TA-18 PRESENTATION - MAJOR JOB has been providedS.pptx
1. TA-18 MAJOR JOB
Plant : MS BLOCK
Name of Job : CCR Reactor Inspection and compliance to UOP
recommendations
Scope In Brief : Complete overhauling and inspection of reactor
including removal and re-installation of internals;
replacement of internal gaskets / fasteners to
comply UOP recommendations.
Job Duration : 22 Days (Mechanical Scope)
Material Availability Status:
Dur-O-Lok couplings P.O. – 4300000082 CDD - 03.08.2018
Internal Gaskets P.O. – 4300000076 CDD - 27.07.2018
Stud bolts P.O. – 4300000015 CDD - 11.05.2018
Service Status : Under Tendering