013
40
41
Fire Pump Control
42
Accesories
43
Action Cards
44
Action Cards
45
Testing and using the system
• Requirements originally:
• DEMA:
All of the foam generators have to be testet with foam liquid once a year.
The Cooling system and pumps have to be tested once a year.
All valves in the system have to be tested once a year.
• Environmental Authorities:
The Foam concentrate must not get into the Great Belt.
The Foam concentrate must not get into the API, Oil Seperator.
All of the water and foam mixtures must be collected after use.
What is the toxic impact of the AFFF-LF foam?
46
Reports and investigations
• Toxic report and recommendations:
47
48
The Yearly Test
• The test of foam generators.
We need 3 mobile tanks 30 m³ each
• Total use:
200 m³ Sea Water
6 m³ Foam Concentrate
Hose for connecting discarge to mobile tank
Aggreement with a company, witch can handle the mixed seawater with Foam, ie.
Chemical Disposal Plant.
49
Media: Brandvæsen
50
51

More Related Content

What's hot

Essential training on non water based fire protection
Essential training on non water based fire protection Essential training on non water based fire protection
Essential training on non water based fire protection Sabrul Jamil
 
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...AVEBIOM
 
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTION
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTIONSTANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTION
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTIONSreesankar Jayasingrajan
 
Fire Protection System Design
Fire Protection System DesignFire Protection System Design
Fire Protection System DesignMostafa Al Wakeel
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"EzazulHaqueSiddique
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentationLee Chun Yee
 
Fire Fighting and Solution for Globus Shopping Mall (bandra)
Fire Fighting and Solution for Globus Shopping  Mall (bandra)Fire Fighting and Solution for Globus Shopping  Mall (bandra)
Fire Fighting and Solution for Globus Shopping Mall (bandra)Esa Shaikh
 
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The HazardMinimaxFire
 
Building services project 2 presentation slides
Building services project 2 presentation slidesBuilding services project 2 presentation slides
Building services project 2 presentation slidesTan Jaden
 
Fire in hospital settings. dr pranav
Fire in hospital settings. dr pranavFire in hospital settings. dr pranav
Fire in hospital settings. dr pranavPranav Bansal
 
Recuperador de calor aquaflam/ Aquaflam insert
Recuperador de calor aquaflam/ Aquaflam insert Recuperador de calor aquaflam/ Aquaflam insert
Recuperador de calor aquaflam/ Aquaflam insert Dynamic444
 
Advanced Design Studio 2
Advanced Design Studio 2Advanced Design Studio 2
Advanced Design Studio 2ong93
 
ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2ong93
 

What's hot (20)

Essential training on non water based fire protection
Essential training on non water based fire protection Essential training on non water based fire protection
Essential training on non water based fire protection
 
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...
Tecnologías de control de emisiones para instalaciones térmicas de biomasa pe...
 
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTION
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTIONSTANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTION
STANDARDIZATION METHODS FOR CONTROL POWER PLANT POLLUTION
 
Fire Protection System Design
Fire Protection System DesignFire Protection System Design
Fire Protection System Design
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentation
 
Dry riser system
Dry riser systemDry riser system
Dry riser system
 
Fs sprinkler systems
Fs sprinkler systemsFs sprinkler systems
Fs sprinkler systems
 
TAC VS OISD RULES
TAC VS OISD RULESTAC VS OISD RULES
TAC VS OISD RULES
 
Fire Fighting and Solution for Globus Shopping Mall (bandra)
Fire Fighting and Solution for Globus Shopping  Mall (bandra)Fire Fighting and Solution for Globus Shopping  Mall (bandra)
Fire Fighting and Solution for Globus Shopping Mall (bandra)
 
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard
2013-10-30 Australian Gas Turbines Conference - Minimax - Fighting The Hazard
 
Building services project 2 presentation slides
Building services project 2 presentation slidesBuilding services project 2 presentation slides
Building services project 2 presentation slides
 
Fire in hospital settings. dr pranav
Fire in hospital settings. dr pranavFire in hospital settings. dr pranav
Fire in hospital settings. dr pranav
 
Recuperador de calor aquaflam/ Aquaflam insert
Recuperador de calor aquaflam/ Aquaflam insert Recuperador de calor aquaflam/ Aquaflam insert
Recuperador de calor aquaflam/ Aquaflam insert
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
Dry & Wet Riser Systems
Dry & Wet Riser SystemsDry & Wet Riser Systems
Dry & Wet Riser Systems
 
Advanced Design Studio 2
Advanced Design Studio 2Advanced Design Studio 2
Advanced Design Studio 2
 
Fire Fighting
Fire FightingFire Fighting
Fire Fighting
 
Novec 1230
Novec 1230Novec 1230
Novec 1230
 
ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2
 

Viewers also liked

New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3Valeriy Ivanov
 
Table for separation distances and containment requirements for tanks nfpa 30...
Table for separation distances and containment requirements for tanks nfpa 30...Table for separation distances and containment requirements for tanks nfpa 30...
Table for separation distances and containment requirements for tanks nfpa 30...zaheer sajid
 
radar tank gauging and dcs
radar tank gauging and dcsradar tank gauging and dcs
radar tank gauging and dcsSaravana Kumar
 
FIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATIONFIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATIONASGHAR KHALIL
 
Chapter 05- Foundations of Firefighting Tactics and Strategies
Chapter 05- Foundations of Firefighting Tactics and StrategiesChapter 05- Foundations of Firefighting Tactics and Strategies
Chapter 05- Foundations of Firefighting Tactics and Strategiessnoshoesam
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaZhao Wei Kim
 
Fire safety-in-high-rise-apartment-buildings
Fire safety-in-high-rise-apartment-buildingsFire safety-in-high-rise-apartment-buildings
Fire safety-in-high-rise-apartment-buildingsFerit Fazliu
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanksbernard347
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise buildingishant_kukreja
 
Fire Safety Management
Fire Safety ManagementFire Safety Management
Fire Safety ManagementNc Das
 

Viewers also liked (16)

Highrise
HighriseHighrise
Highrise
 
Kintec Oil and Gas Presentation
Kintec Oil and Gas PresentationKintec Oil and Gas Presentation
Kintec Oil and Gas Presentation
 
New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3
 
BAYS CONSULTANCY COMPANY PROFILE
BAYS CONSULTANCY COMPANY  PROFILEBAYS CONSULTANCY COMPANY  PROFILE
BAYS CONSULTANCY COMPANY PROFILE
 
Table for separation distances and containment requirements for tanks nfpa 30...
Table for separation distances and containment requirements for tanks nfpa 30...Table for separation distances and containment requirements for tanks nfpa 30...
Table for separation distances and containment requirements for tanks nfpa 30...
 
radar tank gauging and dcs
radar tank gauging and dcsradar tank gauging and dcs
radar tank gauging and dcs
 
FIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATIONFIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATION
 
Chapter 05- Foundations of Firefighting Tactics and Strategies
Chapter 05- Foundations of Firefighting Tactics and StrategiesChapter 05- Foundations of Firefighting Tactics and Strategies
Chapter 05- Foundations of Firefighting Tactics and Strategies
 
Fire fighting
Fire fightingFire fighting
Fire fighting
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in Malaysia
 
Fire safety-in-high-rise-apartment-buildings
Fire safety-in-high-rise-apartment-buildingsFire safety-in-high-rise-apartment-buildings
Fire safety-in-high-rise-apartment-buildings
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Sprinkler system
Sprinkler systemSprinkler system
Sprinkler system
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise building
 
Fire Safety Management
Fire Safety ManagementFire Safety Management
Fire Safety Management
 
Basics of Fire fighting
Basics of Fire fightingBasics of Fire fighting
Basics of Fire fighting
 

Similar to The State of the art in Fire Fighting 2013 V1

Library study on hospital
Library study on hospital Library study on hospital
Library study on hospital manjul gambhir
 
FF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdfFF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdfssuser0aa2d5
 
FIRE FIGHTING Syllabus for for suppresion.pdf
FIRE FIGHTING Syllabus for for suppresion.pdfFIRE FIGHTING Syllabus for for suppresion.pdf
FIRE FIGHTING Syllabus for for suppresion.pdfKj Aswin
 
Marine piping systems
Marine piping systemsMarine piping systems
Marine piping systemskmsu
 
GROUP A - POSTER PRESENTATION - M02MAM
GROUP A - POSTER PRESENTATION - M02MAMGROUP A - POSTER PRESENTATION - M02MAM
GROUP A - POSTER PRESENTATION - M02MAMtolani adeleke
 
Fire safety in hospitals
Fire safety in hospitalsFire safety in hospitals
Fire safety in hospitalsKomal Gupta
 
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGanirbanmaity1992
 
Comparision between NFPA and TAc rules for Power plants
Comparision between NFPA and TAc rules for Power plantsComparision between NFPA and TAc rules for Power plants
Comparision between NFPA and TAc rules for Power plantsvakil jagdish
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2خالد محمود
 
Is codes for 3844 internal fire hydrants and hose
Is codes for 3844 internal fire hydrants and hoseIs codes for 3844 internal fire hydrants and hose
Is codes for 3844 internal fire hydrants and hoseprabhuraj saluja
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...AnkitaGorhe
 
Devnya plant tour_EN
Devnya plant tour_ENDevnya plant tour_EN
Devnya plant tour_ENMarco Maccari
 
Devnya plant tour
Devnya plant tourDevnya plant tour
Devnya plant tourteopetz
 
ProCon Low Pressure Water Mist System "kablo-yanginlari" için
ProCon Low Pressure Water Mist System "kablo-yanginlari" içinProCon Low Pressure Water Mist System "kablo-yanginlari" için
ProCon Low Pressure Water Mist System "kablo-yanginlari" içinNasip Gürgül
 

Similar to The State of the art in Fire Fighting 2013 V1 (20)

fire fighting System
fire fighting Systemfire fighting System
fire fighting System
 
Library study on hospital
Library study on hospital Library study on hospital
Library study on hospital
 
MODULE - 5 (2).pdf
MODULE - 5 (2).pdfMODULE - 5 (2).pdf
MODULE - 5 (2).pdf
 
OISD STD 117.pptx
OISD STD 117.pptxOISD STD 117.pptx
OISD STD 117.pptx
 
FF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdfFF DESIGN BASIS REPORT.pdf
FF DESIGN BASIS REPORT.pdf
 
FIRE FIGHTING Syllabus for for suppresion.pdf
FIRE FIGHTING Syllabus for for suppresion.pdfFIRE FIGHTING Syllabus for for suppresion.pdf
FIRE FIGHTING Syllabus for for suppresion.pdf
 
Marine piping systems
Marine piping systemsMarine piping systems
Marine piping systems
 
GROUP A - POSTER PRESENTATION - M02MAM
GROUP A - POSTER PRESENTATION - M02MAMGROUP A - POSTER PRESENTATION - M02MAM
GROUP A - POSTER PRESENTATION - M02MAM
 
Fire safety in hospitals
Fire safety in hospitalsFire safety in hospitals
Fire safety in hospitals
 
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
 
PWD training
PWD trainingPWD training
PWD training
 
Comparision between NFPA and TAc rules for Power plants
Comparision between NFPA and TAc rules for Power plantsComparision between NFPA and TAc rules for Power plants
Comparision between NFPA and TAc rules for Power plants
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2
 
IOC jaipur
IOC jaipurIOC jaipur
IOC jaipur
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
Is codes for 3844 internal fire hydrants and hose
Is codes for 3844 internal fire hydrants and hoseIs codes for 3844 internal fire hydrants and hose
Is codes for 3844 internal fire hydrants and hose
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...
 
Devnya plant tour_EN
Devnya plant tour_ENDevnya plant tour_EN
Devnya plant tour_EN
 
Devnya plant tour
Devnya plant tourDevnya plant tour
Devnya plant tour
 
ProCon Low Pressure Water Mist System "kablo-yanginlari" için
ProCon Low Pressure Water Mist System "kablo-yanginlari" içinProCon Low Pressure Water Mist System "kablo-yanginlari" için
ProCon Low Pressure Water Mist System "kablo-yanginlari" için
 

The State of the art in Fire Fighting 2013 V1

  • 1. State of the art in Firefighting on Oil Terminals Carsten Zilmer Holbæk, Terminal Manager Inter Terminals SGOT Aps Mobile: +45 24 66 34 84 Carsten.Holbaek@interterminals.com
  • 2. 2 The Beginning! 50 Years with Oil in Stigsnaes
  • 4. 4 State of the art in Firefighting
  • 5. 5 Upgrade of old firefighting equipment 1. The project 1. All Tanks to be covered: 20.000 K€ 2. Only 11 Tanks to be covered 7.000 K€ 2. Building the Foam system 3. Testing the system • Rim-seal fire: Fully Automated Start fire fighting by PC • Tankfarm fire: Semi Automated Start fire fighting • Set up Foam guns manually 2 trailers with 4 guns and 2 km hose each • Start the pumps by PC.
  • 6. 6 The project • The Danish authorities increased in January 2010 the requirements for fire protection of Terminals witch are storing flammable liquids, see BEK28 on technical regulations for flammable liquids. • According to the technical regulations tanks with capacity greater than 10,000 storage units for liquids of Class I and II and tank farms should be fitted with foam system. • Furthermore, tanks that store Class III liquids, and which is less than 50 meters from Class I or II tanks should be fitted with irrigation. • In the spring of 2010 the English company Resource Protection International ( RPI) made a fire protection study for SGOT, and as a result of high costs to meet future requirements for fire safety in all tanks, a restriction of freedom was decided to retain liquids Class II and III. Inter Terminals - liquids Class II : JET FUEL flash point > 38 ° C Cutter Light cycle oil with a flash point > 51 º C Inter Terminals - liquids Class III : GAS OIL flash point > 55 ° C Biodiesel (max. 30%) with a flash point < 100 ° C.
  • 7. 7 • Tanks with a total volume of approx. 409,000 m³, was equipped with permanently installed foam system for any storage of Class II and III liquids. • Tanks for storage of Class III liquids closer than 50 meters from the tanks with storage of Class II liquids was provided with irrigation systems .
  • 9. 9 Application and Approval • The Application was sent to the authorities on 10 November 2010. • DEMA (Danish Emergency Management Agency) permission was granted on 22 December 2011 on the basis of the Agency's terms for authorization of 12 December 2011.
  • 10. 10 Approval and terms • Most significant terms: The authorities approved the use of mobile plant or mobile equipment for foam extinguishing of tank farm fires. Foam extinguishing system response for tank farm fires, should have a capacity of approx. 92 m³ foam concentrate liquid and approx. 14,500 liters/Minute Develop a risk assessment and contingency planning for foam preparedness for tank farm fires, which has to be approved by Emergency Management and other authorities. Foam plants for extinguishing the RIM seal and full-surface fires will be established in accordance with the requirements of TFBV and NFPA 11 Foam facilities for foam cover at tank farms to be established based on the requirements of TFBV and NFPA 11 with a foam concentrate needs 91 m³. Irrigation networks for cooling the tanks are carried out according to the requirements in TFBV and IP 19. Fire water system is performed with a "reserve" of 4,500 liters. minute for fire and rescue services at the request of DEMA ABA systems and CCTV systems will be established in agreement with DEMA.
  • 11. 11 The Building process • Foam system: • To meet the requirements for capabilities of foam systems and hydrants used 2 pcs existing diesel fire pumps each with the following data: • Q flow 1000 m3/h (16,667 liters / min) • H lifting height 102 meters head. • Fire water will be seawater intake through 2 pcs. DN 600 intake pipes fitted with filters at inlet. • Existing underground steel pipes for pumps will, where necessary, be replaced with plastic pipes in material PE in dimension DN 400 (ø400 x 23.7 mm) to meet the requirement of a sufficient min. pressure of 40 meters head at the tanks foam generators and irrigation nozzles. • Operator must under current regulations provide that the diesel tank is filled up by alarm and when the tank is full alarm will be disabled. The minimum tank capacity of 2500 l meaning that one fire pump can be kept in continuous operation for approx. 30 hours before the tank is empty. • There wil be installed 2 pcs. 100% foam pumps which are driven by water turbine with a partial flow from the diesel fire pumps each with a capacity of Q 30 m3/hour flow (500 l / min) H lifting height 110 meters head.
  • 14. 14 • Tank Coverage • All tanks with fixed roofs, which is scheduled Cl. II and Cl. III products is designed for full surface coverage with a specific foam capacity of 4.1 l/min/m2. Foam coverage made with permanently installed equipment. • All valves for water and foam to foam systems and valves for irrigation is remote controlled with electric drive. The valves are normally closed and can only be activated for testing and active fire fighting. • Upon activation of the fire switch or alarm fire detection system will diesel pumps automatically start up at a lower speed of approx. 700 rpm as soon as possible to get the pipes filled with water. Bleeding the piping is done using mechanical ventilation valves or valves with electric drive. • When a fire is detected, a start signal for the tank for active fire fighting and will automatically place the following: • Foam system water valve opens automatically using its electric drive • The pipe system to the current tank is vented and fire pumps operate automatically to the normal discharge pressure of approx. 9.5 bar. This procedure will prevent damage of piping systems as a result of uncontrolled water hammer • While the pumps running up to normal speed will foam valve automatically open using electric drive and the active fire fighting is in operation and can be started. • After the fire fighting or testing both water and foam pipe will be drained.
  • 17. 17 • The system does not consists of fixed foam cover equipment of tanks farms, but with mobile/portable devices. • It will be possible to have both fire pumps and two foam plants in operation simultaneously with consequent increased foam cover. The enhanced foam cover will depend on the equipment and the distance from the pump construction as a result of the pressure drop in the equipment and piping. • Foam extinguishing installations equipped with standard approved foam generators for equal distribution of foam on the tanks. • Floating roof tanks, the foam generators being situated higher than the tanks shroud edge whereby it is physically not possible to products that can penetrate into the foam pipe and generators. • At fixed roof tanks will be established a lyre ranked higher than the tanks shell edge thus physically not possible that there may penetrate products upstream of foam pipe. • Above ground piping will be made of hot galvanized steel for fire protection. Under-ground pipelines and pipelines in the pump housing to be built in plastic in quality PE. • The type of foam to be 3% AFFF-LF Low Freeze Class B for hydrocarbon fuels. Accredited to EN 1568 Part 3 (3%) • The total design fire quantity of water is 1000 m3/hr (16,667 liters / min.). • Foam Liquid will be stored in a storage tank of stainless steel or fiberglass insulated and the trace and placed under an overhang. • Foam Pump and valve placed frost-free in the same room as fire pumps.
  • 21. 21
  • 23. 23 Fire Detection system • Fire Detection system: • Fire detection system performed by DBI Guideline 232 "Automatic fire alarm systems", including testing and component standards in DS/EN54 "Fire detection and fire alarm systems.” • Fire detection is carried out by means of heat-sensitive cables. For floating roof tanks mounted cables on the floating roof foam barrier and for tanks with fixed roof mounted cables at all vents. • From the stand placed a fire-safe two-wire cable to the top of the tank where it is connected to the heat sensitive cable. As the heat sensitive cable is proposed a digital two-wire type, which at the exceeding of a predetermined temperature (at least 79 ° C / max. Of 95 ° C) of> 5 sec. establish a short circuit in the cable and thereby gives an alarm at the control panel. The cable is a two-wire with an outer diameter of <5 mm. • After a fire, the area of the cable which have been exposed to direct flame or heat above 79 ° C changed. • In floating roof tanks the heat cable is fitted in the middle of Rim Seal. • On tanks with fixed roofs kept the heat cable around the tank roof and over all vents. • Visual monitoring of the terminal is done by 8 pcs video cameras. In Port Office control stations and terminal fire station installed 40" flat screens for viewing surveillance images.
  • 25. 25 Visual surveillance systems • Establish a visual surveillance systems where both under normal visibility in the dark / fog can identify and observe any fire from the terminal's own operational security, the fire department of fire services. The system can also be extended so that monitoring can be remotely displayed. • The cameras will be installed on 4 pieces 30 m high masts, each with 2 video cameras, 1 day / night camera and 1 thermo graphic camera. Each camera is encased in a weatherproof camera housing equipped with heating and sprinkler / wiper. Below each mast is located 2 pcs. 25 liters sprinkler tank with sprinkler pump. • The server and hard disk recorder is installed in the port office. This can store recordings for min. 14 days.
  • 26. 26
  • 27. 27
  • 29. 29
  • 31. 31
  • 32. 32 Trailer: • 1 pcs. Waterwall • 2 pcs. Hosebaskets w. 2x15 mtr. • 93 pcs. A-hoses 15 mtr.
  • 33. 33
  • 34. 34
  • 36. 36
  • 37. 37
  • 38. 38
  • 40. 40
  • 45. 45 Testing and using the system • Requirements originally: • DEMA: All of the foam generators have to be testet with foam liquid once a year. The Cooling system and pumps have to be tested once a year. All valves in the system have to be tested once a year. • Environmental Authorities: The Foam concentrate must not get into the Great Belt. The Foam concentrate must not get into the API, Oil Seperator. All of the water and foam mixtures must be collected after use. What is the toxic impact of the AFFF-LF foam?
  • 46. 46 Reports and investigations • Toxic report and recommendations:
  • 47. 47
  • 48. 48 The Yearly Test • The test of foam generators. We need 3 mobile tanks 30 m³ each • Total use: 200 m³ Sea Water 6 m³ Foam Concentrate Hose for connecting discarge to mobile tank Aggreement with a company, witch can handle the mixed seawater with Foam, ie. Chemical Disposal Plant.
  • 50. 50
  • 51. 51