2. 1. Project Status
2. Summary of Public & Stakeholder Input
3. Strategies Applicable Study Area-Wide
4. Summary of Two Alternatives
5. Evaluation of Two Alternatives
6. Next Steps
3. Developing Two Alternatives for Evaluation.
Stakeholder Roundtable & Public Input.
Internal NFTA Meetings.
Obtain Direction on Further Developing an Alternative.
5. “Canalside Station”
Remove Special Events Station/
New Double Crossover
Improve Access To/From Amtrak
Support New
Amtrak Station
Streetscape Enhancements
Improve Access To/From First Ward
Improve Connection Between
Canalside & Cobblestone
Riverwalk Improvements
Support TOD
Redevelopment
Adaptive to Outer Harbor Access
Bricks for Buffalo
9. Requires Reconstruction of South Park (11’ lanes);
Can Operate with DL&W Work as Later Phase;
Rework of Yard;
Maintains Track 4, 5, 7, 9, 10, 12;
Ability to Backload Station;
Reconfigure Loop - Only Access to Shop Track 1;
Shop Track 2 & 3 have to be front loaded.
10.
11.
12.
13. Rework of Yard;
Maintains Track 4, 5, 7. Provides Track 5a;
Ability to Backload Station;
Maintains Loop, Access to Shop Track 1, 2 & 3;
Requires DL&W Work;
Loss of Storage.
21. Metro Rail Operations
Maintenance and Storage
User Convenience
Safety and Security
Right-of-Way
Multimodal Connectivity
Future Expansion
DL&W 2nd Floor Reuse
Redevelopment Potential
22. Pros Cons
Minimal impact on Metro Rail service
and scheduling
Eliminates Special Events Station
Maintain existing storage capacity
Upgrade yard infrastructure
Opportunity to phase improvements
to DL&W
Provides improved transit access and
connectivity in study area
Higher visibility of Metro Rail
Accommodates future expansion
along South Park or NFTA ROW
Provides access and invites users to
2nd floor of DL&W
Promotes redevelopment of
Cobblestone District
Significant construction impacts on
yard operations
Potential impact on shop operations
Potential conflict between Metro Rail
riders and vehicle traffic
Requires total reconstruction of South
Park Avenue
Requires full length high-level station
platform
Exposure to weather
23. Pros Cons
Minimal impact on Metro Rail service
and scheduling
Eliminates Special Events Station
Upgrade yard infrastructure
No impact to shop operations
Coatless connections – sheltered
from weather
Provides improved transit access and
connectivity in study area
Complete separation of Metro Rail
and vehicle traffic – track remains on
NFTA property
Requires minor reconstruction of
South Park Ave for station entrances
Accommodates futures expansion
along NFTA ROW
Provides access and brings users
directly to 2nd floor of DL&W
Promotes redevelopment of
Cobblestone District
Reduces vehicle and equipment
storage capacity
Requires immediate upgrades to
DL&W
Requires additional security between
public and non-public areas
24. Item Alternative A Alternative B
Road Work $1,780,000 $730,000
Station $4,900,000 $3,400,000
Pedestrian Corridors/ Bridges &
Elevators/ Stairs
$6,000,000 $12,000,000
Trackwork $2,390,000 $2,278,922
OCS Modifications $2,510,000 $2,457,227
Signals & Communications $800,000 $1,295,520
Building Modifications - $1,500,000
ESTIMATED SUBTOTAL $18,380,000 $23,661,669
Escalation to 2018 (2% per year) $1,126,000 $1,448,331
40% Contingency $7,800,000 $10,040,000
TOTAL CAPITAL COSTS $27,306,000 $35,150,000
Engineering/ Design $5,470,000 $7,030,000
ESTIMATED TOTAL $32,776,000 $42,180,000
26. Chose an Alternative to Move Forward;
Further Develop Chosen Alternative and Area Strategies;
Identify Environmental and Permitting Requirements;
Identify Financing Options;
Final Report