SlideShare a Scribd company logo
ADVANCED HIGH VOLTAGE TECHNIQUE
Assistant Professor Suna BOLAT
Office: ee 106
Phone: 366 2197
REVIEW
What is high voltage?
What is voltage for that matter?
Voltage
• Potential, V:
Electrical location of a point according to a reference.
unit: volt
• Voltage, U:
unit: volt
2
1
V2
V1
U = V2 - V1
referenceVr
Potential, V:
Electrical location of a point according to a reference.
unit: volt
Voltage
2
1
+V2
+ V1
- V3
referenceVr
3
Voltage
Voltage, U: potential difference
unit: volt
Reference, Vr
V1
V2
U = V2 - V1
Alternating voltage
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
-1.5
-1
-0.5
0
0.5
1
1.5
Umax
Voltage, U(t)
Time, t
Period, T = 1/f
Ue = effective value = Umax/2
Direct voltage constant
DIRECT VOLTAGE
IMPULSE VOLTAGE
High voltage
U > 1000 Volt = 1 kiloVolt
High voltage (HV)
U ≤ 1000 Volt = 1 kiloVolt
Low voltage (LV)
High voltage levels in Turkey
Nominal
voltage, Un
kV
Permissible
maximum
operating voltage,
Umax [kV]
Medium
voltage
3 3.6
6 7.2
10 12
15 17.5
20 24
30 (34.5) 36
High
voltage
66 72
154 170
Extra high
voltage
380 420 (400)
High voltage levels in TRNC
Nominal
voltage, Un
kV
Permissible
maximum
operating voltage,
Umax [kV]
Medium
voltage
11 12
22 24
High
voltage
66 72
132 145
High DC voltage
± 100 kV
± 200 kV
± 300 kV
± 400 kV
± 800 kV
Why do we need high voltage
1. MORE POWER
• Electrical power: P = V*I I = V/Z P = V2/ Z
• Electrical energy: W = P*t
Why do we need high voltage
2. DISTANCE BETWEEN ENERGY SOURCE AND THE CONSUMER
In order to cover voltage drops in long distances. As the line is
resistive, a voltage drop will occur along the line. The voltage at
the generator, UG, is higher than the voltage at the load, UL.
Why do we need high voltage
3. REDUCING LOSSES (1)
• If R is the overall line resistance, the following power transmission
losses, PΩ, occur:
• Relating the power losses to the transmitted power, we obtain the
relative power losses:
• Equation illustrates the inversely proportional relationship of the
transmission losses to the square of the line voltage.
• To keep losses low, power transmission lines are operated at
voltages which should, theoretically, be as high as possible.
Why do we need high voltage
3. REDUCING LOSSES (2)
coronaconsumption
generation
-P
P
P-P
heat
Leakage current
Why do we need high voltage
4. REDUCING DIMENSIONS & COST
Increasing the line voltage also implies an increase of the
insulation costs associated with components such as
transformers.
Decreasing losses imply increasing equipment costs.
REVIEW
Basic concepts and terminology
Electric network
Operating equipment
All the components that are connected to the electric power
system and carry high voltage and currents.
• Generator (supply)
• Transformer (conversion)
• Lines, cables, conductors, switchgears
• Measurement transformers, devices
Electrical network
Electrical installations with the same operating voltage
Insulation
Precaution against network faults between phases or phase to
neutral
Insulator
Material used for precaution in the insulation system
• Gas
• Liquid
• Solid
• Vacuum
Nominal system voltage, Un
The RMS phase to phase voltage by which an operating
equipment is designated and named.
Nominal voltage should be compatible with the operating
voltage
Operating voltage, Uop
It is the voltage by which an operating equipment is operated or
used.
Maximum system voltage, Um
It is the maximum voltage by which a system can be operated
Um = 15-20% Un+Un
Nominal withstand voltage
It is the voltage without resulting in short-circuit
• Nominal alternating-current withstand voltage
• Nominal impulse withstand voltage
Nominal a.c. withstand voltage
Short-duration&low frequency
• Raise the test voltage of each sample to a specific voltage
level with network frequency (50 Hz) in not more than 30
seconds
• Hold for 1 minute
• Does the insulator withstand to that voltage level?
Un Um Uw,ac Uw,impulse
30 kV 36 kV 70 kV 170 kV
Nominal impulse withstand voltage
This is the peak value of the switching or lightning impulse test voltage
at which an insulation shall not show any disruptive discharge when
subjected to a specified number of applications of this impulse under
specified conditions
• Apply 10 (or 15) positive and 10 (or 15) negative consecutive
impulses
• The wave should be 1.2 / 50 µs and conform to the requirements in
IEEE Std 4-1978
• If one flashover occurs, 10 (or 15) additional impulses shall be
applied
• Does the insulator withstand?
REVIEW
What does withstand mean?
What is withstanding to what?
Electrical discharges
• U Ub : Breakdown voltage 𝐸 =
𝑈
𝑑
•  𝐸 𝑏 =
𝑈 𝑏
𝑑
: Breakdown electric field, breakdown strength
U
DISCHARGE
Discharge can be in a form of
- Breakdown
- Flashover
- Partial discharge
Insulation ability
The behavior of an inlator against applied voltage type
Impulse characteristic
Insulation level
The threshold voltage for an insulator without any discharges
Insulation level
• Every electrical equipment has to undergo different abnormal transient
over voltage situation in different times during its total service life period.
• lightning impulses, switching impulses and/or short duration power
frequency over voltages.
• Depending upon the maximum level of impulse voltages and short
duration power frequency over voltages that one power system
component can withstand, the insulation level of high voltage power
system is determined.
• For the system rated less than 300 kV, the lightning impulse withstand
voltage and short duration power frequency withstand voltage are
considered.
• For equipment rated more or equal 300 kV, switching impulse withstand
voltage and short duration power frequency withstand voltage are
considered
Protection level
These are the highest peak voltage value which should not be
exceeded at the terminals of a protective device when switching
impulses and lightning impulses of standard shape and rate
values are applied under specific conditions.
Circuit, device,
system, ...
To be protected
Protection level
Insulation co-ordination
The selection of the electric strength of equipment in relation to the
voltages which can appear on the system for which the equipment is
intended.
The overall aim is to reduce to
• an economically and operationally acceptable level the cost and
disturbance caused by insulation failure and resulting system
outages.
• To keep interruptions to a minimum, the insulation of the various
parts of the system must be so graded that flashovers only occur at
intended points.
• With increasing system voltage, the need to reduce the amount of
insulation in the system, by proper co-ordination of the insulating
levels become more critical
Insulation co-ordination
Insulation
coordination
Insulation
Over
voltage
Protection
Grounded (earthed)&insulated networks
Z=0
directly grounded
network
Z=∞ insulated
network
Circuit, device,
system, ...
To be protected
Z = 0
Factor of earthing
• This is the ratio of the highest r.m.s. phase-to-earth power
frequency voltage on a sound phase during an earth fault to
the r.m.s. phase-to-phase power frequency voltage which
would be obtained at the selected location without the fault.
• This ratio characterizes, in general terms, the earthing
conditions of a system as viewed from the selected fault
location.
𝑚 =
𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒
𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ
Factor of earthing
𝑚 =
𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒
𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ
𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒: voltage between two phases
𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ: voltage of the phase without short circuit according
to the earth
Network
Grounded (earthed)&insulated networks
Up-p
Ue
Short circuit
Factor of earthing
• Neutral point directly grounded:
m ≤ 0.8
• Neutral point is insulated
m < 0.8
Neutral point is grounded
𝑚 =
𝑈 𝑝−𝑝
𝑈 𝑒
≤ 0.8
𝑈𝑒 ≤ 0.8 × 𝑈 𝑝−𝑝, 𝑈𝑒 ≤ 0.8 × 𝑈 𝑛
Un -> 3, 10, 15, 20, 30, 154, 380, ... kV
For Un=10 kV (phase to phase)
𝑈𝑒 ≤ 0.8 × 10 = 8 𝑘𝑉
It means: during a short circuit in one phase, 8 kV on each line!
OVERVOLTAGES
1. Voltage rise
Incidents which result in a voltage rise:
• Ferranti effect
• Load rejection
• Capacitance switching
• Shortcircuit and fault clearances
• Ferroresonance
2. Internal overvoltages
• Switching overvoltages
• Shortcircuit
• Resonance phenomena
3. External overvoltages
• Overvoltages as a consequence of direct lightning strokes.

More Related Content

What's hot

ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
karikalan123
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONMd Sarowar Alam
 
Protection Application Guide & BOOK
Protection Application Guide & BOOK Protection Application Guide & BOOK
Protection Application Guide & BOOK
Power System Operation
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
michaeljmack
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitation
NTPC
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
Sumeet Ratnawat
 
Distributed generation placement
Distributed generation placementDistributed generation placement
Distributed generation placement
Satish Kansal
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
Power System Operation
 
Alternatorexcitation
AlternatorexcitationAlternatorexcitation
AlternatorexcitationRanjan Naik
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
kishore kish
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
Himmelstern
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
Muthar Hussain
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
CS V
 
Protection against overvoltage
Protection against overvoltageProtection against overvoltage
Protection against overvoltage
vishalgohel12195
 

What's hot (20)

ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Basic protection and relaying
Basic protection and relayingBasic protection and relaying
Basic protection and relaying
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATION
 
Protection Application Guide & BOOK
Protection Application Guide & BOOK Protection Application Guide & BOOK
Protection Application Guide & BOOK
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitation
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
 
Distributed generation placement
Distributed generation placementDistributed generation placement
Distributed generation placement
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Alternatorexcitation
AlternatorexcitationAlternatorexcitation
Alternatorexcitation
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
Voltage Regulation
Voltage RegulationVoltage Regulation
Voltage Regulation
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 
Protection against overvoltage
Protection against overvoltageProtection against overvoltage
Protection against overvoltage
 

Viewers also liked

Мистецтво Відродження
Мистецтво ВідродженняМистецтво Відродження
Мистецтво Відродження
dawidovoksana
 
Выводы комиссии по Дубовой роще
Выводы комиссии по Дубовой рощеВыводы комиссии по Дубовой роще
Выводы комиссии по Дубовой роще
antikorzp
 
GNU Make でも使ってみようか
GNU Make でも使ってみようかGNU Make でも使ってみようか
GNU Make でも使ってみようか
Y M
 
AndroidDevelopmentTrainingPortfolio
AndroidDevelopmentTrainingPortfolioAndroidDevelopmentTrainingPortfolio
AndroidDevelopmentTrainingPortfolioMaurice Moore
 
Folklore espitual
Folklore espitualFolklore espitual
Folklore espitual
Jessica Revelo Burbano
 
Christine Vo
Christine VoChristine Vo
Christine Vo
STEM2
 
Resident Connections Volume 2 Number 12
Resident Connections Volume 2 Number 12Resident Connections Volume 2 Number 12
Resident Connections Volume 2 Number 12HsiaoTieh Hsu
 
Kim Walkers (CV)
Kim Walkers (CV)Kim Walkers (CV)
Kim Walkers (CV)Kim Walker
 
Аудит УКС Запорожского городского совета
Аудит УКС Запорожского городского советаАудит УКС Запорожского городского совета
Аудит УКС Запорожского городского совета
antikorzp
 
Propiedadesdelarandano
PropiedadesdelarandanoPropiedadesdelarandano
Propiedadesdelarandano
bryanlh
 
Stop hitting yourself
Stop hitting yourselfStop hitting yourself
Stop hitting yourself
Sharon Summers
 
be awesome
be awesomebe awesome
be awesome
Sharon Summers
 
давиденко оксана
давиденко оксанадавиденко оксана
давиденко оксана
dawidovoksana
 
Guía redes sociales
Guía redes socialesGuía redes sociales
Guía redes sociales
Nicolas Prierto perez
 

Viewers also liked (20)

Мистецтво Відродження
Мистецтво ВідродженняМистецтво Відродження
Мистецтво Відродження
 
Выводы комиссии по Дубовой роще
Выводы комиссии по Дубовой рощеВыводы комиссии по Дубовой роще
Выводы комиссии по Дубовой роще
 
Fekry NEW 2NEW 2015 qatargas=segas
Fekry NEW 2NEW 2015 qatargas=segasFekry NEW 2NEW 2015 qatargas=segas
Fekry NEW 2NEW 2015 qatargas=segas
 
GNU Make でも使ってみようか
GNU Make でも使ってみようかGNU Make でも使ってみようか
GNU Make でも使ってみようか
 
AndroidDevelopmentTrainingPortfolio
AndroidDevelopmentTrainingPortfolioAndroidDevelopmentTrainingPortfolio
AndroidDevelopmentTrainingPortfolio
 
FCL_Credentials_Portfolio
FCL_Credentials_PortfolioFCL_Credentials_Portfolio
FCL_Credentials_Portfolio
 
Felix, Steven
Felix, StevenFelix, Steven
Felix, Steven
 
Folklore espitual
Folklore espitualFolklore espitual
Folklore espitual
 
Christine Vo
Christine VoChristine Vo
Christine Vo
 
Resident Connections Volume 2 Number 12
Resident Connections Volume 2 Number 12Resident Connections Volume 2 Number 12
Resident Connections Volume 2 Number 12
 
Kim Walkers (CV)
Kim Walkers (CV)Kim Walkers (CV)
Kim Walkers (CV)
 
Summer See 2 - 3
Summer See 2 - 3Summer See 2 - 3
Summer See 2 - 3
 
Аудит УКС Запорожского городского совета
Аудит УКС Запорожского городского советаАудит УКС Запорожского городского совета
Аудит УКС Запорожского городского совета
 
Propiedadesdelarandano
PropiedadesdelarandanoPropiedadesdelarandano
Propiedadesdelarandano
 
Stop hitting yourself
Stop hitting yourselfStop hitting yourself
Stop hitting yourself
 
be awesome
be awesomebe awesome
be awesome
 
давиденко оксана
давиденко оксанадавиденко оксана
давиденко оксана
 
Africa
AfricaAfrica
Africa
 
Micah_portfolio
Micah_portfolio Micah_portfolio
Micah_portfolio
 
Guía redes sociales
Guía redes socialesGuía redes sociales
Guía redes sociales
 

Similar to Turkey hv

6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordinationRui Zhang
 
Power Quality
Power QualityPower Quality
Power Quality
Elshemy Mohamed
 
Distribu pQ.pptx
Distribu pQ.pptxDistribu pQ.pptx
Distribu pQ.pptx
bhuvana71
 
Overvoltages 1
Overvoltages 1Overvoltages 1
Overvoltages 1
ahmedasdasd
 
Design Development and Testing of an Overvoltage and Undervoltage Protection ...
Design Development and Testing of an Overvoltage and Undervoltage Protection ...Design Development and Testing of an Overvoltage and Undervoltage Protection ...
Design Development and Testing of an Overvoltage and Undervoltage Protection ...
Kunal Maity
 
Introduction to Power Quality Problems
Introduction to Power Quality ProblemsIntroduction to Power Quality Problems
Introduction to Power Quality Problems
SUNYANI TECHNICAL UNIVERSITY
 
power qualit
 power qualit power qualit
power qualit
dharmesh dabhi
 
ET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptxET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptx
ChristianAceSolidum1
 
Cdi t1 10_adv_unit3_revision_notes_eot
Cdi t1 10_adv_unit3_revision_notes_eotCdi t1 10_adv_unit3_revision_notes_eot
Cdi t1 10_adv_unit3_revision_notes_eot
CDI Aljeer
 
Study tour to optcl
Study tour to optclStudy tour to optcl
Study tour to optcl
SoumyaRanjanDas13
 
Cdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eotCdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eot
CDI Aljeer
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
Parth Patel
 
Apparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering StudentsApparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering Students
kannan348865
 
Power quality &amp; demand side management
Power quality &amp; demand side managementPower quality &amp; demand side management
Power quality &amp; demand side management
Mark Anthony Enoy
 
High voltage technology &amp; insulation testing
High voltage technology &amp; insulation testingHigh voltage technology &amp; insulation testing
High voltage technology &amp; insulation testing
Zeeshan Akhtar
 
Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020
RekaNext Capital
 
Week-High voltage engineering presentstion
Week-High voltage engineering presentstionWeek-High voltage engineering presentstion
Week-High voltage engineering presentstion
20bee084
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
Parameshwar Tummeti
 

Similar to Turkey hv (20)

6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination
 
Power Quality
Power QualityPower Quality
Power Quality
 
Surge supressor
Surge supressorSurge supressor
Surge supressor
 
Distribu pQ.pptx
Distribu pQ.pptxDistribu pQ.pptx
Distribu pQ.pptx
 
Overvoltages 1
Overvoltages 1Overvoltages 1
Overvoltages 1
 
Design Development and Testing of an Overvoltage and Undervoltage Protection ...
Design Development and Testing of an Overvoltage and Undervoltage Protection ...Design Development and Testing of an Overvoltage and Undervoltage Protection ...
Design Development and Testing of an Overvoltage and Undervoltage Protection ...
 
Introduction to Power Quality Problems
Introduction to Power Quality ProblemsIntroduction to Power Quality Problems
Introduction to Power Quality Problems
 
power qualit
 power qualit power qualit
power qualit
 
ET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptxET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptx
 
Cdi t1 10_adv_unit3_revision_notes_eot
Cdi t1 10_adv_unit3_revision_notes_eotCdi t1 10_adv_unit3_revision_notes_eot
Cdi t1 10_adv_unit3_revision_notes_eot
 
Study tour to optcl
Study tour to optclStudy tour to optcl
Study tour to optcl
 
Cdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eotCdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eot
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
 
Apparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering StudentsApparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering Students
 
Power quality &amp; demand side management
Power quality &amp; demand side managementPower quality &amp; demand side management
Power quality &amp; demand side management
 
High voltage technology &amp; insulation testing
High voltage technology &amp; insulation testingHigh voltage technology &amp; insulation testing
High voltage technology &amp; insulation testing
 
Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020
 
Week-High voltage engineering presentstion
Week-High voltage engineering presentstionWeek-High voltage engineering presentstion
Week-High voltage engineering presentstion
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 

Recently uploaded

Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
708pb191
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
M. A. Architect
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
farazahmadas6
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
n0tivyq
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
ResDraft
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
PrabhjeetSingh219035
 
Let's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons ShirtLet's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons Shirt
TeeFusion
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 

Recently uploaded (20)

Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
 
Let's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons ShirtLet's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons Shirt
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 

Turkey hv

  • 1. ADVANCED HIGH VOLTAGE TECHNIQUE Assistant Professor Suna BOLAT Office: ee 106 Phone: 366 2197
  • 2. REVIEW What is high voltage? What is voltage for that matter?
  • 3. Voltage • Potential, V: Electrical location of a point according to a reference. unit: volt • Voltage, U: unit: volt 2 1 V2 V1 U = V2 - V1 referenceVr
  • 4. Potential, V: Electrical location of a point according to a reference. unit: volt Voltage 2 1 +V2 + V1 - V3 referenceVr 3
  • 5. Voltage Voltage, U: potential difference unit: volt Reference, Vr V1 V2 U = V2 - V1
  • 6. Alternating voltage 0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 -1.5 -1 -0.5 0 0.5 1 1.5 Umax Voltage, U(t) Time, t Period, T = 1/f Ue = effective value = Umax/2
  • 7. Direct voltage constant DIRECT VOLTAGE IMPULSE VOLTAGE
  • 8. High voltage U > 1000 Volt = 1 kiloVolt High voltage (HV) U ≤ 1000 Volt = 1 kiloVolt Low voltage (LV)
  • 9. High voltage levels in Turkey Nominal voltage, Un kV Permissible maximum operating voltage, Umax [kV] Medium voltage 3 3.6 6 7.2 10 12 15 17.5 20 24 30 (34.5) 36 High voltage 66 72 154 170 Extra high voltage 380 420 (400)
  • 10. High voltage levels in TRNC Nominal voltage, Un kV Permissible maximum operating voltage, Umax [kV] Medium voltage 11 12 22 24 High voltage 66 72 132 145
  • 11. High DC voltage ± 100 kV ± 200 kV ± 300 kV ± 400 kV ± 800 kV
  • 12. Why do we need high voltage 1. MORE POWER • Electrical power: P = V*I I = V/Z P = V2/ Z • Electrical energy: W = P*t
  • 13. Why do we need high voltage 2. DISTANCE BETWEEN ENERGY SOURCE AND THE CONSUMER In order to cover voltage drops in long distances. As the line is resistive, a voltage drop will occur along the line. The voltage at the generator, UG, is higher than the voltage at the load, UL.
  • 14. Why do we need high voltage 3. REDUCING LOSSES (1) • If R is the overall line resistance, the following power transmission losses, PΩ, occur: • Relating the power losses to the transmitted power, we obtain the relative power losses: • Equation illustrates the inversely proportional relationship of the transmission losses to the square of the line voltage. • To keep losses low, power transmission lines are operated at voltages which should, theoretically, be as high as possible.
  • 15. Why do we need high voltage 3. REDUCING LOSSES (2) coronaconsumption generation -P P P-P heat Leakage current
  • 16. Why do we need high voltage 4. REDUCING DIMENSIONS & COST Increasing the line voltage also implies an increase of the insulation costs associated with components such as transformers. Decreasing losses imply increasing equipment costs.
  • 19. Operating equipment All the components that are connected to the electric power system and carry high voltage and currents. • Generator (supply) • Transformer (conversion) • Lines, cables, conductors, switchgears • Measurement transformers, devices
  • 20. Electrical network Electrical installations with the same operating voltage
  • 21. Insulation Precaution against network faults between phases or phase to neutral
  • 22. Insulator Material used for precaution in the insulation system • Gas • Liquid • Solid • Vacuum
  • 23. Nominal system voltage, Un The RMS phase to phase voltage by which an operating equipment is designated and named. Nominal voltage should be compatible with the operating voltage
  • 24. Operating voltage, Uop It is the voltage by which an operating equipment is operated or used.
  • 25. Maximum system voltage, Um It is the maximum voltage by which a system can be operated Um = 15-20% Un+Un
  • 26. Nominal withstand voltage It is the voltage without resulting in short-circuit • Nominal alternating-current withstand voltage • Nominal impulse withstand voltage
  • 27. Nominal a.c. withstand voltage Short-duration&low frequency • Raise the test voltage of each sample to a specific voltage level with network frequency (50 Hz) in not more than 30 seconds • Hold for 1 minute • Does the insulator withstand to that voltage level? Un Um Uw,ac Uw,impulse 30 kV 36 kV 70 kV 170 kV
  • 28. Nominal impulse withstand voltage This is the peak value of the switching or lightning impulse test voltage at which an insulation shall not show any disruptive discharge when subjected to a specified number of applications of this impulse under specified conditions • Apply 10 (or 15) positive and 10 (or 15) negative consecutive impulses • The wave should be 1.2 / 50 µs and conform to the requirements in IEEE Std 4-1978 • If one flashover occurs, 10 (or 15) additional impulses shall be applied • Does the insulator withstand?
  • 29. REVIEW What does withstand mean? What is withstanding to what?
  • 30. Electrical discharges • U Ub : Breakdown voltage 𝐸 = 𝑈 𝑑 •  𝐸 𝑏 = 𝑈 𝑏 𝑑 : Breakdown electric field, breakdown strength U DISCHARGE Discharge can be in a form of - Breakdown - Flashover - Partial discharge
  • 31. Insulation ability The behavior of an inlator against applied voltage type Impulse characteristic
  • 32. Insulation level The threshold voltage for an insulator without any discharges
  • 33. Insulation level • Every electrical equipment has to undergo different abnormal transient over voltage situation in different times during its total service life period. • lightning impulses, switching impulses and/or short duration power frequency over voltages. • Depending upon the maximum level of impulse voltages and short duration power frequency over voltages that one power system component can withstand, the insulation level of high voltage power system is determined. • For the system rated less than 300 kV, the lightning impulse withstand voltage and short duration power frequency withstand voltage are considered. • For equipment rated more or equal 300 kV, switching impulse withstand voltage and short duration power frequency withstand voltage are considered
  • 34. Protection level These are the highest peak voltage value which should not be exceeded at the terminals of a protective device when switching impulses and lightning impulses of standard shape and rate values are applied under specific conditions. Circuit, device, system, ... To be protected
  • 36. Insulation co-ordination The selection of the electric strength of equipment in relation to the voltages which can appear on the system for which the equipment is intended. The overall aim is to reduce to • an economically and operationally acceptable level the cost and disturbance caused by insulation failure and resulting system outages. • To keep interruptions to a minimum, the insulation of the various parts of the system must be so graded that flashovers only occur at intended points. • With increasing system voltage, the need to reduce the amount of insulation in the system, by proper co-ordination of the insulating levels become more critical
  • 38. Grounded (earthed)&insulated networks Z=0 directly grounded network Z=∞ insulated network Circuit, device, system, ... To be protected Z = 0
  • 39. Factor of earthing • This is the ratio of the highest r.m.s. phase-to-earth power frequency voltage on a sound phase during an earth fault to the r.m.s. phase-to-phase power frequency voltage which would be obtained at the selected location without the fault. • This ratio characterizes, in general terms, the earthing conditions of a system as viewed from the selected fault location. 𝑚 = 𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒 𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ
  • 40. Factor of earthing 𝑚 = 𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒 𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ 𝑈 𝑝ℎ𝑎𝑠𝑒−𝑡𝑜−𝑝ℎ𝑎𝑠𝑒: voltage between two phases 𝑈𝑡𝑜−𝑒𝑎𝑟𝑡ℎ: voltage of the phase without short circuit according to the earth
  • 42. Factor of earthing • Neutral point directly grounded: m ≤ 0.8 • Neutral point is insulated m < 0.8
  • 43. Neutral point is grounded 𝑚 = 𝑈 𝑝−𝑝 𝑈 𝑒 ≤ 0.8 𝑈𝑒 ≤ 0.8 × 𝑈 𝑝−𝑝, 𝑈𝑒 ≤ 0.8 × 𝑈 𝑛 Un -> 3, 10, 15, 20, 30, 154, 380, ... kV For Un=10 kV (phase to phase) 𝑈𝑒 ≤ 0.8 × 10 = 8 𝑘𝑉 It means: during a short circuit in one phase, 8 kV on each line!
  • 44.
  • 46. 1. Voltage rise Incidents which result in a voltage rise: • Ferranti effect • Load rejection • Capacitance switching • Shortcircuit and fault clearances • Ferroresonance
  • 47. 2. Internal overvoltages • Switching overvoltages • Shortcircuit • Resonance phenomena
  • 48. 3. External overvoltages • Overvoltages as a consequence of direct lightning strokes.