SlideShare a Scribd company logo
1 of 5
International Journal of Science and Research (IJSR)
ISSN (Online): 2319-7064
Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611
Volume 5 Issue 1, January 2016
www.ijsr.net
Licensed Under Creative Commons Attribution CC BY
Simulink Analysis of Vector Groups of
Transformers Installed at 132kV Grid Station
Qasimabad, Hyderabad and their Effects on
System Operation
Sunny Katyara1
,Sunny Kumar Gemnani2
1, 2
Wroclaw University of Technology Poland
Abstract: In this paper we have simulated the vector groups of transformers installed at 132 kV Grid Station Qasimabad Hyderabad
Pakistan with the use of MATLAB Simulink Software. We also make some real time changes in the vector groups of the installed
transformers and would analyze their effects on the system operation. The main objective of this paper is to understand the vector
groups of transformers, their need in the transformer parallel operation and to make comparative analysis by considering different
scenarios of vector groups for transformers installed at 132 kV Grid station Qasimabad Hyderabad Pakistan.
Keywords: Transformer, Vector Groups, Parallel Operation, Voltage Dip and MATLAB software
1. Introduction
The windings of three phase transformer can be connected
in different ways so as to meet the application requirements
[1]. Based on these connections of transformer, vectors
groups are specified for transformer on its name plate.
Actually vector group represents the phases shift between
the primary and secondary winding of transformer
according to their connections [2]. The vector groups would
necessarily been considered when transformers are required
to be paralleled to meet the increased load demand. If
transformers of different vectors groups are connected in
parallel then large circulating currents would flow between
two transformers which are dangerous and unnecessary [3-
4]. Since the transformers are used in different power
system applications such as; transmission, distribution and
insulation. The 132 kV grid station is at distribution level of
the power system. Therefore at 132 kV grid station,
delta/star connected transformers are invariably used, so as
to have three phase four wire system, for supplying single
phase as well as three phase loads [5]. Loads at the
distribution side are always unbalanced so there is always
some current in the neutral wire, which provides return
path. Therefore to compensate this unbalanced neutral
current, delta side of transformer allows the circulating
current to flow through its windings [6]. In electrical power
system engineering, vector group is the method for
characterizing the high tension (H.T) and low tension (L.T)
windings connections of three phase transformers, which is
being approved by international electro technical
commission (IEC). In practice, the voltage measurements
on two sides are used to deduce the vector group from the
literature about the vector geometries [7-8].
In this paper the authors have fed the readings to a special
purpose MATLAB Simulink Model of 132 kV grid station
Qasimabad Hyderabad and confirm the exact vector groups
and phase angles by means of simulation results. Also
vectors groups of transformers connected in parallel are
varied and their effects on system operation are also
simulated.
2. General Aspects of Vector Groups of
Transformers
2.1 Phase Rotation
According to IEC coding technique, vector groups are
represented by letters for each set of winding. The high
tension (H.T) winding is represented by upper case letter
while low tension (L.T) winding is represented by lower
case letter. The phasor related with (H.T) is taken as
reference and is stationary at 12 0’ clock, while (L.T) side
vector is rotating anti clockwise with reference (H.T)
vector, to represent phase displacement between two sides
of transformers. In the vector group code, the first letter
which is upper case is dedicated to (H.T) side, while second
letter which is in lower case is for (L.T) side, third letter is
related neutral connection especially in case of distribution
transformers and then fourth letter represents the phase
displacement value between the transformer windings.
Since the phase displacement of vector group is analogous
to hour and minute dials movement in the clock, hour dial
for (H.T) and minute dial is for (L.T). Each hour is
dedicated to 300
therefore 1st
hour= 300
, 2nd
hour= 600
and
so on. The sign for phase displacement depend upon the
rotation of (L.T) phasor with respect to (H.T), for anti-
clockwise it’s positive and negative for clockwise rotation.
Paper ID: NOV152593 1697
International Journal of Science and Research (IJSR)
ISSN (Online): 2319-7064
Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611
Volume 5 Issue 1, January 2016
www.ijsr.net
Licensed Under Creative Commons Attribution CC BY
Figure 1: Clock Showing Phase Displacement
2.2 Different Vector Groups of Transformers
Three phase, two winding, power transformers, can be
divided onto four major categories as shown in Table 01.
Table 1: Classification of Transformers Vector Groups
Group 0’ CLOCK TC Vector Rotation
Group I 0 O’ Clock , 0o
Delta/Delta
Star/Star
Dd0, Yy0, Dz0
Group II 6 O’ Clock , 180o
Delta/Delta,
Star/Star
Dd6, Yy6, Dz6
Group III 1 O’ Clock , -30o
Delta/Star,
Star/Delta
Dy1, Yd1, Yz1
Group IV 11 O’ Clock , +30o
Delta/Star,
Star/Delta
Dy11, Yd11, Yz11
Group I: In this group, high tension (H.T) and low tension
(L.T) windings are connected in same fashion either in
star/star or delta/delta with zero phase displacement. But by
doing some external changes we can designation of this
vector group from Dd0 to Dd4 (-1200
) or Dd8 (+1200
).
Group II: In this group, high tension (H.T) and low tension
(L.T) windings are connected in either delta/delta or
star/star with 1800
displacement, represented as Dd6 or Yy6.
By making some changes this vector can be changed to Dd2
(-600
) or Dd10 (+600
).
Group III: In this group high tension (H.T) and low tension
(L.T) windings are connected in different fashion either in
Delta/Star or Star/Delta with -300
phase displacement.
Through some changes, designation of this vector group can
be changed to Dyn5 (-1500
) of Dyn9 (+90).
Group IV: In this vector group, high tension (H.T) and low
tension (L.T) windings are connected in delta/star or
star/delta with +300
phase displacement. By doing some
external changes this vector group van be changed to either
Dyn7 (+1500
) or Dyn3 (-900
) connection
3. System Description and Simulink Modeling
At 132 kV grid station Qasimabad Hyderabad, Pakistan,
four transformers are installed as shown in Figure A. Three
of which are rated at 26 MVA and third one is rated at 40
MVA. They all operate in parallel to supply the cumulative
load demand on system. All these transformers have same
vector groups i-e; Dyn11, which is key requirement for the
parallel operation. But all these transformers have different
Iron and copper losses and also the excitation current as
shown in Tables 01, 02, 03 and 04.
Figure 2: Graphical representation of 132 kV grid station Qasimabad, Hyderabad
Paper ID: NOV152593 1698
International Journal of Science and Research (IJSR)
ISSN (Online): 2319-7064
Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611
Volume 5 Issue 1, January 2016
www.ijsr.net
Licensed Under Creative Commons Attribution CC BY
Table 2: The Rating of Transformer 1
Description Of Asgen Transformer 2 Of Qasimabad Grid
Transformer type TLTN7552 Tap position
H.V Side
Voltage
L.V Side
Voltage
H.V Side Current
A
L.V Side Current
Rated power 20/26MVA 1 145200V - 80/103 -
Insulation level A Class 12 13200 11500 87/114 1004/1305
Excitation Current 0.25% at 20MVA 23 118800 - 97/126 -
Iron losses 14.6 kW Short Circuit Duration 3 Second
Quantity of oil 20105 Litters Oil Weight 17669 kg
Total weight 61500 kg Vector Group Dyn 11
Table 3: The Rating of Transformer 2
Description of Siemens transformer 1 of Qasimabad grid
Transformer type TLPN7652 Tap position
H.V Side
Voltage
L.V Side
Voltage
H.V Side Current
A
L.V Side Current
Rated power 31.5/40MVA 1 145200V - 125.3/159 -
Insulation level A Class 12 13200 11500 137.8/175 1581.4/2008.2
Excitation Current 0.5% at 31.5MVA 23 118800 - 153.1/194.4 -
Iron losses 22.6 kW Short Circuit Duration 3 Second
Quantity of oil 22100 Litters Oil Weight 19669 kg
Total weight 73500 kg Vector Group Dyn 11
Table 4: The Rating of Transformer 3
Description Of Iran-Transfo Transformer 3 Of Qasimabad Grid
Transformer type TLTN7452 Tap position
H.V Side
Voltage
L.V Side
Voltage
H.V Side Current
A
L.V Side Current
Rated power 20/26MVA 1 145200V - 80/103 -
Insulation level A Class 12 13200 11500 87/114 1004/1305
Excitation Current 0.21% at 20 MVA 23 118800 - 97/126 -
Iron losses 12.6 kW Short Circuit Duration 3 Second
Quantity of oil 19705 Litters Oil Weight 16669 kg
Total weight 59500 kg Vector Group Dyn 11
Table 5: The Rating of Transformer 4
Description Of PEL Transformer 4 Of Qasimabad Grid
Transformer type TMAO 26/145
Tap
position
H.V Side
Voltage
L.V Side
Voltage
H.V Side
Current A
L.V Side
Current
Rated power 20/26MVA 1 145200V - 80/103 -
Insulation level A Class 12 13200 11500 87/114 1004/1305
Excitation Current 0.21% at 20 MVA 23 118800 - 97/126 -
Iron losses 12.6 kW Short Circuit Duration 3 Second
Quantity of oil 19705 Litters Oil Weight 16669 kg
Total weight 59500 kg Vector Group Dyn 11
Figure 2: Simulink Vector Group Analysis Design of 132
kV grid station Qasimabad, Hyderabad
Figure.02 represents Simulink model of 132 kV grid station
Qasimabad for vector group analysis, consisted of 132 kV
incoming line from Thermal power station Jamshoro and
Hala Power System. This grid station consists of four
parallel connected transformers supplying load, as shown by
cumulative loads for each transformer in figure.02. We can
notice that, all transformers are connected in Dyn11 fashion,
as the star point being connected with ground point of load
to suppress the zero sequence currents and also to manage
unbalanced loading.
4. Simulink Results
Figures 03, 04, 05 and 06 show phase displacements for
transformer 1, transformer 2, transformer 3 and transformer
04 respectively
Paper ID: NOV152593 1699
International Journal of Science and Research (IJSR)
ISSN (Online): 2319-7064
Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611
Volume 5 Issue 1, January 2016
www.ijsr.net
Licensed Under Creative Commons Attribution CC BY
Figure 3: Vector group Phase Displacement for Dyn11
Transformer 1 before changes
Figure 4: Vector group Phase Displacement for Dyn11
Transformer 2 before changes when transformer 1 is Dyn11
connected
Figure 5: Vector group Phase Displacement for Dyn11
Transformer 3 before changes when transformer 1 is Dyn11
connected
Figure 6: Vector group Phase Displacement for Dyn11
Transformer 4 before changes when transformer 1 is Dyn11
connected
We can see that all figures 03, 04, 05 and 06 have same
parameters and Simulink results, it is because all
transformers connected at grid station at 132 kV grid station
Qasimabad Hyderabad, Pakistan have same vector groups
which is the key requirement for paralleling transformers to
supply the increased power demand. From these figures we
can notice that Low tension (L.T) side voltage lags High
Tension (H.T) side by 30 degrees.
Now let’s make some changes in the vector groups of
transformers connected and compare the actual results of
vector groups of transformers. Let’s make the Dyn7 be the
new vector group for transformer and analyze the results
Figure 7: Vector group Phase Displacement for Dyn7
Transformer 1 after changes
Figure 8: Vector group Phase Displacement for Dyn11
Transformer 2 before changes when transformer 1 is Dyn7
connected
Figure 9: Vector group Phase Displacement for Dyn11
Transformer 3 before changes when transformer 1 is Dyn7
connected
Figure 10: Vector group Phase Displacement for Dyn11
Transformer 4 before changes when transformer 1 is Dyn7
connected
Since when the transformers of different vectors are
paralleled then circulating currents flows between them
which eventually cause short circuit between the
transformers and hence the voltage of the all transformers
Paper ID: NOV152593 1700
International Journal of Science and Research (IJSR)
ISSN (Online): 2319-7064
Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611
Volume 5 Issue 1, January 2016
www.ijsr.net
Licensed Under Creative Commons Attribution CC BY
connected dips down. You can analyze from these effects
from figures 07, 08, 09 and 10. We can see that in figures
07, 08, 09 and 10, the high tension and low tension voltages
are much less than the voltages in figures 03, 04, 05 and 06,
which is only due to these circulating currents caused by
paralleling different vector groups transformers.
5. Conclusion
By thoroughly going through these Simulink results we
have concluded that all transformers should have same
vector groups paralleling transformers. Otherwise large
circulating currents will flow and finally they cause short
circuit between the transformers. We also found that for the
distribution purpose we should select transformer with
Dyn11 vector group when generating side is Yd1 connected
and Dyn1 vector when the generating side is
Yd11connected. This vector group Dyn11 has many
advantages such as, it does not allow zero sequence currents
to pass across the transformer, and thus the yn side of
transformer is separately derived system, in which all earth
fault currents must flow through the neutral of transformer.
With this configuration, earth fault protection is possible
and practical. Likewise, earth fault protection on the
primary side is not affected by earth faults on the secondary
side of transformer if given transformer is connected in
Dyn11 fashion
References
[1] Iwanusiw O. W., “The Measurement of Transformer
Characteristics and Power Loss”, ITMA Journal,
Jan/Feb-(2011)
[2] Geno P., “A Review About Vector Group Connections
In Transformers”, International Journal Of
Advancements In Technology, ISSN: 0976-4860
(Online), Vol: 2, No. 2, 2011
[3] The Effect of Transformer’s Vector Group on Retained
Voltage Magnitude and Sag Frequency at V Industrial
Sites Due to Faults “World Academy of Science,
Engineering and Technology International Journal of
Electrical, Robotics, Electronics and Communications
Engineering” Vol: 7 No: 7, (2013)
[4] J. Parmar, Vector Group of Transformer,
http://electricalnotes.wordpress.com/2012/05/23/vector-
group-oftransformer
[5] A review about Testing of Distribution Transformers”
International Journal of Advancements in Technology
(IJoAT)” ,Vol 2, No 1. Geno Peter. P ,2011
[6] IEC 60076 -1 , “Power Transformers” –Part 1: General,
2000
[7] M. Aung, and J. Milanovic, “The Influence of
Transformer Winding Connections on the Propagation
of Voltage Sags”, IEEE Trans. on Power Delivery, vol.
21, no. 1, pp. 262–269, January 2006.
[8] Manitoba HVDC Research Center, PSCAD-Power
Systems Simulation Software, Version 4.2, Canada,
2004
Paper ID: NOV152593 1701

More Related Content

What's hot

153010010 mohammad babor
153010010  mohammad  babor153010010  mohammad  babor
153010010 mohammad baborBabor10
 
star delta transformation
star delta transformationstar delta transformation
star delta transformationShubhsWagh
 
Star delta trsformation
Star delta trsformationStar delta trsformation
Star delta trsformationHem Bhattarai
 
transmission line
transmission line transmission line
transmission line singh1515
 
Star delta transformation
Star delta transformation Star delta transformation
Star delta transformation Nishant Katara
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission lineDhananjay Jha
 
3phase circuits
3phase circuits3phase circuits
3phase circuitsPradeepa M
 
Three phase-circuits
Three phase-circuitsThree phase-circuits
Three phase-circuitsrsamurti
 
Representation of short & medium transmission lines
Representation of short & medium transmission linesRepresentation of short & medium transmission lines
Representation of short & medium transmission linesvishalgohel12195
 
EM_2131005_3_phasetransformers
EM_2131005_3_phasetransformersEM_2131005_3_phasetransformers
EM_2131005_3_phasetransformersJitin Pillai
 
short transmission line
short transmission lineshort transmission line
short transmission lineMohil Shah
 
Power Flow in a Transmission line
Power Flow in a Transmission linePower Flow in a Transmission line
Power Flow in a Transmission lineAyyarao T S L V
 
Three phase delta connection
Three phase delta connectionThree phase delta connection
Three phase delta connectionMayur Ekhande
 

What's hot (20)

153010010 mohammad babor
153010010  mohammad  babor153010010  mohammad  babor
153010010 mohammad babor
 
star delta transformation
star delta transformationstar delta transformation
star delta transformation
 
Star delta trsformation
Star delta trsformationStar delta trsformation
Star delta trsformation
 
Iit delhi star delta
Iit delhi star deltaIit delhi star delta
Iit delhi star delta
 
Power system calculations
Power system calculationsPower system calculations
Power system calculations
 
transmission line
transmission line transmission line
transmission line
 
Star delta transformation
Star delta transformation Star delta transformation
Star delta transformation
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
3phase circuits
3phase circuits3phase circuits
3phase circuits
 
Measurement of various line and phase quantities for a three phase ac circuit
Measurement of various line and phase quantities for a three phase ac circuitMeasurement of various line and phase quantities for a three phase ac circuit
Measurement of various line and phase quantities for a three phase ac circuit
 
Three phase-circuits
Three phase-circuitsThree phase-circuits
Three phase-circuits
 
Representation of short & medium transmission lines
Representation of short & medium transmission linesRepresentation of short & medium transmission lines
Representation of short & medium transmission lines
 
Ac distribution
Ac distributionAc distribution
Ac distribution
 
3-phase circuit
3-phase circuit3-phase circuit
3-phase circuit
 
EM_2131005_3_phasetransformers
EM_2131005_3_phasetransformersEM_2131005_3_phasetransformers
EM_2131005_3_phasetransformers
 
short transmission line
short transmission lineshort transmission line
short transmission line
 
Pdf star delta stater
Pdf star delta staterPdf star delta stater
Pdf star delta stater
 
Power Flow in a Transmission line
Power Flow in a Transmission linePower Flow in a Transmission line
Power Flow in a Transmission line
 
Three phase delta connection
Three phase delta connectionThree phase delta connection
Three phase delta connection
 
Ch11 polyphase
Ch11 polyphaseCh11 polyphase
Ch11 polyphase
 

Similar to Simulink Analysis of Vector groups of Transformers installed at 132kV Grid Station Qasimabad, Hyderabad and their effects on System operation

Development of a Novel Three Phase Grid-Tied Multilevel Inverter Topology
Development of a Novel Three Phase Grid-Tied Multilevel Inverter TopologyDevelopment of a Novel Three Phase Grid-Tied Multilevel Inverter Topology
Development of a Novel Three Phase Grid-Tied Multilevel Inverter TopologyIAES-IJPEDS
 
150513095337
150513095337150513095337
150513095337RK Semwal
 
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...ijsrd.com
 
Single and three phase Transformers
Single and three phase TransformersSingle and three phase Transformers
Single and three phase TransformersMohammed Waris Senan
 
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...IJMER
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...IDES Editor
 
4_5857160069648490643.ppt
4_5857160069648490643.ppt4_5857160069648490643.ppt
4_5857160069648490643.pptCali60
 
Chp 1 Intro to Transformers
Chp 1 Intro to TransformersChp 1 Intro to Transformers
Chp 1 Intro to Transformersable357
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...Alexander Decker
 
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...IAES-IJPEDS
 
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdf
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdfSVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdf
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdfgulie
 

Similar to Simulink Analysis of Vector groups of Transformers installed at 132kV Grid Station Qasimabad, Hyderabad and their effects on System operation (20)

O044057984
O044057984O044057984
O044057984
 
Development of a Novel Three Phase Grid-Tied Multilevel Inverter Topology
Development of a Novel Three Phase Grid-Tied Multilevel Inverter TopologyDevelopment of a Novel Three Phase Grid-Tied Multilevel Inverter Topology
Development of a Novel Three Phase Grid-Tied Multilevel Inverter Topology
 
150513095337
150513095337150513095337
150513095337
 
I010246467
I010246467I010246467
I010246467
 
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...
Analysis of Multilevel Inverter using Bipolar and Unipolar Switching Schemes ...
 
Transformers TR.pptx
Transformers TR.pptxTransformers TR.pptx
Transformers TR.pptx
 
Dy34760764
Dy34760764Dy34760764
Dy34760764
 
Single and three phase Transformers
Single and three phase TransformersSingle and three phase Transformers
Single and three phase Transformers
 
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...
Performance Evaluation of Nine Level Modified CHB Multilevel Inverter for Var...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Transformer.pptx
Transformer.pptxTransformer.pptx
Transformer.pptx
 
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...
A Single-Stage High-Frequency Isolated Secondary- Side Controlled AC-DC Conve...
 
Du36723729
Du36723729Du36723729
Du36723729
 
4_5857160069648490643.ppt
4_5857160069648490643.ppt4_5857160069648490643.ppt
4_5857160069648490643.ppt
 
[IJET-V1I6P3] Authors:Bachwad M.R. , Maske Ashadeep M
[IJET-V1I6P3] Authors:Bachwad M.R. , Maske Ashadeep M[IJET-V1I6P3] Authors:Bachwad M.R. , Maske Ashadeep M
[IJET-V1I6P3] Authors:Bachwad M.R. , Maske Ashadeep M
 
Chp 1 Intro to Transformers
Chp 1 Intro to TransformersChp 1 Intro to Transformers
Chp 1 Intro to Transformers
 
B230918
B230918B230918
B230918
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
 
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...
Estimation of Harmonics in Three-phase and Six-phase (Multi- phase) Load Circ...
 
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdf
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdfSVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdf
SVM-plus-Phase-Shift Modulation Strategy for Single-Stage.pdf
 

Recently uploaded

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Simulink Analysis of Vector groups of Transformers installed at 132kV Grid Station Qasimabad, Hyderabad and their effects on System operation

  • 1. International Journal of Science and Research (IJSR) ISSN (Online): 2319-7064 Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611 Volume 5 Issue 1, January 2016 www.ijsr.net Licensed Under Creative Commons Attribution CC BY Simulink Analysis of Vector Groups of Transformers Installed at 132kV Grid Station Qasimabad, Hyderabad and their Effects on System Operation Sunny Katyara1 ,Sunny Kumar Gemnani2 1, 2 Wroclaw University of Technology Poland Abstract: In this paper we have simulated the vector groups of transformers installed at 132 kV Grid Station Qasimabad Hyderabad Pakistan with the use of MATLAB Simulink Software. We also make some real time changes in the vector groups of the installed transformers and would analyze their effects on the system operation. The main objective of this paper is to understand the vector groups of transformers, their need in the transformer parallel operation and to make comparative analysis by considering different scenarios of vector groups for transformers installed at 132 kV Grid station Qasimabad Hyderabad Pakistan. Keywords: Transformer, Vector Groups, Parallel Operation, Voltage Dip and MATLAB software 1. Introduction The windings of three phase transformer can be connected in different ways so as to meet the application requirements [1]. Based on these connections of transformer, vectors groups are specified for transformer on its name plate. Actually vector group represents the phases shift between the primary and secondary winding of transformer according to their connections [2]. The vector groups would necessarily been considered when transformers are required to be paralleled to meet the increased load demand. If transformers of different vectors groups are connected in parallel then large circulating currents would flow between two transformers which are dangerous and unnecessary [3- 4]. Since the transformers are used in different power system applications such as; transmission, distribution and insulation. The 132 kV grid station is at distribution level of the power system. Therefore at 132 kV grid station, delta/star connected transformers are invariably used, so as to have three phase four wire system, for supplying single phase as well as three phase loads [5]. Loads at the distribution side are always unbalanced so there is always some current in the neutral wire, which provides return path. Therefore to compensate this unbalanced neutral current, delta side of transformer allows the circulating current to flow through its windings [6]. In electrical power system engineering, vector group is the method for characterizing the high tension (H.T) and low tension (L.T) windings connections of three phase transformers, which is being approved by international electro technical commission (IEC). In practice, the voltage measurements on two sides are used to deduce the vector group from the literature about the vector geometries [7-8]. In this paper the authors have fed the readings to a special purpose MATLAB Simulink Model of 132 kV grid station Qasimabad Hyderabad and confirm the exact vector groups and phase angles by means of simulation results. Also vectors groups of transformers connected in parallel are varied and their effects on system operation are also simulated. 2. General Aspects of Vector Groups of Transformers 2.1 Phase Rotation According to IEC coding technique, vector groups are represented by letters for each set of winding. The high tension (H.T) winding is represented by upper case letter while low tension (L.T) winding is represented by lower case letter. The phasor related with (H.T) is taken as reference and is stationary at 12 0’ clock, while (L.T) side vector is rotating anti clockwise with reference (H.T) vector, to represent phase displacement between two sides of transformers. In the vector group code, the first letter which is upper case is dedicated to (H.T) side, while second letter which is in lower case is for (L.T) side, third letter is related neutral connection especially in case of distribution transformers and then fourth letter represents the phase displacement value between the transformer windings. Since the phase displacement of vector group is analogous to hour and minute dials movement in the clock, hour dial for (H.T) and minute dial is for (L.T). Each hour is dedicated to 300 therefore 1st hour= 300 , 2nd hour= 600 and so on. The sign for phase displacement depend upon the rotation of (L.T) phasor with respect to (H.T), for anti- clockwise it’s positive and negative for clockwise rotation. Paper ID: NOV152593 1697
  • 2. International Journal of Science and Research (IJSR) ISSN (Online): 2319-7064 Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611 Volume 5 Issue 1, January 2016 www.ijsr.net Licensed Under Creative Commons Attribution CC BY Figure 1: Clock Showing Phase Displacement 2.2 Different Vector Groups of Transformers Three phase, two winding, power transformers, can be divided onto four major categories as shown in Table 01. Table 1: Classification of Transformers Vector Groups Group 0’ CLOCK TC Vector Rotation Group I 0 O’ Clock , 0o Delta/Delta Star/Star Dd0, Yy0, Dz0 Group II 6 O’ Clock , 180o Delta/Delta, Star/Star Dd6, Yy6, Dz6 Group III 1 O’ Clock , -30o Delta/Star, Star/Delta Dy1, Yd1, Yz1 Group IV 11 O’ Clock , +30o Delta/Star, Star/Delta Dy11, Yd11, Yz11 Group I: In this group, high tension (H.T) and low tension (L.T) windings are connected in same fashion either in star/star or delta/delta with zero phase displacement. But by doing some external changes we can designation of this vector group from Dd0 to Dd4 (-1200 ) or Dd8 (+1200 ). Group II: In this group, high tension (H.T) and low tension (L.T) windings are connected in either delta/delta or star/star with 1800 displacement, represented as Dd6 or Yy6. By making some changes this vector can be changed to Dd2 (-600 ) or Dd10 (+600 ). Group III: In this group high tension (H.T) and low tension (L.T) windings are connected in different fashion either in Delta/Star or Star/Delta with -300 phase displacement. Through some changes, designation of this vector group can be changed to Dyn5 (-1500 ) of Dyn9 (+90). Group IV: In this vector group, high tension (H.T) and low tension (L.T) windings are connected in delta/star or star/delta with +300 phase displacement. By doing some external changes this vector group van be changed to either Dyn7 (+1500 ) or Dyn3 (-900 ) connection 3. System Description and Simulink Modeling At 132 kV grid station Qasimabad Hyderabad, Pakistan, four transformers are installed as shown in Figure A. Three of which are rated at 26 MVA and third one is rated at 40 MVA. They all operate in parallel to supply the cumulative load demand on system. All these transformers have same vector groups i-e; Dyn11, which is key requirement for the parallel operation. But all these transformers have different Iron and copper losses and also the excitation current as shown in Tables 01, 02, 03 and 04. Figure 2: Graphical representation of 132 kV grid station Qasimabad, Hyderabad Paper ID: NOV152593 1698
  • 3. International Journal of Science and Research (IJSR) ISSN (Online): 2319-7064 Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611 Volume 5 Issue 1, January 2016 www.ijsr.net Licensed Under Creative Commons Attribution CC BY Table 2: The Rating of Transformer 1 Description Of Asgen Transformer 2 Of Qasimabad Grid Transformer type TLTN7552 Tap position H.V Side Voltage L.V Side Voltage H.V Side Current A L.V Side Current Rated power 20/26MVA 1 145200V - 80/103 - Insulation level A Class 12 13200 11500 87/114 1004/1305 Excitation Current 0.25% at 20MVA 23 118800 - 97/126 - Iron losses 14.6 kW Short Circuit Duration 3 Second Quantity of oil 20105 Litters Oil Weight 17669 kg Total weight 61500 kg Vector Group Dyn 11 Table 3: The Rating of Transformer 2 Description of Siemens transformer 1 of Qasimabad grid Transformer type TLPN7652 Tap position H.V Side Voltage L.V Side Voltage H.V Side Current A L.V Side Current Rated power 31.5/40MVA 1 145200V - 125.3/159 - Insulation level A Class 12 13200 11500 137.8/175 1581.4/2008.2 Excitation Current 0.5% at 31.5MVA 23 118800 - 153.1/194.4 - Iron losses 22.6 kW Short Circuit Duration 3 Second Quantity of oil 22100 Litters Oil Weight 19669 kg Total weight 73500 kg Vector Group Dyn 11 Table 4: The Rating of Transformer 3 Description Of Iran-Transfo Transformer 3 Of Qasimabad Grid Transformer type TLTN7452 Tap position H.V Side Voltage L.V Side Voltage H.V Side Current A L.V Side Current Rated power 20/26MVA 1 145200V - 80/103 - Insulation level A Class 12 13200 11500 87/114 1004/1305 Excitation Current 0.21% at 20 MVA 23 118800 - 97/126 - Iron losses 12.6 kW Short Circuit Duration 3 Second Quantity of oil 19705 Litters Oil Weight 16669 kg Total weight 59500 kg Vector Group Dyn 11 Table 5: The Rating of Transformer 4 Description Of PEL Transformer 4 Of Qasimabad Grid Transformer type TMAO 26/145 Tap position H.V Side Voltage L.V Side Voltage H.V Side Current A L.V Side Current Rated power 20/26MVA 1 145200V - 80/103 - Insulation level A Class 12 13200 11500 87/114 1004/1305 Excitation Current 0.21% at 20 MVA 23 118800 - 97/126 - Iron losses 12.6 kW Short Circuit Duration 3 Second Quantity of oil 19705 Litters Oil Weight 16669 kg Total weight 59500 kg Vector Group Dyn 11 Figure 2: Simulink Vector Group Analysis Design of 132 kV grid station Qasimabad, Hyderabad Figure.02 represents Simulink model of 132 kV grid station Qasimabad for vector group analysis, consisted of 132 kV incoming line from Thermal power station Jamshoro and Hala Power System. This grid station consists of four parallel connected transformers supplying load, as shown by cumulative loads for each transformer in figure.02. We can notice that, all transformers are connected in Dyn11 fashion, as the star point being connected with ground point of load to suppress the zero sequence currents and also to manage unbalanced loading. 4. Simulink Results Figures 03, 04, 05 and 06 show phase displacements for transformer 1, transformer 2, transformer 3 and transformer 04 respectively Paper ID: NOV152593 1699
  • 4. International Journal of Science and Research (IJSR) ISSN (Online): 2319-7064 Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611 Volume 5 Issue 1, January 2016 www.ijsr.net Licensed Under Creative Commons Attribution CC BY Figure 3: Vector group Phase Displacement for Dyn11 Transformer 1 before changes Figure 4: Vector group Phase Displacement for Dyn11 Transformer 2 before changes when transformer 1 is Dyn11 connected Figure 5: Vector group Phase Displacement for Dyn11 Transformer 3 before changes when transformer 1 is Dyn11 connected Figure 6: Vector group Phase Displacement for Dyn11 Transformer 4 before changes when transformer 1 is Dyn11 connected We can see that all figures 03, 04, 05 and 06 have same parameters and Simulink results, it is because all transformers connected at grid station at 132 kV grid station Qasimabad Hyderabad, Pakistan have same vector groups which is the key requirement for paralleling transformers to supply the increased power demand. From these figures we can notice that Low tension (L.T) side voltage lags High Tension (H.T) side by 30 degrees. Now let’s make some changes in the vector groups of transformers connected and compare the actual results of vector groups of transformers. Let’s make the Dyn7 be the new vector group for transformer and analyze the results Figure 7: Vector group Phase Displacement for Dyn7 Transformer 1 after changes Figure 8: Vector group Phase Displacement for Dyn11 Transformer 2 before changes when transformer 1 is Dyn7 connected Figure 9: Vector group Phase Displacement for Dyn11 Transformer 3 before changes when transformer 1 is Dyn7 connected Figure 10: Vector group Phase Displacement for Dyn11 Transformer 4 before changes when transformer 1 is Dyn7 connected Since when the transformers of different vectors are paralleled then circulating currents flows between them which eventually cause short circuit between the transformers and hence the voltage of the all transformers Paper ID: NOV152593 1700
  • 5. International Journal of Science and Research (IJSR) ISSN (Online): 2319-7064 Index Copernicus Value (2013): 6.14 | Impact Factor (2014): 5.611 Volume 5 Issue 1, January 2016 www.ijsr.net Licensed Under Creative Commons Attribution CC BY connected dips down. You can analyze from these effects from figures 07, 08, 09 and 10. We can see that in figures 07, 08, 09 and 10, the high tension and low tension voltages are much less than the voltages in figures 03, 04, 05 and 06, which is only due to these circulating currents caused by paralleling different vector groups transformers. 5. Conclusion By thoroughly going through these Simulink results we have concluded that all transformers should have same vector groups paralleling transformers. Otherwise large circulating currents will flow and finally they cause short circuit between the transformers. We also found that for the distribution purpose we should select transformer with Dyn11 vector group when generating side is Yd1 connected and Dyn1 vector when the generating side is Yd11connected. This vector group Dyn11 has many advantages such as, it does not allow zero sequence currents to pass across the transformer, and thus the yn side of transformer is separately derived system, in which all earth fault currents must flow through the neutral of transformer. With this configuration, earth fault protection is possible and practical. Likewise, earth fault protection on the primary side is not affected by earth faults on the secondary side of transformer if given transformer is connected in Dyn11 fashion References [1] Iwanusiw O. W., “The Measurement of Transformer Characteristics and Power Loss”, ITMA Journal, Jan/Feb-(2011) [2] Geno P., “A Review About Vector Group Connections In Transformers”, International Journal Of Advancements In Technology, ISSN: 0976-4860 (Online), Vol: 2, No. 2, 2011 [3] The Effect of Transformer’s Vector Group on Retained Voltage Magnitude and Sag Frequency at V Industrial Sites Due to Faults “World Academy of Science, Engineering and Technology International Journal of Electrical, Robotics, Electronics and Communications Engineering” Vol: 7 No: 7, (2013) [4] J. Parmar, Vector Group of Transformer, http://electricalnotes.wordpress.com/2012/05/23/vector- group-oftransformer [5] A review about Testing of Distribution Transformers” International Journal of Advancements in Technology (IJoAT)” ,Vol 2, No 1. Geno Peter. P ,2011 [6] IEC 60076 -1 , “Power Transformers” –Part 1: General, 2000 [7] M. Aung, and J. Milanovic, “The Influence of Transformer Winding Connections on the Propagation of Voltage Sags”, IEEE Trans. on Power Delivery, vol. 21, no. 1, pp. 262–269, January 2006. [8] Manitoba HVDC Research Center, PSCAD-Power Systems Simulation Software, Version 4.2, Canada, 2004 Paper ID: NOV152593 1701