ERP
© 2008 by SAP AG. All rights reserved.2
What are Enterprise Resource Planning (ERP) Systems?
Incredibly large, extensive software packages used to manage a
firm’s business processes.
Standard software packages that must be configured to meet the
needs of a company
Database programs with the following functions:
Input
Storage/Retrieval
Manipulation
Output
28,610+ Tables in SAP
ERP
© 2008 by SAP AG. All rights reserved.3
Who are the big ERP vendors?
SAP, the German juggernaut
Systeme,Anwendungen, Produkte in der Datenverarbeitung, or
Systems,Analysis and Products in Data Processing.
Don’t be a sap!
Oracle/PeopleSoft/J. D. Edwards (J.D. Orisoft)
Microsoft Great Plains, aimed at smaller companies
SAP Business One is competing product
SAP R/3 Enterprise
© 2008 by SAP AG. All rights reserved.4
FI
Financial
Accounting
CO
Controlling
Workflow
PP
Prod.
Planning
SD
Sales &
Distrib.
MM
Materials
Mgmt.
QM
Quality
Mgmt.
PM
Plant
Maint.
HR
Human
Resources
AM
Asset
Mgmt.
PS
Project
System
SAP R/3 Enterprise
© 2008 by SAP AG. All rights reserved.5
Oracle
DB2
MSSQL
SAP can use a
number of
database programs
to actually store
the data.
FI
Financial
Accounting
CO
Controlling
Workflow
PP
Prod.
Planning
SD
Sales &
Distrib.
MM
Materials
Mgmt.
QM
Quality
Mgmt.
PM
Plant
Maint.
HR
Human
Resources
AM
Asset
Mgmt.
PS
Project
System
FI
Financial
Accounting
CO
Controlling
Workflow
PP
Prod.
Planning
SD
Sales &
Distrib.
MM
Materials
Mgmt.
QM
Quality
Mgmt.
PM
Plant
Maint.
HR
Human
Resources
AM
Asset
Mgmt.
PS
Project
System
Configuration
© 2008 by SAP AG. All rights reserved.6
Configuration is the process of making standard software
fit your business. SAP, as an example, has:
Over 8000 configuration decisions
Data structuring
Sales divisions, distribution channels
Rewriting Code (Modifications)
Not recommended because of compatibility problems when updated
versions of the software are installed.
Customization
Writing code at SAP-specified user exits
Third-party software solutions
A typical manufacturing company
© 2008 by SAP AG. All rights reserved.7
Manufacturing
Process
Inputs Outputs
FI
CO
Material
Master
Vendor
Master
Pricing
Cust.
Master
Pricing
Basic
Data
Calendars
Currencies
© 2008 by SAP AG. All rights reserved.8
USER PCs
USER PCs
Application
Server
Application
Server
Application
Server
Application
Server
Database
Server
Three-tier Client/Server Architecture
© 2008 by SAP AG. All rights reserved.9
User PCs
Database and
Application
Server
Two-tier Client/Server Architecture
(configuration typical for training)
© 2008 by SAP AG. All rights reserved.10
Database and
Application
Server
Nothing is saved on your PC. Only things saved on our
server in Missouri are saved, and they are saved for good.
SAP vs MS Office
© 2008 by SAP AG. All rights reserved.11
 In Window Applications, you save often
so you don’t lose everything when you
get the Blue Screen of Death:
Saving in Windows vs SAP
© 2008 by SAP AG. All rights reserved.12
 In SAP, there are very few delete
options:
 Don’t save if things don’t look 100%
correct! Exit the transaction and start
over
Saving in Windows vs SAP ...2
Clients in SAP R/3
© 2008 by SAP AG. All rights reserved.13
What is a client?
A way to separate data in the system
In some ways, a separate database
Also, a table entry
Field
Mandt
201
201
201
202
202
Column (attribute)
Row
(Record)
Client
© 2008 by SAP AG. All rights reserved.14
SAP 5 Server
Client 501
01 Fitter Snacker
02 Fitter Snacker
03 Fitter Snacker
99 Fitter Snacker
Client 502
01 Fitter Snacker
02 Fitter Snacker
03 Fitter Snacker
99 Fitter Snacker
Client 503
01 Fitter Snacker
02 Fitter Snacker
03 Fitter Snacker
99 Fitter Snacker
Client setup for a hypothetical company
© 2008 by SAP AG. All rights reserved.15
 I am data set number 00, not you!
Enter Cred. Contr. area ##CR
and Currency USD
Data Set Number (##)
© 2008 by SAP AG. All rights reserved.16
201
Config.
202
CATT Test
203
FS Master
501
FS Student
502
FS Student
503
FS Student
System landscape for student use
© 2008 by SAP AG. All rights reserved.17
 To log on to an R/3 system with the SAP Gui, you
need the proprietary SAP Gui (Graphical User
Interface) software loaded on your system and an
internet connection
Account on
SAP R/3 System
at hosting site
Internet Connection
PC with SAP Gui
Logging On – SAP GUI
© 2008 by SAP AG. All rights reserved.18
 First, you need to tell the SAP Gui which system you
want to log into:
If you don’t have
any systems defined,
click on New Item
SAP GUI Configuration
© 2008 by SAP AG. All rights reserved.19
Text description (free)
Address of system (e.g.
sapd.umsystem.edu)
SAP Router usually
not required
R/3 System Selected
System Number
Frequently 00, but not always
System ID
Logical name of system
System Definition (provided by UCC)
Configured SAP Gui
© 2008 by SAP AG. All rights reserved.20
Select System:
double-click or
Logon button
© 2008 by SAP AG. All rights reserved.21
Enter Client
Enter User (R/3 Account)
Enter Password (R/3 Account)
Don’t worry about language—
English will default in
Logging On
SAPGUI - System ID IS4
SAPGUI - Description IS4 -SAP ERP 2005 (6.0)
SAPGUI - Application Server sbasap72.sba.uwm.edu
SAPGUI - System Number 00
Client Number 225
Student Userids ... Will be advised
Student Passwords
(case sensitive)
... Will be advised
SAP User-IDs and Passwords
© 2008 by SAP AG. All rights reserved.23
On the first time logging in to
a new account, you will have
to change the password—try
To remember your new
Password WITHOUT WRITING
IT DOWN!
Then a message or two
Then . . . .
Logging On ...2
© 2008 by SAP AG. All rights reserved.24
SAP Easy Access
•Master Data Entry
•Transaction Data Entry
Success !!
Implementation Guide (IMG)
© 2008 by SAP AG. All rights reserved.25
Where Configuration
Takes Place
Data Types
© 2008 by SAP AG. All rights reserved.26
Master Data
Data that is relatively stable
Materials, Customers,Vendors
Transaction Data
Data that is relatively temporary
Stored at various stages of a business process
Customer orders, purchase orders, production orders, customer payments
Transaction Data
© 2008 by SAP AG. All rights reserved.27
Transactions flow down
the river of time
contact@saptrainingsonline.com
Skpe: saptrainingsonline
India: +91 9052775398
USA +13152825809

Sap introduction

  • 1.
    Call UsToday! India +919052775398 USA +13152825809|| contact@saptrainingsonline.com Introduction to SAP ERP
  • 2.
    ERP © 2008 bySAP AG. All rights reserved.2 What are Enterprise Resource Planning (ERP) Systems? Incredibly large, extensive software packages used to manage a firm’s business processes. Standard software packages that must be configured to meet the needs of a company Database programs with the following functions: Input Storage/Retrieval Manipulation Output 28,610+ Tables in SAP
  • 3.
    ERP © 2008 bySAP AG. All rights reserved.3 Who are the big ERP vendors? SAP, the German juggernaut Systeme,Anwendungen, Produkte in der Datenverarbeitung, or Systems,Analysis and Products in Data Processing. Don’t be a sap! Oracle/PeopleSoft/J. D. Edwards (J.D. Orisoft) Microsoft Great Plains, aimed at smaller companies SAP Business One is competing product
  • 4.
    SAP R/3 Enterprise ©2008 by SAP AG. All rights reserved.4 FI Financial Accounting CO Controlling Workflow PP Prod. Planning SD Sales & Distrib. MM Materials Mgmt. QM Quality Mgmt. PM Plant Maint. HR Human Resources AM Asset Mgmt. PS Project System
  • 5.
    SAP R/3 Enterprise ©2008 by SAP AG. All rights reserved.5 Oracle DB2 MSSQL SAP can use a number of database programs to actually store the data. FI Financial Accounting CO Controlling Workflow PP Prod. Planning SD Sales & Distrib. MM Materials Mgmt. QM Quality Mgmt. PM Plant Maint. HR Human Resources AM Asset Mgmt. PS Project System FI Financial Accounting CO Controlling Workflow PP Prod. Planning SD Sales & Distrib. MM Materials Mgmt. QM Quality Mgmt. PM Plant Maint. HR Human Resources AM Asset Mgmt. PS Project System
  • 6.
    Configuration © 2008 bySAP AG. All rights reserved.6 Configuration is the process of making standard software fit your business. SAP, as an example, has: Over 8000 configuration decisions Data structuring Sales divisions, distribution channels Rewriting Code (Modifications) Not recommended because of compatibility problems when updated versions of the software are installed. Customization Writing code at SAP-specified user exits Third-party software solutions
  • 7.
    A typical manufacturingcompany © 2008 by SAP AG. All rights reserved.7 Manufacturing Process Inputs Outputs FI CO Material Master Vendor Master Pricing Cust. Master Pricing Basic Data Calendars Currencies
  • 8.
    © 2008 bySAP AG. All rights reserved.8 USER PCs USER PCs Application Server Application Server Application Server Application Server Database Server Three-tier Client/Server Architecture
  • 9.
    © 2008 bySAP AG. All rights reserved.9 User PCs Database and Application Server Two-tier Client/Server Architecture (configuration typical for training)
  • 10.
    © 2008 bySAP AG. All rights reserved.10 Database and Application Server Nothing is saved on your PC. Only things saved on our server in Missouri are saved, and they are saved for good. SAP vs MS Office
  • 11.
    © 2008 bySAP AG. All rights reserved.11  In Window Applications, you save often so you don’t lose everything when you get the Blue Screen of Death: Saving in Windows vs SAP
  • 12.
    © 2008 bySAP AG. All rights reserved.12  In SAP, there are very few delete options:  Don’t save if things don’t look 100% correct! Exit the transaction and start over Saving in Windows vs SAP ...2
  • 13.
    Clients in SAPR/3 © 2008 by SAP AG. All rights reserved.13 What is a client? A way to separate data in the system In some ways, a separate database Also, a table entry Field Mandt 201 201 201 202 202 Column (attribute) Row (Record) Client
  • 14.
    © 2008 bySAP AG. All rights reserved.14 SAP 5 Server Client 501 01 Fitter Snacker 02 Fitter Snacker 03 Fitter Snacker 99 Fitter Snacker Client 502 01 Fitter Snacker 02 Fitter Snacker 03 Fitter Snacker 99 Fitter Snacker Client 503 01 Fitter Snacker 02 Fitter Snacker 03 Fitter Snacker 99 Fitter Snacker Client setup for a hypothetical company
  • 15.
    © 2008 bySAP AG. All rights reserved.15  I am data set number 00, not you! Enter Cred. Contr. area ##CR and Currency USD Data Set Number (##)
  • 16.
    © 2008 bySAP AG. All rights reserved.16 201 Config. 202 CATT Test 203 FS Master 501 FS Student 502 FS Student 503 FS Student System landscape for student use
  • 17.
    © 2008 bySAP AG. All rights reserved.17  To log on to an R/3 system with the SAP Gui, you need the proprietary SAP Gui (Graphical User Interface) software loaded on your system and an internet connection Account on SAP R/3 System at hosting site Internet Connection PC with SAP Gui Logging On – SAP GUI
  • 18.
    © 2008 bySAP AG. All rights reserved.18  First, you need to tell the SAP Gui which system you want to log into: If you don’t have any systems defined, click on New Item SAP GUI Configuration
  • 19.
    © 2008 bySAP AG. All rights reserved.19 Text description (free) Address of system (e.g. sapd.umsystem.edu) SAP Router usually not required R/3 System Selected System Number Frequently 00, but not always System ID Logical name of system System Definition (provided by UCC)
  • 20.
    Configured SAP Gui ©2008 by SAP AG. All rights reserved.20 Select System: double-click or Logon button
  • 21.
    © 2008 bySAP AG. All rights reserved.21 Enter Client Enter User (R/3 Account) Enter Password (R/3 Account) Don’t worry about language— English will default in Logging On
  • 22.
    SAPGUI - SystemID IS4 SAPGUI - Description IS4 -SAP ERP 2005 (6.0) SAPGUI - Application Server sbasap72.sba.uwm.edu SAPGUI - System Number 00 Client Number 225 Student Userids ... Will be advised Student Passwords (case sensitive) ... Will be advised SAP User-IDs and Passwords
  • 23.
    © 2008 bySAP AG. All rights reserved.23 On the first time logging in to a new account, you will have to change the password—try To remember your new Password WITHOUT WRITING IT DOWN! Then a message or two Then . . . . Logging On ...2
  • 24.
    © 2008 bySAP AG. All rights reserved.24 SAP Easy Access •Master Data Entry •Transaction Data Entry Success !!
  • 25.
    Implementation Guide (IMG) ©2008 by SAP AG. All rights reserved.25 Where Configuration Takes Place
  • 26.
    Data Types © 2008by SAP AG. All rights reserved.26 Master Data Data that is relatively stable Materials, Customers,Vendors Transaction Data Data that is relatively temporary Stored at various stages of a business process Customer orders, purchase orders, production orders, customer payments
  • 27.
    Transaction Data © 2008by SAP AG. All rights reserved.27 Transactions flow down the river of time
  • 28.