Supply Chain Management -
Projects
Content
2
 Project Terminology
 Challenges and Factors Deciding Success of a Project
 Supply Chain Management: Critical Function
 Functional Role During Project Stages
 Outsourcing of Services (Contracting): Major Project Driver
 Structuring and Management of Service Contract
 Supply Chain Organization Structure
 Use of Technology
 Best Practices
 Case Study
Project Terminology
3
4
Defining Project
Temporary
Endeavour
Unique End
product/
service
Every project has finite
/specified duration
Prototype of a machine with
new design / concept
Invention of new drug
Re-engineering of Business
Processes
Refinery built on turnkey basis
Unique set of coordinated activities that has:
 Finite life span
 Specified amount of resources
 Measurable deliverables
 Organization structure for managing project and to meet
specified objectives
5
Other Definitions
Offshore Platform
6
Township
Building
Project
Power Plant
Project Network
Example
7
8
May have several start
points, but only one end
Distinct / unique end
product
Involves capital expenditure
Very large number of
activities with complex
inter-relations
Uncertainties, risk and
dynamism inherent to
project sector
Long term impact on future
of organization (sometimes,
a game changer)
Many first time / non –
repetitive activities
Longer time frames,
impact of delays far
reaching
Large outlays, spend now,
and benefits in future
Typical Characteristics
Order of magnitude for one large project
Example: Project: Reliance Jamnagar Refinery Phase 2
• Duration: 2005 to 2008
• Cost: USD 6.3 Billion
• Concrete used: 1.9 Million Cubic Meter
• Piping: 4 Million Meter
• Major Equipment: 4400
• Workers: 80,000
• Engineers: 2800
• Engineering and supply documents: 200,000
9
Challenges and Factors Deciding
Success of a Project
10
11
Quality, Health, Safety and
Environment Issues
Adequacy of Skills withNewly Created Project Team
Confict of Interests
Authority and Time Availablefor Making Decisions
Very Large Outlays, HugeConsequences of Delays
Uncertainties, Surprises,Changes, Lack of Clarity
Inadequate Resources /
Contingencies
12
Inadequate
Resources /
Contingencies
• Efficient Project
Management
• Optimum utilization
of funds
Uncertainties,
Surprises, Changes,
Lack of Clarity
• Strong Document
Management
• Appropriate Project
Processes
• Dynamic Change
Management
• Adequate Clarity of
End Result
Very Large Outlays,
Huge Consequences
of Delays
• Robust Planning
• Efficient Review and
Control
Mechanisms
• Real Time Risks
Management
13
Authority and
Time Available
for Making
Decisions
• Maximum
Delegation of
Authority to
Project Team
• Management
Decision Making
Ability
• Swifter Decision
Making Process
Confict of
Interests
• Commitment
and Support
from the Top
Management
• Team Spirit
Adequacy of
Skills with
Newly Created
Project Team
• Competent and
Experienced
Project Manager
and Functional
Leads
Quality, Health,
Safety and
Environment
Issues
• Commitment to
QHSE Plan at All
Levels
Supply Chain Management -
Critical Function
14
Perception of Internal Customer
15
Perception of Supply Chain
16
• 50 to 80 % of total project cost
• Includes very high risk areas causing project delays and cost
overruns
• Large and diverse scope many first time and customized buying
activities
• Complex multi-modal logistics across borders
• Very high dependence on multiple suppliers
17
Functional Role During Project
Stages
18
Budgeting phase Planning Phase Execution Phase
Budgeting phase
19
• Early Involvement is Key to Success
• Ownership of Cost and Time Estimates
• Invoke Support from Strategic Suppliers for Packages and Service
Contracts
• Enter in to ‘Back to Back’ Arrangements
• Broad Planning for ‘Critical Material List’
• Identify Major Supply Chain Risks / Mitigation Plan / Costs
• Finalize / Renew Call Off Agreements
• Broad Cash Flow for Supply Chain
• Broad Supply Chain Organization Chart
Planning Phase
20
• Formulate Project Supply Chain Strategies (component or
package, lease or buy, local or international, approved or new
source, etc.)
• Prepare Approved Suppliers List
• Draw Out Project Specific Supply Chain Procedure
• Prepare Materials Control Chart / Logistics Plan / Cash Flow
• Establish Micro level Plan for Critical Material list
• Detailed Supply Chain Risk Management Plan
• Finalize Project Supply Chain Organization
Execution Phase
21
• Fast Track Ordering of Critical Materials List
• Finalize Back to Back Orders for Strategic Supplies
• Continuously Look for Cost Savings
• Maximize Savings on Leverage Items (consolidate)
• Invoke Call Off Agreements / Suppliers Managed Inventories for
Non-Critical Materials
• Frequent Review of Materials Tracking List with Project Team
• Track Contract Progress / Manage Variations and Claims
• Corrective Actions ( Cancellation / New Orders / Cost of Crashing)
• Procurement Related Cash Flow Management
• Full and Final Settlement of Major Supply / Service Order
• Invoke Buy Back Arrangements With Suppliers
Outsourcing of Services
(Contracting) : Major Project
Driver
22
23
Reasons why services are largely
outsourced
Reducing and controlling project costs
For enhancing
capability
Gaining access to
diverse
capabilities /
expertise
Reducing capital
costs
Freeing internal
resources for other
projects
Improving focus on
project
Agility, fexibility,
ease of managing
changes
24
Importance of outsourcing activity
Significant
costs
Complexities due
to
interdependence
Contract
management crucial
to project success
Legal Angle
Challenges in
communication
/interfacing
Few examples of services outsourced:
25
• Detailed Engineering Services
• Project Management Consultancy Services
• Expediting Services
• Inspection Services
• Erection and Commissioning Services
• Site works (civil, mechanical, electrical, instrumentation etc.)
Contracts
• Logistics Services
• Setting up and Managing Site Accommodations / Facilities
Structuring and Management of
Service Contracts
26
Contracting Scenarios:
• Project owner undertake works with in-house resources
• Project owner outsources most works to many specialized
contractors
• Project owner awards work to single contractor (turnkey contract)
Types of Contract:
• Cost Plus Fee Contract
• Measurable contracts (Time and Material OR Unit Price contracts)
• Lump sum Contract (Fixed Price Contract)
• Turnkey Contracts (EPC Contract)
27
Points for Consideration in Framing & Management of Service
Contracts
28
• Clarity in scope of work (Battery limits, quantum, client
obligations: extremely critical for lump sum contract)
• Clear specifications for supply and services to be delivered
• Clarity in contractual terms (Standard (like FIDIC) or tailor made
format)
• Mechanism for monitoring and approval of variations
• Factoring local regulations / conditions
• Deployment Plan (histogram) of manpower, construction
equipment , other required resources
• Applicable mode of measurement (example carpet area, or built
up area)
• Responsibility for stores management, material reconciliations
(Free Issue Materials)
Points for Consideration in Framing & Management of Service
Contracts
29
• Monitoring of progress and corrective actions
• Mechanism to admit extra claims (for extra work /Idle time /
extended stay etc.), if admissible
• Mechanism to record counter claims
• Assigning single point contact and responsible person to address
concerns
• Provision for Dispute Resolution
• Specifying applicable jurisdiction
• Liquidated Damages
• Performance Guarantees
• Applicable Taxes and duties
Supply Chain Organization
Structure
30
Project
Manager
Engineering
Lead
Supply
Chain Lead
Buyer-
Materials
Buyer-
Services
Expediter
Logistics
Coordinator
Material
Controller
Constructio
n Lead
Project
Controls
31
Head of Supply
Chain
• Matrix structure found to be most suitable
• Supply Chain Lead reports to head of procurement, as well as to
the project manager of assigned project
• Matrix structure combines functional expertise and operational
accountability
• This also empowers project manager who is responsible for
timely completion of project within budget.
• Supply Chain lead must be a great team player with leadership
qualities
• Buyers (Materials / Services), expediters, logistics coordinators,
materials controllers are part of supply chain function.
• Team spirit and versatility important factor in selection of team
member
32
Use of Technology
33
Use of Technology
• Use of suitable ERP system must for large projects
• Many project companies use separate software for Design and
Engineering, Planning, Document Control etc.
• Industry specific software integrating above are developed.
• Complete Supply Chain Cycle, starting from publishing RFQ can be
performed on ERP system
• Integration of supplier / contractors to ERP system.
• Electronic work fow for approvals of ordering decisions extremely
helpful
• RFID (Radio Frequency Identification) / Bar Coding being used for
material control
34
Best Practices
35
36
 Early involvement (at bidding /
budgeting stage)
 End to end responsibility
 Involvement of project team in
ordering decisions
 Delegation of authority for swift
decision making
 Development of specialized
buying expertise
 Training and competency
building
 Industry specific ERPs (like
AVEVA/ EPICOR/ Use of
Technology
 Back to back arrangement
for critical supplies /
contracts
 Rigorous supplier /
contractor assessment and
monitoring of supplies
 End to end responsibility of
supply chain function within
project
s
Best Practices
 Early involvement (at
bidding / budgeting stage)
 End to end responsibility
 Involvement of project team
in ordering decisions
 Delegation of authority for
swift decision making
Case Study
37
Oil Storage Terminal
38
Case Study: Cost savings by optimizing
specification / quantity consolidation
• Overview:
▫ Construction of Oil Storage terminals.
▫ Approximately 18000 M.T. Steel Plates (6 mm to 38 mm
thickness) were required for construction of Oil Storage
Terminals on Turnkey Basis.
▫ Detailed engineering was scheduled to take 16 weeks to finalize
all thickness and quantities progressively.
▫ Tank fabrication work must start within 4 weeks of project start
date.
▫ Steel plates was single major bulk item having saving potential.
39
• Approach :
▫ During discussion with project team, buyer realized that jacking
method of construction required lower thickness (6 and 8 mm)
plates first. Higher thickness plates may be delivered later.
▫ Engineering manager explained that theoretical thickness is
calculated and then next higher standard thickness is selected.
Also, that 6 and 8 thick plate can be ordered immediately.
▫ Buyer negotiated with steel mills willing to book order based on
total approximate tonnage and tentative thickness. Require final
thickness couple of weeks prior to rolling. Also, mills agree to
roll non standard thickness if individual thickness tonnage is
higher.
▫ Buyer ordered smaller thickness plates(15% of total tonnage)
from local stockist and remaining higher thickness plates from
mill.
40
• Result:
▫ Reduction of tonnage due to non standard thickness and
competitive price from mill for larger consolidated quantity
resulted in net 8% savings on major line item in project cost
sheet. Also, deliveries were made as per project requirement.
• Conclusion:
▫ Consolidation of quantities and optimization of specification can
result in bigger savings.
▫ By out of box thinking and by working beyond departmental
boundaries, supply chain function can add value.
41
THANK YOU

More Related Content

What's hot

Supply chain management Collaboration
Supply chain management CollaborationSupply chain management Collaboration
Supply chain management Collaborationbosp1
 
Supply Chain Planning
Supply Chain PlanningSupply Chain Planning
Supply Chain Planningmubarak2009
 
Strategic Sourcing
Strategic Sourcing Strategic Sourcing
Strategic Sourcing mubarak2009
 
Sourcing Process A
Sourcing Process ASourcing Process A
Sourcing Process Ampatejdl
 
Digital supply chains and the smart factories
Digital supply chains and the smart factoriesDigital supply chains and the smart factories
Digital supply chains and the smart factoriesParasuram Balasubramanian
 
SUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONSUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONZamri Yahya
 
Strategic Sourcing And Supplier Development Strategy
Strategic Sourcing And Supplier Development StrategyStrategic Sourcing And Supplier Development Strategy
Strategic Sourcing And Supplier Development Strategymashley
 
Introduction to supply chain management
Introduction to supply chain managementIntroduction to supply chain management
Introduction to supply chain managementAhmed Gamal
 
Logistics outsourcing
Logistics outsourcingLogistics outsourcing
Logistics outsourcingMarwan Bahgat
 
Sourcing Strategy Development
Sourcing Strategy DevelopmentSourcing Strategy Development
Sourcing Strategy DevelopmentJason D Barr
 
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...Bill Kohnen
 
Supply chain management & case study
Supply chain management & case studySupply chain management & case study
Supply chain management & case studyDhruv Patel
 
Supply Chain Strategy Or Design
Supply Chain Strategy Or DesignSupply Chain Strategy Or Design
Supply Chain Strategy Or DesignTanuj Poddar
 
Procurement and Sourcing Strategies
Procurement and Sourcing StrategiesProcurement and Sourcing Strategies
Procurement and Sourcing StrategiesShaikh Mahmood
 
Distribution network desing
Distribution network desingDistribution network desing
Distribution network desingSohag Hasan
 
Strategic Sourcing & E Procurement
Strategic Sourcing & E ProcurementStrategic Sourcing & E Procurement
Strategic Sourcing & E ProcurementAnand Subramaniam
 

What's hot (20)

Supply chain management Collaboration
Supply chain management CollaborationSupply chain management Collaboration
Supply chain management Collaboration
 
Supply Chain Planning
Supply Chain PlanningSupply Chain Planning
Supply Chain Planning
 
Strategic Sourcing
Strategic Sourcing Strategic Sourcing
Strategic Sourcing
 
Supply Chain Management
Supply Chain ManagementSupply Chain Management
Supply Chain Management
 
Sourcing Process A
Sourcing Process ASourcing Process A
Sourcing Process A
 
Supply Chain Performance
Supply Chain PerformanceSupply Chain Performance
Supply Chain Performance
 
Supply chain relationships and collaboration
Supply chain relationships and collaborationSupply chain relationships and collaboration
Supply chain relationships and collaboration
 
Digital supply chains and the smart factories
Digital supply chains and the smart factoriesDigital supply chains and the smart factories
Digital supply chains and the smart factories
 
SUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONSUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATION
 
Strategic Sourcing And Supplier Development Strategy
Strategic Sourcing And Supplier Development StrategyStrategic Sourcing And Supplier Development Strategy
Strategic Sourcing And Supplier Development Strategy
 
Introduction to supply chain management
Introduction to supply chain managementIntroduction to supply chain management
Introduction to supply chain management
 
Logistics outsourcing
Logistics outsourcingLogistics outsourcing
Logistics outsourcing
 
Logistics Management
Logistics ManagementLogistics Management
Logistics Management
 
Sourcing Strategy Development
Sourcing Strategy DevelopmentSourcing Strategy Development
Sourcing Strategy Development
 
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...
Strategic Sourcing and B2B E Commerce Solutions For ASEAN Purchasing Professi...
 
Supply chain management & case study
Supply chain management & case studySupply chain management & case study
Supply chain management & case study
 
Supply Chain Strategy Or Design
Supply Chain Strategy Or DesignSupply Chain Strategy Or Design
Supply Chain Strategy Or Design
 
Procurement and Sourcing Strategies
Procurement and Sourcing StrategiesProcurement and Sourcing Strategies
Procurement and Sourcing Strategies
 
Distribution network desing
Distribution network desingDistribution network desing
Distribution network desing
 
Strategic Sourcing & E Procurement
Strategic Sourcing & E ProcurementStrategic Sourcing & E Procurement
Strategic Sourcing & E Procurement
 

Similar to Supply chain management in project

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsJeremie Averous
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management OfficeJosh Folgado
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Aconex
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
Towards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsTowards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsRachid Meziani, PhD, CGEIT, PMP
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project managementSanjeev Deshmukh
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope ManagementSAJJAD KHUDHUR ABBAS
 
Project Management
Project ManagementProject Management
Project ManagementXubitech
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounPMILebanonChapter
 
Regulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and ModelsRegulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and ModelsPaul Kuiken
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptxJacquesTwubahimana1
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
CSCM Chapter 8 outsourcing cscm
CSCM Chapter 8 outsourcing cscmCSCM Chapter 8 outsourcing cscm
CSCM Chapter 8 outsourcing cscmEst
 
Managing outsource IT contracts - Transition management
Managing outsource IT contracts - Transition managementManaging outsource IT contracts - Transition management
Managing outsource IT contracts - Transition managementRonald Bartels
 

Similar to Supply chain management in project (20)

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
PM ppt unit 1.ppt
PM ppt unit 1.pptPM ppt unit 1.ppt
PM ppt unit 1.ppt
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Towards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsTowards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methods
 
Presentation
PresentationPresentation
Presentation
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope Management
 
Project Management
Project ManagementProject Management
Project Management
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
Regulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and ModelsRegulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and Models
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
SUDHIR_-_CV -Latest
SUDHIR_-_CV -LatestSUDHIR_-_CV -Latest
SUDHIR_-_CV -Latest
 
Introduction to pm
Introduction to pmIntroduction to pm
Introduction to pm
 
Construction management I lecture note (QUS 3166).pptx
Construction management I lecture note  (QUS 3166).pptxConstruction management I lecture note  (QUS 3166).pptx
Construction management I lecture note (QUS 3166).pptx
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
CSCM Chapter 8 outsourcing cscm
CSCM Chapter 8 outsourcing cscmCSCM Chapter 8 outsourcing cscm
CSCM Chapter 8 outsourcing cscm
 
Managing outsource IT contracts - Transition management
Managing outsource IT contracts - Transition managementManaging outsource IT contracts - Transition management
Managing outsource IT contracts - Transition management
 

Recently uploaded

Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7ickkoo5
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importanceajay0134
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxssuserf63bd7
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Reviewyalehistoricalreview
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.aruny7087
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garganuragrcsec2023
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsPAmudhaKumar
 

Recently uploaded (15)

Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importance
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Review
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garg
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholars
 

Supply chain management in project

  • 1. January 18, 2018 Mukesh Doshi B.E. – Production Foundation Diploma – CIPS, UK PGDMM – IIMM, Bangalore 1 Supply Chain Management - Projects
  • 2. Content 2  Project Terminology  Challenges and Factors Deciding Success of a Project  Supply Chain Management: Critical Function  Functional Role During Project Stages  Outsourcing of Services (Contracting): Major Project Driver  Structuring and Management of Service Contract  Supply Chain Organization Structure  Use of Technology  Best Practices  Case Study
  • 4. 4 Defining Project Temporary Endeavour Unique End product/ service Every project has finite /specified duration Prototype of a machine with new design / concept Invention of new drug Re-engineering of Business Processes Refinery built on turnkey basis
  • 5. Unique set of coordinated activities that has:  Finite life span  Specified amount of resources  Measurable deliverables  Organization structure for managing project and to meet specified objectives 5 Other Definitions
  • 8. 8 May have several start points, but only one end Distinct / unique end product Involves capital expenditure Very large number of activities with complex inter-relations Uncertainties, risk and dynamism inherent to project sector Long term impact on future of organization (sometimes, a game changer) Many first time / non – repetitive activities Longer time frames, impact of delays far reaching Large outlays, spend now, and benefits in future Typical Characteristics
  • 9. Order of magnitude for one large project Example: Project: Reliance Jamnagar Refinery Phase 2 • Duration: 2005 to 2008 • Cost: USD 6.3 Billion • Concrete used: 1.9 Million Cubic Meter • Piping: 4 Million Meter • Major Equipment: 4400 • Workers: 80,000 • Engineers: 2800 • Engineering and supply documents: 200,000 9
  • 10. Challenges and Factors Deciding Success of a Project 10
  • 11. 11 Quality, Health, Safety and Environment Issues Adequacy of Skills withNewly Created Project Team Confict of Interests Authority and Time Availablefor Making Decisions Very Large Outlays, HugeConsequences of Delays Uncertainties, Surprises,Changes, Lack of Clarity Inadequate Resources / Contingencies
  • 12. 12 Inadequate Resources / Contingencies • Efficient Project Management • Optimum utilization of funds Uncertainties, Surprises, Changes, Lack of Clarity • Strong Document Management • Appropriate Project Processes • Dynamic Change Management • Adequate Clarity of End Result Very Large Outlays, Huge Consequences of Delays • Robust Planning • Efficient Review and Control Mechanisms • Real Time Risks Management
  • 13. 13 Authority and Time Available for Making Decisions • Maximum Delegation of Authority to Project Team • Management Decision Making Ability • Swifter Decision Making Process Confict of Interests • Commitment and Support from the Top Management • Team Spirit Adequacy of Skills with Newly Created Project Team • Competent and Experienced Project Manager and Functional Leads Quality, Health, Safety and Environment Issues • Commitment to QHSE Plan at All Levels
  • 14. Supply Chain Management - Critical Function 14
  • 15. Perception of Internal Customer 15
  • 17. • 50 to 80 % of total project cost • Includes very high risk areas causing project delays and cost overruns • Large and diverse scope many first time and customized buying activities • Complex multi-modal logistics across borders • Very high dependence on multiple suppliers 17
  • 18. Functional Role During Project Stages 18 Budgeting phase Planning Phase Execution Phase
  • 19. Budgeting phase 19 • Early Involvement is Key to Success • Ownership of Cost and Time Estimates • Invoke Support from Strategic Suppliers for Packages and Service Contracts • Enter in to ‘Back to Back’ Arrangements • Broad Planning for ‘Critical Material List’ • Identify Major Supply Chain Risks / Mitigation Plan / Costs • Finalize / Renew Call Off Agreements • Broad Cash Flow for Supply Chain • Broad Supply Chain Organization Chart
  • 20. Planning Phase 20 • Formulate Project Supply Chain Strategies (component or package, lease or buy, local or international, approved or new source, etc.) • Prepare Approved Suppliers List • Draw Out Project Specific Supply Chain Procedure • Prepare Materials Control Chart / Logistics Plan / Cash Flow • Establish Micro level Plan for Critical Material list • Detailed Supply Chain Risk Management Plan • Finalize Project Supply Chain Organization
  • 21. Execution Phase 21 • Fast Track Ordering of Critical Materials List • Finalize Back to Back Orders for Strategic Supplies • Continuously Look for Cost Savings • Maximize Savings on Leverage Items (consolidate) • Invoke Call Off Agreements / Suppliers Managed Inventories for Non-Critical Materials • Frequent Review of Materials Tracking List with Project Team • Track Contract Progress / Manage Variations and Claims • Corrective Actions ( Cancellation / New Orders / Cost of Crashing) • Procurement Related Cash Flow Management • Full and Final Settlement of Major Supply / Service Order • Invoke Buy Back Arrangements With Suppliers
  • 22. Outsourcing of Services (Contracting) : Major Project Driver 22
  • 23. 23 Reasons why services are largely outsourced Reducing and controlling project costs For enhancing capability Gaining access to diverse capabilities / expertise Reducing capital costs Freeing internal resources for other projects Improving focus on project Agility, fexibility, ease of managing changes
  • 24. 24 Importance of outsourcing activity Significant costs Complexities due to interdependence Contract management crucial to project success Legal Angle Challenges in communication /interfacing
  • 25. Few examples of services outsourced: 25 • Detailed Engineering Services • Project Management Consultancy Services • Expediting Services • Inspection Services • Erection and Commissioning Services • Site works (civil, mechanical, electrical, instrumentation etc.) Contracts • Logistics Services • Setting up and Managing Site Accommodations / Facilities
  • 26. Structuring and Management of Service Contracts 26
  • 27. Contracting Scenarios: • Project owner undertake works with in-house resources • Project owner outsources most works to many specialized contractors • Project owner awards work to single contractor (turnkey contract) Types of Contract: • Cost Plus Fee Contract • Measurable contracts (Time and Material OR Unit Price contracts) • Lump sum Contract (Fixed Price Contract) • Turnkey Contracts (EPC Contract) 27
  • 28. Points for Consideration in Framing & Management of Service Contracts 28 • Clarity in scope of work (Battery limits, quantum, client obligations: extremely critical for lump sum contract) • Clear specifications for supply and services to be delivered • Clarity in contractual terms (Standard (like FIDIC) or tailor made format) • Mechanism for monitoring and approval of variations • Factoring local regulations / conditions • Deployment Plan (histogram) of manpower, construction equipment , other required resources • Applicable mode of measurement (example carpet area, or built up area) • Responsibility for stores management, material reconciliations (Free Issue Materials)
  • 29. Points for Consideration in Framing & Management of Service Contracts 29 • Monitoring of progress and corrective actions • Mechanism to admit extra claims (for extra work /Idle time / extended stay etc.), if admissible • Mechanism to record counter claims • Assigning single point contact and responsible person to address concerns • Provision for Dispute Resolution • Specifying applicable jurisdiction • Liquidated Damages • Performance Guarantees • Applicable Taxes and duties
  • 32. • Matrix structure found to be most suitable • Supply Chain Lead reports to head of procurement, as well as to the project manager of assigned project • Matrix structure combines functional expertise and operational accountability • This also empowers project manager who is responsible for timely completion of project within budget. • Supply Chain lead must be a great team player with leadership qualities • Buyers (Materials / Services), expediters, logistics coordinators, materials controllers are part of supply chain function. • Team spirit and versatility important factor in selection of team member 32
  • 34. Use of Technology • Use of suitable ERP system must for large projects • Many project companies use separate software for Design and Engineering, Planning, Document Control etc. • Industry specific software integrating above are developed. • Complete Supply Chain Cycle, starting from publishing RFQ can be performed on ERP system • Integration of supplier / contractors to ERP system. • Electronic work fow for approvals of ordering decisions extremely helpful • RFID (Radio Frequency Identification) / Bar Coding being used for material control 34
  • 36. 36  Early involvement (at bidding / budgeting stage)  End to end responsibility  Involvement of project team in ordering decisions  Delegation of authority for swift decision making  Development of specialized buying expertise  Training and competency building  Industry specific ERPs (like AVEVA/ EPICOR/ Use of Technology  Back to back arrangement for critical supplies / contracts  Rigorous supplier / contractor assessment and monitoring of supplies  End to end responsibility of supply chain function within project s Best Practices  Early involvement (at bidding / budgeting stage)  End to end responsibility  Involvement of project team in ordering decisions  Delegation of authority for swift decision making
  • 39. Case Study: Cost savings by optimizing specification / quantity consolidation • Overview: ▫ Construction of Oil Storage terminals. ▫ Approximately 18000 M.T. Steel Plates (6 mm to 38 mm thickness) were required for construction of Oil Storage Terminals on Turnkey Basis. ▫ Detailed engineering was scheduled to take 16 weeks to finalize all thickness and quantities progressively. ▫ Tank fabrication work must start within 4 weeks of project start date. ▫ Steel plates was single major bulk item having saving potential. 39
  • 40. • Approach : ▫ During discussion with project team, buyer realized that jacking method of construction required lower thickness (6 and 8 mm) plates first. Higher thickness plates may be delivered later. ▫ Engineering manager explained that theoretical thickness is calculated and then next higher standard thickness is selected. Also, that 6 and 8 thick plate can be ordered immediately. ▫ Buyer negotiated with steel mills willing to book order based on total approximate tonnage and tentative thickness. Require final thickness couple of weeks prior to rolling. Also, mills agree to roll non standard thickness if individual thickness tonnage is higher. ▫ Buyer ordered smaller thickness plates(15% of total tonnage) from local stockist and remaining higher thickness plates from mill. 40
  • 41. • Result: ▫ Reduction of tonnage due to non standard thickness and competitive price from mill for larger consolidated quantity resulted in net 8% savings on major line item in project cost sheet. Also, deliveries were made as per project requirement. • Conclusion: ▫ Consolidation of quantities and optimization of specification can result in bigger savings. ▫ By out of box thinking and by working beyond departmental boundaries, supply chain function can add value. 41