SlideShare a Scribd company logo
Case Study of Regulatory
Asset build up in Delhi and
the best possible way for its
amortization
A presentation by,
Amit Kumar
NPTI
MBA 14th Batch
What is a regulatory asset?
 By definition, regulatory assets include previously-incurred losses that are in the nature of
deferred expenditure and that can be recovered from consumers in future provided allowed by
regulatory authorities. It is also can be termed as the revenue gaps which have been carried over by
utility companies over a period of time.
 For fear of a consumer backlash and/or to avoid the required retail tariff increases, the revenue
recovery although recognized, is deferred for the future.
 Accumulated RAs have a considerable impact across 15 distribution utilities, more serious &
essentially confined to about 8 States in India.
 This effects the ability of the distribution utilities to raise commercial debt in the market, as their
balance sheets get compromised on account of building up its RAs.
 Lack of fresh investments for improving the network and the service standards, result in poor
Quality of service for the customer as highlighted by recent instances of outages and power cuts by
several discoms.
National Tariff Policy in view of regulatory assets
The facility of a regulatory asset has been adopted by some Regulatory Commissions in the past to
limit tariff impact in a particular year. This should be done only as exception, and subject to the
following guidelines:
 The circumstances should be clearly defined through regulations, and should only include
natural causes or force majeure conditions. Under business as usual conditions, the opening
balances of uncovered gap must be covered through transition financing arrangement or capital
restructuring;
 Carrying cost of Regulatory Asset should be allowed to the utilities;
 Recovery of Regulatory Asset should be time-bound and within a period not exceeding three
years at the most and preferably within control period;
 The use of the facility of Regulatory Asset should not be repetitive.
 In cases where regulatory asset is proposed to be adopted, it should be ensured that the return
on equity should not become unreasonably low in any year so that the capability of the licensee
to borrow is not adversely affected.
Situation in New Delhi
 The three private Discoms namely Tata Power Delhi Distribution Ltd, BSES Rajdhani Pvt. Ltd. and
BSES Yamuna Pvt. Ltd have a massive regulatory asset of around 16,000-20,000 crores.
 The State Govt. also pulled the plug on financial aid from 2003 onwards leaving the Discoms on
their own.
 Rising fuel costs and lack of cost reflective tariffs have worsened the situation. The DERC has
disallowed tariff hikes and costs to the Discoms on multiple occasions.
 Since 2003 the power purchase costs have spiked by up to 300% but the consumer tariffs have
only increased by up to 90%.
 Delhi Discoms are tied up in costly Power Purchase Agreements with inefficient State and Central
generating stations with no exit clause. As a result, the Discoms are forced to buy ‘costly’ power
from these stations without any alternatives.
Regulatory Assets of Delhi Discoms
FY 2013-
14
FY 2014-
15
FY 2015-16
(Surplus
Projected)
Total
Regulatory
assets till date
BRPL 5105.28 407.05 78.27 5434.06
BYPL 3051.19 173.25 174.84 3049.6
TPDDL 3351.48 268.84 326.11 3294.21
Total 11777.87
*As approved by DERC
Regulatory asset build up and its impact
 Current tariff rates don’t cover current costs.
 DISCOMS claim that the actual RA buildup is around Rs. 22,000 Crs.
 Only Rs. 10,000 worth of regulatory asset is recognized till date.
Particulars Amount (In Cr.)
RA recognized by DERC upto FY
12-13
9,811
ATE judgments yet to be
implemented
5,824
Revenue gap during FY 13-14 4,030
Carrying cost till FY 14-15 3,015
Total revenue gap upto FY 2015-
16
22,680
Regulatory assets in different states
States
Total regulatory assets till date (In
Rs. Crs)
Tamil Nadu 24,642
Rajasthan 36,039.89
Odisha 3,450.06
Uttar Pradesh 20,261.1
West Bengal 8,895.32
Jharkhand 6,154.65
* This data has been sourced from the tariff orders of various SERC’s
Causes behind the build up of regulatory assets
 Costly long term PPA’s
 Non cost reflective tariffs.
 Inadequate PPAC formula.
 Loss on account of sale of surplus power.
 Issues with the State electricity regulatory commissions.
 Inadequate carrying cost rates.
 Inadequate surcharge rate of 8% levied from consumers.
 Absence of any clear plan to amortize the regulatory assets.
 Difference between subsides booked and subsidy realized.
Costly long term PPA’s
 Delhi discoms are tied up with the PPA’s which were
signed during the tenure of DVB.
 Many of the generating stations in the existing PPA have
outlived there useful life and thus have become highly
inefficient.
 In addition to the above, Delhi Discoms are burdened
with costly gas based plants such as Bawana, GT and
Pragati which are showing unprecedented high costs on
account of limited availability of gas for the past 2-3
years.
 Use of foreign coal by generators.
 Retail Supply Tariff has changed from Rs
4.3/unit to Rs 7.18/unit, thereby showing an
increase of about 70%.
 On the other hand Bulk supply tariff has shown
an increase of 162.67% in the period of 2007-08
t0 2014-15 i.e Rs 2.09/unit to Rs. 5.49/unit.
1.5
1.6
1.3 1.3
1.7
0.8
2.3
3.2
2.4
2.3
3
2.9
0
0.5
1
1.5
2
2.5
3
3.5
Dadri Gas BTPS Anta Auraiya Gas
Turbine
Dulhasti
Hydro
Rs/Kwh
Change in Variable Cost
2007-08 2014-15
Barriers in the reduction of high cost
power
 PPA is legal Document enforceable by Law.
 No Exit Clause in PPAs
 No off-takers for costly power for reallocation by MoP, GoI.
 Limitations in Backing Down of Plants- 70% to 75%.
 Forced scheduling of Gencos by SLDC due to Transmission
constraints.
 Loss on Sale of Surplus Power.
Power Purchase cost from various sources
Pragati 3-Bawana Aravali Jhajjar Dulhasti Sewa-2 Gas Turbine Dhauliganga Dadri gas
Power Purchase Cost 5.84 6.93 6.87 5.68 6.15 7.31 5.16
Current Market price 4.4 4.4 4.4 4.4 4.4 4.4 4.4
Power Exchange 3.4 3.4 3.4 3.4 3.4 3.4 3.4
UI rate 3.48 3.48 3.48 3.48 3.48 3.48 3.48
0
1
2
3
4
5
6
7
8
RateinRs/Unit
Power Purchase Cost from various sources
Power Purchase Cost Current Market price Power Exchange UI rate
Non-cost reflective tariffs
 Over the years Delhi Discoms have proposed tariff hikes in consecutive tariff petitions in order to
cover for the spiking PPAC charges. DERC did approve some of the hikes but not fully and from
December 2014, no tariff hike was granted.
FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16
Particulars Proposed
Tariff
Approved
Tariff
Proposed
Tariff
Approved
Tariff
Proposed
Tariff
Approved
Tariff
Proposed
Tariff
Approved
Tariff
Above 66/33
kV level
6.20 4.71 6.27 4.92 6.57 5.61 6.31 5.61
At 11kv level 6.27 4.76 6.34 5.02 6.64 5.72 6.38 5.72
At LT level 8.04 5.69 7.87 5.88 8.19 6.65 7.90 6.65
Difference between Bulk supply tariff and Retail
Supply tariff
*We can see that the bulk power cost has increased by 142.73% while retail tariff has gone up by only
74.11% leading to a huge mismatch of costs.
2.41
4.25
2.68
4.34
3.43
4.344.3 4.37
5.38
4.9
5.37
6.22
5.36
7.06
5.85
7.4
0
1
2
3
4
5
6
7
8
Bulk Supply Tariff Retail Supply Tariff
TariffRates(Rs/unit)
Years
Differences between Bulk Supply Tariff and Retail Supply Tariff
FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015
Inadequate PPAC formula
 Discoms in Delhi have been asking for a change in the PPAC formula, as the existing formula does not
takes into account the variations in term of short term power purchase transactions.
 A PPAC surcharge is levied from the consumers to compensate the utilities for the fluctuations in fuel
rates, transmission charges etc.
 This cost is funded by the Discoms alone and is purely revenue gap which will attract at least two years
of carrying cost.
 A consultant, appointed by GoNCTD to look into the matters related to the operational issues of Delhi
Discoms, has suggested a change in the PPAC formula which will reflect the changes in the fuel cost on
a monthly basis.
 It said that the existing formula used by DERC, does not recognize cost on account of arrears payable to
the GENCOS or TRANSCOS. This formula also does not covers losses on account of sale of surplus
power.
 In FY 2015-16 DERC allowed the Discoms to levy PPAC surcharge from the consumers for the
remaining three quarters, but this order lapsed in March 2016 due to delay in filing of tariff petitions.
Losses on account of sale of surplus power
 DERC has fixed a base rate of Rs. 4/unit for the sale of surplus power.
 However the Discoms have been unable to dispose off surplus power at such rate as the power
exchange rates and UI rates are much lower compared to the base rate.
 DERC has said that the Discoms (especially BYPL), instead of making serious efforts to sell power in
power exchanges or get into banking transactions with other states, have sold much of their power in
UI exchanges.
 The UI rates are very low compared to other rates, which has led to substantial losses for the Discoms.
 It has been alleged that the discoms are buying 'excess' power and selling it at a low price, thereby
booking huge losses which leads to unwarranted tariff burden on consumers.
 DERC must be realistic while fixing the base rate for the sale of surplus power, while DISCOMS must
put an all out effort to sell surplus power at the best rates possible.
 The demand projection of New Delhi is also highly unpredictable, leading to confusion while buying
power. It is very difficult to clearly determine the load curve for Delhi.
Electricity rates Rs/unit
UI rate 1.78
Average power purchase rate 3.78
IEX rate 2.31
Inadequate carrying cost
 A carrying cost is the rate of interest allowed on the regulatory asset being carried
over to the subsequent fiscal years.
 It is comprised of two components, return on equity and return on debt.
 RoE is 16% , while the cost of debt should be on par with the SBI PLR rate.
 However, DERC allows change in the cost of debt, only when the deviation in the
SBI PLR is more than 1%.
 Due to this, the DISCOMS are not able to get proper returns as per market
scenarios.
 Disallowance of adequate carrying costs has artificially discounted the revenue
gap by 182 crore.
 Formula for calculating the carrying cost rate= (70 x PLR rate + 30 x
RoE Rate)
Comparison between SBI PLR rates
and DERC approved rates
12.69 12.79
11.78
12.26
14.4 14.61 14.58
14.05
10.9
11.38 11.33 11.64
12.45
9.54 9.34 9.27
0
2
4
6
8
10
12
14
16
FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15
Comparison between SBI PLR rates and the cost on debt allowed by DERC
SBI PLR Rates (%) Cost of Debt allowed by DERC (%)
Inadequate surcharge rate
 From 2012, DERC allowed the Discoms to levy 8% surcharge rate from the
consumers in Delhi. This surcharge was to be charged against the total payable
amount, mentioned in the electricity bill.
 This surcharge rate is supposed to compensate the Discoms for the carrying
cost being charged on the regulatory assets.
 This surcharge rate needs continuous revision every year in order to
compensate the Discoms for the losses incurred on account of power purchase.
 While the carrying costs are decided at the rates of 14-15% p.a. it is strange that
the surcharge rate allowed is merely 8%.
 Hon’ble ATE judgment dated 01/01/2011 clearly mandates that the rate of
carrying cost should be fixed at such rate so that the Discoms can not only
recover the carrying cost on the RA for the current year but also it should be
able to recover 1/3rd of the principle amount.
Sample electricity bill showing surcharge rate
Absence of any clear plan to amortize the regulatory
assets
 Discoms have repeatedly asked DERC to provide a clear roadmap for the amortization
of regulatory assets.
 Delhi discoms are private entities which makes them non-eligible for the benefits
from financial assistance plans such as FRP 2012 and UDAY.
 The discoms cite their inability to pay the power purchase bills due to huge financial
stress. The primary losers is the general public of New Delhi who are constantly under
the threat of intermittent load shedding and impending blackouts.
 The amount of regulatory assets has risen to such alarming levels that every electricity
consumer in Delhi owes the Discoms around Rs. 20,000.
 The Delhi Govt. withdrew the financial support in 2003 which was meant for the
aiding the discoms.
 Apart from 8% surcharge rate, there is no other provision from DERC to liquidate the
regulatory assets.
Delay in filing of tariff petitions and
issuance of tariff orders
 Timely filing of tariff petitions and timely issuance of tariff orders help
in saving of costly capital.
 Until March 2016, none of the Delhi Discoms have filed their tariff
petitions for 2016-17.
 The reason being stated is that DERC has failed to come up with new
MYT regulations for 2016-17, due to which the Discoms are hesitant to
file tariff petitions.
 Due to this delay, Delhi Discoms won’t be able to levy fuel surcharge
from consumers which was allowed last year by DERC.
 The Delhi Electricity Regulatory Commission (DERC) had allowed
power discoms to levy PPAC surcharge following a directive from the
Appellate Tribunal for Electricity (APTEL) since June 15, 2015.
Measures taken up by other states to liquidate
regulatory assets
1. Tamil Nadu : Subsidy Package of Rs. 6879.33 and Govt. takeover of the revenue gap
 2. Rajasthan : Tariff hike in 2014-15 and Govt. approval to join UDAY scheme.
3. Jharkhand : Joined UDAY scheme in January 2016 to mitigate losses of around Rs.
7353 crores
4. Odisha : Has regulatory assets worth Rs 3,450 crores and is considering joining
UDAY scheme via it’s bulk power purchaser GRIDCO.
5. Haryana : Tariff hikes in 2014-15 and 2015-16 and the state Govt. will take over a
total debt of around Rs. 25,000 crores under the UDAY scheme.
International Practices-Brazil
 Low amounts of rainfall resulted in a severe shortage of electricity in
2000-01, as the country depends on hydroelectric power for more than
70% of its electricity needs.
 This led the Govt. to resort to power rationing and systematic
blackouts all over the country.
 However due to these power rationing measures, the power producers
and other electrical utilities faced huge financial losses.
 In order to reimburse the utilities for their losses, Govt. introduced
several surcharges and tariff increases in electricity rates.
 These surcharges and tariff increments were set for a period of 7-8
years and it was assumed that the utilities would recover their costs in
this period (till 2008).
International Practices-Canada
 Any losses incurred to the utilities on account of
uncontrollable costs are recovered from the
consumers in the form of rate riders.
 These rate riders are allowed on a regular basis
and hence the problem of regulatory assets is
nullified.
 A rate rider is a temporary credit or charge that
is added to the bill on behalf of the electricity or
gas distributor. A rate rider collects or refunds
the difference between actual and estimated
costs for delivering energy.
 Electricity and gas distribution companies in
Canada use rate riders to adjust any differences
between the actual cost and the approved rate
for providing service. in India become as pro-
active as those in Canada, then the utilities
won’t be saddled with ever increasing debts and
deferred costs.
Conclusion
 Cost reflective tariffs are a must for covering losses on account of fuel price change.
 Annual tariff revisions must be done to prevent the regulatory assets from further build-up.
 8% surcharge, which is levied from consumers, needs further increment. The amount of surcharge is
not enough to meet the carrying costs for the regulatory assets. DERC must take a view of this issue
and solve it.
 The carrying cost which is allowed by the commission on the regulatory assets needs to be updated
regularly as per current SBI PLR rates.
 Need for revising costly PPAs and surrendering the allocation from costly and inefficient plants.
However, surrendering costly power all at once is not a feasible solution as it will leave a number of
power plants stranded due to lack of customers. Instead the surrendering should be done in a phase-
wise manner, so that the Govt. can reallocate those power plants to other interested buyers.
 Discoms must make a serious effort towards sale of surplus power via banking and power exchanges.
They must deter from dumping surplus power via UI channel as much as possible.
 DERC should come up with an amicable solution to amortize the regulatory assets. The longer this
process is delayed, the higher stress the companies will face financially.
Recommendations
 Govt. reimburses the consumer to compensate for the
impact of tariff hikes
 LPG subsidy reimbursement model can also be tried for the consumers in Delhi. Since Delhi has a high
literacy rate and maximum people have bank accounts too, this plan can be implemented without much
hassle.
 Govt. should target consumers with low income or such consumers who will be hit hard most due to tariff
hikes. These people could be provided with subsidy directly in their bank accounts. If not fully, then the
consumers could be partially reimbursed (say ~60-70%) for the hike in the tariff rates.
 Industrial consumers, consumers with high consumption and those consumers whose income is good
enough to bear the brunt of tariff shocks, should be exempted from the subsidy scheme.
 Also subsidy could be provided to those consumers also who manage to bring their consumption rates
below a certain limit. Subsidy rates for these people could be different from what is being provided to low
income consumers.
 This scheme could be a win-win scenario for both consumers and Discoms as consumers will be fully or
partially saved from tariff shock and Discoms would be compensated for their losses.
 This scheme could be implemented in a time frame of 4-5 years and tariff also should be increased
gradually in this period. Also the suggestions proposed in previous slide should also be implemented
along with this plan (minus the loans from PFC & REC). This will help in not putting the whole burden on
the Govt. and letting the Discoms share the responsibility too.
Recommendations
 Loan from Power Finance Corp. or any other Govt. financing institution
 Loan can be provided by any of the above given financial bodies.
 A time period of 7-8 years should be set as a target to amortize the regulatory assets.
 Interest rate on loans should be less than prevailing market rates, say around 10%.
 The loan component can cover around 50-60% of the regulatory assets.
 Delhi Govt. or the Central Govt. can take guarantee for 50% of the loan amount.
 2 years of moratorium period can be provided on the loan.
 After the moratorium period, discoms can start paying back the loan along with interest.
 For the remaining half of regulatory assets, the following measures could be taken:
- Increment of fixed charges which is to be levied from every consumers. As new MYT regulations are coming up,
so this provision could be made in the MYT order.
- Very moderate tariff hikes in this time period. (~ Rs. 1-1.5/unit)
- Benefits from the reduced Bulk supply rates due to falling fuel prices to be utilized for this purpose.
- Adequate revision in surcharge rate is required every year (10-12%).
- Funds released after conclusion of pending APTEL judgment (Rs. 5,824 Cr as claimed by BSES) could be
diverted towards towards this purpose. Speedy completion of pending APTEL judgments.
 For this method to work, DERC and the discoms must ensure that there are no future revenue gaps and regular tariff
revisions should happen.
Recommendations
 Discoms get approval from the Govt. to join the UDAY scheme
 As per current norms a private utility is not eligible to join UDAY scheme.
 Delhi Discoms being private companies thereby cannot join UDAY, and they are on the verge of missing
out on a good opportunity to solve their financial woes.
 Under the UDAY Scheme two steps could be taken:
 - Issuance of tax free bonds repayable in 10 years for 50% of regulatory assets (approx. Rs. 12,500 Cr)
 - Arrange loan for 25% of regulatory assets at Base lending rate. The impact on tariff due to issuance of
Tax-free bonds at lower rate of interest of 8% per annum would be:
Scenario Impact on tariff (Rs./unit)
Tax-free bonds repayable from
10th year onwards
0.50
Benchmark Prime lending rate 0.25
Recommendations (Contd…)
Our Hon’ble Power minister has recently stated that his ministry is looking into making a case for
private utilities to join the UDAY. But those companies will not get any financial benefits from UDAY
scheme. Instead they will stand to benefit from the operational grants and schemes covered under the
UDAY scheme which are as follows:
 Reduction in fuel cost through coal swapping.
 Time bound loss reduction trajectory. Although it must be noted that Delhi discoms have done a
commendable job at bringing down the loss levels in these years.
 This scheme also provides for quarterly fuel cost adjustment.
 Annual tariff revisions has been highly recommended in the UDAY scheme.
 Grants for the strengthening of distribution network and infrastructure will be covered under the
IPDS scheme.
 Compulsory smart metering and AMR infrastructure to reduce losses. Funds will be granted under
the IPDS scheme.
 IT enablement of distribution system.
 Recently Ministry of Power has agreed to fund the project for removal of old wires and replacing
them with new underground cables in the area of Old Delhi region. This will be covered under the
IPDS scheme.
Bibliography
 Energy.economictimes.com
 BYPL Tariff orders 2010-11 to 2015-16.
 Financialexpress.com
 Tariff orders of Haryana, Rajasthan, Jharkhand, Orissa and Tamil Nadu.
 PFC reports on financial status of discoms.
 Report on the problem of regulatory assets by Forum of Regulators.
THE END

More Related Content

What's hot

Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
Alok Ghildiyal
 
Ancillary Service market
Ancillary Service marketAncillary Service market
Ancillary Service marketIPPAI
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
Mahim Srivastava
 
Solar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar MissionSolar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar Mission
HIMADRI BANERJI
 
NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)
Ravi Pohani
 
Availability based tariff
Availability based tariffAvailability based tariff
Availability based tariff
Power grid corporation of india limited
 
Power trading
Power tradingPower trading
Energy scenario in india
Energy scenario  in indiaEnergy scenario  in india
Energy scenario in india
rameshss
 
Policies for smart grid
Policies for smart gridPolicies for smart grid
Policies for smart grid
Ashfaq khan
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
PSPCL
 
Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In GridTejaswi Shukla
 
Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in indiaAnkur Mahajan
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulations
Akshat Goel
 
Open access
Open accessOpen access
Open access
Jay Ranvir
 
Abt meter
Abt meterAbt meter
Abt meter
Jay Ranvir
 
Government Solar and Net Metering Policies
Government Solar and Net Metering PoliciesGovernment Solar and Net Metering Policies
Government Solar and Net Metering Policies
Neha Barangali SolarQuarter and E-Mobility Plus
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
Mustafa Sonasath
 
Tariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulationTariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulation
Sushant Kumar Sinha
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
Spark Network
 

What's hot (20)

Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
Cerc Deviation Settlement Mechanism ( DSM ) 4th ammendment Summary wef 01/01/...
 
Ancillary Service market
Ancillary Service marketAncillary Service market
Ancillary Service market
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
 
Solar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar MissionSolar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar Mission
 
NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)
 
Availability based tariff
Availability based tariffAvailability based tariff
Availability based tariff
 
Power trading
Power tradingPower trading
Power trading
 
Energy scenario in india
Energy scenario  in indiaEnergy scenario  in india
Energy scenario in india
 
Policies for smart grid
Policies for smart gridPolicies for smart grid
Policies for smart grid
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
 
Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In Grid
 
Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in india
 
Electricity laws and regulations
Electricity laws and regulationsElectricity laws and regulations
Electricity laws and regulations
 
Open access
Open accessOpen access
Open access
 
Abt meter
Abt meterAbt meter
Abt meter
 
Microgrid
MicrogridMicrogrid
Microgrid
 
Government Solar and Net Metering Policies
Government Solar and Net Metering PoliciesGovernment Solar and Net Metering Policies
Government Solar and Net Metering Policies
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
 
Tariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulationTariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulation
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
 

Similar to What is a regulatory asset

Tariff and Financial issues impacting Delhi Discom’s and Delhi consumers
Tariff and Financial issues impacting Delhi Discom’s and Delhi consumersTariff and Financial issues impacting Delhi Discom’s and Delhi consumers
Tariff and Financial issues impacting Delhi Discom’s and Delhi consumers
Tata Power Delhi Distribution Limited
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
 
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in DelhiFAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
Tata Power Delhi Distribution Limited
 
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
Divyesh Kumar
 
Esci rec presentation 13 feb 2013
Esci rec presentation   13 feb 2013Esci rec presentation   13 feb 2013
Esci rec presentation 13 feb 2013Sandeep Melana
 
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
Private Consultants
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptx
msounak95
 
Utility Distribution Franchisee Business in India
Utility Distribution Franchisee Business in IndiaUtility Distribution Franchisee Business in India
Utility Distribution Franchisee Business in India
Abhisek Bhattacharya
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
IPPAI
 
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013Mekhala Leelasagar
 
Recharging the-power-sector
Recharging the-power-sectorRecharging the-power-sector
Recharging the-power-sector
L&C
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
Manish Ranjan
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
 
Innovative Ratemaking- Multiyear Rate Plans
Innovative Ratemaking- Multiyear Rate Plans Innovative Ratemaking- Multiyear Rate Plans
Innovative Ratemaking- Multiyear Rate Plans
ScottMadden, Inc.
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGRAVI PAL SINGH
 
Nepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptxNepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptx
ssuserfbc60b
 
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement CostsFAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
Tata Power Delhi Distribution Limited
 
Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
msounak95
 

Similar to What is a regulatory asset (20)

Tariff and Financial issues impacting Delhi Discom’s and Delhi consumers
Tariff and Financial issues impacting Delhi Discom’s and Delhi consumersTariff and Financial issues impacting Delhi Discom’s and Delhi consumers
Tariff and Financial issues impacting Delhi Discom’s and Delhi consumers
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012
 
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in DelhiFAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
FAQ’s Sl. No. 1 : Tata Power-DDL’s power distribution operations in Delhi
 
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
Systems Analysis for Tata Power Corporation’s (TPC) distribution business in ...
 
Esci rec presentation 13 feb 2013
Esci rec presentation   13 feb 2013Esci rec presentation   13 feb 2013
Esci rec presentation 13 feb 2013
 
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
Mobilizing Renewable Energy to Overcome the Energy and Financial Crisis: The ...
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptx
 
Utility Distribution Franchisee Business in India
Utility Distribution Franchisee Business in IndiaUtility Distribution Franchisee Business in India
Utility Distribution Franchisee Business in India
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013
Credit outlook for India’s Wind Power Producers Remains Stable’-09-02-2013
 
Ppt nep n ntp
Ppt nep n ntpPpt nep n ntp
Ppt nep n ntp
 
Recharging the-power-sector
Recharging the-power-sectorRecharging the-power-sector
Recharging the-power-sector
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
 
Innovative Ratemaking- Multiyear Rate Plans
Innovative Ratemaking- Multiyear Rate Plans Innovative Ratemaking- Multiyear Rate Plans
Innovative Ratemaking- Multiyear Rate Plans
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
 
Nepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptxNepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptx
 
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement CostsFAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
 
Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
 

What is a regulatory asset

  • 1. Case Study of Regulatory Asset build up in Delhi and the best possible way for its amortization A presentation by, Amit Kumar NPTI MBA 14th Batch
  • 2. What is a regulatory asset?  By definition, regulatory assets include previously-incurred losses that are in the nature of deferred expenditure and that can be recovered from consumers in future provided allowed by regulatory authorities. It is also can be termed as the revenue gaps which have been carried over by utility companies over a period of time.  For fear of a consumer backlash and/or to avoid the required retail tariff increases, the revenue recovery although recognized, is deferred for the future.  Accumulated RAs have a considerable impact across 15 distribution utilities, more serious & essentially confined to about 8 States in India.  This effects the ability of the distribution utilities to raise commercial debt in the market, as their balance sheets get compromised on account of building up its RAs.  Lack of fresh investments for improving the network and the service standards, result in poor Quality of service for the customer as highlighted by recent instances of outages and power cuts by several discoms.
  • 3. National Tariff Policy in view of regulatory assets The facility of a regulatory asset has been adopted by some Regulatory Commissions in the past to limit tariff impact in a particular year. This should be done only as exception, and subject to the following guidelines:  The circumstances should be clearly defined through regulations, and should only include natural causes or force majeure conditions. Under business as usual conditions, the opening balances of uncovered gap must be covered through transition financing arrangement or capital restructuring;  Carrying cost of Regulatory Asset should be allowed to the utilities;  Recovery of Regulatory Asset should be time-bound and within a period not exceeding three years at the most and preferably within control period;  The use of the facility of Regulatory Asset should not be repetitive.  In cases where regulatory asset is proposed to be adopted, it should be ensured that the return on equity should not become unreasonably low in any year so that the capability of the licensee to borrow is not adversely affected.
  • 4. Situation in New Delhi  The three private Discoms namely Tata Power Delhi Distribution Ltd, BSES Rajdhani Pvt. Ltd. and BSES Yamuna Pvt. Ltd have a massive regulatory asset of around 16,000-20,000 crores.  The State Govt. also pulled the plug on financial aid from 2003 onwards leaving the Discoms on their own.  Rising fuel costs and lack of cost reflective tariffs have worsened the situation. The DERC has disallowed tariff hikes and costs to the Discoms on multiple occasions.  Since 2003 the power purchase costs have spiked by up to 300% but the consumer tariffs have only increased by up to 90%.  Delhi Discoms are tied up in costly Power Purchase Agreements with inefficient State and Central generating stations with no exit clause. As a result, the Discoms are forced to buy ‘costly’ power from these stations without any alternatives.
  • 5. Regulatory Assets of Delhi Discoms FY 2013- 14 FY 2014- 15 FY 2015-16 (Surplus Projected) Total Regulatory assets till date BRPL 5105.28 407.05 78.27 5434.06 BYPL 3051.19 173.25 174.84 3049.6 TPDDL 3351.48 268.84 326.11 3294.21 Total 11777.87 *As approved by DERC
  • 6. Regulatory asset build up and its impact  Current tariff rates don’t cover current costs.  DISCOMS claim that the actual RA buildup is around Rs. 22,000 Crs.  Only Rs. 10,000 worth of regulatory asset is recognized till date. Particulars Amount (In Cr.) RA recognized by DERC upto FY 12-13 9,811 ATE judgments yet to be implemented 5,824 Revenue gap during FY 13-14 4,030 Carrying cost till FY 14-15 3,015 Total revenue gap upto FY 2015- 16 22,680
  • 7. Regulatory assets in different states States Total regulatory assets till date (In Rs. Crs) Tamil Nadu 24,642 Rajasthan 36,039.89 Odisha 3,450.06 Uttar Pradesh 20,261.1 West Bengal 8,895.32 Jharkhand 6,154.65 * This data has been sourced from the tariff orders of various SERC’s
  • 8. Causes behind the build up of regulatory assets  Costly long term PPA’s  Non cost reflective tariffs.  Inadequate PPAC formula.  Loss on account of sale of surplus power.  Issues with the State electricity regulatory commissions.  Inadequate carrying cost rates.  Inadequate surcharge rate of 8% levied from consumers.  Absence of any clear plan to amortize the regulatory assets.  Difference between subsides booked and subsidy realized.
  • 9. Costly long term PPA’s  Delhi discoms are tied up with the PPA’s which were signed during the tenure of DVB.  Many of the generating stations in the existing PPA have outlived there useful life and thus have become highly inefficient.  In addition to the above, Delhi Discoms are burdened with costly gas based plants such as Bawana, GT and Pragati which are showing unprecedented high costs on account of limited availability of gas for the past 2-3 years.  Use of foreign coal by generators.  Retail Supply Tariff has changed from Rs 4.3/unit to Rs 7.18/unit, thereby showing an increase of about 70%.  On the other hand Bulk supply tariff has shown an increase of 162.67% in the period of 2007-08 t0 2014-15 i.e Rs 2.09/unit to Rs. 5.49/unit. 1.5 1.6 1.3 1.3 1.7 0.8 2.3 3.2 2.4 2.3 3 2.9 0 0.5 1 1.5 2 2.5 3 3.5 Dadri Gas BTPS Anta Auraiya Gas Turbine Dulhasti Hydro Rs/Kwh Change in Variable Cost 2007-08 2014-15
  • 10. Barriers in the reduction of high cost power  PPA is legal Document enforceable by Law.  No Exit Clause in PPAs  No off-takers for costly power for reallocation by MoP, GoI.  Limitations in Backing Down of Plants- 70% to 75%.  Forced scheduling of Gencos by SLDC due to Transmission constraints.  Loss on Sale of Surplus Power.
  • 11. Power Purchase cost from various sources Pragati 3-Bawana Aravali Jhajjar Dulhasti Sewa-2 Gas Turbine Dhauliganga Dadri gas Power Purchase Cost 5.84 6.93 6.87 5.68 6.15 7.31 5.16 Current Market price 4.4 4.4 4.4 4.4 4.4 4.4 4.4 Power Exchange 3.4 3.4 3.4 3.4 3.4 3.4 3.4 UI rate 3.48 3.48 3.48 3.48 3.48 3.48 3.48 0 1 2 3 4 5 6 7 8 RateinRs/Unit Power Purchase Cost from various sources Power Purchase Cost Current Market price Power Exchange UI rate
  • 12. Non-cost reflective tariffs  Over the years Delhi Discoms have proposed tariff hikes in consecutive tariff petitions in order to cover for the spiking PPAC charges. DERC did approve some of the hikes but not fully and from December 2014, no tariff hike was granted. FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 Particulars Proposed Tariff Approved Tariff Proposed Tariff Approved Tariff Proposed Tariff Approved Tariff Proposed Tariff Approved Tariff Above 66/33 kV level 6.20 4.71 6.27 4.92 6.57 5.61 6.31 5.61 At 11kv level 6.27 4.76 6.34 5.02 6.64 5.72 6.38 5.72 At LT level 8.04 5.69 7.87 5.88 8.19 6.65 7.90 6.65
  • 13. Difference between Bulk supply tariff and Retail Supply tariff *We can see that the bulk power cost has increased by 142.73% while retail tariff has gone up by only 74.11% leading to a huge mismatch of costs. 2.41 4.25 2.68 4.34 3.43 4.344.3 4.37 5.38 4.9 5.37 6.22 5.36 7.06 5.85 7.4 0 1 2 3 4 5 6 7 8 Bulk Supply Tariff Retail Supply Tariff TariffRates(Rs/unit) Years Differences between Bulk Supply Tariff and Retail Supply Tariff FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015
  • 14. Inadequate PPAC formula  Discoms in Delhi have been asking for a change in the PPAC formula, as the existing formula does not takes into account the variations in term of short term power purchase transactions.  A PPAC surcharge is levied from the consumers to compensate the utilities for the fluctuations in fuel rates, transmission charges etc.  This cost is funded by the Discoms alone and is purely revenue gap which will attract at least two years of carrying cost.  A consultant, appointed by GoNCTD to look into the matters related to the operational issues of Delhi Discoms, has suggested a change in the PPAC formula which will reflect the changes in the fuel cost on a monthly basis.  It said that the existing formula used by DERC, does not recognize cost on account of arrears payable to the GENCOS or TRANSCOS. This formula also does not covers losses on account of sale of surplus power.  In FY 2015-16 DERC allowed the Discoms to levy PPAC surcharge from the consumers for the remaining three quarters, but this order lapsed in March 2016 due to delay in filing of tariff petitions.
  • 15. Losses on account of sale of surplus power  DERC has fixed a base rate of Rs. 4/unit for the sale of surplus power.  However the Discoms have been unable to dispose off surplus power at such rate as the power exchange rates and UI rates are much lower compared to the base rate.  DERC has said that the Discoms (especially BYPL), instead of making serious efforts to sell power in power exchanges or get into banking transactions with other states, have sold much of their power in UI exchanges.  The UI rates are very low compared to other rates, which has led to substantial losses for the Discoms.  It has been alleged that the discoms are buying 'excess' power and selling it at a low price, thereby booking huge losses which leads to unwarranted tariff burden on consumers.  DERC must be realistic while fixing the base rate for the sale of surplus power, while DISCOMS must put an all out effort to sell surplus power at the best rates possible.  The demand projection of New Delhi is also highly unpredictable, leading to confusion while buying power. It is very difficult to clearly determine the load curve for Delhi. Electricity rates Rs/unit UI rate 1.78 Average power purchase rate 3.78 IEX rate 2.31
  • 16. Inadequate carrying cost  A carrying cost is the rate of interest allowed on the regulatory asset being carried over to the subsequent fiscal years.  It is comprised of two components, return on equity and return on debt.  RoE is 16% , while the cost of debt should be on par with the SBI PLR rate.  However, DERC allows change in the cost of debt, only when the deviation in the SBI PLR is more than 1%.  Due to this, the DISCOMS are not able to get proper returns as per market scenarios.  Disallowance of adequate carrying costs has artificially discounted the revenue gap by 182 crore.  Formula for calculating the carrying cost rate= (70 x PLR rate + 30 x RoE Rate)
  • 17. Comparison between SBI PLR rates and DERC approved rates 12.69 12.79 11.78 12.26 14.4 14.61 14.58 14.05 10.9 11.38 11.33 11.64 12.45 9.54 9.34 9.27 0 2 4 6 8 10 12 14 16 FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 Comparison between SBI PLR rates and the cost on debt allowed by DERC SBI PLR Rates (%) Cost of Debt allowed by DERC (%)
  • 18. Inadequate surcharge rate  From 2012, DERC allowed the Discoms to levy 8% surcharge rate from the consumers in Delhi. This surcharge was to be charged against the total payable amount, mentioned in the electricity bill.  This surcharge rate is supposed to compensate the Discoms for the carrying cost being charged on the regulatory assets.  This surcharge rate needs continuous revision every year in order to compensate the Discoms for the losses incurred on account of power purchase.  While the carrying costs are decided at the rates of 14-15% p.a. it is strange that the surcharge rate allowed is merely 8%.  Hon’ble ATE judgment dated 01/01/2011 clearly mandates that the rate of carrying cost should be fixed at such rate so that the Discoms can not only recover the carrying cost on the RA for the current year but also it should be able to recover 1/3rd of the principle amount.
  • 19. Sample electricity bill showing surcharge rate
  • 20. Absence of any clear plan to amortize the regulatory assets  Discoms have repeatedly asked DERC to provide a clear roadmap for the amortization of regulatory assets.  Delhi discoms are private entities which makes them non-eligible for the benefits from financial assistance plans such as FRP 2012 and UDAY.  The discoms cite their inability to pay the power purchase bills due to huge financial stress. The primary losers is the general public of New Delhi who are constantly under the threat of intermittent load shedding and impending blackouts.  The amount of regulatory assets has risen to such alarming levels that every electricity consumer in Delhi owes the Discoms around Rs. 20,000.  The Delhi Govt. withdrew the financial support in 2003 which was meant for the aiding the discoms.  Apart from 8% surcharge rate, there is no other provision from DERC to liquidate the regulatory assets.
  • 21. Delay in filing of tariff petitions and issuance of tariff orders  Timely filing of tariff petitions and timely issuance of tariff orders help in saving of costly capital.  Until March 2016, none of the Delhi Discoms have filed their tariff petitions for 2016-17.  The reason being stated is that DERC has failed to come up with new MYT regulations for 2016-17, due to which the Discoms are hesitant to file tariff petitions.  Due to this delay, Delhi Discoms won’t be able to levy fuel surcharge from consumers which was allowed last year by DERC.  The Delhi Electricity Regulatory Commission (DERC) had allowed power discoms to levy PPAC surcharge following a directive from the Appellate Tribunal for Electricity (APTEL) since June 15, 2015.
  • 22. Measures taken up by other states to liquidate regulatory assets 1. Tamil Nadu : Subsidy Package of Rs. 6879.33 and Govt. takeover of the revenue gap  2. Rajasthan : Tariff hike in 2014-15 and Govt. approval to join UDAY scheme. 3. Jharkhand : Joined UDAY scheme in January 2016 to mitigate losses of around Rs. 7353 crores 4. Odisha : Has regulatory assets worth Rs 3,450 crores and is considering joining UDAY scheme via it’s bulk power purchaser GRIDCO. 5. Haryana : Tariff hikes in 2014-15 and 2015-16 and the state Govt. will take over a total debt of around Rs. 25,000 crores under the UDAY scheme.
  • 23. International Practices-Brazil  Low amounts of rainfall resulted in a severe shortage of electricity in 2000-01, as the country depends on hydroelectric power for more than 70% of its electricity needs.  This led the Govt. to resort to power rationing and systematic blackouts all over the country.  However due to these power rationing measures, the power producers and other electrical utilities faced huge financial losses.  In order to reimburse the utilities for their losses, Govt. introduced several surcharges and tariff increases in electricity rates.  These surcharges and tariff increments were set for a period of 7-8 years and it was assumed that the utilities would recover their costs in this period (till 2008).
  • 24. International Practices-Canada  Any losses incurred to the utilities on account of uncontrollable costs are recovered from the consumers in the form of rate riders.  These rate riders are allowed on a regular basis and hence the problem of regulatory assets is nullified.  A rate rider is a temporary credit or charge that is added to the bill on behalf of the electricity or gas distributor. A rate rider collects or refunds the difference between actual and estimated costs for delivering energy.  Electricity and gas distribution companies in Canada use rate riders to adjust any differences between the actual cost and the approved rate for providing service. in India become as pro- active as those in Canada, then the utilities won’t be saddled with ever increasing debts and deferred costs.
  • 25. Conclusion  Cost reflective tariffs are a must for covering losses on account of fuel price change.  Annual tariff revisions must be done to prevent the regulatory assets from further build-up.  8% surcharge, which is levied from consumers, needs further increment. The amount of surcharge is not enough to meet the carrying costs for the regulatory assets. DERC must take a view of this issue and solve it.  The carrying cost which is allowed by the commission on the regulatory assets needs to be updated regularly as per current SBI PLR rates.  Need for revising costly PPAs and surrendering the allocation from costly and inefficient plants. However, surrendering costly power all at once is not a feasible solution as it will leave a number of power plants stranded due to lack of customers. Instead the surrendering should be done in a phase- wise manner, so that the Govt. can reallocate those power plants to other interested buyers.  Discoms must make a serious effort towards sale of surplus power via banking and power exchanges. They must deter from dumping surplus power via UI channel as much as possible.  DERC should come up with an amicable solution to amortize the regulatory assets. The longer this process is delayed, the higher stress the companies will face financially.
  • 26. Recommendations  Govt. reimburses the consumer to compensate for the impact of tariff hikes  LPG subsidy reimbursement model can also be tried for the consumers in Delhi. Since Delhi has a high literacy rate and maximum people have bank accounts too, this plan can be implemented without much hassle.  Govt. should target consumers with low income or such consumers who will be hit hard most due to tariff hikes. These people could be provided with subsidy directly in their bank accounts. If not fully, then the consumers could be partially reimbursed (say ~60-70%) for the hike in the tariff rates.  Industrial consumers, consumers with high consumption and those consumers whose income is good enough to bear the brunt of tariff shocks, should be exempted from the subsidy scheme.  Also subsidy could be provided to those consumers also who manage to bring their consumption rates below a certain limit. Subsidy rates for these people could be different from what is being provided to low income consumers.  This scheme could be a win-win scenario for both consumers and Discoms as consumers will be fully or partially saved from tariff shock and Discoms would be compensated for their losses.  This scheme could be implemented in a time frame of 4-5 years and tariff also should be increased gradually in this period. Also the suggestions proposed in previous slide should also be implemented along with this plan (minus the loans from PFC & REC). This will help in not putting the whole burden on the Govt. and letting the Discoms share the responsibility too.
  • 27. Recommendations  Loan from Power Finance Corp. or any other Govt. financing institution  Loan can be provided by any of the above given financial bodies.  A time period of 7-8 years should be set as a target to amortize the regulatory assets.  Interest rate on loans should be less than prevailing market rates, say around 10%.  The loan component can cover around 50-60% of the regulatory assets.  Delhi Govt. or the Central Govt. can take guarantee for 50% of the loan amount.  2 years of moratorium period can be provided on the loan.  After the moratorium period, discoms can start paying back the loan along with interest.  For the remaining half of regulatory assets, the following measures could be taken: - Increment of fixed charges which is to be levied from every consumers. As new MYT regulations are coming up, so this provision could be made in the MYT order. - Very moderate tariff hikes in this time period. (~ Rs. 1-1.5/unit) - Benefits from the reduced Bulk supply rates due to falling fuel prices to be utilized for this purpose. - Adequate revision in surcharge rate is required every year (10-12%). - Funds released after conclusion of pending APTEL judgment (Rs. 5,824 Cr as claimed by BSES) could be diverted towards towards this purpose. Speedy completion of pending APTEL judgments.  For this method to work, DERC and the discoms must ensure that there are no future revenue gaps and regular tariff revisions should happen.
  • 28. Recommendations  Discoms get approval from the Govt. to join the UDAY scheme  As per current norms a private utility is not eligible to join UDAY scheme.  Delhi Discoms being private companies thereby cannot join UDAY, and they are on the verge of missing out on a good opportunity to solve their financial woes.  Under the UDAY Scheme two steps could be taken:  - Issuance of tax free bonds repayable in 10 years for 50% of regulatory assets (approx. Rs. 12,500 Cr)  - Arrange loan for 25% of regulatory assets at Base lending rate. The impact on tariff due to issuance of Tax-free bonds at lower rate of interest of 8% per annum would be: Scenario Impact on tariff (Rs./unit) Tax-free bonds repayable from 10th year onwards 0.50 Benchmark Prime lending rate 0.25
  • 29. Recommendations (Contd…) Our Hon’ble Power minister has recently stated that his ministry is looking into making a case for private utilities to join the UDAY. But those companies will not get any financial benefits from UDAY scheme. Instead they will stand to benefit from the operational grants and schemes covered under the UDAY scheme which are as follows:  Reduction in fuel cost through coal swapping.  Time bound loss reduction trajectory. Although it must be noted that Delhi discoms have done a commendable job at bringing down the loss levels in these years.  This scheme also provides for quarterly fuel cost adjustment.  Annual tariff revisions has been highly recommended in the UDAY scheme.  Grants for the strengthening of distribution network and infrastructure will be covered under the IPDS scheme.  Compulsory smart metering and AMR infrastructure to reduce losses. Funds will be granted under the IPDS scheme.  IT enablement of distribution system.  Recently Ministry of Power has agreed to fund the project for removal of old wires and replacing them with new underground cables in the area of Old Delhi region. This will be covered under the IPDS scheme.
  • 30. Bibliography  Energy.economictimes.com  BYPL Tariff orders 2010-11 to 2015-16.  Financialexpress.com  Tariff orders of Haryana, Rajasthan, Jharkhand, Orissa and Tamil Nadu.  PFC reports on financial status of discoms.  Report on the problem of regulatory assets by Forum of Regulators.