Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Wind Power Project Appraisal.pptx
1. PROJECT FINANCIAL APPRAISAL
WIND POWER PLANT
Final Assignment
Financial Management - FNCE675
Instructor: Dr. NGUYEN TAN BINH
Students: LE NGOC LONG
HO ANH CUONG
HUYNH HUU QUOC
3. GDP Growth Rate p.a
Generation increase p.a
Vietnam Power Development & Energy Security Strategy
2011 -2030
Toward Competitive Power Generation Market
Priority Wind, Solar, and Bioenergy
7%
14%
Renewable energy contribution in 2020
6.5%
11% Renewable energy contribution in 2030
Source: Revised National Power Development Plan VII (by MoIT-2016)
PROJECT RATIONALE
5. PROJECT INFORMATION
Project name Hoa Thang 1.2
Location Binh Thuan
Num. of turbines 15
Installed Capacity30 MW
Start of Operation 2020
Years in Operation 20 years
Binh Thuan Provincial
WPD Plan until 2020
8. FINANCING
By KfW – German Development Bank
Maturity 12 years
Interest 2%
Grace period 1 year
Redemption Annuity
70%
Total Investment 57.0 Mil. USD
(1.9 Mil. USD/MW)
30%
Equity
16. PROJECT APPRAISAL CRITERIA
TIP EIP
NPV, nominal 951,413 367,772
IRR, nominal 12.4% 24.0%
NPV, real 951,413 367,772
IRR, real 8.3% 20.0%
TIP: Total Investment Point
EIP: Equity Investment Point
18. OBJECTIVES & PROCEDURE
Objectives:
• Increase the probability and impact of positive events
• Decrease the probability and impact of negative events
Procedure:
• Step 1 : Identity the risks
• Step 2 : Sensitivity analysis
• Step 3 : Scenarios analysis
• Step 4 : Monte Carlo Simulation
23. Risk Evaluation Summary
1/ Risk Source Sensitivity
• Capacity factor is the most sensitive variable
2/ Scenario
• Profit on all scenarios
3/ Probability
• 90% profit greater than 447,000 mil VND
• 75% profit greater than 690,850 mil VND
• 50% profit greater than 949,700 mil VND
26. Risks Assesment
NPV > 0
In the worst case of 03 typical risks combination
90% NPV exceed 447,000 (>0)
By simulation with most critical input Capacity factor