SlideShare a Scribd company logo
Partnership To Advance Clean Energy-Deployment (PACE-D)
Technical Assistance Program
Presented by
USAID PACE-D TA Program
Apr-18
Solar PV Rooftop Training Program For Entrepreneurs
Session:
Project Costing & Economics
Contents
Project Variations
Project cost components
Project Financing and Revenues
Tariff Determination by the Regulators
Conclusions – Keys make a good business case
Project Variations – Investment Models (1/2)
Capex Opex (BOO / BOOT)
‘Sale’ of system to customer Sale of energy over lifetime
Investment as working capital till
commissioning
Long term investment till transfer of
system or withdrawal of system
O&M chargeable basis O&M own costs
Warranties of components in customer’s
name
Warranties in own name
No possibility of claiming Accelerated
Depreciation Benefit – customer can avail
avail it
Possible to avail Accelerated Benefit
Project Variations – Investment Models (2/2)
Gross metering Net metering
Capacity limited by investment and
available area
Capacity limited (additionally) by
contract demand and transformer
capacity
Revenue depends on PPA rate and
probably would be constant over a
period
Revenue is from saved energy and
depends on consumer tariff and
probably would be increasing
continuously
Bankability based on utility financial
strength
Bankability based on own business
growth and energy requirement
Dependence also on overall state / utility
energy requirement in future
Dependence on own energy
requirement projections and tariff rates
in future
Project Cost Components
Project Cost Components
Fixed Component
 System equipment capital cost
 Site related cost – roof rent / strengthening /
new roofing
 O&M costs over a period
 Fixed charges for project approval /
registration / sanction
 Utility charges – based on units of electricity –
over a period
 Debt / loan related upfront charges –
processing
 Pre-operative costs – interest, marketing costs
Variable Component
 Structure – Aluminium / GI
 Surface – flat / sloping RCC / sloping tinned
roof / super structure
 Interconnection voltage level – 230V / 415V /
11KV / 33KV
 Interconnection point distance from inverter
 String inverters / central inverters
 Fixed structure / tracking (single axis / double
axis)
Project Capital Cost (Rs./KWp)
Components
For about
500 KWp
and
above
For about
100 kWp
For about
50 kWp
For about
10 kWp
For about
1 kWp
Solar Modules 24,000 24,000 25,000 26,000 28,000
Module mounting
structure
3,000 3,000 4,000 5,000 5,000
Inverters 7,000 8,000 10,000 13,000 18,000
Electrical Balance of
system components
6,000 8,000 10,000 12,000 13,000
Civil Structures 3,000 3,000 3,000 4,000 5,000
I&C and Transportation 3,000 3,000 4,000 5,000 5,000
Total 46,000 49,000 56,000 65,000 74,000 Above are tentative cost estimates, of course will change in different scenarios
 These are costs. Taxes, profit and other contingencies not considered
Basis for Effects on System Capital Costs
Sr No Components For about 500
kWp and above
For about
100 kWp
Share in
Cost
Share in
Cost
1 Solar Modules 24,000 24,000 52% 49%
2 Module mounting 3,000 3,000 7% 6%
3 Inverters 7,000 8,000 15% 16%
4 Electrical Components 6,000 8,000 13% 16%
5 Miscellaneous 3,000 3,000 7% 6%
6 I&C and allied 3,000 3,000 7% 6%
Total 46,000 49,000
Factors affecting System Capital Costs
Deviation Original
assumption
Change Original cost
per kWp
New Cost
per kWp
Percentage
Effect on
46,000/-
Sloping roof GI structure
on flat roof
Al structure
on sloping
roof
Rs. 3,000/- Rs. 2,500/- 1.1%
reduction
Super structure
structure
Flat RCC roof
roof
mounted
Raised
structure of
10’
Rs. 3,000/- Rs. 9,000/- 13% increase
Interconnectio
n voltage
230 V 1
Phase or 415
415 V 3
Phase
11 / 33 KV 3
Phase
Rs. 0/- Rs. 20,000/-
Rs. 4,000/-
42% increase
8% increase
Inverter type String
inverters
Central
inverter
Rs. 7,500/- Rs. 4,500/- 6% reduction
Factors affecting System Capital Costs
Deviation Original
assumption
Change Original
cost per
kWp
New Cost
per kWp
Percentage
Effect on
46,000/-
Distance between
array and inverter
Less than 10
M
About 50
M
Rs. 2,000/- Rs. 6,000/- 8% increase
Distance between
inverter and
interconnection
Less than 25
M
About
100 M
Rs. 1,000/- Rs. 4,000/- 6% increase
Net Meter Net meter not
included
Net
included
Rs. 0/- Rs. 150/- 0.3% increase
increase
Project Financing & Revenues
Options
 Debt : Equity = 70:30 / 75:25 – normal
financing norms for banks
 Equity – own / own land and private
equity / own and community sourcing
 Debt – public sector banks / private
banks / NBFCs / IREDA / foreign
institutional / foreign individual
Variables
 Tariff and its pattern – constant /
increasing
 Energy generation
 Location
 Azimuth – clear or angular (direction
of array face)
 Shadowing objects
 Grid outages / quality of grid
 Debt (term loan) interest rate
 Repayment period of debt and
moratorium
 Possibility of availing Accelerated
Depreciation benefit
TARIFF DETERMINATION BY THE REGULATORS
Tariff Determination by the Regulators
Tariff Determination
Tariff Determination
 CERC publishes order for Renewable Energy
tariffs and is either adopted by SERCs or
some changes are made based state
specific conditions
 Normally announced for a control period of
five years, but may change on annual basis
 Based on certain defined assumptions
 Tariff designed to provide the investors a
market based motivational Return of
Investment
Observations
 Auxiliary consumption is taken as NIL
 No de-rating considered in solar modules
 Capacity Utilization Factor (CUF) considered
on limited experience in India or within a
state
 Interest rate on loan (debt) considered
based on State Bank of India
 Charges to utilities not considered
Arriving at Levelized Cost of Energy
S.
No.
Assumption
Head
Sub - Head Sub – Head (2) Assumptions Unit
1 Power
Generation
Capacity Installed Power generation
capacity
Auxiliary Consumption
CUF
Useful Life
1
0.00
19.0
25
MW
%
%
Years
2 Project Cost Capital
Cost/ MW
Power Plant Cost 530.02 Rs Lacs/MW
3 Financial
Assumptions
Debt: Equity
Tariff Period
Debt
Equity
Total Debt Amount
Total Equity Amount
25
70%
30%
371.02
159.01
Years
%
%
Rs Lacs
Rs Lacs
Arriving at Levelized Cost of Energy
S.
No
Assumption
Head
Sub - Head Sub – Head (2) Assumptions Unit
4 Financial
Assumptions
Debt Component
Equity
Component
Fiscal
Assumptions
Loan Amount
Moratorium Period
Repayment Period
Interest Rate
Equity Amount
Return on Equity (RoE) for
first 10 years
RoE after 10th year
Weighted average RoE
Discount Rate
Income Tax
MAT for first 10 years
371.02
0
12
12.76
159.01
20
24
22.40
10.64
34.61
21.34
Rs Lacs
Years
Years
%
Rs Lacs
% p.a.
% p.a.
%
%
%
Arriving at Levelized Cost of Energy
S.
No
Assumption
Head
Sub - Head Sub – Head (2) Assumptions Unit
5 Financial
Assumptions
Depreciation Depreciation for 12 years
Depreciation after 13th
year
5.83
1.54
%
%
6 Working Capital Fixed charges
Variable charges
O&M charges
Maintenance spare
Receivables for Debtors
Working capital Int.
1
15
2
13.26
Month
%
Months
%
7 Operation &
Maintenance
O&M expenses (2016-17)
O&M expn. escalation
O&M expn. (2012-13)
7.00
5.72
11.00
Rs Lacs
%
Rs Lacs
Arriving at Levelized Cost of Energy
Arriving at Levelized Cost of Energy –
with AD (not the latest Rate – 40%)
CREATING BUSINESS CASE FOR A PROJECT
 Building blocks of project financials – common for most of the models
 Models
 On premises Captive
 Net metering
 Open access – Third party sale
 Open access – Captive consumption
 Effect of varying parameters
Creating Business Case for a Project
Please see Excel file for detailed working
Creating Business Case for a Project
Creating Business Case for a Project
Year Basis 1 2 3
Units Generated (in Lakh kWH) 16.00 15.84 15.68
Utility Grid Losses (Wheeling) 0.96 0.95 0.94
Net Units sold 15.04 14.89 14.74
Tariff of sold units (Rs.) with inflation 5% 6.50 6.83 7.17
Revenue from sale of energy 97.76 101.62 105.64
Operational Cost 0.00 10.27 10.78
Operational Charges to Utility 29.96 29.66 29.36
Inverter replacement cost (12th year) 0.00 0.00 0.00
Total expenses 29.96 39.93 40.14
Gross Earnings (510.50) 67.80 61.70 65.49
Repayment of Term Loan 19.40 21.92 24.77
EBIDTA 48.40 39.77 40.72
Cumulative EBIDTA 510.50 48.40 88.17 128.89
Interest on Term Loan 46.46 43.93 41.08
Total expenses and repayments 95.82 105.78 106.00
Open Access Third Party Sale 1MW
Creating Business Case for a Project
Scenarios Case 1 Case 2 Case 3 Case 4 Case 5 Case 6
Tariff of sold energy in the First
year
11.00 9.00 11.00 10.00 10.00 8.00
Increment in tariff every year 4% 4% 0% 3% 0% 5%
Total Revenue in first year 330.88 270.72 330.88 300.80 300.80 240.64
Total Expenses in first year 59.92 59.92 59.92 59.92 59.92 59.92
Gross in hand in first year 270.96 210.80 270.96 240.88 240.88 180.72
Repayment of Debt in first year 151.76 151.76 151.76 151.76 151.76 151.76
Net in hand in first year before
taxes
119.20 59.04 119.20 89.12 89.12 28.96
Equity Payback Estimate
Equity Payback (years) 3 5 3 4 5 8
Equity IRR 37% 25% 28% 28% 21% 22%
Project Payback Estimate
Project Payback (years) 5 8 7 7 10 10
Project IRR 24% 19% 19% 20% 16% 18%
Different scenario comparison
Keys to a Good Business Case
Conclusion
 Many DISCOMS and SNAs also have empanelment or registration processes for
some components like inverters, meters etc.
 Reducing capital cost only one of the factors affecting economics
 Energy generation probably most important factor
 Quality of components, workmanship and performance over life
 Term loan interest rate and period another important factor
 Low interest loans or increased self contribution
 Focus on tariff in the first year in itself not as important as its pattern over the
years
Keys to a Good Business Case
Conclusion
 Solar is long term investment project
 Expect continued returns over 25 years, but at lower rates than some other
businesses
 Modules have output warranty of 25 years but continue to generate
electricity even after that
 Inverters may require one replacement within 25 years
 Other components may not require any replacement within 25 years
 Low maintenance requirement; washing of modules is the only regular activity
25
Anurag Mishra
Senior Clean Energy Specialist
USAID/India
Email: amishra@usaid.gov
Disclaimer:
This training material is made possible by the support of the American
People through the United States Agency for International
Development (USAID). The contents of this material are the sole
responsibility of Nexant, Inc. and do not necessarily reflect the views of
USAID or the United States Government. This material was prepared
under Contract Number AID-386-C-12-00001.

More Related Content

What's hot

Session 09 spvrt business models
Session 09   spvrt business modelsSession 09   spvrt business models
Session 09 spvrt business models
Chirag Jain
 
quiz Solar PV Rooftop Training Entrepreneurship Development
quiz Solar PV Rooftop Training Entrepreneurship Developmentquiz Solar PV Rooftop Training Entrepreneurship Development
quiz Solar PV Rooftop Training Entrepreneurship Development
Chirag Jain
 
Session 19 project performance evaluation Operation & Maintenance planning
Session 19   project performance evaluation Operation & Maintenance planningSession 19   project performance evaluation Operation & Maintenance planning
Session 19 project performance evaluation Operation & Maintenance planning
Chirag Jain
 
Session 11 overview of simulation software
Session 11   overview of simulation softwareSession 11   overview of simulation software
Session 11 overview of simulation software
Chirag Jain
 
Solar and wind power forecasting
Solar and wind power forecastingSolar and wind power forecasting
Solar and wind power forecasting
RCREEE
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overview
Chirag Jain
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Gensol Engineering Limited
 
2 sun shot perspective-pathways to reducing pv lcoe
2   sun shot perspective-pathways to reducing pv lcoe2   sun shot perspective-pathways to reducing pv lcoe
2 sun shot perspective-pathways to reducing pv lcoe
Sandia National Laboratories: Energy & Climate: Renewables
 
Agreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusAgreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plus
Private Consultants
 
Solar ppa guvnl final
Solar ppa guvnl finalSolar ppa guvnl final
Solar ppa guvnl final
PRIYANK JAIN
 
Flywheel Action Plan
Flywheel Action PlanFlywheel Action Plan
Flywheel Action Plan
eccafepatron
 
Session 05 grid connected inverter
Session 05   grid connected inverterSession 05   grid connected inverter
Session 05 grid connected inverter
Chirag Jain
 
Demand Response in the US
Demand Response in the US Demand Response in the US
Demand Response in the US
IEA DSM Implementing Agreement (IA)
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Gensol Engineering Limited
 
9 incorporating energy storage into pv system design
9   incorporating energy storage into pv system design9   incorporating energy storage into pv system design
9 incorporating energy storage into pv system design
Sandia National Laboratories: Energy & Climate: Renewables
 
PG&E Demand Response Programs
PG&E Demand Response ProgramsPG&E Demand Response Programs
PG&E Demand Response Programs
michaeljmack
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
Private Consultants
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Anil Kumar Bohra
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdf
Avijit Choudhury
 
Financing of New Nuclear Capacities
Financing of New Nuclear CapacitiesFinancing of New Nuclear Capacities
Financing of New Nuclear Capacities
Alexander Wolski
 

What's hot (20)

Session 09 spvrt business models
Session 09   spvrt business modelsSession 09   spvrt business models
Session 09 spvrt business models
 
quiz Solar PV Rooftop Training Entrepreneurship Development
quiz Solar PV Rooftop Training Entrepreneurship Developmentquiz Solar PV Rooftop Training Entrepreneurship Development
quiz Solar PV Rooftop Training Entrepreneurship Development
 
Session 19 project performance evaluation Operation & Maintenance planning
Session 19   project performance evaluation Operation & Maintenance planningSession 19   project performance evaluation Operation & Maintenance planning
Session 19 project performance evaluation Operation & Maintenance planning
 
Session 11 overview of simulation software
Session 11   overview of simulation softwareSession 11   overview of simulation software
Session 11 overview of simulation software
 
Solar and wind power forecasting
Solar and wind power forecastingSolar and wind power forecasting
Solar and wind power forecasting
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overview
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
2 sun shot perspective-pathways to reducing pv lcoe
2   sun shot perspective-pathways to reducing pv lcoe2   sun shot perspective-pathways to reducing pv lcoe
2 sun shot perspective-pathways to reducing pv lcoe
 
Agreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plusAgreements for Net metering, Net accounting, Net plus
Agreements for Net metering, Net accounting, Net plus
 
Solar ppa guvnl final
Solar ppa guvnl finalSolar ppa guvnl final
Solar ppa guvnl final
 
Flywheel Action Plan
Flywheel Action PlanFlywheel Action Plan
Flywheel Action Plan
 
Session 05 grid connected inverter
Session 05   grid connected inverterSession 05   grid connected inverter
Session 05 grid connected inverter
 
Demand Response in the US
Demand Response in the US Demand Response in the US
Demand Response in the US
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
9 incorporating energy storage into pv system design
9   incorporating energy storage into pv system design9   incorporating energy storage into pv system design
9 incorporating energy storage into pv system design
 
PG&E Demand Response Programs
PG&E Demand Response ProgramsPG&E Demand Response Programs
PG&E Demand Response Programs
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdf
 
Financing of New Nuclear Capacities
Financing of New Nuclear CapacitiesFinancing of New Nuclear Capacities
Financing of New Nuclear Capacities
 

Similar to Session 12 project costing & economics

Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...
SustainableEnergyAut
 
Presentation aes eletropaulo_3_q12_sem discurso_v2
Presentation aes eletropaulo_3_q12_sem discurso_v2Presentation aes eletropaulo_3_q12_sem discurso_v2
Presentation aes eletropaulo_3_q12_sem discurso_v2
AES Eletropaulo
 
TPDDL Excellence Journey
TPDDL Excellence JourneyTPDDL Excellence Journey
TPDDL Excellence Journey
Tata Power Delhi Distribution Limited
 
Financial Sensitivity in the Wind Industry The Numbers You Really Need to Know
Financial Sensitivity in the Wind Industry The Numbers You Really Need to KnowFinancial Sensitivity in the Wind Industry The Numbers You Really Need to Know
Financial Sensitivity in the Wind Industry The Numbers You Really Need to Know
mtingle
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta
 
Merc approach paper for determination of soalr tariff 2014
Merc approach paper for determination of soalr tariff 2014Merc approach paper for determination of soalr tariff 2014
Merc approach paper for determination of soalr tariff 2014
indianpowerindustry.com
 
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
Farming Futures
 
Key Steps and Success Factors in EPC Implementation
Key Steps and Success Factors in EPC ImplementationKey Steps and Success Factors in EPC Implementation
Key Steps and Success Factors in EPC Implementation
ZAINI ABDUL WAHAB
 
Financial Model Logical Operation Presentation for Captive Power Plant
Financial Model Logical Operation Presentation for Captive Power PlantFinancial Model Logical Operation Presentation for Captive Power Plant
Financial Model Logical Operation Presentation for Captive Power Plant
S. W. Leung
 
The economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenuesThe economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenues
Sentient Science
 
Repowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic ResearchRepowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic Research
Aditya Parchure
 
Value of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed ApproachValue of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed Approach
John Farrell
 
SunBurn Test
SunBurn TestSunBurn Test
SunBurn Test
Fadi Maalouf, PMP
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
RAVI PAL SINGH
 
Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012
Ronald Moore
 
Switch Presentation 2023.pdf
Switch Presentation 2023.pdfSwitch Presentation 2023.pdf
Switch Presentation 2023.pdf
EmilLerner
 
Energy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementEnergy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and management
kiranpatilsjce
 
Wind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxWind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptx
lengoclong8513
 
SunBurn Test Presentation
SunBurn Test PresentationSunBurn Test Presentation
SunBurn Test Presentation
Fadi Maalouf, PMP
 
PwC_Case_Competition_Baker_Hughes_Final_Round
PwC_Case_Competition_Baker_Hughes_Final_RoundPwC_Case_Competition_Baker_Hughes_Final_Round
PwC_Case_Competition_Baker_Hughes_Final_Round
Evan Chen
 

Similar to Session 12 project costing & economics (20)

Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...
 
Presentation aes eletropaulo_3_q12_sem discurso_v2
Presentation aes eletropaulo_3_q12_sem discurso_v2Presentation aes eletropaulo_3_q12_sem discurso_v2
Presentation aes eletropaulo_3_q12_sem discurso_v2
 
TPDDL Excellence Journey
TPDDL Excellence JourneyTPDDL Excellence Journey
TPDDL Excellence Journey
 
Financial Sensitivity in the Wind Industry The Numbers You Really Need to Know
Financial Sensitivity in the Wind Industry The Numbers You Really Need to KnowFinancial Sensitivity in the Wind Industry The Numbers You Really Need to Know
Financial Sensitivity in the Wind Industry The Numbers You Really Need to Know
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
Merc approach paper for determination of soalr tariff 2014
Merc approach paper for determination of soalr tariff 2014Merc approach paper for determination of soalr tariff 2014
Merc approach paper for determination of soalr tariff 2014
 
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
 
Key Steps and Success Factors in EPC Implementation
Key Steps and Success Factors in EPC ImplementationKey Steps and Success Factors in EPC Implementation
Key Steps and Success Factors in EPC Implementation
 
Financial Model Logical Operation Presentation for Captive Power Plant
Financial Model Logical Operation Presentation for Captive Power PlantFinancial Model Logical Operation Presentation for Captive Power Plant
Financial Model Logical Operation Presentation for Captive Power Plant
 
The economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenuesThe economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenues
 
Repowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic ResearchRepowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic Research
 
Value of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed ApproachValue of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed Approach
 
SunBurn Test
SunBurn TestSunBurn Test
SunBurn Test
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
 
Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012
 
Switch Presentation 2023.pdf
Switch Presentation 2023.pdfSwitch Presentation 2023.pdf
Switch Presentation 2023.pdf
 
Energy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementEnergy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and management
 
Wind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxWind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptx
 
SunBurn Test Presentation
SunBurn Test PresentationSunBurn Test Presentation
SunBurn Test Presentation
 
PwC_Case_Competition_Baker_Hughes_Final_Round
PwC_Case_Competition_Baker_Hughes_Final_RoundPwC_Case_Competition_Baker_Hughes_Final_Round
PwC_Case_Competition_Baker_Hughes_Final_Round
 

More from Chirag Jain

Session 15 spvrt project financing
Session 15   spvrt project financingSession 15   spvrt project financing
Session 15 spvrt project financing
Chirag Jain
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
Chirag Jain
 
Session 08 design & safety overview
Session 08   design & safety overviewSession 08   design & safety overview
Session 08 design & safety overview
Chirag Jain
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
Chirag Jain
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system components
Chirag Jain
 
Session 04 solar pv modules
Session 04   solar pv modulesSession 04   solar pv modules
Session 04 solar pv modules
Chirag Jain
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologies
Chirag Jain
 

More from Chirag Jain (7)

Session 15 spvrt project financing
Session 15   spvrt project financingSession 15   spvrt project financing
Session 15 spvrt project financing
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
 
Session 08 design & safety overview
Session 08   design & safety overviewSession 08   design & safety overview
Session 08 design & safety overview
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system components
 
Session 04 solar pv modules
Session 04   solar pv modulesSession 04   solar pv modules
Session 04 solar pv modules
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologies
 

Recently uploaded

Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
Bisnar Chase Personal Injury Attorneys
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
ak6969907
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
Kavitha Krishnan
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 

Session 12 project costing & economics

  • 1. Partnership To Advance Clean Energy-Deployment (PACE-D) Technical Assistance Program Presented by USAID PACE-D TA Program Apr-18 Solar PV Rooftop Training Program For Entrepreneurs Session: Project Costing & Economics
  • 2. Contents Project Variations Project cost components Project Financing and Revenues Tariff Determination by the Regulators Conclusions – Keys make a good business case
  • 3. Project Variations – Investment Models (1/2) Capex Opex (BOO / BOOT) ‘Sale’ of system to customer Sale of energy over lifetime Investment as working capital till commissioning Long term investment till transfer of system or withdrawal of system O&M chargeable basis O&M own costs Warranties of components in customer’s name Warranties in own name No possibility of claiming Accelerated Depreciation Benefit – customer can avail avail it Possible to avail Accelerated Benefit
  • 4. Project Variations – Investment Models (2/2) Gross metering Net metering Capacity limited by investment and available area Capacity limited (additionally) by contract demand and transformer capacity Revenue depends on PPA rate and probably would be constant over a period Revenue is from saved energy and depends on consumer tariff and probably would be increasing continuously Bankability based on utility financial strength Bankability based on own business growth and energy requirement Dependence also on overall state / utility energy requirement in future Dependence on own energy requirement projections and tariff rates in future
  • 5. Project Cost Components Project Cost Components Fixed Component  System equipment capital cost  Site related cost – roof rent / strengthening / new roofing  O&M costs over a period  Fixed charges for project approval / registration / sanction  Utility charges – based on units of electricity – over a period  Debt / loan related upfront charges – processing  Pre-operative costs – interest, marketing costs Variable Component  Structure – Aluminium / GI  Surface – flat / sloping RCC / sloping tinned roof / super structure  Interconnection voltage level – 230V / 415V / 11KV / 33KV  Interconnection point distance from inverter  String inverters / central inverters  Fixed structure / tracking (single axis / double axis)
  • 6. Project Capital Cost (Rs./KWp) Components For about 500 KWp and above For about 100 kWp For about 50 kWp For about 10 kWp For about 1 kWp Solar Modules 24,000 24,000 25,000 26,000 28,000 Module mounting structure 3,000 3,000 4,000 5,000 5,000 Inverters 7,000 8,000 10,000 13,000 18,000 Electrical Balance of system components 6,000 8,000 10,000 12,000 13,000 Civil Structures 3,000 3,000 3,000 4,000 5,000 I&C and Transportation 3,000 3,000 4,000 5,000 5,000 Total 46,000 49,000 56,000 65,000 74,000 Above are tentative cost estimates, of course will change in different scenarios  These are costs. Taxes, profit and other contingencies not considered
  • 7. Basis for Effects on System Capital Costs Sr No Components For about 500 kWp and above For about 100 kWp Share in Cost Share in Cost 1 Solar Modules 24,000 24,000 52% 49% 2 Module mounting 3,000 3,000 7% 6% 3 Inverters 7,000 8,000 15% 16% 4 Electrical Components 6,000 8,000 13% 16% 5 Miscellaneous 3,000 3,000 7% 6% 6 I&C and allied 3,000 3,000 7% 6% Total 46,000 49,000
  • 8. Factors affecting System Capital Costs Deviation Original assumption Change Original cost per kWp New Cost per kWp Percentage Effect on 46,000/- Sloping roof GI structure on flat roof Al structure on sloping roof Rs. 3,000/- Rs. 2,500/- 1.1% reduction Super structure structure Flat RCC roof roof mounted Raised structure of 10’ Rs. 3,000/- Rs. 9,000/- 13% increase Interconnectio n voltage 230 V 1 Phase or 415 415 V 3 Phase 11 / 33 KV 3 Phase Rs. 0/- Rs. 20,000/- Rs. 4,000/- 42% increase 8% increase Inverter type String inverters Central inverter Rs. 7,500/- Rs. 4,500/- 6% reduction
  • 9. Factors affecting System Capital Costs Deviation Original assumption Change Original cost per kWp New Cost per kWp Percentage Effect on 46,000/- Distance between array and inverter Less than 10 M About 50 M Rs. 2,000/- Rs. 6,000/- 8% increase Distance between inverter and interconnection Less than 25 M About 100 M Rs. 1,000/- Rs. 4,000/- 6% increase Net Meter Net meter not included Net included Rs. 0/- Rs. 150/- 0.3% increase increase
  • 10. Project Financing & Revenues Options  Debt : Equity = 70:30 / 75:25 – normal financing norms for banks  Equity – own / own land and private equity / own and community sourcing  Debt – public sector banks / private banks / NBFCs / IREDA / foreign institutional / foreign individual Variables  Tariff and its pattern – constant / increasing  Energy generation  Location  Azimuth – clear or angular (direction of array face)  Shadowing objects  Grid outages / quality of grid  Debt (term loan) interest rate  Repayment period of debt and moratorium  Possibility of availing Accelerated Depreciation benefit
  • 11. TARIFF DETERMINATION BY THE REGULATORS
  • 12. Tariff Determination by the Regulators Tariff Determination Tariff Determination  CERC publishes order for Renewable Energy tariffs and is either adopted by SERCs or some changes are made based state specific conditions  Normally announced for a control period of five years, but may change on annual basis  Based on certain defined assumptions  Tariff designed to provide the investors a market based motivational Return of Investment Observations  Auxiliary consumption is taken as NIL  No de-rating considered in solar modules  Capacity Utilization Factor (CUF) considered on limited experience in India or within a state  Interest rate on loan (debt) considered based on State Bank of India  Charges to utilities not considered
  • 13. Arriving at Levelized Cost of Energy S. No. Assumption Head Sub - Head Sub – Head (2) Assumptions Unit 1 Power Generation Capacity Installed Power generation capacity Auxiliary Consumption CUF Useful Life 1 0.00 19.0 25 MW % % Years 2 Project Cost Capital Cost/ MW Power Plant Cost 530.02 Rs Lacs/MW 3 Financial Assumptions Debt: Equity Tariff Period Debt Equity Total Debt Amount Total Equity Amount 25 70% 30% 371.02 159.01 Years % % Rs Lacs Rs Lacs
  • 14. Arriving at Levelized Cost of Energy S. No Assumption Head Sub - Head Sub – Head (2) Assumptions Unit 4 Financial Assumptions Debt Component Equity Component Fiscal Assumptions Loan Amount Moratorium Period Repayment Period Interest Rate Equity Amount Return on Equity (RoE) for first 10 years RoE after 10th year Weighted average RoE Discount Rate Income Tax MAT for first 10 years 371.02 0 12 12.76 159.01 20 24 22.40 10.64 34.61 21.34 Rs Lacs Years Years % Rs Lacs % p.a. % p.a. % % %
  • 15. Arriving at Levelized Cost of Energy S. No Assumption Head Sub - Head Sub – Head (2) Assumptions Unit 5 Financial Assumptions Depreciation Depreciation for 12 years Depreciation after 13th year 5.83 1.54 % % 6 Working Capital Fixed charges Variable charges O&M charges Maintenance spare Receivables for Debtors Working capital Int. 1 15 2 13.26 Month % Months % 7 Operation & Maintenance O&M expenses (2016-17) O&M expn. escalation O&M expn. (2012-13) 7.00 5.72 11.00 Rs Lacs % Rs Lacs
  • 16. Arriving at Levelized Cost of Energy
  • 17. Arriving at Levelized Cost of Energy – with AD (not the latest Rate – 40%)
  • 18. CREATING BUSINESS CASE FOR A PROJECT
  • 19.  Building blocks of project financials – common for most of the models  Models  On premises Captive  Net metering  Open access – Third party sale  Open access – Captive consumption  Effect of varying parameters Creating Business Case for a Project
  • 20. Please see Excel file for detailed working Creating Business Case for a Project
  • 21. Creating Business Case for a Project Year Basis 1 2 3 Units Generated (in Lakh kWH) 16.00 15.84 15.68 Utility Grid Losses (Wheeling) 0.96 0.95 0.94 Net Units sold 15.04 14.89 14.74 Tariff of sold units (Rs.) with inflation 5% 6.50 6.83 7.17 Revenue from sale of energy 97.76 101.62 105.64 Operational Cost 0.00 10.27 10.78 Operational Charges to Utility 29.96 29.66 29.36 Inverter replacement cost (12th year) 0.00 0.00 0.00 Total expenses 29.96 39.93 40.14 Gross Earnings (510.50) 67.80 61.70 65.49 Repayment of Term Loan 19.40 21.92 24.77 EBIDTA 48.40 39.77 40.72 Cumulative EBIDTA 510.50 48.40 88.17 128.89 Interest on Term Loan 46.46 43.93 41.08 Total expenses and repayments 95.82 105.78 106.00 Open Access Third Party Sale 1MW
  • 22. Creating Business Case for a Project Scenarios Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Tariff of sold energy in the First year 11.00 9.00 11.00 10.00 10.00 8.00 Increment in tariff every year 4% 4% 0% 3% 0% 5% Total Revenue in first year 330.88 270.72 330.88 300.80 300.80 240.64 Total Expenses in first year 59.92 59.92 59.92 59.92 59.92 59.92 Gross in hand in first year 270.96 210.80 270.96 240.88 240.88 180.72 Repayment of Debt in first year 151.76 151.76 151.76 151.76 151.76 151.76 Net in hand in first year before taxes 119.20 59.04 119.20 89.12 89.12 28.96 Equity Payback Estimate Equity Payback (years) 3 5 3 4 5 8 Equity IRR 37% 25% 28% 28% 21% 22% Project Payback Estimate Project Payback (years) 5 8 7 7 10 10 Project IRR 24% 19% 19% 20% 16% 18% Different scenario comparison
  • 23. Keys to a Good Business Case Conclusion  Many DISCOMS and SNAs also have empanelment or registration processes for some components like inverters, meters etc.  Reducing capital cost only one of the factors affecting economics  Energy generation probably most important factor  Quality of components, workmanship and performance over life  Term loan interest rate and period another important factor  Low interest loans or increased self contribution  Focus on tariff in the first year in itself not as important as its pattern over the years
  • 24. Keys to a Good Business Case Conclusion  Solar is long term investment project  Expect continued returns over 25 years, but at lower rates than some other businesses  Modules have output warranty of 25 years but continue to generate electricity even after that  Inverters may require one replacement within 25 years  Other components may not require any replacement within 25 years  Low maintenance requirement; washing of modules is the only regular activity
  • 25. 25 Anurag Mishra Senior Clean Energy Specialist USAID/India Email: amishra@usaid.gov Disclaimer: This training material is made possible by the support of the American People through the United States Agency for International Development (USAID). The contents of this material are the sole responsibility of Nexant, Inc. and do not necessarily reflect the views of USAID or the United States Government. This material was prepared under Contract Number AID-386-C-12-00001.