The document summarizes the history of electricity issues and reforms in the Philippines. It discusses the power crisis in the 1990s that stemmed from insufficient generating capacity. This prompted President Ramos to issue licenses to Independent Power Producers (IPPs) to build new plants. The IPPs solved the short-term crisis but their contracts proved costly. This led to the 2001 Electric Power Industry Reform Act that restructured the industry, privatized generation assets, and established an independent regulator. The document reviews key elements and impacts of the reforms, including the purchased power adjustment mechanism and issues raised around IPPs and distribution utility rates.
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)Elvin Uy
Analysis of RA 9136, the Electric Power Industry Reform Act, for my Policy Analysis I course in Carnegie Mellon in 2010. Full paper can be viewed here: http://scr.bi/HNHTHU
Demand Side Management” means the actions of a Distribution Licensee, beyond the customer's meter, with the objective of altering the end-use of electricity
The document covers the newly implemented regulation "Deviation settlement and mechanism" by CERC (central electricity regulatory commission.
This regulation has replaced the UI Regulation and mechanism.
Reforming the Philippine Electric Power Industry Reform Act (EPIRA)Elvin Uy
Analysis of RA 9136, the Electric Power Industry Reform Act, for my Policy Analysis I course in Carnegie Mellon in 2010. Full paper can be viewed here: http://scr.bi/HNHTHU
Demand Side Management” means the actions of a Distribution Licensee, beyond the customer's meter, with the objective of altering the end-use of electricity
The document covers the newly implemented regulation "Deviation settlement and mechanism" by CERC (central electricity regulatory commission.
This regulation has replaced the UI Regulation and mechanism.
Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Fourth Amendment) Regulations, 2018 effective from 01.01.2019
This presentation gives a brief about the Indian Power sector. It covers evolution, growth, major players of Power sectors. Also, it focuses various acts, regulations and tariffs related to it. The important part is issues which are there in Power sector and we have made an attempt to provide recommendations for the same.
Tariff structure for Conventional and Non Conventional electricity generation sources, For tariff regulation of 2009-14 & 2014-19 and Renewable tariff order for 2015
Central Electricity Regulatory Commission implemented the Deviation Settlement Mechanism w.e.f 17.02.2014 throughout the country by bringing out the CERC (Deviation Settlement Regulations and other matters) Regulations, 2014. This regulation had a far-reaching consequences on any stakeholder like STUs, IPPs, ISGS for deviating from the injection/drawal Schedule in a time block beyond a certain prescribed limit by levying Deviation Charges including Additional Deviation Charges
4.1. INTRODUCTION[ http://www.pmintpc.com/interface/research_activities_published_paper_ICPS04.pdf]
Electricity is a non-storable commodity, which indicates the electricity generated should be consumed timely. In competitive environment, the price is determined by stochastic supply and demand functions. The price can change at any time.As a consequence of increased volatility, a market participant could make trading contracts with other parties to hedge possible risks and get better returns.
Open access is the key to a free and fair electricity market. Power producers (sellers) and dealers/customers (buyers) have to share a common transmission network for wheeling the power from the point of generation to the point of consumption. Thus, interconnected transmission system is considered to be a natural monopoly so as to avoid the duplicity, the problem of right-of-the-way, huge investment for new infrastructure and to take the advantage of the interconnected network viz. reduced installed capacity,increased system reliability and improved system performance.
4.2. POWER TRADING
According to the Electricity Act 2003,
“Power trading is an activity in which the utility having surplus power transfers electricity to the utility having deficit of power, at some price (mostly Rs/Kwh)”
According to Section 2(Definitions), Sub-section 71 of the Act,
„Trading‟ means purchase of electricity for resale thereof.
According to Section 2(Definitions), Sub-section 47 of the Act,
„Open access‟ means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the appropriate commission.
EMA Energy Management Training for Organisations and IndividualsEMEX
EMA Energy Management training will help organisations to strengthen their commitment to strategically decrease energy consumption and ultimately energy cost. Training employees will contribute to increasing their productivity and have a positive impact on organisation’s profitability.
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...Davide Bonomi
This presentation was presented at the masterclass session during 11th Energy Storage World Forum in 2018, Berlin.
How To Apply Energy Storage Technologies In Commercial And Industrial Applications – by ENEA explains two reasons why facilities should be interested in storage projects:
1. Market & value for C&I energy storage is finally booming in numerous locations
2. Startups and large utilities now compete to provide C&I facilities with turnkey solutions
If you’d like to get a deep industry insights and learn in person from energy storage professionals, join our next masterclass at https://energystorageforum.com/register
Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Fourth Amendment) Regulations, 2018 effective from 01.01.2019
This presentation gives a brief about the Indian Power sector. It covers evolution, growth, major players of Power sectors. Also, it focuses various acts, regulations and tariffs related to it. The important part is issues which are there in Power sector and we have made an attempt to provide recommendations for the same.
Tariff structure for Conventional and Non Conventional electricity generation sources, For tariff regulation of 2009-14 & 2014-19 and Renewable tariff order for 2015
Central Electricity Regulatory Commission implemented the Deviation Settlement Mechanism w.e.f 17.02.2014 throughout the country by bringing out the CERC (Deviation Settlement Regulations and other matters) Regulations, 2014. This regulation had a far-reaching consequences on any stakeholder like STUs, IPPs, ISGS for deviating from the injection/drawal Schedule in a time block beyond a certain prescribed limit by levying Deviation Charges including Additional Deviation Charges
4.1. INTRODUCTION[ http://www.pmintpc.com/interface/research_activities_published_paper_ICPS04.pdf]
Electricity is a non-storable commodity, which indicates the electricity generated should be consumed timely. In competitive environment, the price is determined by stochastic supply and demand functions. The price can change at any time.As a consequence of increased volatility, a market participant could make trading contracts with other parties to hedge possible risks and get better returns.
Open access is the key to a free and fair electricity market. Power producers (sellers) and dealers/customers (buyers) have to share a common transmission network for wheeling the power from the point of generation to the point of consumption. Thus, interconnected transmission system is considered to be a natural monopoly so as to avoid the duplicity, the problem of right-of-the-way, huge investment for new infrastructure and to take the advantage of the interconnected network viz. reduced installed capacity,increased system reliability and improved system performance.
4.2. POWER TRADING
According to the Electricity Act 2003,
“Power trading is an activity in which the utility having surplus power transfers electricity to the utility having deficit of power, at some price (mostly Rs/Kwh)”
According to Section 2(Definitions), Sub-section 71 of the Act,
„Trading‟ means purchase of electricity for resale thereof.
According to Section 2(Definitions), Sub-section 47 of the Act,
„Open access‟ means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the appropriate commission.
EMA Energy Management Training for Organisations and IndividualsEMEX
EMA Energy Management training will help organisations to strengthen their commitment to strategically decrease energy consumption and ultimately energy cost. Training employees will contribute to increasing their productivity and have a positive impact on organisation’s profitability.
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...Davide Bonomi
This presentation was presented at the masterclass session during 11th Energy Storage World Forum in 2018, Berlin.
How To Apply Energy Storage Technologies In Commercial And Industrial Applications – by ENEA explains two reasons why facilities should be interested in storage projects:
1. Market & value for C&I energy storage is finally booming in numerous locations
2. Startups and large utilities now compete to provide C&I facilities with turnkey solutions
If you’d like to get a deep industry insights and learn in person from energy storage professionals, join our next masterclass at https://energystorageforum.com/register
The Hydropower plants in Mindanao which supplies 52% of its electricity is planned to be sold to private investors. This should not happen. We are opposing the privatization and here is the reason why.
Miniature linear screw adjustment, lightweight gear drive lifting, lightweight screw mechanism for lifting, micro worm gear screw actuators Features
1. Lifting Force 2.5kN. Under max. lifting force, drive torque 1.2Nm (high speed), 0.4Nm (low speed).
2. Lifting screw diameter 16 mm, pitch 4 mm.
3. High gear ratio 1/4, low gear ratio 1/16.
4. Translating screw, travelling nut rotating screw, keyed translating screw configurations in upright or inverted mounting orientations.
5. Precision positioning, self-locking lead screw which supports the loads and hold position with no need to employ brake mechanism or other locking systems.
6. Hand-operated screw jack by hand wheel or crank handle, or electric driven screw jack by 3-phase or single phase motor or gear reduction motor.
7. No standard lead screw travel length, all lead screw travel length is processed according customers requirements. Maximum permissible 300mm travel length.
8. Lead screw end fittings include top plate, clevis end, plain end and threaded end.
9. Individually or multiple screw jack lift system arrangements are available.
Applications
Micro-miniature screw jacks matching mini bevel gearboxes with parts are composed of small screw jacks lifting system, which widely used in beverage can conveyor systems height adjustment and beverage can washing area of the production line, saving man-hours and lowering the down time, crucial for increasing output and are extremely pleased with the recent financial benefits. Prior to the upgrade when the can washer area on each line required to be changed to accommodate a run taller or shorter cans the conversion would be completed manually. Small screw jack lifting systems is utilized several stages for washing and blow drying the cans. Suitable for lifting height adjustment and washing in aluminium can production lines, magnetic conveying systems, steel can line, aluminium can line, food can line, upgrade fill and packaging line, conversion steel aluminum can line, bottle conveyor systems, case and pallet conveyor systems.
SCOPE FOR DESIGN & DEVELOPMENT OF 2R EDGE TRIMMING MECHANISM & TOOL ADJUSTMENTIAEME Publication
The most relevant problem in wood-working Enterprises consists in an optimal selection of standard stock sizes and trimming of edges while finishing of the panels sheets according to specified requirements, so that the waste is minimized & finishing of the wooden panel took place. The efficiency of the production processes also depends on the organization of a good production scheduling and a fine operations sequence in order to minimize the time of operation & maximum number of production improving the automated material handling systems while visiting DATTA ENTERPRISES,MIDC, Butibori, Nagpur, we found a problem concern with the operation perform in the industry.
International Journal of Engineering and Science Invention (IJESI) is an international journal intended for professionals and researchers in all fields of computer science and electronics. IJESI publishes research articles and reviews within the whole field Engineering Science and Technology, new teaching methods, assessment, validation and the impact of new technologies and it will continue to provide information on the latest trends and developments in this ever-expanding subject. The publications of papers are selected through double peer reviewed to ensure originality, relevance, and readability. The articles published in our journal can be accessed online.
An analysis of california’s electric utility industry introducing competitio...Blake Wedekind
A research paper that examines the economic forces behind the electricity market in California, specifically on the competition between Investor Owned Utilities (IOUs) and Community Choice Aggregation programs (CCAs). I develop a theoretical model using microeconomic theory to evaluate the nature and effectiveness of an 'exit fee' assessed to CCA customers, known as the Power Charge Indifference Adjustment (PCIA). Background information on the history of the electricity market, the development of the IOU, Community Choice Aggregation, and relevant legislation are also discussed.
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Fernando Penarroyo
The enactment of the Renewable Energy Act of 2008 (“RE Act”) and its implementing rules and regulations was expected to open the way for the entry of risk capital in geothermal exploration, development and utilization. The Department of Energy (“DOE”) admitted that progress on implementing support systems for renewable energy development in the power sector has been hobbled by delays. The Philippine government initiated major structural reforms in the geothermal industry sector by undertaking the privatisation of geothermal generating assets and divesting its interests in the state-owned geothermal development company. Like in any resource development project, the Philippine government needs to address issues related to the complicated approval and permitting process to reduce and expedite procedures particularly in foreign ownership, land use, environment and social acceptability regulations. Needless to say, streamlining the permit process by government regulators will have an impact on geothermal development, as shorter project periods would reduce uncertainty for policy and market dynamics when modelling economic returns. As geothermal projects are characterized by significant upfront capital investment for exploration, well drilling, and the installation of plant and equipment, the DOE must develop publicly available database protocols and tools for geothermal resource assessments to facilitate access by developers to risk capital. Government regulators must also develop guidelines for the inclusion of non-conventional and leading edge geothermal technologies in the setting up of feed-in tariff rates. Risk mitigation instruments like risk guarantee schemes and geologic risk insurance will also encourage investments in geothermal exploration.
With a population of almost 100 million people and annual economic growth averaging between 6 to 7%, the Philippines’ is anticipated to continue to have a robust energy demand. The Government’s refusal to subsidize power, heavy reliance on expensive fossil fuel imports, and added transmission cost because of the country’s archipelagic configuration have resulted in electricity prices being among the highest in the world. Thus, renewable energy projects present a viable business opportunity to resource developers.
The business community believes that the introduction of retail competition and open access is the logical move to bring the power industry to the next level and establish a competitive market structure. There is a need to further diversify the energy mix and the government is banking on renewable energy to wean the country from its dependence on fossil fuel. The government through the Renewable Energy Act of 2008 (“RE Act”) sought to address the issues on the absence of a ready and guaranteed market for the output of RE power plants and the recovery of investments through electricity tariffs.
Dr. Jan Carr, Strategic Advisor, International Initiatives, Gowlings International, spoke about renewable energy in Canada during the JPAC's public forum in Toronto on April 18. Find out more: http://www.cec.org/energy2012
Business case study of a utility scale wind project acquisition. Concepts include financial proforma modeling, due diligence, M&A, strategic analysis, wind energy, negotiation, utilities, wholesale power markets, and energy development.
DevOps and Testing slides at DASA ConnectKari Kakkonen
My and Rik Marselis slides at 30.5.2024 DASA Connect conference. We discuss about what is testing, then what is agile testing and finally what is Testing in DevOps. Finally we had lovely workshop with the participants trying to find out different ways to think about quality and testing in different parts of the DevOps infinity loop.
Accelerate your Kubernetes clusters with Varnish CachingThijs Feryn
A presentation about the usage and availability of Varnish on Kubernetes. This talk explores the capabilities of Varnish caching and shows how to use the Varnish Helm chart to deploy it to Kubernetes.
This presentation was delivered at K8SUG Singapore. See https://feryn.eu/presentations/accelerate-your-kubernetes-clusters-with-varnish-caching-k8sug-singapore-28-2024 for more details.
Essentials of Automations: Optimizing FME Workflows with ParametersSafe Software
Are you looking to streamline your workflows and boost your projects’ efficiency? Do you find yourself searching for ways to add flexibility and control over your FME workflows? If so, you’re in the right place.
Join us for an insightful dive into the world of FME parameters, a critical element in optimizing workflow efficiency. This webinar marks the beginning of our three-part “Essentials of Automation” series. This first webinar is designed to equip you with the knowledge and skills to utilize parameters effectively: enhancing the flexibility, maintainability, and user control of your FME projects.
Here’s what you’ll gain:
- Essentials of FME Parameters: Understand the pivotal role of parameters, including Reader/Writer, Transformer, User, and FME Flow categories. Discover how they are the key to unlocking automation and optimization within your workflows.
- Practical Applications in FME Form: Delve into key user parameter types including choice, connections, and file URLs. Allow users to control how a workflow runs, making your workflows more reusable. Learn to import values and deliver the best user experience for your workflows while enhancing accuracy.
- Optimization Strategies in FME Flow: Explore the creation and strategic deployment of parameters in FME Flow, including the use of deployment and geometry parameters, to maximize workflow efficiency.
- Pro Tips for Success: Gain insights on parameterizing connections and leveraging new features like Conditional Visibility for clarity and simplicity.
We’ll wrap up with a glimpse into future webinars, followed by a Q&A session to address your specific questions surrounding this topic.
Don’t miss this opportunity to elevate your FME expertise and drive your projects to new heights of efficiency.
Search and Society: Reimagining Information Access for Radical FuturesBhaskar Mitra
The field of Information retrieval (IR) is currently undergoing a transformative shift, at least partly due to the emerging applications of generative AI to information access. In this talk, we will deliberate on the sociotechnical implications of generative AI for information access. We will argue that there is both a critical necessity and an exciting opportunity for the IR community to re-center our research agendas on societal needs while dismantling the artificial separation between the work on fairness, accountability, transparency, and ethics in IR and the rest of IR research. Instead of adopting a reactionary strategy of trying to mitigate potential social harms from emerging technologies, the community should aim to proactively set the research agenda for the kinds of systems we should build inspired by diverse explicitly stated sociotechnical imaginaries. The sociotechnical imaginaries that underpin the design and development of information access technologies needs to be explicitly articulated, and we need to develop theories of change in context of these diverse perspectives. Our guiding future imaginaries must be informed by other academic fields, such as democratic theory and critical theory, and should be co-developed with social science scholars, legal scholars, civil rights and social justice activists, and artists, among others.
Key Trends Shaping the Future of Infrastructure.pdfCheryl Hung
Keynote at DIGIT West Expo, Glasgow on 29 May 2024.
Cheryl Hung, ochery.com
Sr Director, Infrastructure Ecosystem, Arm.
The key trends across hardware, cloud and open-source; exploring how these areas are likely to mature and develop over the short and long-term, and then considering how organisations can position themselves to adapt and thrive.
Neuro-symbolic is not enough, we need neuro-*semantic*Frank van Harmelen
Neuro-symbolic (NeSy) AI is on the rise. However, simply machine learning on just any symbolic structure is not sufficient to really harvest the gains of NeSy. These will only be gained when the symbolic structures have an actual semantics. I give an operational definition of semantics as “predictable inference”.
All of this illustrated with link prediction over knowledge graphs, but the argument is general.
"Impact of front-end architecture on development cost", Viktor TurskyiFwdays
I have heard many times that architecture is not important for the front-end. Also, many times I have seen how developers implement features on the front-end just following the standard rules for a framework and think that this is enough to successfully launch the project, and then the project fails. How to prevent this and what approach to choose? I have launched dozens of complex projects and during the talk we will analyze which approaches have worked for me and which have not.
State of ICS and IoT Cyber Threat Landscape Report 2024 previewPrayukth K V
The IoT and OT threat landscape report has been prepared by the Threat Research Team at Sectrio using data from Sectrio, cyber threat intelligence farming facilities spread across over 85 cities around the world. In addition, Sectrio also runs AI-based advanced threat and payload engagement facilities that serve as sinks to attract and engage sophisticated threat actors, and newer malware including new variants and latent threats that are at an earlier stage of development.
The latest edition of the OT/ICS and IoT security Threat Landscape Report 2024 also covers:
State of global ICS asset and network exposure
Sectoral targets and attacks as well as the cost of ransom
Global APT activity, AI usage, actor and tactic profiles, and implications
Rise in volumes of AI-powered cyberattacks
Major cyber events in 2024
Malware and malicious payload trends
Cyberattack types and targets
Vulnerability exploit attempts on CVEs
Attacks on counties – USA
Expansion of bot farms – how, where, and why
In-depth analysis of the cyber threat landscape across North America, South America, Europe, APAC, and the Middle East
Why are attacks on smart factories rising?
Cyber risk predictions
Axis of attacks – Europe
Systemic attacks in the Middle East
Download the full report from here:
https://sectrio.com/resources/ot-threat-landscape-reports/sectrio-releases-ot-ics-and-iot-security-threat-landscape-report-2024/
Transcript: Selling digital books in 2024: Insights from industry leaders - T...BookNet Canada
The publishing industry has been selling digital audiobooks and ebooks for over a decade and has found its groove. What’s changed? What has stayed the same? Where do we go from here? Join a group of leading sales peers from across the industry for a conversation about the lessons learned since the popularization of digital books, best practices, digital book supply chain management, and more.
Link to video recording: https://bnctechforum.ca/sessions/selling-digital-books-in-2024-insights-from-industry-leaders/
Presented by BookNet Canada on May 28, 2024, with support from the Department of Canadian Heritage.
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Ramesh Iyer
In today's fast-changing business world, Companies that adapt and embrace new ideas often need help to keep up with the competition. However, fostering a culture of innovation takes much work. It takes vision, leadership and willingness to take risks in the right proportion. Sachin Dev Duggal, co-founder of Builder.ai, has perfected the art of this balance, creating a company culture where creativity and growth are nurtured at each stage.
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
the economics of electricity in the Philippines
1. Economics of Electric Energy
IPPs, the PPA, and the Electric Power
Industry Reform Act
Patrick Cesar T. Ballesteros
Economics for Managers
ATENEO-REGIS MBA PROGRAM
2. What Happened?
҉In 1990, the Philippines was confronted with a crisis of
insufficient electrical generating capacity.
҉Metro Manila and the 33 provinces in Luzon power grid
experienced brownouts of up to 4 hours a day.
҉The root of the problem was the decision by Marcos regime
to build a 620 megawatt nuclear-power plant on the Bataan
Peninsula.
҉The Aquino government decided not to use the facility
mainly because it was located in a seismic fault.
҉As a result, a badly needed expansion of generating
capacity in Luzon, which accounted for 75% of national
electric consumption, did not come on line.
3. Cont..
҉ The then president Fidel V. Ramos acted upon the
situation and addresses the congress through his state of
the nation address to enact a law that would create an
energy department that would plan and manage the
Philippines’ energy demands.
҉ The congress responded by not only creating the
Department of Energy but also giving FVR emergency
powers to resolve the energy crisis.
҉ President Ramos eventually issued licenses to
Independent Power Producers (IPP) to construct power
plants in 24 months. He also issued supply contracts that
guaranteed the government would buy whatever power
the IPPs produced under the contract in U.S. dollars to
entice investments in power plants.
҉ This solved the power crisis and created a stable supply of
electricity in a growing & developing economy of the
Philippines.
4. Cont..
҉In 1997, the Asian Financial Crisis affected the
Philippines and other countries in Southeast
Asia.
҉This has led to closing of some companies which
created a surplus in electricity.
҉Also because of the crisis, Philippine Peso
devaluated rapidly leaving a great concern for
the contracts of IPPs.
5. Independent Power Producers
҉ An entity which is not a public
utility, which owns facilities that
generate electric power for sale to
utilities and end users.
҉ The National Power Corporation or NPC
secured the accreditation of more than
40 Independent Power Producers or
IPP contracts.
҉ The 1994 World Bank study notes that
the average price of some 13 projects it
analysed was 6.52 U.S.
cents/kWh, which the World Bank
conceded was quite high compared to
the 6.37 U.S. cent/kWh bulk energy
tariff of the NPC at that time.
6. Cont..
҉ IPPs were largely petroleum based, with lower installation costs
but higher fuel costs.
҉ Not only did the government throw out its energy mix program
of relying more on indigenous energy sources, the consumers
were subjected to high fuel price risks in imported petroleum
that consumers assumed through fuel adjustment clauses for
tariffs in the IPP contracts.
҉ There is likewise an exchange risk in pegging the wholesale
tariff to the dollar.
҉ The government and the consumers also assumed the market
risk through generous take or pay guarantees.
҉ In addition to the initial high cost of the IPPs, the Asian Crisis
also dramatically upset all the economic growth of the country
and foreign exchange assumptions of the IPPs.
҉ This meant much higher fuel costs and oversupply of electricity
capacity.
҉ investors are fully covered by the fuel cost adjustment
mechanism and take or pay guarantees for which end users are
now paying a heavy price.
7. Purchased Power Adjustments
Purchased power adjustment or PPA
represents the increase in the cost of power
purchased from the National Power
Corporation (NPC) and other suppliers or IPPs.
The PPA is a cost adjustment mechanism
approved by Energy Regulatory Commission
(ERC) to reflect changes in the cost of power
bought from NPC and IPPs.
8. Currency Exchange Rate Adjustment
Currency exchange rate adjustment or CERA is
another type of cost adjustment mechanism
approved by ERC. This aims to recover the
change in foreign denominated operating
costs and principal debts repayment due to
exchange rate movements.
9. Impact of PPA & CERA
҉ PPA and CERA are additional monthly costs being shoulder
over and above the daily consumption of electricity and
expenses to meet the needs of every member of the
family such as food and clothing, education, health and
transportation expenses, water and shelter.
҉ Everyone was affected by the imposition of PPA & CERA
҉ Generally electricity rates in the Philippines, with PPA
included, are higher compared to neighbouring nation.
҉ This makes investments in the Philippines hard to
materialize.
10. Supreme Court Intervention
The Supreme Court of the Philippines ruled to
compel distribution utilities like MERALCO to
refund its customers billions of Pesos
perceived to be PPA payments of its
consumers and to abide by the Court’s
decision with respect to payment of taxes
which formed part of the Company’s operating
expenses.
11. Republic Act 9136 Electric Power Industry Reform Act
҉ As the Philippines experience power outages enough to be
regarded as a national crisis, Ramos Administration turned
to private sectors for solutions.
҉ Using the 1987 Executive Order that allowed the private
sector to generate electricity, and by enacting a Build-
Operate-Transfer (BOT) law in infrastructure projects, the
government opened the floodgates for contracts with
private generation companies or Independent Power
Producers (IPP).
҉ After the onslaught of the Asian Financial Crisis, in 2001
Republic Act 9136 or the Electric Power Industry Reform
Act was signed in to law.
12. Section 2 of EPIRA declares the objective of the law
҉ To ensure and accelerate the total electrification of the country;
҉ To ensure the quality, reliability, security and affordability of the
supply of electric power;
҉ To ensure transparent and reasonable prices of electricity in a regime
of free and fair competition and full public accountability to achieve
greater operational and economic efficiency and enhance the
competitiveness of Philippine products in the global market;
҉ To enhance the inflow of private capital and broaden the ownership
base of the power generation, transmission and distribution sectors;
҉ To ensure fair and non-discriminatory treatment of public and private
sector entities in the process of restructuring the electric power
industry;
13. Cont..
҉ To protect the public interest as it is affected by the rates
and services of electric utilities and other providers of
electric power;
҉ To assure socially and environmentally compatible energy
sources and infrastructure;
҉ To promote the utilization of indigenous and new and
renewable energy resources in power generation in order
to reduce dependence on imported energy;
҉ To provide for an orderly and transparent privatization of
the assets and liabilities of the National Power Corporation
(NPC);
҉ To establish a strong and purely independent regulatory
body and system to ensure consumer protection and
enhance the competitive operation of the electricity
market; and
҉ To encourage the efficient use of energy and other
modalities of demand side management.
14.
15.
16. Unbundled
҉NPC’s generation and transmission functions were
unbundled.
҉National Transmission Corporation (TRANSCO) was
created to own and operate the transmission assets
and perform the transmission functions previously
under NPC.
҉A fully privatized corporation which is National Grid
Corporation of the Philippines took over TRANSCO’s
responsibilities.
҉The missionary electrification program is undertaken
by NPC through the Small Power Utilities Group
(SPUG)
҉PSALM Power Sector Assets and Liabilities
Management Corp. was created to liquidate the
assets and liabilities of NPC
17.
18. 5 Types of
Privatization
of the Power
Build-Operate- Divestiture (full
Industry Transfer (BOT) privatization)
contracts through asset sale
Corporatization of
Management
electric
contract
cooperatives
Concession
agreement
20. Status Report on EPIRA Implementation
Prepared by the Department of Energy, the most
recent is on it’s 18th edition covered the month of
November 2010 to April 2011. It serves as a
summary update of particular developments in
pursuit of the Government to restructure and
privatize the power sector.
21. Privatization
҉The 18th status report stated that the activities
in the privatization of NPC/PSALM generating
assets and IPP contracts were deferred with the
new administration’s call for a review of the
Privatization Plan and the need to address the
seasonal supply interruptions.
҉Also stated in the status report are the
developments on PSALM’s continuing activity
for the completion of the remaining
legal, financial and technical requirements for
the smooth turn-over of the privatized power
plants and IPP contracts as follows:
29. Lifeline Subsidy Program
kWh Consumption Bracket Lifeline Discount
0 – 20 kWh per month 100%
21 – 50 kWh per month 50%
51 – 70 kWh per month 35%
71 – 100 kWh per month 20%
30. Electrification
Barangay Electrification Status as of 31May 2011
Region Potential Electrified Barangays Unelectrified Barangays Electrification Level (%)
Barangays
CAR 1,176 1,176 0 100.00%
I 3,265 3,265 0 100.00%
II 2,311 2,311 0 100.00%
III 3,102 3,102 0 100.00%
IV-A 4,010 3,983 27 99.33%
IV-B 1,458 1,458 0 100.00%
V 3,469 3,469 0 100.00%
NCR 1,695 1,695 0 100.00%
SUB-TOTAL 2,0486 2,0459 27 99.87%
LUZON
VI 4,050 4,050 0 100.00%
VII 3,003 3,003 0 100.00%
VIII 4,389 4,389 0 100.00%
SUB-TOTAL 11,442 11,442 0 100.00%
VISAYAS
IX 1,904 1,904 0 100.00%
X 2,020 2,020 0 100.00%
XI 1,160 1,160 0 100.00%
XII 1,194 1,194 0 100.00%
CARAGA 1,310 1,310 0 100.00%
ARMM 2,459 2,441 18 99.27%
SUB-TOTAL 1,0047 1,0029 18 99.82%
MINDANAO
TOTAL 41,975 41,930 45 99.89%
PHILIPPINES
31. “Our Company’s gain will be the Philippines
as well, borne by MERALCOs intrinsic role as
a major contributor to nation building”
Manuel M. Lopez
MERALCO Chairman
The End