SlideShare a Scribd company logo
PORTAL FRAMES
Version II
36 - 19
15 m
30 m
5 m c / c
3 m
6 m
3.25 m
15 m
0.6 m 0.6 m
A
B
C
D
E
F
G
Job No: Sheet 1 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Problem
Analyse and Design a single span portal frame with gabled roof. The frame
has a span of 15 m, the column height 6m and the rafter rise 3m. Purlins are
provided @ 2.5 m c/c.
Load
1.0 Load Calculation
1.1 Dead Load
Weight of asbestos sheeting = 0.17 kN/m2
Fixings = 0.025 kN/m2
Services = 0.100 kN/m2
Weight of purlin = 0.100 kN/m2
---------------
Total load /m2
= 0.395 kN/m2
---------------
PORTAL FRAMES
Version II
36 - 20
13.8 m
1 m
( 300 + 60 ) 300
B F
6.9 m
Job No: Sheet 2 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Dead load/m run = 0.395 * 5
= 1.975 kN / m
2.0 kN/m
1.2 Live Load
Angle of rafter = tan-1
(3/7.5) = 21.80
From IS: 875 (part 2) – 1987; Table 2 (cl 4.1),
= 2.57 kN/m
1.3 Crane Loading
Overhead electric crane capacity = 300 kN
Approximate weight of crane girder = 300 kN
Weight of crab = 60 kN
The extreme position of crane hook is assumed as 1 m from the centre line of
rail. The span of crane is approximately taken as 13.8 m. And the wheel
base has been taken as 3.8 m
1.3.1 Vertical load
The weight of the crane is shared equally by four wheels on both sides. The
reaction on wheel due to the lifted weight and the crab can be obtained by
taking moments about the centreline of wheels.
MB = 0
5
*
10)
(21.8
0.02
0.75
run
m
/
load
Live
PORTAL FRAMES
Version II
36 - 21
Job No: Sheet 3 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
2 RF (13.8) = (300 + 60) * 1 + 300 * (6.90)
RF = 88 kN
MF = 0
2 RB (13.8) = (300 + 60) * (13.8-1) + 300 * (6.9)
RB = 242 kN
To get maximum wheel load on a frame from gantry girder BB', taking the
gantry girder as simply supported.
Centre to centre distance between frames is 5 m c/c.
Assuming impact @ 25%
Maximum wheel Load @ B = 1.25 (242 (1 + (5-3.8)/5)
= 375 kN.
Minimum wheel Load @ B = (88 /242)*375
=136.4 kN
1.3.2 Transverse Load:
Lateral load per wheel = 5% (300 + 60)/2 = 9 kN
(i.e. Lateral load is assumed as 5% of the lifted load and the weight of the
trolley acting on each rail).
Lateral load on each column *375
242
9
= 13.9 kN
(By proportion)
242 kN 242 kN
3.8 m
5 m
B' B
PORTAL FRAMES
Version II
36 - 22
Job No: Sheet 4 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
1.4 Wind Load
Design wind speed, Vz = k1 k2 k3 Vb
From Table 1; IS: 875 (part 3) – 1987
k1 = 1.0 (risk coefficient assuming 50 years of design life)
From Table 2;IS: 875 (part 3) – 1987
k2 = 0.8 (assuming terrain category 4)
k3 = 1.0 (topography factor)
Assuming the building is situated in Chennai, the basic wind speed is
50 m /sec
Design wind speed, Vz = k1 k2 k3 Vb
Vz = 1 * 0.8 *1 * 50
Vz = 40 m/sec
Basic design wind pressure, Pd = 0.6*Vz
2
= 0.6 * (40)2
= 0.96 kN/m2
1.4.1. Wind Load on individual surfaces
The wind load, WL acting normal to the individual surfaces is given by
WL = (Cpe – Cpi ) A*Pd
(a) Internal pressure coefficient
Assuming buildings with low degree of permeability
Cpi = 0.2
PORTAL FRAMES
Version II
36 - 23
h
w
w
L
plan elevation
Job No: Sheet 5 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
(b) External pressure coefficient
External pressure coefficient for walls and roofs are tabulated in Table 1 (a)
and Table 1(b)
1.4.2 Calculation of total wind load
(a) For walls
h/w = 6/15 = 0.4
L/w = 30/15 = 2.0
Exposed area of wall per frame @ 5 m c/c
is
A = 5 * 6 = 30 m2
For walls, A pd = 30 * 0.96 = 28.8 kN
Table 1 (a): Total wind load for wall
Cpe Cpi Cpe – Cpi Total wind(kN)
(Cpe-Cpi )Apd
Wind
Angle
Wind-
ward
Lee-
ward
Wind
ward
Lee
ward
Wind
ward
Lee
ward
0.2 0.5 -0.45 14.4 -12.9
00
0.7 -0.25
-0.2 0.9 -0.05 25.9 -1.4
0.2 -0.7 -0.7 -20.2 -20.2
900
-0.5 -0.5
-0.2 -0.3 -0.3 -8.6 -8.6
(b) For roofs
Exposed area of each sloping roof per frame @ 5 m c/c is
2
2
2
m
40.4
7.5
3.0
*
5
A
PORTAL FRAMES
Version II
36 - 24
15 m
Job No: Sheet 6 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
For roof, Apd = 38.7 kN
Table 1 (b): Total wind load for roof
Pressure Coefficient Cpe – Cpi Total Wind Load(kN)
(Cpe – Cpi) Apd
Cpe Cpe Wind
ward
Lee
ward
Wind
ward
Lee
ward
Wind
angle
Wind Lee
Cpi
Int. Int.
-0.328 -0.4 0.2 -0.528 -0.6 -20.4 -23.2
00
-0.328 -0.4 -0.2 -0.128 -0.2 -4.8 -7.8
-0.7 -0.7 0.2 -0.9 -0.9 -34.8 -34.8
900
-0.7 -0.7 -0.2 -0.5 -0.5 -19.4 -19.4
2.0 Equivalent Load Calculation
2.1 Dead Load
Dead Load = 2.0 kN/m
Replacing the distributed dead load on rafter by equivalent concentrated
loads at two intermediate points on each
rafter,
kN
6
15
*
2.0
WD 5
2.2 Superimposed Load
Superimposed Load = 2.57 kN/m
Concentrated load , purlin
kN/
6.4
6
15
*
2.57
L
W
PORTAL FRAMES
Version II
36 - 25
Job No: Sheet 7 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
2.3 Crane Load
Maximum Vertical Load on columns = 375 kN (acting at an eccentricity of
600 mm from column centreline)
Moment on column = 375 *0.6 = 225 kNm.
Minimum Vertical Load on Column = 136.4 kN (acting at an eccentricity of
600 mm)
Maximum moment = 136.4 * 0.6 = 82 kNm
3.0 Partial Safety Factors
3.1 Load Factors
For dead load, f = 1.5
For major live load, f = 1.5
For minor live load or defined live load, f = 1.05
3.2 Material Safety factor
m = 1.10
4.0 Analysis
In this example, the following load combinations are considered, as they are
found to be critical.
Similar steps can be followed for plastic analysis under other load
combinations.
(i) 1.5D.L + 1.05 C .L + 1.5 W.L
PORTAL FRAMES
Version II
36 - 26
kN
2.6
2
5.2
eaves
@
2
w
35
7
kN
2
eaves
@
2
w
94
.
1
88
.
3
Job No: Sheet 8 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
(ii) 1.5 D.L + 1.05 C.L+ 1.5 L.L
4.1. 1.5 D.L + 1.05 C.L+ 1.5 W.L
4.1.1Dead Load and Wind Load
(a) Vertical Load
w @ intermediate points on windward side
w = 1.5 * 5.0 – 1.5 *(4.8/3) cos21.8
= 5.27 kN.
w @ intermediate points on leeward side
w = 1.5 * 5.0 – 1.5 * 7.8/3 cos21.8
= 3.88 kN
Total vertical load @ the ridge = 2.635 + 1.94 = 4.575 kN
b) Horizontal Load
H @ intermediate points on windward side
H = 1.5 * 4.8/3 sin 21.8
= 0.89 kN
PORTAL FRAMES
Version II
36 - 27
Job No: Sheet 9 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
H/2 @ eaves points = 0.89/2 = 0.445 kN
H @ intermediate purlin points on leeward side
= 1.5 * 7.8 /3 sin 21.8
= 1.45 kN
H/2 @ eaves = 0.725 kN
Total horizontal load @ the ridge = 0.725 - 0.445 = 0.28 kN
Table 3: Loads acting on rafter points
Vertical Load (kN) Horizontal Load (kN)
Windward Leeward Windward Leeward
Intermediate
Points 5.27 3.88 0.89 1.45
Eaves 2.635 1.94 0.445 0.725
Ridge 4.575 0.28
4.1.2 Crane Loading
Moment @ B = 1.05 * 225 = 236.25 kNm
Moment @ F = 1.05 * 82 = 86.1 kNm
Horizontal load @ B & @ F = 1.05 * 13.9 = 14.6 kN
Note: To find the total moment @ B and F we have to consider the moment
due to the dead load from the weight of the rail and the gantry girder. Let us
assume the weight of rail as 0.3 kN/m and weight of gantry girder as 2.0
kN/m
Dead load on the column =
Factored moment @ B & F = 1.05 * 5.75 * 0.6 = 3.623 kNm
kN
5.75
5
*
2
0.3
2
PORTAL FRAMES
Version II
36 - 28
Job No: Sheet 10 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Total moment @ B = 236.25 + 3.623 = 239.9 kNm
@ F = 86.1 + 3.623 = 89.7 kNm
4.2 1.5 D.L + 1.05 C.L + 1.5 L.L
4.2.1 Dead Load and Live Load
@ intermediate points on windward side = 1.5 * 5.0 + 1.5 * 6.4
= 17.1 kN
@ ridge = 17.1 kN
@ eaves = 17.1 / 2 8.55 kN.
15 m
3 m
6 m
3.25 m
14.6 kN
14.6 kN
239.9 89.7
38.85 kN 2.1 kN
Factored Load (1.5D.L+1.05 C.L +1.5 W.L)
1.45 kN
1.45 kN
0.725 kN
0.28 kN
4.575 kN
3.88 kN
3.88 kN
1.94 kN
0.89 kN
0.89 kN
5.27 kN
5.27 kN
2.635 kN
0.445 kN
PORTAL FRAMES
Version II
36 - 29
Job No: Sheet 11 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
4.2.2 Crane Load
Moment @ B = 239.9 kNm
Horizontal load @ B = 14.6 kN
Moment @ F = 89.7 kNm
Horizontal load @ F = 14.6 kN
4.3 Mechanisms
We will consider the following mechanisms, namely
(i) Beam mechanism
(ii) Sway mechanism
(iii) Gable mechanism and
(iv) Combined mechanism
Factored Load (1.5 D.L + 1.05 C.L + 1.5 L.L)
3 m
6 m
3.25 m
17.1 kN
17.1 kN
17.1 kN
17.1 kN
8.55 kN
17.1 kN
15 m
14.6 kN
14.6 kN
239.9 89.7
kNm kNm
PORTAL FRAMES
Version II
36 - 30
Job No: Sheet 12 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
4.3.1 Beam Mechanism
(1) Member CD
Case 1: 1.5 D.L + 1.05 C.L + 1.5 W.L
Internal Work done, Wi = Mp + Mp ( /2) + Mp ( + /2)
= Mp(3 )
External Work done, We = 5.27 * 2.5 - 0.89 * 1 * +5.27 * 2.5 * /2 – 0.89
* 1 * /2
= 18.43
Equating internal work done to external work done
Wi = We
Mp (3 ) = 18.43
Mp = 6.14 kNm
Case 2: 1.5 D.L + 1.05 C.L + 1.5 L.L
Internal Work done, Wi = Mp ( + /2 + + /2)
Wi = Mp 3
4.575 kN
0.89 kN
5.27 kN
0.89 kN
0.445 kN
5.27 kN
0.28 kN
2.635 kN
/2
PORTAL FRAMES
Version II
36 - 31
Job No: Sheet 13 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External work done, We = 17.1 * 2.5 + 17.1 *2.5 /2
= 64.125
Equating Wi = We,
Mp (3 ) = 64.125
Mp = 21.375 kNm
Note: Member DE beam mechanism will not
govern.
(2) Member AC
Internal Work done,
p
M
3.69
13
11
p
M
13
11
p
M
p
M
i
W
17.1 kN
17.1 kN
17.1 kN
8.55 kN
/2
14.6 kN
38.85 kN
11 /13
239.9 kNm
PORTAL FRAMES
Version II
36 - 32
Job No: Sheet 14 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External Work done,
Equating Wi = We, we get
3.69 Mp = 296.6
Mp = 80.38 kNm.
(3) Member EG
Internal Work done,
External Work done,
Equating Wi = We, we get
3.69 Mp = 321.7
p
M
3.69
13
11
p
M
13
11
p
M
p
M
i
W
6
.
296
*
85
.
38
*
*
9
.
239
*
*
6
.
14
13
11
3.25
2
1
13
11
13
11
3.25
We
13
11
3.25
*
)
(
2
1
*
13
11
*
3.25
*
We
7
.
321
3
.
30
9
.
239
6
.
14
14.6 kN
239.9 kNm
30.3 kN
11 /13
PORTAL FRAMES
Version II
36 - 33
Job No: Sheet 15 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Mp = 87.2 kNm
For members AC & EG, the 1st
load combination will govern the failure
mechanism.
4.3.2 Panel Mechanism
Case 1: 1.5 D.L + 1.05 C.L + 1.5 W.L
Internal Work done, Wi = Mp ( ) + Mp ( ) + Mp ( ) + Mp ( )
= 4Mp
External Work done, We
We = 1/2 (38.85) * 6 + 14.6 * 3.25 + 239.9 - 0.445 * 6 - 0.89 * 6 -
0.89(6 )+ 0.28 * 6 + 1.45 *6 + 1.45 * 6 + 0.725 * 6 +1/2 (2.1) * 6 +
14.6 * 3.25 - 89.7 *
= 378.03
14.6 kN
239.9 kNm
14.6 kN
89.7 kNm
38.85 kN 2.1 kN
1.45
1.45
0.725
0.28
4.575
3.88
3.88
1.94
5.27
0.89
5.27
0.89
2.635
0.445
PORTAL FRAMES
Version II
36 - 34
Job No: Sheet 16 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Equating Wi = Wc, we get
4Mp = 378.03
Mp = 94.51 kNm
The second load combination will not govern.
4.3.3 Gable Mechanism
Case 1: 1.5 D.L + 1.5 W.L + 1.05 C.L
Internal Work done = Mp + Mp2 + Mp (2 ) + Mp = 6Mp
External Work done, We =
-0.89 * 1 * - 0.89 * 2 * + 0.28 * 3 * + 1.45 * 4 * + 1.45 * 5 * +
0.725 * 6 * + 5.27 * 2.5 * + 5.27 * 5 * + 4.575 * 7.5 * + 3.88 * 5 *
+ 3.88 * 2.5 * + ½ * 2.1 * 6 + 14.6 * 3.25 * - 89.7*
We = 82.56
1.45
1.45
0.725
0.28
4.575
3.88
3.88
1.94
0.89
0.89
5.27
5.27
2.63
5
0.445
14.6 kN
239.9 kNm
14.6 kN
89.7 kNm
38.85 kN 2.1 kN
PORTAL FRAMES
Version II
36 - 35
Job No: Sheet 17 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Equating Wi = We, we get
6Mp = 82.56
Mp = 13.76 kNm.
Case 2: 1.5 D.L + 1.5L.L + 1.05 C.L
Internal Work done, Wi = Mp + Mp (2 ) + Mp (2 ) + Mp =6Mp
External Work done, We
= 17.1 * 2.5* + 17.1 * 5 * + 17.1 * 7.5 + 17.1 * 5 * + 17.1 * 2.5 -
89.7 * + 14.6 * 3.25
= 342.5
Equating Wi = We, we get
6Mp = 342.5
Mp = 57.1 kNm
17.1
17.1
17.1
17.1
8.55
17.1
14.6 kN
14.6 kN
239.9kNm 89.7 kNm
8.55
PORTAL FRAMES
Version II
36 - 36
Job No: Sheet 18 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
4.3.4 Combined Mechanism
Case1: 1.5 D.L + 1.5 W.L + 1.05 C.L
(i)
Internal Work done, Wi = Mp ( ) + Mp ( + /2) + Mp ( /2 + /2) + Mp ( /2)
= Mp ( + + /2 + /2 + /2 + /2 + /2)
= 4 Mp
External Work done, We=
1/2 * 38.85 * 6 + 14.6 * 3.25* + 239.9 - 0.445 * 12 * /2 - 0.89 * 11 *
/2 - 0.89 * 10 * /2 + 0.28 * 9 * /2 + 1.45 * 8 * /2 + 1.45 * 7 * /2 +
0.725 * 6* /2 + 1/2 (2.1) * 6 /2 + 14.6 * 3.25 * /2 – 89.7 * /2 – 5.27 * 2.5
* /2 – 5.27 * 5.0 * /2 – 4.575 * 7.5 * /2 – 3.88 * 5 * /2 – 3.88 * 2.5 * /2
= 336.75
/2
/2
/2
14.6 kN
239.9 kNm
14.6 kN
89.7 kNm
38.85 kN
2.1 kN
1.45
1.45
0.725
0.28
4.575
3.88
3.88
1.94
0.89
0.89
5.27
5.27
2.635
0.445
12 m
PORTAL FRAMES
Version II
36 - 37
Job No: Sheet 19 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Equating Wi = We
4Mp = 336.75
Mp = 84.2 kNm
(ii) Internal work done, Wi = Mp /2 + Mp ( /2 + /2) + Mp ( /2 + )
+Mp
Wi = 4Mp
/2
/2 /2
14.6 kN
239.9 kNm
14.6 kN
89.7 kNm
38.85 kN 2.1 kN
1.45
1.45
0.725
0.28
4.575
3.88
3.88
1.94
0.89
0.89
5.27
5.27
2.635
0.445
12 m
PORTAL FRAMES
Version II
36 - 38
2
1
3.25
2
2.5
2
5.0
2
12
5
0.
2
11
1.
2
10
1.
2
7.5
7
4.
2
5.0
5.2
2
2.5
5.2
2
9
0.
2
8
0.
2
7
0.
2
6
0.
2
6
2
1
2
2
3.25
We
*
1
.
2
*
*
7
.
89
*
6
.
14
*
*
88
.
3
*
*
88
.
3
*
*
72
*
*
45
*
*
45
*
*
5
5
*
*
7
*
*
7
*
*
28
*
*
89
*
*
89
*
*
445
*
85
.
38
*
*
9
.
239
*
*
6
.
14
Job No: Sheet 20 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External Work done,
= 230.3
Equating Wi = We, we get
4Mp = 230.3
Mp = 57.575 kNm
(iii)
36 m
0.28
4.575
3.88
3.88
1.98
5 /6
38.85 kN
0.89
0.89
5.27
5.27
2.635
0.445
14.6 kN
239.9 kNm
/6 /6
1.45
1.45
0.725
2.1 kN
14.6 kN
89.7 kNm
PORTAL FRAMES
Version II
36 - 39
p
4M
)
p
M
6
p
M
6
6
p
M
6
p
M
)
(6
)
(
2
1
*
3.25
*
6
*
2.5
*
6
*
5.0
*
6
*
7.5
*
7
4.
6
*
10
*
5.2
6
*
12.5
*
5.2
6
*
36
*
5
0.
6
*
35
*
1.
6
*
34
*
1.
6
*33*
0.
6
*
34
*
0.
6
*
35
*
0.
6
*
6
*
0.
6
*
6
*
*
2
1
6
*
6
*
*3.25
*
1
.
2
7
.
89
6
.
14
88
.
3
88
.
3
5
5
7
7
72
45
45
28
89
89
445
85
.
38
9
.
239
6
.
14
Job No: Sheet 21 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Internal work done, Wi
External Work done, We =
We = 341.07
Equating Wi = We, we get
4Mp = 341.07
Mp = 85.27 kNm
(iv) Internal Work done,
p
4M
p
M
3
p
M
3
3
2
p
M
3
2
p
M
i
W
PORTAL FRAMES
Version II
36 - 40
Job No: Sheet 22 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External Work done, We =
Equating Wi = We, we get
4Mp = 293.22
Mp = 73.3 kNm
W
*
)
(
2
1
*
3.25
*
3
2.5
*
3
*
*5.0
3
*
18
*
5
0.
3
*
17
*
1.
3
*
16
*
1.
3
*
15
*
0.
3
7.5*
*
7
4.
3
2
*
5
*
5.2
3
2
*
2.5
*
5.2
3
*
*15
0.
3
*
16
*
0.
3
2
*
7
*
0.
3
2
*
6
*
0.
3
2
*
6
*
*
2
1
3
2
*
3
2
*
*3.25
e 22
.
293
1
.
2
7
.
89
6
.
14
88
.
3
88
.
3
72
45
45
28
5
5
7
7
28
89
89
445
85
.
38
9
.
239
6
.
14
2 /3
/3
/3
14.6 kN
239.9 kNm
14.6 kN
89.7 kNm
38.85 kN 2.1 kN
1.45
1.45
0.725
0.28
4.575
3.88
3.88
1.94
0.89
0.89
5.27
5.27
2.635
0.445
18 m
PORTAL FRAMES
Version II
36 - 41
Job No: Sheet 23 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Case 2: 1.5 D.L + 1.5 L.L + 1.05 C.L
(i) Assuming plastic hinge is formed @ purlin point 2 and 7 and at fixed
supports.
Internal Work done
p
4M
p
M
6
p
M
6
6
p
M
6
p
M
5 /6
/6 /6
17.1
17.1
17.1
17.1
8.55
17.1
14.6 kN
14.6 kN
239.9 kNm 89.7
36 m
8.55
5 /6
/6
PORTAL FRAMES
Version II
36 - 42
Job No: Sheet 24 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External Work done =We
Equating Wi =We, we get
4Mp = 304.1
Mp = 76.03 kNm
Plastic hinge is formed @ 3 and 7
.
3
3.25
6
2.5
6
5.0
6
7.5
6
10
6
2.5
1
6
6
3.25
1
04
7
.
89
*
*
6
.
14
*
*
1
.
17
*
*
1
.
17
*
*
1
.
17
*
*
1
.
17
*
*
1
.
17
*
9
.
239
*
*
6
.
14
/3 /3
17.1
17.1
17.1
17.1
8.55
17.1
14.6 kN
14.6 kN
239.9
kNm
89.7
18 m
8.55
2 /3
PORTAL FRAMES
Version II
36 - 43
.
3
3.25
3
2.5
1
3
5.0
1
3
7.5
1
3
2
5.0
1
3
2
2.5
1
3
2
3
2
3.25
3
20
7
.
89
*
6
.
14
*
*
1
.
7
*
*
1
.
7
*
*
1
.
7
*
*
1
.
7
*
*
1
.
7
*
9
.
239
*
*
6
.
14
p
p
p
p
p
i
M
M
M
M
M
W
4
3
3
3
2
3
2
Job No: Sheet 25 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Internal work done,
External Work done, We=
Equating Wi = We, we get
4Mp = 320.3
Mp = 80.1 kNm
(ii) Plastic hinged is formed at 4 and 7
Internal Work done
p
M
4
p
M
2
p
M
2
2
p
M
2
p
M
PORTAL FRAMES
Version II
36 - 44
Job No: Sheet 26 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
External Work done, We =
Equating Wi = We
4Mp = 293.8
Mp = 73.45 kNm
/2
/2 /2
17.1
17.1
17.1
17.1
8.55
17.1
14.6 kN
14.6 kN
239.9 89.7
12 m
8.55
/2
8
.
293
7
.
89
25
.
3
*
6
.
14
2
*
5
.
2
*
1
.
17
2
*
0
.
5
*
1
.
17
2
*
5
.
7
*
1
.
17
2
*
0
.
5
*
1
.
17
2
*
5
.
2
*
1
.
17
2
*
9
.
239
2
*
25
.
3
*
6
.
14
PORTAL FRAMES
Version II
36 - 45
3
W
*
3.25
*
*2.5
1
*
5.0
*
1
2
*
7.5
*
1
2
*
5.0
*
1
2
*
2.5
*
1
2
*
2
*
*3.25
e 3
.
56
7
.
89
1
.
14
1
.
7
1
.
7
1
.
7
1
.
7
1
.
7
9
.
239
6
.
14
Job No: Sheet 27 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
(iii) Plastic hinge is formed @ 5 and 7
Internal Work Done,Wi =
External work done, We =
p
M
5
i
W
p
M
p
M
2
p
M
2
p
M
6 m
/2
17.1
17.1
17.1
17.1
8.55
14.6 kN
14.6 kN
239.9
/2
17.1
89.7
PORTAL FRAMES
Version II
36 - 46
Job No: Sheet 28 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Equating Wi = We
5Mp = 356.3 *
Mp = 71.26 kNm
Design Plastic Moment = 94.51 kNm.
5.0 DESIGN
For the design it is assumed that the frame is adequately laterally braced so
that it fails by forming mechanism. Both the column and rafter are
analysed assuming equal plastic moment capacity. Other ratios may
be adopted to arrive at an optimum design solution.
5.1 Selection of section
Plastic Moment capacity required= 94.51 kNm
Required section modulus, Z = Mp/ fyd
From IS: 800 (Appendix I)
ISMB 300 @ 0.46 kN/ m provides
Zp = 651 * 10-3
mm3
b = 140 mm
Ti = 12.4 mm
A = 5.626 * 10 3
mm2
tw =7.5 mm
rxx =124 mm
ryy =28.4 mm
3
3
10
*
84
.
415
51
.
94
mm
1.1
250
*106
PORTAL FRAMES
Version II
36 - 47
1
f
T
b
4
.
9
65
4
.
2
5.
1
70
T
b
1
f
Job No: Sheet 29 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
5.2 Secondary Design Considerations
5.2.1 Check for Local buckling of flanges and webs
Flanges
bf = 140/2 = 70 mm
T1 = 12.4 mm
t = 7.5 mm
Web
O.K.
5.2.2 Effect of axial force
Maximum axial force in column, P = 51.3 kN
9
.
83
40
5
.
7
300
t
d1
PORTAL FRAMES
Version II
36 - 48
kN
27
*10
5.
1.1
250 3
8
1
626
Job No: Sheet 30 of 30 Rev
Job Title: Portal Frame Analysis and Design
Worked Example: 1
Made By
PU
Date
Structural Steel
Design Project
Calculation Sheet
Checked By
VK
Date
Axial load causing yielding, Py = fyd * A
Therefore the effect of axial force can be neglected.
5.2.3 Check for the effect of shear force
Shear force at the end of the girder = P- w/2
= 51.3 –8.55 kN
= 42.75 kN
Maximum shear capacity Vym, of a beam under shear and moment is given
by
Vym = 0.5 Aw* fyd / 1.1
= 0.5 * 300* 7.5* 250/1.1
=255.7 kN>> 42.75 kN
Hence O.K.
0.15
0.0
127
P
P
y
4
8
3
.
51

More Related Content

What's hot

Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Hossam Shafiq II
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
sathananthankartheep
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
Priodeep Chowdhury
 
Analysis of psc sections for flexure
Analysis of psc sections for flexureAnalysis of psc sections for flexure
Analysis of psc sections for flexure
ManjunathM137700
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
Mahesh Raj Bhatt
 
Bridge
BridgeBridge
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Pooja Lonare
 
Introduction to Bridges.pdf
Introduction to Bridges.pdfIntroduction to Bridges.pdf
Introduction to Bridges.pdf
karthik sampath
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Hossam Shafiq II
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Hossam Shafiq II
 
H Igh Rise 02 Lateral Load Systems 01
H Igh Rise 02 Lateral Load Systems 01H Igh Rise 02 Lateral Load Systems 01
H Igh Rise 02 Lateral Load Systems 01
tharwat sakr
 
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul LeslieModelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Rahul Leslie
 
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSEDDESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
LOGESH S
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Reportherry924
 
Bs procedure
Bs procedureBs procedure
Bs procedurehlksd
 
Chapter 4 (deep foundation)
Chapter 4 (deep foundation)Chapter 4 (deep foundation)
Chapter 4 (deep foundation)
Kaizer Bo
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
mbrsalman
 
Hot weather concreting
Hot weather concretingHot weather concreting
Hot weather concreting
AbduBasit2
 

What's hot (20)

Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Analysis of psc sections for flexure
Analysis of psc sections for flexureAnalysis of psc sections for flexure
Analysis of psc sections for flexure
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
Bridge
BridgeBridge
Bridge
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Introduction to Bridges.pdf
Introduction to Bridges.pdfIntroduction to Bridges.pdf
Introduction to Bridges.pdf
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
H Igh Rise 02 Lateral Load Systems 01
H Igh Rise 02 Lateral Load Systems 01H Igh Rise 02 Lateral Load Systems 01
H Igh Rise 02 Lateral Load Systems 01
 
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul LeslieModelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
 
bridge design
 bridge design bridge design
bridge design
 
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSEDDESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
DESIGN OF CONTINUOUS MEMBERS IN PRESTRESSED
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Report
 
Bs procedure
Bs procedureBs procedure
Bs procedure
 
Chapter 4 (deep foundation)
Chapter 4 (deep foundation)Chapter 4 (deep foundation)
Chapter 4 (deep foundation)
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
Hot weather concreting
Hot weather concretingHot weather concreting
Hot weather concreting
 

Similar to Structural Steel Design Project.pdf

Steel Warehouse Project
Steel Warehouse ProjectSteel Warehouse Project
Steel Warehouse ProjectJawad Shaukat
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
Anjneya Srivastava
 
Chapter 1-types of structures and loads
Chapter 1-types of structures and loadsChapter 1-types of structures and loads
Chapter 1-types of structures and loads
ISET NABEUL
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
DP NITHIN
 
Example314b taskgroupb-c-120730160543-phpapp01
Example314b taskgroupb-c-120730160543-phpapp01Example314b taskgroupb-c-120730160543-phpapp01
Example314b taskgroupb-c-120730160543-phpapp01
Ramil Artates
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural Analysis
DavidJPCChai
 
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
irjes
 
EQ21.pdf
EQ21.pdfEQ21.pdf
Design of housing apartment
Design of  housing apartmentDesign of  housing apartment
Design of housing apartment
SUBHOJIT BERA
 
Structural Analysis of a Bungalow Report
Structural Analysis of a Bungalow ReportStructural Analysis of a Bungalow Report
Structural Analysis of a Bungalow Report
douglasloon
 
Structural analysis of a bungalow report
Structural analysis of a bungalow reportStructural analysis of a bungalow report
Structural analysis of a bungalow report
ChengWei Chia
 
Cee 312(2)
Cee 312(2)Cee 312(2)
Cee 312(2)
apudgr8
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
IRJET Journal
 
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Kumar Aman
 
Structural Analysis of a Bungalow
Structural Analysis of a BungalowStructural Analysis of a Bungalow
Structural Analysis of a Bungalow
Jing Fan Koh
 
Building Structures
Building StructuresBuilding Structures
Building Structures
Yuan0623
 
Design of Various Types of Industrial Buildings and Their Comparison
Design of Various Types of Industrial Buildings and Their ComparisonDesign of Various Types of Industrial Buildings and Their Comparison
Design of Various Types of Industrial Buildings and Their Comparison
IRJESJOURNAL
 
Design of manual solar tracking system wps
Design of manual solar tracking system wpsDesign of manual solar tracking system wps
Design of manual solar tracking system wps
Microware Technologies Private Limited
 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI House
Carmen Chan
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
sabishanu
 

Similar to Structural Steel Design Project.pdf (20)

Steel Warehouse Project
Steel Warehouse ProjectSteel Warehouse Project
Steel Warehouse Project
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
Chapter 1-types of structures and loads
Chapter 1-types of structures and loadsChapter 1-types of structures and loads
Chapter 1-types of structures and loads
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
 
Example314b taskgroupb-c-120730160543-phpapp01
Example314b taskgroupb-c-120730160543-phpapp01Example314b taskgroupb-c-120730160543-phpapp01
Example314b taskgroupb-c-120730160543-phpapp01
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural Analysis
 
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
Comparative Study of Pre-Engineered and Conventional Steel Frames for Differe...
 
EQ21.pdf
EQ21.pdfEQ21.pdf
EQ21.pdf
 
Design of housing apartment
Design of  housing apartmentDesign of  housing apartment
Design of housing apartment
 
Structural Analysis of a Bungalow Report
Structural Analysis of a Bungalow ReportStructural Analysis of a Bungalow Report
Structural Analysis of a Bungalow Report
 
Structural analysis of a bungalow report
Structural analysis of a bungalow reportStructural analysis of a bungalow report
Structural analysis of a bungalow report
 
Cee 312(2)
Cee 312(2)Cee 312(2)
Cee 312(2)
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
 
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
 
Structural Analysis of a Bungalow
Structural Analysis of a BungalowStructural Analysis of a Bungalow
Structural Analysis of a Bungalow
 
Building Structures
Building StructuresBuilding Structures
Building Structures
 
Design of Various Types of Industrial Buildings and Their Comparison
Design of Various Types of Industrial Buildings and Their ComparisonDesign of Various Types of Industrial Buildings and Their Comparison
Design of Various Types of Industrial Buildings and Their Comparison
 
Design of manual solar tracking system wps
Design of manual solar tracking system wpsDesign of manual solar tracking system wps
Design of manual solar tracking system wps
 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI House
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 

Structural Steel Design Project.pdf

  • 1. PORTAL FRAMES Version II 36 - 19 15 m 30 m 5 m c / c 3 m 6 m 3.25 m 15 m 0.6 m 0.6 m A B C D E F G Job No: Sheet 1 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Problem Analyse and Design a single span portal frame with gabled roof. The frame has a span of 15 m, the column height 6m and the rafter rise 3m. Purlins are provided @ 2.5 m c/c. Load 1.0 Load Calculation 1.1 Dead Load Weight of asbestos sheeting = 0.17 kN/m2 Fixings = 0.025 kN/m2 Services = 0.100 kN/m2 Weight of purlin = 0.100 kN/m2 --------------- Total load /m2 = 0.395 kN/m2 ---------------
  • 2. PORTAL FRAMES Version II 36 - 20 13.8 m 1 m ( 300 + 60 ) 300 B F 6.9 m Job No: Sheet 2 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Dead load/m run = 0.395 * 5 = 1.975 kN / m 2.0 kN/m 1.2 Live Load Angle of rafter = tan-1 (3/7.5) = 21.80 From IS: 875 (part 2) – 1987; Table 2 (cl 4.1), = 2.57 kN/m 1.3 Crane Loading Overhead electric crane capacity = 300 kN Approximate weight of crane girder = 300 kN Weight of crab = 60 kN The extreme position of crane hook is assumed as 1 m from the centre line of rail. The span of crane is approximately taken as 13.8 m. And the wheel base has been taken as 3.8 m 1.3.1 Vertical load The weight of the crane is shared equally by four wheels on both sides. The reaction on wheel due to the lifted weight and the crab can be obtained by taking moments about the centreline of wheels. MB = 0 5 * 10) (21.8 0.02 0.75 run m / load Live
  • 3. PORTAL FRAMES Version II 36 - 21 Job No: Sheet 3 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 2 RF (13.8) = (300 + 60) * 1 + 300 * (6.90) RF = 88 kN MF = 0 2 RB (13.8) = (300 + 60) * (13.8-1) + 300 * (6.9) RB = 242 kN To get maximum wheel load on a frame from gantry girder BB', taking the gantry girder as simply supported. Centre to centre distance between frames is 5 m c/c. Assuming impact @ 25% Maximum wheel Load @ B = 1.25 (242 (1 + (5-3.8)/5) = 375 kN. Minimum wheel Load @ B = (88 /242)*375 =136.4 kN 1.3.2 Transverse Load: Lateral load per wheel = 5% (300 + 60)/2 = 9 kN (i.e. Lateral load is assumed as 5% of the lifted load and the weight of the trolley acting on each rail). Lateral load on each column *375 242 9 = 13.9 kN (By proportion) 242 kN 242 kN 3.8 m 5 m B' B
  • 4. PORTAL FRAMES Version II 36 - 22 Job No: Sheet 4 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 1.4 Wind Load Design wind speed, Vz = k1 k2 k3 Vb From Table 1; IS: 875 (part 3) – 1987 k1 = 1.0 (risk coefficient assuming 50 years of design life) From Table 2;IS: 875 (part 3) – 1987 k2 = 0.8 (assuming terrain category 4) k3 = 1.0 (topography factor) Assuming the building is situated in Chennai, the basic wind speed is 50 m /sec Design wind speed, Vz = k1 k2 k3 Vb Vz = 1 * 0.8 *1 * 50 Vz = 40 m/sec Basic design wind pressure, Pd = 0.6*Vz 2 = 0.6 * (40)2 = 0.96 kN/m2 1.4.1. Wind Load on individual surfaces The wind load, WL acting normal to the individual surfaces is given by WL = (Cpe – Cpi ) A*Pd (a) Internal pressure coefficient Assuming buildings with low degree of permeability Cpi = 0.2
  • 5. PORTAL FRAMES Version II 36 - 23 h w w L plan elevation Job No: Sheet 5 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date (b) External pressure coefficient External pressure coefficient for walls and roofs are tabulated in Table 1 (a) and Table 1(b) 1.4.2 Calculation of total wind load (a) For walls h/w = 6/15 = 0.4 L/w = 30/15 = 2.0 Exposed area of wall per frame @ 5 m c/c is A = 5 * 6 = 30 m2 For walls, A pd = 30 * 0.96 = 28.8 kN Table 1 (a): Total wind load for wall Cpe Cpi Cpe – Cpi Total wind(kN) (Cpe-Cpi )Apd Wind Angle Wind- ward Lee- ward Wind ward Lee ward Wind ward Lee ward 0.2 0.5 -0.45 14.4 -12.9 00 0.7 -0.25 -0.2 0.9 -0.05 25.9 -1.4 0.2 -0.7 -0.7 -20.2 -20.2 900 -0.5 -0.5 -0.2 -0.3 -0.3 -8.6 -8.6 (b) For roofs Exposed area of each sloping roof per frame @ 5 m c/c is 2 2 2 m 40.4 7.5 3.0 * 5 A
  • 6. PORTAL FRAMES Version II 36 - 24 15 m Job No: Sheet 6 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date For roof, Apd = 38.7 kN Table 1 (b): Total wind load for roof Pressure Coefficient Cpe – Cpi Total Wind Load(kN) (Cpe – Cpi) Apd Cpe Cpe Wind ward Lee ward Wind ward Lee ward Wind angle Wind Lee Cpi Int. Int. -0.328 -0.4 0.2 -0.528 -0.6 -20.4 -23.2 00 -0.328 -0.4 -0.2 -0.128 -0.2 -4.8 -7.8 -0.7 -0.7 0.2 -0.9 -0.9 -34.8 -34.8 900 -0.7 -0.7 -0.2 -0.5 -0.5 -19.4 -19.4 2.0 Equivalent Load Calculation 2.1 Dead Load Dead Load = 2.0 kN/m Replacing the distributed dead load on rafter by equivalent concentrated loads at two intermediate points on each rafter, kN 6 15 * 2.0 WD 5 2.2 Superimposed Load Superimposed Load = 2.57 kN/m Concentrated load , purlin kN/ 6.4 6 15 * 2.57 L W
  • 7. PORTAL FRAMES Version II 36 - 25 Job No: Sheet 7 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 2.3 Crane Load Maximum Vertical Load on columns = 375 kN (acting at an eccentricity of 600 mm from column centreline) Moment on column = 375 *0.6 = 225 kNm. Minimum Vertical Load on Column = 136.4 kN (acting at an eccentricity of 600 mm) Maximum moment = 136.4 * 0.6 = 82 kNm 3.0 Partial Safety Factors 3.1 Load Factors For dead load, f = 1.5 For major live load, f = 1.5 For minor live load or defined live load, f = 1.05 3.2 Material Safety factor m = 1.10 4.0 Analysis In this example, the following load combinations are considered, as they are found to be critical. Similar steps can be followed for plastic analysis under other load combinations. (i) 1.5D.L + 1.05 C .L + 1.5 W.L
  • 8. PORTAL FRAMES Version II 36 - 26 kN 2.6 2 5.2 eaves @ 2 w 35 7 kN 2 eaves @ 2 w 94 . 1 88 . 3 Job No: Sheet 8 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date (ii) 1.5 D.L + 1.05 C.L+ 1.5 L.L 4.1. 1.5 D.L + 1.05 C.L+ 1.5 W.L 4.1.1Dead Load and Wind Load (a) Vertical Load w @ intermediate points on windward side w = 1.5 * 5.0 – 1.5 *(4.8/3) cos21.8 = 5.27 kN. w @ intermediate points on leeward side w = 1.5 * 5.0 – 1.5 * 7.8/3 cos21.8 = 3.88 kN Total vertical load @ the ridge = 2.635 + 1.94 = 4.575 kN b) Horizontal Load H @ intermediate points on windward side H = 1.5 * 4.8/3 sin 21.8 = 0.89 kN
  • 9. PORTAL FRAMES Version II 36 - 27 Job No: Sheet 9 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date H/2 @ eaves points = 0.89/2 = 0.445 kN H @ intermediate purlin points on leeward side = 1.5 * 7.8 /3 sin 21.8 = 1.45 kN H/2 @ eaves = 0.725 kN Total horizontal load @ the ridge = 0.725 - 0.445 = 0.28 kN Table 3: Loads acting on rafter points Vertical Load (kN) Horizontal Load (kN) Windward Leeward Windward Leeward Intermediate Points 5.27 3.88 0.89 1.45 Eaves 2.635 1.94 0.445 0.725 Ridge 4.575 0.28 4.1.2 Crane Loading Moment @ B = 1.05 * 225 = 236.25 kNm Moment @ F = 1.05 * 82 = 86.1 kNm Horizontal load @ B & @ F = 1.05 * 13.9 = 14.6 kN Note: To find the total moment @ B and F we have to consider the moment due to the dead load from the weight of the rail and the gantry girder. Let us assume the weight of rail as 0.3 kN/m and weight of gantry girder as 2.0 kN/m Dead load on the column = Factored moment @ B & F = 1.05 * 5.75 * 0.6 = 3.623 kNm kN 5.75 5 * 2 0.3 2
  • 10. PORTAL FRAMES Version II 36 - 28 Job No: Sheet 10 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Total moment @ B = 236.25 + 3.623 = 239.9 kNm @ F = 86.1 + 3.623 = 89.7 kNm 4.2 1.5 D.L + 1.05 C.L + 1.5 L.L 4.2.1 Dead Load and Live Load @ intermediate points on windward side = 1.5 * 5.0 + 1.5 * 6.4 = 17.1 kN @ ridge = 17.1 kN @ eaves = 17.1 / 2 8.55 kN. 15 m 3 m 6 m 3.25 m 14.6 kN 14.6 kN 239.9 89.7 38.85 kN 2.1 kN Factored Load (1.5D.L+1.05 C.L +1.5 W.L) 1.45 kN 1.45 kN 0.725 kN 0.28 kN 4.575 kN 3.88 kN 3.88 kN 1.94 kN 0.89 kN 0.89 kN 5.27 kN 5.27 kN 2.635 kN 0.445 kN
  • 11. PORTAL FRAMES Version II 36 - 29 Job No: Sheet 11 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 4.2.2 Crane Load Moment @ B = 239.9 kNm Horizontal load @ B = 14.6 kN Moment @ F = 89.7 kNm Horizontal load @ F = 14.6 kN 4.3 Mechanisms We will consider the following mechanisms, namely (i) Beam mechanism (ii) Sway mechanism (iii) Gable mechanism and (iv) Combined mechanism Factored Load (1.5 D.L + 1.05 C.L + 1.5 L.L) 3 m 6 m 3.25 m 17.1 kN 17.1 kN 17.1 kN 17.1 kN 8.55 kN 17.1 kN 15 m 14.6 kN 14.6 kN 239.9 89.7 kNm kNm
  • 12. PORTAL FRAMES Version II 36 - 30 Job No: Sheet 12 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 4.3.1 Beam Mechanism (1) Member CD Case 1: 1.5 D.L + 1.05 C.L + 1.5 W.L Internal Work done, Wi = Mp + Mp ( /2) + Mp ( + /2) = Mp(3 ) External Work done, We = 5.27 * 2.5 - 0.89 * 1 * +5.27 * 2.5 * /2 – 0.89 * 1 * /2 = 18.43 Equating internal work done to external work done Wi = We Mp (3 ) = 18.43 Mp = 6.14 kNm Case 2: 1.5 D.L + 1.05 C.L + 1.5 L.L Internal Work done, Wi = Mp ( + /2 + + /2) Wi = Mp 3 4.575 kN 0.89 kN 5.27 kN 0.89 kN 0.445 kN 5.27 kN 0.28 kN 2.635 kN /2
  • 13. PORTAL FRAMES Version II 36 - 31 Job No: Sheet 13 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External work done, We = 17.1 * 2.5 + 17.1 *2.5 /2 = 64.125 Equating Wi = We, Mp (3 ) = 64.125 Mp = 21.375 kNm Note: Member DE beam mechanism will not govern. (2) Member AC Internal Work done, p M 3.69 13 11 p M 13 11 p M p M i W 17.1 kN 17.1 kN 17.1 kN 8.55 kN /2 14.6 kN 38.85 kN 11 /13 239.9 kNm
  • 14. PORTAL FRAMES Version II 36 - 32 Job No: Sheet 14 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External Work done, Equating Wi = We, we get 3.69 Mp = 296.6 Mp = 80.38 kNm. (3) Member EG Internal Work done, External Work done, Equating Wi = We, we get 3.69 Mp = 321.7 p M 3.69 13 11 p M 13 11 p M p M i W 6 . 296 * 85 . 38 * * 9 . 239 * * 6 . 14 13 11 3.25 2 1 13 11 13 11 3.25 We 13 11 3.25 * ) ( 2 1 * 13 11 * 3.25 * We 7 . 321 3 . 30 9 . 239 6 . 14 14.6 kN 239.9 kNm 30.3 kN 11 /13
  • 15. PORTAL FRAMES Version II 36 - 33 Job No: Sheet 15 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Mp = 87.2 kNm For members AC & EG, the 1st load combination will govern the failure mechanism. 4.3.2 Panel Mechanism Case 1: 1.5 D.L + 1.05 C.L + 1.5 W.L Internal Work done, Wi = Mp ( ) + Mp ( ) + Mp ( ) + Mp ( ) = 4Mp External Work done, We We = 1/2 (38.85) * 6 + 14.6 * 3.25 + 239.9 - 0.445 * 6 - 0.89 * 6 - 0.89(6 )+ 0.28 * 6 + 1.45 *6 + 1.45 * 6 + 0.725 * 6 +1/2 (2.1) * 6 + 14.6 * 3.25 - 89.7 * = 378.03 14.6 kN 239.9 kNm 14.6 kN 89.7 kNm 38.85 kN 2.1 kN 1.45 1.45 0.725 0.28 4.575 3.88 3.88 1.94 5.27 0.89 5.27 0.89 2.635 0.445
  • 16. PORTAL FRAMES Version II 36 - 34 Job No: Sheet 16 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Equating Wi = Wc, we get 4Mp = 378.03 Mp = 94.51 kNm The second load combination will not govern. 4.3.3 Gable Mechanism Case 1: 1.5 D.L + 1.5 W.L + 1.05 C.L Internal Work done = Mp + Mp2 + Mp (2 ) + Mp = 6Mp External Work done, We = -0.89 * 1 * - 0.89 * 2 * + 0.28 * 3 * + 1.45 * 4 * + 1.45 * 5 * + 0.725 * 6 * + 5.27 * 2.5 * + 5.27 * 5 * + 4.575 * 7.5 * + 3.88 * 5 * + 3.88 * 2.5 * + ½ * 2.1 * 6 + 14.6 * 3.25 * - 89.7* We = 82.56 1.45 1.45 0.725 0.28 4.575 3.88 3.88 1.94 0.89 0.89 5.27 5.27 2.63 5 0.445 14.6 kN 239.9 kNm 14.6 kN 89.7 kNm 38.85 kN 2.1 kN
  • 17. PORTAL FRAMES Version II 36 - 35 Job No: Sheet 17 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Equating Wi = We, we get 6Mp = 82.56 Mp = 13.76 kNm. Case 2: 1.5 D.L + 1.5L.L + 1.05 C.L Internal Work done, Wi = Mp + Mp (2 ) + Mp (2 ) + Mp =6Mp External Work done, We = 17.1 * 2.5* + 17.1 * 5 * + 17.1 * 7.5 + 17.1 * 5 * + 17.1 * 2.5 - 89.7 * + 14.6 * 3.25 = 342.5 Equating Wi = We, we get 6Mp = 342.5 Mp = 57.1 kNm 17.1 17.1 17.1 17.1 8.55 17.1 14.6 kN 14.6 kN 239.9kNm 89.7 kNm 8.55
  • 18. PORTAL FRAMES Version II 36 - 36 Job No: Sheet 18 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 4.3.4 Combined Mechanism Case1: 1.5 D.L + 1.5 W.L + 1.05 C.L (i) Internal Work done, Wi = Mp ( ) + Mp ( + /2) + Mp ( /2 + /2) + Mp ( /2) = Mp ( + + /2 + /2 + /2 + /2 + /2) = 4 Mp External Work done, We= 1/2 * 38.85 * 6 + 14.6 * 3.25* + 239.9 - 0.445 * 12 * /2 - 0.89 * 11 * /2 - 0.89 * 10 * /2 + 0.28 * 9 * /2 + 1.45 * 8 * /2 + 1.45 * 7 * /2 + 0.725 * 6* /2 + 1/2 (2.1) * 6 /2 + 14.6 * 3.25 * /2 – 89.7 * /2 – 5.27 * 2.5 * /2 – 5.27 * 5.0 * /2 – 4.575 * 7.5 * /2 – 3.88 * 5 * /2 – 3.88 * 2.5 * /2 = 336.75 /2 /2 /2 14.6 kN 239.9 kNm 14.6 kN 89.7 kNm 38.85 kN 2.1 kN 1.45 1.45 0.725 0.28 4.575 3.88 3.88 1.94 0.89 0.89 5.27 5.27 2.635 0.445 12 m
  • 19. PORTAL FRAMES Version II 36 - 37 Job No: Sheet 19 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Equating Wi = We 4Mp = 336.75 Mp = 84.2 kNm (ii) Internal work done, Wi = Mp /2 + Mp ( /2 + /2) + Mp ( /2 + ) +Mp Wi = 4Mp /2 /2 /2 14.6 kN 239.9 kNm 14.6 kN 89.7 kNm 38.85 kN 2.1 kN 1.45 1.45 0.725 0.28 4.575 3.88 3.88 1.94 0.89 0.89 5.27 5.27 2.635 0.445 12 m
  • 20. PORTAL FRAMES Version II 36 - 38 2 1 3.25 2 2.5 2 5.0 2 12 5 0. 2 11 1. 2 10 1. 2 7.5 7 4. 2 5.0 5.2 2 2.5 5.2 2 9 0. 2 8 0. 2 7 0. 2 6 0. 2 6 2 1 2 2 3.25 We * 1 . 2 * * 7 . 89 * 6 . 14 * * 88 . 3 * * 88 . 3 * * 72 * * 45 * * 45 * * 5 5 * * 7 * * 7 * * 28 * * 89 * * 89 * * 445 * 85 . 38 * * 9 . 239 * * 6 . 14 Job No: Sheet 20 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External Work done, = 230.3 Equating Wi = We, we get 4Mp = 230.3 Mp = 57.575 kNm (iii) 36 m 0.28 4.575 3.88 3.88 1.98 5 /6 38.85 kN 0.89 0.89 5.27 5.27 2.635 0.445 14.6 kN 239.9 kNm /6 /6 1.45 1.45 0.725 2.1 kN 14.6 kN 89.7 kNm
  • 21. PORTAL FRAMES Version II 36 - 39 p 4M ) p M 6 p M 6 6 p M 6 p M ) (6 ) ( 2 1 * 3.25 * 6 * 2.5 * 6 * 5.0 * 6 * 7.5 * 7 4. 6 * 10 * 5.2 6 * 12.5 * 5.2 6 * 36 * 5 0. 6 * 35 * 1. 6 * 34 * 1. 6 *33* 0. 6 * 34 * 0. 6 * 35 * 0. 6 * 6 * 0. 6 * 6 * * 2 1 6 * 6 * *3.25 * 1 . 2 7 . 89 6 . 14 88 . 3 88 . 3 5 5 7 7 72 45 45 28 89 89 445 85 . 38 9 . 239 6 . 14 Job No: Sheet 21 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Internal work done, Wi External Work done, We = We = 341.07 Equating Wi = We, we get 4Mp = 341.07 Mp = 85.27 kNm (iv) Internal Work done, p 4M p M 3 p M 3 3 2 p M 3 2 p M i W
  • 22. PORTAL FRAMES Version II 36 - 40 Job No: Sheet 22 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External Work done, We = Equating Wi = We, we get 4Mp = 293.22 Mp = 73.3 kNm W * ) ( 2 1 * 3.25 * 3 2.5 * 3 * *5.0 3 * 18 * 5 0. 3 * 17 * 1. 3 * 16 * 1. 3 * 15 * 0. 3 7.5* * 7 4. 3 2 * 5 * 5.2 3 2 * 2.5 * 5.2 3 * *15 0. 3 * 16 * 0. 3 2 * 7 * 0. 3 2 * 6 * 0. 3 2 * 6 * * 2 1 3 2 * 3 2 * *3.25 e 22 . 293 1 . 2 7 . 89 6 . 14 88 . 3 88 . 3 72 45 45 28 5 5 7 7 28 89 89 445 85 . 38 9 . 239 6 . 14 2 /3 /3 /3 14.6 kN 239.9 kNm 14.6 kN 89.7 kNm 38.85 kN 2.1 kN 1.45 1.45 0.725 0.28 4.575 3.88 3.88 1.94 0.89 0.89 5.27 5.27 2.635 0.445 18 m
  • 23. PORTAL FRAMES Version II 36 - 41 Job No: Sheet 23 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Case 2: 1.5 D.L + 1.5 L.L + 1.05 C.L (i) Assuming plastic hinge is formed @ purlin point 2 and 7 and at fixed supports. Internal Work done p 4M p M 6 p M 6 6 p M 6 p M 5 /6 /6 /6 17.1 17.1 17.1 17.1 8.55 17.1 14.6 kN 14.6 kN 239.9 kNm 89.7 36 m 8.55 5 /6 /6
  • 24. PORTAL FRAMES Version II 36 - 42 Job No: Sheet 24 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External Work done =We Equating Wi =We, we get 4Mp = 304.1 Mp = 76.03 kNm Plastic hinge is formed @ 3 and 7 . 3 3.25 6 2.5 6 5.0 6 7.5 6 10 6 2.5 1 6 6 3.25 1 04 7 . 89 * * 6 . 14 * * 1 . 17 * * 1 . 17 * * 1 . 17 * * 1 . 17 * * 1 . 17 * 9 . 239 * * 6 . 14 /3 /3 17.1 17.1 17.1 17.1 8.55 17.1 14.6 kN 14.6 kN 239.9 kNm 89.7 18 m 8.55 2 /3
  • 25. PORTAL FRAMES Version II 36 - 43 . 3 3.25 3 2.5 1 3 5.0 1 3 7.5 1 3 2 5.0 1 3 2 2.5 1 3 2 3 2 3.25 3 20 7 . 89 * 6 . 14 * * 1 . 7 * * 1 . 7 * * 1 . 7 * * 1 . 7 * * 1 . 7 * 9 . 239 * * 6 . 14 p p p p p i M M M M M W 4 3 3 3 2 3 2 Job No: Sheet 25 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Internal work done, External Work done, We= Equating Wi = We, we get 4Mp = 320.3 Mp = 80.1 kNm (ii) Plastic hinged is formed at 4 and 7 Internal Work done p M 4 p M 2 p M 2 2 p M 2 p M
  • 26. PORTAL FRAMES Version II 36 - 44 Job No: Sheet 26 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date External Work done, We = Equating Wi = We 4Mp = 293.8 Mp = 73.45 kNm /2 /2 /2 17.1 17.1 17.1 17.1 8.55 17.1 14.6 kN 14.6 kN 239.9 89.7 12 m 8.55 /2 8 . 293 7 . 89 25 . 3 * 6 . 14 2 * 5 . 2 * 1 . 17 2 * 0 . 5 * 1 . 17 2 * 5 . 7 * 1 . 17 2 * 0 . 5 * 1 . 17 2 * 5 . 2 * 1 . 17 2 * 9 . 239 2 * 25 . 3 * 6 . 14
  • 27. PORTAL FRAMES Version II 36 - 45 3 W * 3.25 * *2.5 1 * 5.0 * 1 2 * 7.5 * 1 2 * 5.0 * 1 2 * 2.5 * 1 2 * 2 * *3.25 e 3 . 56 7 . 89 1 . 14 1 . 7 1 . 7 1 . 7 1 . 7 1 . 7 9 . 239 6 . 14 Job No: Sheet 27 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date (iii) Plastic hinge is formed @ 5 and 7 Internal Work Done,Wi = External work done, We = p M 5 i W p M p M 2 p M 2 p M 6 m /2 17.1 17.1 17.1 17.1 8.55 14.6 kN 14.6 kN 239.9 /2 17.1 89.7
  • 28. PORTAL FRAMES Version II 36 - 46 Job No: Sheet 28 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Equating Wi = We 5Mp = 356.3 * Mp = 71.26 kNm Design Plastic Moment = 94.51 kNm. 5.0 DESIGN For the design it is assumed that the frame is adequately laterally braced so that it fails by forming mechanism. Both the column and rafter are analysed assuming equal plastic moment capacity. Other ratios may be adopted to arrive at an optimum design solution. 5.1 Selection of section Plastic Moment capacity required= 94.51 kNm Required section modulus, Z = Mp/ fyd From IS: 800 (Appendix I) ISMB 300 @ 0.46 kN/ m provides Zp = 651 * 10-3 mm3 b = 140 mm Ti = 12.4 mm A = 5.626 * 10 3 mm2 tw =7.5 mm rxx =124 mm ryy =28.4 mm 3 3 10 * 84 . 415 51 . 94 mm 1.1 250 *106
  • 29. PORTAL FRAMES Version II 36 - 47 1 f T b 4 . 9 65 4 . 2 5. 1 70 T b 1 f Job No: Sheet 29 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date 5.2 Secondary Design Considerations 5.2.1 Check for Local buckling of flanges and webs Flanges bf = 140/2 = 70 mm T1 = 12.4 mm t = 7.5 mm Web O.K. 5.2.2 Effect of axial force Maximum axial force in column, P = 51.3 kN 9 . 83 40 5 . 7 300 t d1
  • 30. PORTAL FRAMES Version II 36 - 48 kN 27 *10 5. 1.1 250 3 8 1 626 Job No: Sheet 30 of 30 Rev Job Title: Portal Frame Analysis and Design Worked Example: 1 Made By PU Date Structural Steel Design Project Calculation Sheet Checked By VK Date Axial load causing yielding, Py = fyd * A Therefore the effect of axial force can be neglected. 5.2.3 Check for the effect of shear force Shear force at the end of the girder = P- w/2 = 51.3 –8.55 kN = 42.75 kN Maximum shear capacity Vym, of a beam under shear and moment is given by Vym = 0.5 Aw* fyd / 1.1 = 0.5 * 300* 7.5* 250/1.1 =255.7 kN>> 42.75 kN Hence O.K. 0.15 0.0 127 P P y 4 8 3 . 51