1. 1. Understand the workflow steps
WOR Survey (operation)
1. PE prepare TP survey and submit to Technical and commercial
(T&C)
2. T&C submit WOP to CE
3. CE issue PO survey
4. T&C submit handover to PE
5. PE develop manpower and equipment timesheet and arrange for
survey with workpack.
2. • Site survey (operation)
1. General supervisor(GS) and project engineer cover the site survey
2. GS come out with signed survey report
3. PE need to present survey report to CE
4. PE directly share timesheet (from OTS) with DC
• WOR Execution (operation)
1. PE follow on WOR execution (CE)
2. Technical package (TP) operation
3. WOP (T&C MCM)
5. 4. Meeting with Client
• Mr Yakin Mat Isa (Senior pipeline engineer, PMO/UPSTERAM-
Petronas)
• Prrovision Of Riser Corrosion Prevention System And Maintenance
For PCSB for Package C (PMA)
• Dulang Platform Project, DLA, DLB, DLC, DLD
• Purchase Order ; WOR 2020 -002
6. • Based on photo report from site survey (Visual inspection) on 22 FEB 2020.
• Site survey by:
• mohd hanizam (supervisor DPSB)
• muhamad saat (Rigger DPSB)
• Area survey = valve, major barrel, minor barrel, reducer, pipe support, end
closure door, riser pipe, top flange, line work, riser bend, hanger pipe,
MOV/SDV, neoprene coating, riser clamp
• Site survey objective (to detail the scope of work);
• visual inspect
• assess the accessibility
• identify solution and method required
• quantity the scaffolding required.