SlideShare a Scribd company logo
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Mark Howitt, Director
07910 020 686
mhowitt@storelectric.com
www.storelectric.com
Storelectric Ltd
Enabling Renewables
to Power the Grid
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Problem and Solution
The Problem
• Renewables are intermittent
• GW scale renewables need GW scale back-up
GW = Gigawatt, enough electricity to power a million people with their industry and infrastructure
The Solution
• Large scale, long duration storage
• Each plant stores more electricity than a year’s output of Elon Musk’s Gigafactory
• The UK has geological potential to power Europe for a week
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Problem and Solution
The Problem
Renewables are intermittent
They generate when they want to, not when we need them
Therefore they need back-up – at the same scale
Fossil fueled power station operating inefficiently
£2bn p.a. to back up electricity now, doubling in ~5 years
GW scale renewables need GW scale back-up
Consider a windless winter night (a frequent occurrence) when renewables are powering all variable demand on the grid
There is a 5-hour peak in demand coming up, as happens every night
The peak is up to 30GW more demand than baseload generation, which is normal
Will 30-60 minute duration battery supply the 5-hour peak?
Will megawatt scale batteries satisfy gigawatt scale need?
The Solution
Large scale, long duration storage
Each installation can replace a power station
Complements batteries, interconnectors and other technologies
The UK has geological potential to power Europe for a week
Suitable geologies globally
Does not compete with batteries, except on the periphery. Consider the road system: side and feeder roads are needed to support trunk
roads and motorways; the latter are required to take the load off the former and enable them to work effectively. We are like the trunk
roads and motorways; they are like the side and feeder roads. All are needed, all are complementary – as with interconnectors, flywheels,
demand side response etc. With large scale long duration storage, the system works; without it, it fails.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The world’s biggest battery, using
just air, water, salt and equipment
Typical sizes:
40MW, 200-500MWh
500MW, 3-12GWh
Compressed Air
Energy Storage
using Thermal
Energy Storage
Storelectric’s
TES CAES
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The world’s most efficient and cost-effective large scale electricity storage.
Round trip efficiency ~62-64% for 40MW, ~70% for 500MW (existing plants are 42-50%)
Almost as efficient as pumped hydro, less than 1/3 of the cost (depending in part on
location), much closer to both supply and demand
Capex for a 5 hour plant is comparable with capex of a half-hour battery of the same rating
Efficiency increases with scale, in contrast with batteries
Notes page for Storelectric’s TES CAES
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Comparison with other CAES technologies
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Compressed Air
Energy Storage
within a
Combined Cycle
Gas Turbine
power station
Grid,
Storelectric’s
CCGT CAES
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for Storelectric’s TES CAES
Round trip efficiency ~60% (existing plants 42-50%; new versions aspire to 54%)
The only CAES technology that can be retro-fitted to CCGT or OCGT power
stations over the right geology
Gives new life to stranded power station assets:
• Almost halves emissions
• Adds storage related revenue streams
• As electricity price volatility increases (see a later slide), opex drops significantly
below that of the power station
Much cheaper than any other CAES technology – but can’t estimate costs
because that depends on what we’re retro-fitting. New, it costs only ~£10-15m
more than a CCGT.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
A salt mine much smaller
than our caverns which
are ~300m tall
An Idea of Scale
Cavern Size
• Our small plants’ caverns
~2 x St Paul’s Cathedral
• Our large plants’ caverns
~25 x St Paul’s Cathedral
What is a Cavern?
• Drill a hole, pump in water, pump out brine,
what’s left is the cavern
• Cheap, well known technology
• ~1/3 of Europe’s natural gas reserve is
stored in salt caverns
• Naturally hermetic
• Pressure is determined by depth
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for An Idea of Scale
Note: This is a mine, not a salt cavern. It’s shown only to illustrate scale: for our small
pilot plant (200MWh) we will use two caverns each almost as big as St Paul’s
Cathedral in London.
People and machines go down mines.
To make a cavern,
1.Drill a hole into the salt basin
2.Pump in water, pump out brine; what’s left is the cavern.
Salt caverns are naturally hermetic and self-healing in case cracks develop.
Approaching 1/3 of all natural gas storage in Europe is stored in such salt caverns.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Market
Top-Down
• $1trn market to deliver dispatchable power
• And that’s just the capital cost of building them
• 3-6x more to deliver baseload
• 3-10x more to support de-carbonisation of transportation and industry
Bottom-Up
• Each 40MW plant delivers 12-15% IRR
• Each 500MW plant delivers 15+% IRR
• Whole project IRR – much greater if largely project financed
• IRR growing as renewables penetration grows
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Market
In the UK the market is over 20GW.
The government’s TINA (Technology Innovation Needs Analysis) for Electricity Networks and Storage determined that the country needs a
median 27.4GW and 128GWh (i.e. 5 hours average duration) of new storage. https://www.carbontrust.com/media/168551/tina-electricity-
networks-storage-summary-report.pdf – see Chart 2.
• We can ignore their breakdown of technologies. Total new pumped hydro planning applications are 1.05GW, none of which looks to be
sufficiently cost-effective to be built.
• For batteries, 0.1GW are operational, 0.6GW in construction, 1.1GW planning approved, 1.7GW planning pending [total so far 3.4GW]
and a further 12GW with DNO applications outstanding (see https://auroraer.us11.list-
manage.com/track/click?u=095bcc5477fce868775bbbd67&id=ded62ab359&e=e8860559df) but most of which are unlikely to be built due
to:
1. The elimination of EFR (see Stage 1: Rationalisation p14 in https://www.nationalgrid.com/sites/default/files/documents/Product
Roadmap for Frequency Response and Reserve.pdf ),
2. The saturation of the Primary Frequency Response market (see https://utilityweek.co.uk/frequency-response-market-nearing-
saturation-industry-warned/ ) and
3. The heavy de-rating of batteries in the Capacity Market (see https://www.emrdeliverybody.com/Lists/Latest
News/Attachments/150/Duration Limited Storage De-Rating Factor Assessment - Final.pdf – table E1 p5).
Other analyses lead to similar conclusions: superimposing actual wind patterns on 2030 forecast wind generation yields a need for 30GW
storage; the National Infrastructure Planning document sees needs at a similar level, etc.
And that is just for peak smoothing, i.e. enabling renewables to deliver variable power. When baseload plants close (and few, if any, nuclear
plants will open in time) then we need 3-6 times as much storage to enable renewables to supply baseload. And much more is needed to
support the greening of heating (mainly via electrically driven heat pumps), transportation (electricity and hydrogen) and industry.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
IP, Competition
Intellectual Property
• Patentable: thermal storage system
• Knowhow: system integration, trading, sites, partnerships
Competition
Storelectric
Adiabatic CAES
Existing CAES Isothermal CAES Status Quo
Efficiency 68-70% 50% Unsuccessful
(targeted 70%)
Power stations operate
very inefficiently
Emissions
(% of a power station)
0% 50-60% Scavenging heat
(large scale impossible)
>> 100%
Capex
(% of a power station)
150% 180% >> 200% 100%
Opex (2025 estimate)
(% of a power station)
60% 85% n/a 100%
CAES = Compressed Air Energy Storage
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for IP, Competition
Intellectual Property
Patentable: thermal storage system
Over one-third more efficient than current technologies (~70% v 50%)
IP will keep us ahead of competitors – efficiency goes straight to profits
Knowhow: system integration, trading, sites, partnerships
Competition
Existing CAES
50% efficient – we are 68-70%
50-60% of emissions of a CCGT – ours are zero
More expensive capex than ours
The Status Quo
Balancing renewables using fossil fueled power stations, inefficient and high emissions
Isothermal CAES
Different technology from ours: isothermal rather than adiabatic
Adiabatic (us) balances heat over the whole cycle; isothermal (them) optimises compression
Fundamentally weak concept: 3 existing businesses folded / folding
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Team Partner Companies
Paul Davies, Chairman
Former Senior Partner, PwC Corporate
Finance Infrastructure; former Director,
HSBC infrastructure
Tallat Azad, Managing Director
Chartered Engineer; former Director,
Alstom Power – new technologies,
responsible for energy storage.
Mark Howitt, Chief Technical Officer
Inventor, Physicist, business experience
in both multinationals and consultancy,
3 start-up subsidiaries, IP experience
Jeff Draper, Chief Financial Officer
Accountant, Physicist, entrepreneur,
former partner in accounting firm
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Team Partner Companies
Our partner companies provide all the capabilities we need.
Siemens – top-side equipment and control systems
Costain – engineering and civils
PwC – corporate finance and advisory
Maloney Metalcraft – thermal energy subsystem
Dentons – legal and advisory
Fortum – dynamic modelling and optimization support
KBB UT – rock mechanical analysis, cavern design and support
ERM – planning and environmental support
Oswald – the initial calculations and analyses of alternatives
Durham University – R&D on future technological developments
Shell Springboard awarded us our first money when we won their regional competition
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Ask: 4 investment opportunities – 1. Topco
1. Topco
Storelectric Ltd
• £1m at £10m valuation
• Develop new sites in preparation for setting up an SPV
• These SPVs will develop revenues in 6-12 months
• Develop capabilities in project management, plant operation, trading
• Already raised £550k at valuations up to £2.5m in previous rounds
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Ask: 4 investment opportunities – 1. Topco
Topco
£1m at £10m valuation
IRR 15%, SEIS pre-approved, seeking EIS confirmation but this is far from guaranteed as Inland
Revenue’s rules changed.
Develop new sites (4-6 p.a. initially, increasing) using 2 technologies, to flip / spin off
Develop capabilities in project management, plant operation, trading
Will also develop new and hybrid technologies
Storelectric licenses TES CAES from TES CAES Technology Ltd, whose three main shareholders /
directors are common to both
Storelectric owns the other technology and future developments that are not specific to TES CAES
Already raised £400k at valuations up to £2.5m
Also raised £150k for IP company
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Ask: 4 investment opportunities – 2. Development
2 and 3. Plant Development SPVs (both types)
SPV = Special Purpose Vehicle / Company – a separate company from Storelectric
• 2. Distribution Connected Plant (up to 50MW)
• £2.5m at £4m valuation (60%)
• IRR 12-15%
• Develop a new plant to shovel ready, 1 year (local planning process)
• Exit by flipping – reinvest in next plants if EIS invested
• 3. Transmission Connected Plant (typically 500MW)
• £8m at £13.3m valuation (60%)
• IRR 15%+
• Develop a new plant to shovel ready, 3 years (NSIP planning process)
• Exit by flipping – reinvest in next plants if EIS invested
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Ask: 4 investment opportunities – 2. Development
Plant Development
£2.5m at £4m valuation (60%)
Connected to the distribution grid
Typical size 40MW, 200MWh
IRR 12-15%
Develop a new plant to shovel ready, 1 year
Exit by flipping – reinvest in next plants if EIS invested
Note: EIS status is far from guaranteed as Inland Revenue rules exclude “generation”. Although we don’t generate (which we are
discussing with HMRC), storage is defined legally as consumption plus generation. Even so, this is project development which, if it
does not trade electricity (other than perhaps during commissioning) then it may be acceptable.
£8m at £13.3m valuation (60%)
Connected to the transmission grid
Typical size 500MW, 2.5GWh
IRR 15%+
Develop a new plant to shovel ready, 3 years
Exit by flipping – reinvest in next plants if EIS invested
Note: EIS status is far from guaranteed as Inland Revenue rules exclude “generation”. Although we don’t generate (which we are
discussing with HMRC), storage is defined legally as consumption plus generation. Even so, this is project development which, if it
does not trade electricity (other than perhaps during commissioning) then it may be acceptable.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
The Ask: 4 investment opportunities – 4. Construction
4. Plant Construction SPV
SPV = Special Purpose Vehicle / Company – a separate company from Storelectric
• £50m
• IRR 12-15% at constant revenues and costs
• Revenues are forecast to grow strongly
• Operational costs are forecast to decrease strongly
• Highly flexible plant able to accommodate a rapidly
shifting regulatory landscape
• 5-hour storage is not de-rated for duration on the
Capacity Market, qualifies for Reserve revenue streams
• Develop a new plant from shovel ready to post-
commissioning, 2 years
• An infrastructure play
• Exit by either re-financing (e.g. 75% of the firm at 6%
leads to a return on equity of ~32%) or sale
~25% of revenues are from
arbitrage, following roughly
the top blue dotted line
~80% of opex is electricity
purchase costs, roughly the
bottom blue dotted line
~50% of revenues are
from balancing and
ancillary services
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Notes page for The Ask: 4 investment opportunities – 4. Construction
The IRR is calculated on the assumption of constant trading conditions.
However, trading conditions are improving in almost all revenue
sources and in the main operational cost source, as per the graphs.
Therefore returns on investment should be considerably higher.
www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing.
Mark Howitt, CTO
+44 (0) 7910 020 686
mhowitt@storelectric.com
Storelectric Ltd
Compressed Air Energy Storage
Enabling renewables to power the grid
Jeff Draper, CFO
+44 (0) 7919 536 551
jdraper@storelectric.com
Tallat Azad, MD
+44 (0) 7875 880 262
tallat.azad@storelectric.com
Paul Davies, Chairman
+44 (0) 7802 869 074
pdavies@storelectric.com

More Related Content

What's hot

CCET Case Study
CCET Case StudyCCET Case Study
CCET Case Study
SAMSUNG SDI
 
Introduction to energy storage
Introduction to energy storageIntroduction to energy storage
Introduction to energy storage
Philip Fischer
 
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of FlexibilityNew Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
EMEX
 
Geothermal To the World
Geothermal To the WorldGeothermal To the World
Geothermal To the World
Cyril Stahl
 
Energy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyondEnergy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyond
EMEX
 
Making demand response mainstream
Making demand response mainstreamMaking demand response mainstream
Making demand response mainstream
Sympower
 
Sa energy storage-2018-future proofing ess - charmoille
Sa energy storage-2018-future proofing ess - charmoilleSa energy storage-2018-future proofing ess - charmoille
Sa energy storage-2018-future proofing ess - charmoille
Loic Charmoille
 
Integrated Wind Energy Storage
Integrated Wind Energy StorageIntegrated Wind Energy Storage
Integrated Wind Energy Storage
Milesh Gogad
 
Energy Storage: 1 - Sir David King keynote speech
Energy Storage: 1 - Sir David King keynote speechEnergy Storage: 1 - Sir David King keynote speech
Energy Storage: 1 - Sir David King keynote speech
British Embassy Paris
 
Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)
Finnish_Energy_Hub
 
Prevailing Energy Investor Presentation 3 6909
Prevailing Energy Investor Presentation 3 6909Prevailing Energy Investor Presentation 3 6909
Prevailing Energy Investor Presentation 3 6909lhfrew
 
ESS for Utility
ESS for UtilityESS for Utility
ESS for Utility
SAMSUNG SDI
 
Launch of Dynamic Response Report – the Flexibility Solution
Launch of Dynamic Response Report – the Flexibility SolutionLaunch of Dynamic Response Report – the Flexibility Solution
Launch of Dynamic Response Report – the Flexibility Solution
EMEX
 
Energy Storage - 9: Richard Riley, Highview
Energy Storage - 9: Richard Riley, HighviewEnergy Storage - 9: Richard Riley, Highview
Energy Storage - 9: Richard Riley, Highview
British Embassy Paris
 
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
Alexander Marshall
 
How to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – StorageHow to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – Storage
EMEX
 
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generationTomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
Global Business Events
 
Wind-Sail Overview
Wind-Sail OverviewWind-Sail Overview
Wind-Sail Overview
stieglitz1
 
Thermax Power Solar Brochure
Thermax Power Solar BrochureThermax Power Solar Brochure
Thermax Power Solar Brochure
HongTm15
 
2017 11-15 why hywind oslo exchange
2017 11-15 why hywind oslo exchange2017 11-15 why hywind oslo exchange
2017 11-15 why hywind oslo exchange
Xynteo
 

What's hot (20)

CCET Case Study
CCET Case StudyCCET Case Study
CCET Case Study
 
Introduction to energy storage
Introduction to energy storageIntroduction to energy storage
Introduction to energy storage
 
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of FlexibilityNew Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
New Revenue and Cost Savings Opportunities – Realising the Value of Flexibility
 
Geothermal To the World
Geothermal To the WorldGeothermal To the World
Geothermal To the World
 
Energy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyondEnergy Storage Innovation – Li-ion and beyond
Energy Storage Innovation – Li-ion and beyond
 
Making demand response mainstream
Making demand response mainstreamMaking demand response mainstream
Making demand response mainstream
 
Sa energy storage-2018-future proofing ess - charmoille
Sa energy storage-2018-future proofing ess - charmoilleSa energy storage-2018-future proofing ess - charmoille
Sa energy storage-2018-future proofing ess - charmoille
 
Integrated Wind Energy Storage
Integrated Wind Energy StorageIntegrated Wind Energy Storage
Integrated Wind Energy Storage
 
Energy Storage: 1 - Sir David King keynote speech
Energy Storage: 1 - Sir David King keynote speechEnergy Storage: 1 - Sir David King keynote speech
Energy Storage: 1 - Sir David King keynote speech
 
Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)
 
Prevailing Energy Investor Presentation 3 6909
Prevailing Energy Investor Presentation 3 6909Prevailing Energy Investor Presentation 3 6909
Prevailing Energy Investor Presentation 3 6909
 
ESS for Utility
ESS for UtilityESS for Utility
ESS for Utility
 
Launch of Dynamic Response Report – the Flexibility Solution
Launch of Dynamic Response Report – the Flexibility SolutionLaunch of Dynamic Response Report – the Flexibility Solution
Launch of Dynamic Response Report – the Flexibility Solution
 
Energy Storage - 9: Richard Riley, Highview
Energy Storage - 9: Richard Riley, HighviewEnergy Storage - 9: Richard Riley, Highview
Energy Storage - 9: Richard Riley, Highview
 
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
UN COP24: Gas engines – Cogeneration, Renewable Gas, Flexible Generation
 
How to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – StorageHow to Prepare for the Next Big Thing – Storage
How to Prepare for the Next Big Thing – Storage
 
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generationTomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
Tomas Ronn, Director of Oil & Gas Business at Wartsila - Smart power generation
 
Wind-Sail Overview
Wind-Sail OverviewWind-Sail Overview
Wind-Sail Overview
 
Thermax Power Solar Brochure
Thermax Power Solar BrochureThermax Power Solar Brochure
Thermax Power Solar Brochure
 
2017 11-15 why hywind oslo exchange
2017 11-15 why hywind oslo exchange2017 11-15 why hywind oslo exchange
2017 11-15 why hywind oslo exchange
 

Similar to Storelectric

Hybatec en-data
Hybatec en-dataHybatec en-data
Hybatec en-data
Antonio Guerra
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements
Iceland Geothermal
 
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentationEnergy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
British Embassy Paris
 
Ammonia Fuel Opportunities Markets Issues TSW october 2015 update
Ammonia Fuel Opportunities Markets Issues TSW october 2015 updateAmmonia Fuel Opportunities Markets Issues TSW october 2015 update
Ammonia Fuel Opportunities Markets Issues TSW october 2015 update
Steve Wittrig
 
EC-3-2015 Solar Storage
EC-3-2015 Solar StorageEC-3-2015 Solar Storage
EC-3-2015 Solar StorageJacob Harris
 
The Climate Camelot Final Issue
The Climate Camelot Final IssueThe Climate Camelot Final Issue
The Climate Camelot Final IssueMichael Garvin
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
12629131.ppt
12629131.ppt12629131.ppt
12629131.ppt
BlessyJoy18
 
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
Daymark Energy Advisors
 
Urban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReportUrban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReportDaniel Urban
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1dCORE
 
Hug Teeth
Hug TeethHug Teeth
Hug Teeth
roaudet
 
Global warming: A Case Study of Renewable Energy in India
Global warming: A Case Study of Renewable Energy in IndiaGlobal warming: A Case Study of Renewable Energy in India
Global warming: A Case Study of Renewable Energy in India
AnthonyNimelyCheaJr1
 
Energy storage Technologies & Innovation
Energy storage Technologies & InnovationEnergy storage Technologies & Innovation
Energy storage Technologies & Innovation
Mostafa Ahmed Zein
 
A white paper on Concentrated solar power in India
A white paper on Concentrated solar power in IndiaA white paper on Concentrated solar power in India
A white paper on Concentrated solar power in India
Sindhu Maiyya
 
ITM Power Hydrogen Solutions/ Case Studies
ITM Power Hydrogen Solutions/ Case StudiesITM Power Hydrogen Solutions/ Case Studies
ITM Power Hydrogen Solutions/ Case Studies
Rebecca Markillie
 
GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny Gowdy
Invest Northern Ireland
 
Electric hybrid bv rev3
Electric hybrid bv rev3Electric hybrid bv rev3
Electric hybrid bv rev3
MARTIAL CLAUDEPIERRE
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)
Suresh Sunny
 

Similar to Storelectric (20)

Hybatec en-data
Hybatec en-dataHybatec en-data
Hybatec en-data
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements
 
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentationEnergy Storage - 2: Ian Ellerington, decc innovation delivery presentation
Energy Storage - 2: Ian Ellerington, decc innovation delivery presentation
 
Ammonia Fuel Opportunities Markets Issues TSW october 2015 update
Ammonia Fuel Opportunities Markets Issues TSW october 2015 updateAmmonia Fuel Opportunities Markets Issues TSW october 2015 update
Ammonia Fuel Opportunities Markets Issues TSW october 2015 update
 
EC-3-2015 Solar Storage
EC-3-2015 Solar StorageEC-3-2015 Solar Storage
EC-3-2015 Solar Storage
 
The Climate Camelot Final Issue
The Climate Camelot Final IssueThe Climate Camelot Final Issue
The Climate Camelot Final Issue
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
12629131.ppt
12629131.ppt12629131.ppt
12629131.ppt
 
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
REV 2016: Storage Project & Policy Successes: Enhancing Reneweables Integrati...
 
Urban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReportUrban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReport
 
Tale of Six Cities
Tale of Six CitiesTale of Six Cities
Tale of Six Cities
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1
 
Hug Teeth
Hug TeethHug Teeth
Hug Teeth
 
Global warming: A Case Study of Renewable Energy in India
Global warming: A Case Study of Renewable Energy in IndiaGlobal warming: A Case Study of Renewable Energy in India
Global warming: A Case Study of Renewable Energy in India
 
Energy storage Technologies & Innovation
Energy storage Technologies & InnovationEnergy storage Technologies & Innovation
Energy storage Technologies & Innovation
 
A white paper on Concentrated solar power in India
A white paper on Concentrated solar power in IndiaA white paper on Concentrated solar power in India
A white paper on Concentrated solar power in India
 
ITM Power Hydrogen Solutions/ Case Studies
ITM Power Hydrogen Solutions/ Case StudiesITM Power Hydrogen Solutions/ Case Studies
ITM Power Hydrogen Solutions/ Case Studies
 
GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny Gowdy
 
Electric hybrid bv rev3
Electric hybrid bv rev3Electric hybrid bv rev3
Electric hybrid bv rev3
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)
 

More from CleantechInnovate

Rype Office
Rype OfficeRype Office
Rype Office
CleantechInnovate
 
ThinAir Water Ltd
ThinAir Water LtdThinAir Water Ltd
ThinAir Water Ltd
CleantechInnovate
 
Desolenator
Desolenator Desolenator
Desolenator
CleantechInnovate
 
Cryomation Ltd
Cryomation LtdCryomation Ltd
Cryomation Ltd
CleantechInnovate
 
Cambond Ltd
Cambond LtdCambond Ltd
Cambond Ltd
CleantechInnovate
 
Afternoon Keynote - Chris Huhne
Afternoon Keynote - Chris HuhneAfternoon Keynote - Chris Huhne
Afternoon Keynote - Chris Huhne
CleantechInnovate
 
AirEx
AirEx AirEx
RAB Microfluidics
RAB MicrofluidicsRAB Microfluidics
RAB Microfluidics
CleantechInnovate
 
LightFi
LightFiLightFi
Gapogroup Ltd
Gapogroup LtdGapogroup Ltd
Gapogroup Ltd
CleantechInnovate
 
Brill Power
Brill Power Brill Power
Brill Power
CleantechInnovate
 
Flint Engineering
Flint Engineering Flint Engineering
Flint Engineering
CleantechInnovate
 
Vortex Wave Power
Vortex Wave Power Vortex Wave Power
Vortex Wave Power
CleantechInnovate
 
Skypull
Skypull Skypull
Axis TLB Ltd
Axis TLB LtdAxis TLB Ltd
Axis TLB Ltd
CleantechInnovate
 
Ben Lynch - Cleantech Capital Advisors Limited
Ben Lynch - Cleantech Capital Advisors LimitedBen Lynch - Cleantech Capital Advisors Limited
Ben Lynch - Cleantech Capital Advisors Limited
CleantechInnovate
 
Ashleigh Environmental
Ashleigh Environmental Ashleigh Environmental
Ashleigh Environmental
CleantechInnovate
 
MATR
MATRMATR
Libralato Ltd
Libralato LtdLibralato Ltd
Libralato Ltd
CleantechInnovate
 
Keynote - Rob Saunders
Keynote - Rob SaundersKeynote - Rob Saunders
Keynote - Rob Saunders
CleantechInnovate
 

More from CleantechInnovate (20)

Rype Office
Rype OfficeRype Office
Rype Office
 
ThinAir Water Ltd
ThinAir Water LtdThinAir Water Ltd
ThinAir Water Ltd
 
Desolenator
Desolenator Desolenator
Desolenator
 
Cryomation Ltd
Cryomation LtdCryomation Ltd
Cryomation Ltd
 
Cambond Ltd
Cambond LtdCambond Ltd
Cambond Ltd
 
Afternoon Keynote - Chris Huhne
Afternoon Keynote - Chris HuhneAfternoon Keynote - Chris Huhne
Afternoon Keynote - Chris Huhne
 
AirEx
AirEx AirEx
AirEx
 
RAB Microfluidics
RAB MicrofluidicsRAB Microfluidics
RAB Microfluidics
 
LightFi
LightFiLightFi
LightFi
 
Gapogroup Ltd
Gapogroup LtdGapogroup Ltd
Gapogroup Ltd
 
Brill Power
Brill Power Brill Power
Brill Power
 
Flint Engineering
Flint Engineering Flint Engineering
Flint Engineering
 
Vortex Wave Power
Vortex Wave Power Vortex Wave Power
Vortex Wave Power
 
Skypull
Skypull Skypull
Skypull
 
Axis TLB Ltd
Axis TLB LtdAxis TLB Ltd
Axis TLB Ltd
 
Ben Lynch - Cleantech Capital Advisors Limited
Ben Lynch - Cleantech Capital Advisors LimitedBen Lynch - Cleantech Capital Advisors Limited
Ben Lynch - Cleantech Capital Advisors Limited
 
Ashleigh Environmental
Ashleigh Environmental Ashleigh Environmental
Ashleigh Environmental
 
MATR
MATRMATR
MATR
 
Libralato Ltd
Libralato LtdLibralato Ltd
Libralato Ltd
 
Keynote - Rob Saunders
Keynote - Rob SaundersKeynote - Rob Saunders
Keynote - Rob Saunders
 

Recently uploaded

To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 

Recently uploaded (20)

To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 

Storelectric

  • 1. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Mark Howitt, Director 07910 020 686 mhowitt@storelectric.com www.storelectric.com Storelectric Ltd Enabling Renewables to Power the Grid
  • 2. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Problem and Solution The Problem • Renewables are intermittent • GW scale renewables need GW scale back-up GW = Gigawatt, enough electricity to power a million people with their industry and infrastructure The Solution • Large scale, long duration storage • Each plant stores more electricity than a year’s output of Elon Musk’s Gigafactory • The UK has geological potential to power Europe for a week
  • 3. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Problem and Solution The Problem Renewables are intermittent They generate when they want to, not when we need them Therefore they need back-up – at the same scale Fossil fueled power station operating inefficiently £2bn p.a. to back up electricity now, doubling in ~5 years GW scale renewables need GW scale back-up Consider a windless winter night (a frequent occurrence) when renewables are powering all variable demand on the grid There is a 5-hour peak in demand coming up, as happens every night The peak is up to 30GW more demand than baseload generation, which is normal Will 30-60 minute duration battery supply the 5-hour peak? Will megawatt scale batteries satisfy gigawatt scale need? The Solution Large scale, long duration storage Each installation can replace a power station Complements batteries, interconnectors and other technologies The UK has geological potential to power Europe for a week Suitable geologies globally Does not compete with batteries, except on the periphery. Consider the road system: side and feeder roads are needed to support trunk roads and motorways; the latter are required to take the load off the former and enable them to work effectively. We are like the trunk roads and motorways; they are like the side and feeder roads. All are needed, all are complementary – as with interconnectors, flywheels, demand side response etc. With large scale long duration storage, the system works; without it, it fails.
  • 4. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The world’s biggest battery, using just air, water, salt and equipment Typical sizes: 40MW, 200-500MWh 500MW, 3-12GWh Compressed Air Energy Storage using Thermal Energy Storage Storelectric’s TES CAES
  • 5. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The world’s most efficient and cost-effective large scale electricity storage. Round trip efficiency ~62-64% for 40MW, ~70% for 500MW (existing plants are 42-50%) Almost as efficient as pumped hydro, less than 1/3 of the cost (depending in part on location), much closer to both supply and demand Capex for a 5 hour plant is comparable with capex of a half-hour battery of the same rating Efficiency increases with scale, in contrast with batteries Notes page for Storelectric’s TES CAES
  • 6. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Comparison with other CAES technologies
  • 7. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Compressed Air Energy Storage within a Combined Cycle Gas Turbine power station Grid, Storelectric’s CCGT CAES
  • 8. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for Storelectric’s TES CAES Round trip efficiency ~60% (existing plants 42-50%; new versions aspire to 54%) The only CAES technology that can be retro-fitted to CCGT or OCGT power stations over the right geology Gives new life to stranded power station assets: • Almost halves emissions • Adds storage related revenue streams • As electricity price volatility increases (see a later slide), opex drops significantly below that of the power station Much cheaper than any other CAES technology – but can’t estimate costs because that depends on what we’re retro-fitting. New, it costs only ~£10-15m more than a CCGT.
  • 9. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. A salt mine much smaller than our caverns which are ~300m tall An Idea of Scale Cavern Size • Our small plants’ caverns ~2 x St Paul’s Cathedral • Our large plants’ caverns ~25 x St Paul’s Cathedral What is a Cavern? • Drill a hole, pump in water, pump out brine, what’s left is the cavern • Cheap, well known technology • ~1/3 of Europe’s natural gas reserve is stored in salt caverns • Naturally hermetic • Pressure is determined by depth
  • 10. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for An Idea of Scale Note: This is a mine, not a salt cavern. It’s shown only to illustrate scale: for our small pilot plant (200MWh) we will use two caverns each almost as big as St Paul’s Cathedral in London. People and machines go down mines. To make a cavern, 1.Drill a hole into the salt basin 2.Pump in water, pump out brine; what’s left is the cavern. Salt caverns are naturally hermetic and self-healing in case cracks develop. Approaching 1/3 of all natural gas storage in Europe is stored in such salt caverns.
  • 11. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Market Top-Down • $1trn market to deliver dispatchable power • And that’s just the capital cost of building them • 3-6x more to deliver baseload • 3-10x more to support de-carbonisation of transportation and industry Bottom-Up • Each 40MW plant delivers 12-15% IRR • Each 500MW plant delivers 15+% IRR • Whole project IRR – much greater if largely project financed • IRR growing as renewables penetration grows
  • 12. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Market In the UK the market is over 20GW. The government’s TINA (Technology Innovation Needs Analysis) for Electricity Networks and Storage determined that the country needs a median 27.4GW and 128GWh (i.e. 5 hours average duration) of new storage. https://www.carbontrust.com/media/168551/tina-electricity- networks-storage-summary-report.pdf – see Chart 2. • We can ignore their breakdown of technologies. Total new pumped hydro planning applications are 1.05GW, none of which looks to be sufficiently cost-effective to be built. • For batteries, 0.1GW are operational, 0.6GW in construction, 1.1GW planning approved, 1.7GW planning pending [total so far 3.4GW] and a further 12GW with DNO applications outstanding (see https://auroraer.us11.list- manage.com/track/click?u=095bcc5477fce868775bbbd67&id=ded62ab359&e=e8860559df) but most of which are unlikely to be built due to: 1. The elimination of EFR (see Stage 1: Rationalisation p14 in https://www.nationalgrid.com/sites/default/files/documents/Product Roadmap for Frequency Response and Reserve.pdf ), 2. The saturation of the Primary Frequency Response market (see https://utilityweek.co.uk/frequency-response-market-nearing- saturation-industry-warned/ ) and 3. The heavy de-rating of batteries in the Capacity Market (see https://www.emrdeliverybody.com/Lists/Latest News/Attachments/150/Duration Limited Storage De-Rating Factor Assessment - Final.pdf – table E1 p5). Other analyses lead to similar conclusions: superimposing actual wind patterns on 2030 forecast wind generation yields a need for 30GW storage; the National Infrastructure Planning document sees needs at a similar level, etc. And that is just for peak smoothing, i.e. enabling renewables to deliver variable power. When baseload plants close (and few, if any, nuclear plants will open in time) then we need 3-6 times as much storage to enable renewables to supply baseload. And much more is needed to support the greening of heating (mainly via electrically driven heat pumps), transportation (electricity and hydrogen) and industry.
  • 13. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. IP, Competition Intellectual Property • Patentable: thermal storage system • Knowhow: system integration, trading, sites, partnerships Competition Storelectric Adiabatic CAES Existing CAES Isothermal CAES Status Quo Efficiency 68-70% 50% Unsuccessful (targeted 70%) Power stations operate very inefficiently Emissions (% of a power station) 0% 50-60% Scavenging heat (large scale impossible) >> 100% Capex (% of a power station) 150% 180% >> 200% 100% Opex (2025 estimate) (% of a power station) 60% 85% n/a 100% CAES = Compressed Air Energy Storage
  • 14. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for IP, Competition Intellectual Property Patentable: thermal storage system Over one-third more efficient than current technologies (~70% v 50%) IP will keep us ahead of competitors – efficiency goes straight to profits Knowhow: system integration, trading, sites, partnerships Competition Existing CAES 50% efficient – we are 68-70% 50-60% of emissions of a CCGT – ours are zero More expensive capex than ours The Status Quo Balancing renewables using fossil fueled power stations, inefficient and high emissions Isothermal CAES Different technology from ours: isothermal rather than adiabatic Adiabatic (us) balances heat over the whole cycle; isothermal (them) optimises compression Fundamentally weak concept: 3 existing businesses folded / folding
  • 15. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Team Partner Companies Paul Davies, Chairman Former Senior Partner, PwC Corporate Finance Infrastructure; former Director, HSBC infrastructure Tallat Azad, Managing Director Chartered Engineer; former Director, Alstom Power – new technologies, responsible for energy storage. Mark Howitt, Chief Technical Officer Inventor, Physicist, business experience in both multinationals and consultancy, 3 start-up subsidiaries, IP experience Jeff Draper, Chief Financial Officer Accountant, Physicist, entrepreneur, former partner in accounting firm
  • 16. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Team Partner Companies Our partner companies provide all the capabilities we need. Siemens – top-side equipment and control systems Costain – engineering and civils PwC – corporate finance and advisory Maloney Metalcraft – thermal energy subsystem Dentons – legal and advisory Fortum – dynamic modelling and optimization support KBB UT – rock mechanical analysis, cavern design and support ERM – planning and environmental support Oswald – the initial calculations and analyses of alternatives Durham University – R&D on future technological developments Shell Springboard awarded us our first money when we won their regional competition
  • 17. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Ask: 4 investment opportunities – 1. Topco 1. Topco Storelectric Ltd • £1m at £10m valuation • Develop new sites in preparation for setting up an SPV • These SPVs will develop revenues in 6-12 months • Develop capabilities in project management, plant operation, trading • Already raised £550k at valuations up to £2.5m in previous rounds
  • 18. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Ask: 4 investment opportunities – 1. Topco Topco £1m at £10m valuation IRR 15%, SEIS pre-approved, seeking EIS confirmation but this is far from guaranteed as Inland Revenue’s rules changed. Develop new sites (4-6 p.a. initially, increasing) using 2 technologies, to flip / spin off Develop capabilities in project management, plant operation, trading Will also develop new and hybrid technologies Storelectric licenses TES CAES from TES CAES Technology Ltd, whose three main shareholders / directors are common to both Storelectric owns the other technology and future developments that are not specific to TES CAES Already raised £400k at valuations up to £2.5m Also raised £150k for IP company
  • 19. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Ask: 4 investment opportunities – 2. Development 2 and 3. Plant Development SPVs (both types) SPV = Special Purpose Vehicle / Company – a separate company from Storelectric • 2. Distribution Connected Plant (up to 50MW) • £2.5m at £4m valuation (60%) • IRR 12-15% • Develop a new plant to shovel ready, 1 year (local planning process) • Exit by flipping – reinvest in next plants if EIS invested • 3. Transmission Connected Plant (typically 500MW) • £8m at £13.3m valuation (60%) • IRR 15%+ • Develop a new plant to shovel ready, 3 years (NSIP planning process) • Exit by flipping – reinvest in next plants if EIS invested
  • 20. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Ask: 4 investment opportunities – 2. Development Plant Development £2.5m at £4m valuation (60%) Connected to the distribution grid Typical size 40MW, 200MWh IRR 12-15% Develop a new plant to shovel ready, 1 year Exit by flipping – reinvest in next plants if EIS invested Note: EIS status is far from guaranteed as Inland Revenue rules exclude “generation”. Although we don’t generate (which we are discussing with HMRC), storage is defined legally as consumption plus generation. Even so, this is project development which, if it does not trade electricity (other than perhaps during commissioning) then it may be acceptable. £8m at £13.3m valuation (60%) Connected to the transmission grid Typical size 500MW, 2.5GWh IRR 15%+ Develop a new plant to shovel ready, 3 years Exit by flipping – reinvest in next plants if EIS invested Note: EIS status is far from guaranteed as Inland Revenue rules exclude “generation”. Although we don’t generate (which we are discussing with HMRC), storage is defined legally as consumption plus generation. Even so, this is project development which, if it does not trade electricity (other than perhaps during commissioning) then it may be acceptable.
  • 21. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. The Ask: 4 investment opportunities – 4. Construction 4. Plant Construction SPV SPV = Special Purpose Vehicle / Company – a separate company from Storelectric • £50m • IRR 12-15% at constant revenues and costs • Revenues are forecast to grow strongly • Operational costs are forecast to decrease strongly • Highly flexible plant able to accommodate a rapidly shifting regulatory landscape • 5-hour storage is not de-rated for duration on the Capacity Market, qualifies for Reserve revenue streams • Develop a new plant from shovel ready to post- commissioning, 2 years • An infrastructure play • Exit by either re-financing (e.g. 75% of the firm at 6% leads to a return on equity of ~32%) or sale ~25% of revenues are from arbitrage, following roughly the top blue dotted line ~80% of opex is electricity purchase costs, roughly the bottom blue dotted line ~50% of revenues are from balancing and ancillary services
  • 22. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Notes page for The Ask: 4 investment opportunities – 4. Construction The IRR is calculated on the assumption of constant trading conditions. However, trading conditions are improving in almost all revenue sources and in the main operational cost source, as per the graphs. Therefore returns on investment should be considerably higher.
  • 23. www.storelectric.com© 2018 Storelectric Ltd This presentation represents the current views and intentions of Storelectric at the time of writing. Mark Howitt, CTO +44 (0) 7910 020 686 mhowitt@storelectric.com Storelectric Ltd Compressed Air Energy Storage Enabling renewables to power the grid Jeff Draper, CFO +44 (0) 7919 536 551 jdraper@storelectric.com Tallat Azad, MD +44 (0) 7875 880 262 tallat.azad@storelectric.com Paul Davies, Chairman +44 (0) 7802 869 074 pdavies@storelectric.com