This document discusses scope and time management in project management. It defines scope management as the processes of defining and controlling what is included in a project. Time management involves activity definition, sequencing, estimating durations, developing schedules, and schedule control. The key tools discussed are the work breakdown structure (WBS), network diagrams, Gantt charts, and critical path analysis. Scope management aims to control scope creep through verification and change control processes.
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...SlideTeam
Here we present Project Status Presentation One Pager Presentation Report Infographic PPT PDF Document one pager PowerPoint template. This project presentation will aid you in explaining your project related to product launch. Devise a successful plan for product launch to make the product available for purchase. Introduce the new products into the market utilizing this product launch project presentation PowerPoint one pager. Let your workforce know how this product launch helps in maximizing the sales and building the customer base. Give a short description of your product to make your audience familiar with the product you are offering. Motivate your employees, subordinates and the other staff members by showcasing the main objective behind the product launch. This project presentation one pager PowerPoint template gives you enough space to jot down the name of the project manage, champion, the date of the project, along with the project Id. Present the entire plan of project task by writing down name of the tasks that are yet to be accomplished. Throw a light on the companys team member that involved in accomplishing the tasks and prepare a checklist of the tasks to be done. Present the total project marketing budget by incorporating this readily available product launch plan PowerPoint one pager. Grab this Project Status Presentation One Pager Presentation Report Infographic PPT PDF Document one pager template now. https://bit.ly/3hvfMln
Project Status Report With Highlights And Key Takeaways Printable Presentatio...SlideTeam
Here we present Project Status Report With Highlights And Key Takeaways Printable Presentation Report Infographic PPT PDF Document one pager PowerPoint template. For the success of any project, it is important and necessary that it be well directed for which a project plan becomes necessary, a ready format of which is provided by our summary of project status with other key details PowerPoint template. By making use of this project summary PPT one pager slide, members of the team will be better guided with regards to what is expected out of them. Moreover, all the available resources will be better utilized so also decision making will be easy and quick. This readily available project status report covers information pertaining to project name, previous week accomplishments, following week planning, project path, project milestones and issues and risks. One highlight feature associated with this template is that it is fully editable. Grab this Project Status Report With Highlights And Key Takeaways Printable Presentation Report Infographic PPT PDF Document one pager template now. https://bit.ly/3B6Iksz
How the project Charter is the most important document to any Project manager. This presentation will guide you through the necessary sections and items to include in any Project Charter in order to be a powerful "one step / One site" tool for the entire project Team to use as reference to confirm on what project areas to accomplish or operate was agreed upon as a team - so there will not be any confusion or vagueness.
This is PMBOK Guide Monitor and Control Process Group - Part Two. It includes six Knowledge Area - Project Time Management, Project Cost Management, Project Communications Management, Project Procurement Management, Project Stakeholder Management, and Project Risk Management - with six processes - Control Schedule, Control Costs, Control Communications, Control Control Procurements, Control Stakeholder Engagement and Control Risks -.
The slides provides an overview on the planning phase of the project plan development. It also provides an introduction on the contents and forms of a project work plan
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...SlideTeam
Here we present Project Status Presentation One Pager Presentation Report Infographic PPT PDF Document one pager PowerPoint template. This project presentation will aid you in explaining your project related to product launch. Devise a successful plan for product launch to make the product available for purchase. Introduce the new products into the market utilizing this product launch project presentation PowerPoint one pager. Let your workforce know how this product launch helps in maximizing the sales and building the customer base. Give a short description of your product to make your audience familiar with the product you are offering. Motivate your employees, subordinates and the other staff members by showcasing the main objective behind the product launch. This project presentation one pager PowerPoint template gives you enough space to jot down the name of the project manage, champion, the date of the project, along with the project Id. Present the entire plan of project task by writing down name of the tasks that are yet to be accomplished. Throw a light on the companys team member that involved in accomplishing the tasks and prepare a checklist of the tasks to be done. Present the total project marketing budget by incorporating this readily available product launch plan PowerPoint one pager. Grab this Project Status Presentation One Pager Presentation Report Infographic PPT PDF Document one pager template now. https://bit.ly/3hvfMln
Project Status Report With Highlights And Key Takeaways Printable Presentatio...SlideTeam
Here we present Project Status Report With Highlights And Key Takeaways Printable Presentation Report Infographic PPT PDF Document one pager PowerPoint template. For the success of any project, it is important and necessary that it be well directed for which a project plan becomes necessary, a ready format of which is provided by our summary of project status with other key details PowerPoint template. By making use of this project summary PPT one pager slide, members of the team will be better guided with regards to what is expected out of them. Moreover, all the available resources will be better utilized so also decision making will be easy and quick. This readily available project status report covers information pertaining to project name, previous week accomplishments, following week planning, project path, project milestones and issues and risks. One highlight feature associated with this template is that it is fully editable. Grab this Project Status Report With Highlights And Key Takeaways Printable Presentation Report Infographic PPT PDF Document one pager template now. https://bit.ly/3B6Iksz
How the project Charter is the most important document to any Project manager. This presentation will guide you through the necessary sections and items to include in any Project Charter in order to be a powerful "one step / One site" tool for the entire project Team to use as reference to confirm on what project areas to accomplish or operate was agreed upon as a team - so there will not be any confusion or vagueness.
This is PMBOK Guide Monitor and Control Process Group - Part Two. It includes six Knowledge Area - Project Time Management, Project Cost Management, Project Communications Management, Project Procurement Management, Project Stakeholder Management, and Project Risk Management - with six processes - Control Schedule, Control Costs, Control Communications, Control Control Procurements, Control Stakeholder Engagement and Control Risks -.
The slides provides an overview on the planning phase of the project plan development. It also provides an introduction on the contents and forms of a project work plan
Presenting Project Brief PowerPoint Deck designed to deliver an impactful presentation. Project brief is a statement of what is required to define the possible requirements of your project. Our 55 slides presentation deck ensures to give each aspect of project brief that you would like to have it when you are looking to share information with your people. Some of the key aspects are included in this deck to such as project identification, risk identification, roles and responsibilities, project management, task list, timeline, risk assessment, communication plan etc. Every project holds an importance for the business development and requires professional approach when handling. Be it research, development, job assignment or anything. It should be planned in the systematic way. This presentation deck covers all the basics and gives you a layout as what needs to be done first and how you should move forward. From the first step till you deliver the project; all the information is available in this PowerPoint deck. Download it now to deliver your next project brief presentation in the professional way. Our Project Brief PowerPoint Presentation Slides contain the best of bygone eras. They evoke the charm of days gone by.
Impress your clients by clearly defining base elements of the project and other project planning activities by using our kick-off meeting PowerPoint presentation slides. This project management kick-off meeting PowerPoint template consists a total of 28 ready to use slides like meeting agenda, project description, project scope, core team, project management team, responsibility assignment matrix, project management cycle, work breakdown structure, project cost estimate, project communication plan, project management Gantt chart, project tracking plan and many such slides. All the slides in this project kick-off meeting agenda are completely editable and can be adjusted as per individual requirements and needs. Be it the explaining your services to the client or to your internal team, this kick-off management PPT deck can be used for a crisp, short and very to the point explanation. The diagrams and visuals used in this kick-off agenda slideshow are attractive and self-explanatory to place the content in a stylish manner. Elaborate on holistic healing with our Kickoff Meeting PowerPoint Presentation Slides. Give due importance to the human element.
"You can download this product from SlideTeam.net"
SlideTeam introduces Automation Technology Powerpoint Presentation Slides. Gain access to 49 visually-gripping PPT templates by downloading this comprehensive complete deck. Each PowerPoint slide is 100% customizable. Personalize text, colors, font, patterns, background, orientation, and shapes to achieve any imaginable result. Convert the format into PDF, PNG, or JPG as and when necessary. Access this presentation using standard or widescreen resolutions. It is compatible with Google Slides. https://bit.ly/3HO8wvJ
The concepts and processes on how to perform project quality management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan quality management, manage quality, and control quality.
PMBoK 6 - Chapter 9 for Project Resource Management.
This presentation material is presented for CAPM students of Telkom University Bandung, Indonesia on 16 December 2018.
Topic 1: Overview of the Project Management Landscape
Definition of project, project portfolio and program
Classification of projects
Fundamental of project management
- Topic 2: Traditional Project Management (TPM)
What is Traditional Project Management?
Classification of TPM models
Complexity and Uncertainty in the Project Management Landscape
- Topic 3: Agile Project Management
- Topic 4: Extreme Project Management
- Topic 5: Comparison of TPM – Agile – Extreme Project Management
VDA 6.3 Training Material From VDiversify.com | VDA 6.3 Process Audit Trainin...VDiversify
Note: Whoever is using this Training Material on their Website shall Link back to www.vdiversify.com as the Original Author...
VDA 6.3 full form stands for “Verband Der Deutschen Automobilindustrie”.
VDA 6.3 is one of the excellent tools for in-depth manufacturing process audits within the automotive industry which acts as a guideline for performing audits.
The VDA 6.3 is now considered to be one of the most preferred or used manufacturing process audit tool which helps you find all kinds of gaps throughout the organization, especially in manufacturing lines or production areas which helps to close the gaps with proper robust corrective actions.
Presenting Project Brief PowerPoint Deck designed to deliver an impactful presentation. Project brief is a statement of what is required to define the possible requirements of your project. Our 55 slides presentation deck ensures to give each aspect of project brief that you would like to have it when you are looking to share information with your people. Some of the key aspects are included in this deck to such as project identification, risk identification, roles and responsibilities, project management, task list, timeline, risk assessment, communication plan etc. Every project holds an importance for the business development and requires professional approach when handling. Be it research, development, job assignment or anything. It should be planned in the systematic way. This presentation deck covers all the basics and gives you a layout as what needs to be done first and how you should move forward. From the first step till you deliver the project; all the information is available in this PowerPoint deck. Download it now to deliver your next project brief presentation in the professional way. Our Project Brief PowerPoint Presentation Slides contain the best of bygone eras. They evoke the charm of days gone by.
Impress your clients by clearly defining base elements of the project and other project planning activities by using our kick-off meeting PowerPoint presentation slides. This project management kick-off meeting PowerPoint template consists a total of 28 ready to use slides like meeting agenda, project description, project scope, core team, project management team, responsibility assignment matrix, project management cycle, work breakdown structure, project cost estimate, project communication plan, project management Gantt chart, project tracking plan and many such slides. All the slides in this project kick-off meeting agenda are completely editable and can be adjusted as per individual requirements and needs. Be it the explaining your services to the client or to your internal team, this kick-off management PPT deck can be used for a crisp, short and very to the point explanation. The diagrams and visuals used in this kick-off agenda slideshow are attractive and self-explanatory to place the content in a stylish manner. Elaborate on holistic healing with our Kickoff Meeting PowerPoint Presentation Slides. Give due importance to the human element.
"You can download this product from SlideTeam.net"
SlideTeam introduces Automation Technology Powerpoint Presentation Slides. Gain access to 49 visually-gripping PPT templates by downloading this comprehensive complete deck. Each PowerPoint slide is 100% customizable. Personalize text, colors, font, patterns, background, orientation, and shapes to achieve any imaginable result. Convert the format into PDF, PNG, or JPG as and when necessary. Access this presentation using standard or widescreen resolutions. It is compatible with Google Slides. https://bit.ly/3HO8wvJ
The concepts and processes on how to perform project quality management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan quality management, manage quality, and control quality.
PMBoK 6 - Chapter 9 for Project Resource Management.
This presentation material is presented for CAPM students of Telkom University Bandung, Indonesia on 16 December 2018.
Topic 1: Overview of the Project Management Landscape
Definition of project, project portfolio and program
Classification of projects
Fundamental of project management
- Topic 2: Traditional Project Management (TPM)
What is Traditional Project Management?
Classification of TPM models
Complexity and Uncertainty in the Project Management Landscape
- Topic 3: Agile Project Management
- Topic 4: Extreme Project Management
- Topic 5: Comparison of TPM – Agile – Extreme Project Management
VDA 6.3 Training Material From VDiversify.com | VDA 6.3 Process Audit Trainin...VDiversify
Note: Whoever is using this Training Material on their Website shall Link back to www.vdiversify.com as the Original Author...
VDA 6.3 full form stands for “Verband Der Deutschen Automobilindustrie”.
VDA 6.3 is one of the excellent tools for in-depth manufacturing process audits within the automotive industry which acts as a guideline for performing audits.
The VDA 6.3 is now considered to be one of the most preferred or used manufacturing process audit tool which helps you find all kinds of gaps throughout the organization, especially in manufacturing lines or production areas which helps to close the gaps with proper robust corrective actions.
Project Scope Management typically refers to the extensive collection of processes that ensure the exact description and visualization of the ample scope of a project. The strategies of project scope planning and scope management allow the project managers to assign the recommended amount of work needed to complete a project effectively. It is concerned with the determination of what is included in the project and what is altered
BPP Training on Project Management - Day 1Imoh Etuk
This training was about exposing the employees of the Lagos State Public Service to the Contemporary Project Management Practices they can adopt to Enhance Project Delivery in the Pandemic Era for the Lagos State Public Service.
Upon successful completion of the training, participants s were to apply the generally recognized practices of project management acknowledged by the Project Management Institute (PMI) to successfully manage projects by:
• Getting started with project management fundamentals.
• Identifying organizational influences and project life cycle.
• Working with project management processes.
• Initiating a project.
• Planning a project.
• Planning for project time management.
• Planning project budget, quality, and communications.
• Planning for risk, procurements, and stakeholder management.
• Executing a project.
• Managing project work, scope, schedules, and cost.
• Controlling a project.
• Closing a project.
Identifying Requirements, Creating the Work Breakdown structure, Developing the Project Schedule, Developing a Project Cost Estimate, Planning Quality, Organizing the Project Team, Planning for Potential Risks
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
The Indian economy is classified into different sectors to simplify the analysis and understanding of economic activities. For Class 10, it's essential to grasp the sectors of the Indian economy, understand their characteristics, and recognize their importance. This guide will provide detailed notes on the Sectors of the Indian Economy Class 10, using specific long-tail keywords to enhance comprehension.
For more information, visit-www.vavaclasses.com
How to Split Bills in the Odoo 17 POS ModuleCeline George
Bills have a main role in point of sale procedure. It will help to track sales, handling payments and giving receipts to customers. Bill splitting also has an important role in POS. For example, If some friends come together for dinner and if they want to divide the bill then it is possible by POS bill splitting. This slide will show how to split bills in odoo 17 POS.
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
What is the purpose of the Sabbath Law in the Torah. It is interesting to compare how the context of the law shifts from Exodus to Deuteronomy. Who gets to rest, and why?
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
2. SPECIFIC LEARNING OBJECTIVES:
At the end of this module you MUST be able to:
Demonstrate an understanding of the triple constraints of a project.
Conduct project planning base on the project cycle.
Apply the analytical approach in assessing the financial viability of
projects using analytical tools such as net present value and return of
investment.
Plan the scope of a project using project tools like the work breakdown
structure.
Discuss project time management.
Construct network diagrams and apply the PERT technique to estimate
project time-line.
3. Introduction
This module examines two core areas of the project
management functions – scope and time management.
Project Scope Management includes the processes involved in
defining and controlling what is or is not included in a project.
It ensures that all project stakeholders have the same
understanding of what the deliverables are and how and when
they will be delivered.
4. Introduction
Project time management involves the
processes required to ensure timely
completion of a project.
These include activity definition,
activity sequencing, activity duration
estimating, schedule development, and
schedule control.
5. Project planning
Project planning is a dynamic, “cyclical” process that
continues throughout the project life cycle.
Planning must take place to deal with problems,
changes, or risks as they occur in the project.
Planning begins with the identified and agreed to
requirements in mind.
It is critical to the success of the project to
understand your destination when you start.
6. Project planning
You will know where you are going and you will
have developed plans to arrive at the goal and
complete the project successfully.
Project managers must learn how to develop a
project strategy and plan regarding how to
implement that plan. Your organization, team,
and stakeholders depend on it.
7. Project planning
Project planning is a cycle that is repeated on an on-
going basis. For the duration of the project, it is never
a finished process.
Why? Because resources change or move, factors in
the organization may change causing project
objectives to change, unknown risks can occur, or
technology may change, requiring project managers
to continually monitor and manage this process
throughout the life of the project.
9. Project definition
Key inputs to Project Definition:
Clearly defined requirements
Defined mission and objectives of the project
Defined and agreed to the statement of work.
10. Project definition
The statement of work or scope statement must
clearly state the project objectives and should
follow the SMART concept:
Specific
Measurable
Agreed to by the team and stakeholders
Realistic within the specific environment
Time-constrained.
11. Outputs of Project definition
Project charter
Stakeholder identification and assessment
Risk identification, assessment, and response
Quality plan
Communications plan
Work breakdown structure.
13. Scope management
Project scope management can be defined as
“the processes involved in defining and
controlling what is or is not included in a project”.
It entails making sure that all project stakeholders
have the same understanding of what the
deliverables are and how and when they will be
delivered.
14. Scope management
The five key processes involved in scope management include:
Initiation – beginning a project or continuing to the next phase. Usually
involves the creation of a project charter.
Scope planning – involves establishing decision-making criteria (a. How
do we know when we’re done? b. How do we know when we’ve won? c.
Who gets to decide a & b?) Deliverables include scope statement and
scope management plan.
Scope definition – creating a work breakdown structure (WBS) – to break
major deliverables down into smaller, more manageable components).
Scope verification – formal acceptance of scope definition by key
stakeholders.
Scope change control – controlling ‘scope creep’.
15. Project selection
Projects should support the strategic direction
of the organization and be managed to ensure
tangible benefits to the organization.
The organization’s strategic plan should guide
the project selection process.
16. Project selection : The analytical approach
There are a number of rational analytical models that can be used in
project selection.
1. Need, funding and will (NFW) model
Do people agree that the project needs to be done?
Is the organization prepared to allocate sufficient
funds for the project?
Is there a strong will to make the project succeed
(especially CEO and senior management support)?
17. Project selection : The analytical approach
2.Categorization approach
Problems, opportunities, and directives (POD)
Windows of opportunity – categorization based
on estimated project time or completion dates
Overall priority – high, medium, or low?
18. Project selection : The analytical approach
3.Financial models
Net Present Value (NPV)
Return on Investment (ROI)
Payback Period
Internal Rate of Return (IRR)
Weighted scoring model
19. Project charters
The key document that often defines project initiation is
the project charter.
A project charter is a document that formally recognizes
the existence of a project and provides direction on the
project’s objectives and management. Once the project
charter is signed by the project sponsor, it provides
authorization for the project manager to start planning.
The charter is often used to let key members of the
organization know about the existence of the project,
and to authorize its implementation.
Key project stakeholders should sign the charter.
20. Project charters
At a minimum a project charter should contain:
Title and date of authorization
Name of project manager and contact info
Statement of project Scope
Summary of approach:
roles and responsibilities matrix
a sign-off page for key stakeholders.
21. Project charters
Sample Project Charter Table of Contents
1. Project Name
2. Project Objectives
3. Project Purpose
4. Scope (In and Out of Scope)
5. Key Deliverables
6. High-Level Schedule (Plan)
7. Key Stakeholders (internal and
external)
8. Cross Organization Team
Members
9. Risk Management
10.Links to Other Projects
11.Constraints and Assumptions
12.Completion Criteria
13.Approval.
22. Scope planning
Scope planning involves developing documents to
clarify project scope and the basis for project
decisions including criteria for phase sign-off.
(How do we know when we’re done?) The key output
is a scope statement.
The scope statement, or statement of work, is the key
document used to enunciate and confirm the scope
of the project.
23. Scope planning
It should include the following:
Project justification (What is the business need? Why are we doing
this project?)
Project products (Key products and services – e.g., minimum
hardware and software requirements)
Summary of project deliverables
Scope management plan (cost, time and quality measures of
success and clearly articulates both what the project will deliver and
what it will not deliver) Sometimes called a Statement of Work
Scope definition – The Work Breakdown Structure.
24. Scope definition
The next step in scope management is scope definition – or
breaking the work down into manageable pieces.
Good scope definition:
Helps improve the accuracy of time, cost and resource
estimates
Defines a baseline for performance measurement and project
control
Assists in communicating work responsibilities.
25. The Work Breakdown Structure (WBS)
A work breakdown structure (WBS) is defined as: “a
deliverables oriented depiction of the work involved
in a project that defines the total scope of the
project”.
In simple terms, it’s a detailed listing of what is
required to deliver the product/service of the project.
It is the “heart” or foundation of project management
that provides the basis for planning and
development for the project.
26. WBS Rules
1. Begin with the scope statement
2. Task descriptions developed using a verb and a noun
3. Develop WBS to the lowest level of control required to
effectively manage a project (Work Package – guideline 80
hours of effort)
4. Each work package is developed to accomplish a discrete and
separate element of work
5. Allow assignment to a single organizational unit for exclusive
responsibility
27. WBS Rules
6. Organize the WBS by Task:
phase
activity
task
step.
OR
7. Organize the WBS by Deliverables:
hardware
software
network.
29. Work breakdown structures can be presented in many ways. A common form
and the one used in project management software, such as MS Project, is a
tabular form like this:
30. Scope Management
Scope Creep. This is a phenomenon that often occurs in
projects as a result of the best of intentions. It is the tendency
for project scope to get larger and larger.
Two methods of controlling scope creep are scope verification
and scope change control.
Scope verification involves documenting the project’s
processes and products and getting the key stakeholders to
sign off on them. In a project, this is usually accomplished
through what is known as a Business Requirements Document
and a Technical Specifications Document.
31. Scope Management
Scope Change Control usually entails a formalized process for
changing project scope wherein the implications in terms of
time and cost are clearly stated. Again, key stakeholders are
required to sign-off on accepted changes to the scope of the
project. The best preventative measure for project scope
change is doing a thorough job of requirements and
specifications in the first place.
32. Project time management
Overall, schedule issues are one of the primary
sources of conflict over the life of a project. Scope
and cost can be estimated and debated. The
schedule, once set, tends to be the least flexible and
the most easily measured and evaluated of the three
project constraints.
Definition: Project Time Management involves the
processes required to ensure timely completion of a
project.
33. Project time management
These include:
Activity definition – identifying the activity or task that must be performed
to produce the project deliverables (A task is an element of work that has
an expected duration, cost, and resource requirements.)
Activity sequencing – identifying and documenting the relationships
between project activities (particularly the order of execution).
Activity duration estimating – approximating the amount of time or
number of work periods needed to complete each activity or task.
Schedule development – analyzing activity sequences, duration estimates,
and resource requirements to create a workable schedule.
Schedule control – controlling and managing changes to the project
schedule.
34. Project time management
Activity definition usually entails developing a more detailed work breakdown
structure. The project team should review this revised WBS before moving to
the next step – activity sequencing. Part of activity definition includes
documenting detailed product descriptions, assumptions, and constraints.
Activity sequencing looks at dependencies and relationships – does one activity
need to precede another or can they be done in parallel? Three main types of
dependencies:
Mandatory – ‘hard logic’ – one task cannot start until a previous task is
complete (e.g., can’t test until you build)
Discretionary – ‘soft logic’ – defined by the project team (e.g., no detailed
design until the analysis is signed off)
External – dependent on non-project activity (e.g., software install project
can’t start until the hardware is delivered).
35. Schedule development tools
The key project management tools used to
develop accurate and effective schedules
include:
Network Diagrams,
Gantt charts, and
Critical Path analysis.
36. Network diagrams
A project network diagram is a schematic
display of the logical relationships among
project activities or the sequencing of
project activities.
It is the preferred technique for showing
activity sequencing.
38. Network diagrams
In the above network diagram, the letters represent activities
or tasks. The arrows show the sequencing, and the values
associated with the letters (e.g. D=3) represent the units of
time (days, weeks, etc.) associated with that task or activity.
The example diagram uses the Activity on Arrow (AOA) or
Arrow Diagramming Method (ADM), in which activities are
represented by arrows and are connected at points called
nodes to illustrate activity sequencing. The total estimated
duration of this sample project is the sum of all the numbers
associated with arrows - or 25 days.
39. Activity duration estimating
Duration = actual amount of time worked on an activity plus
elapsed time.
(This may need to take into consideration people working
only half time, waiting for some critical resource, or preceding
activity).
Best estimates will likely come from the people who have to
do the work, although there will be a tendency to pad their
time estimates as a risk mitigation strategy.
40. A Network Diagram that illustrates the Precedence
Diagramming Method (PDM)
41. Gantt charts
A Gantt chart is a standard format for displaying
project schedule information by listing project
activities and their corresponding start and finish
dates in calendar format.
Gantt charts were developed by Henry Gantt
during World War I for scheduling work in
factories.
Today they are usually produced by project
management software.
43. Gantt charts
A tracking Gantt chart is a variation of a Gantt chart that
compares planned and actual project schedule information
(also called total float).
The planned dates are called baseline dates.
A white diamond on a tracking Gantt indicates a slipped
milestone – or a milestone activity that was completed later
than originally planned.
Gantt charts are easy to create and provide a standard format
for displaying planned and actual activities. However, they do
not show relationships and dependencies between tasks as
well as network diagrams or PERT charts do.
44. Critical path analysis
Critical path analysis or the Critical Path Method (CPM) is a
project network analysis technique used to predict total project
duration. Within any project, there will be some tasks, which
have some slack or float time associated with them. That is, if
they don’t get done exactly on schedule, they won’t impact
other activities or the overall completion date.
However, there are some activities, if not completed on time will
impact the timing of other activities and can throw the whole
project off schedule. Thus the critical path for a project is those
series of activities that together determine the earliest time by
which the project can be completed.
45. Critical path analysis
Important definitions:
Free slack – the amount of time an activity can be delayed
without delaying the early start of any immediately following
activity
Early start (ES) – the earliest possible time an activity can start
Total slack– the amount of time an activity can be delayed
from its early start without delaying the planned project
completion date
Forward pass – determine the early start and early finish dates
for each activity
46. Critical path analysis
Important definitions:
Early finish (EF) – the earliest possible time an activity can
finish = early start + duration
Backward pass – determines late start and late finish dates for
each activity
Late start (LS) – latest possible time an activity can start
without delaying the project completion date
Late finish (LF) – latest possible date an activity can be
completed without delaying the overall project completion
date.
47. Techniques for shortening a project schedule
Crashing is a technique for making cost and schedule trade-
offs to obtain the greatest amount of schedule compression
for the least incremental cost. This involves adding more
resources to a critical path item. The trade-off is a shortened
project duration for higher overall project costs.
Fast tracking calls for performing activities in parallel that you
would normally do sequentially or in slightly overlapping time
frames (e.g., starting to program or code before all of the
analysis is complete). The trade-off is shortening the project
duration at the risk of having to do work over and resulting in
a longer overall duration.
48. PERT – Programe evaluation and review
technique
PERT – a network analysis technique used to estimate project
duration when there is a high degree of uncertainty about the
individual duration estimates.
PERT uses probabilistic time estimates – estimates of activity
duration using optimistic, most likely, and pessimistic
estimates of activity duration. Thus PERT attempts to address
the risk associated with duration estimates.
49. PERT – Programe evaluation and review
technique
The basic PERT formula is as follows:
PERT weighted average
= optimistic time + (4X most likely time) + pessimistic
time