The document provides information about an open house for the Eglinton Crosstown LRT project, including details on safety procedures, construction of underground stations using cut-and-cover methods, expected impacts such as road and sidewalk closures during utility relocation and shoring work, and renderings of the planned Eglinton station design and integration with the existing TTC subway line. Temporary bus stop relocations and routing changes are also outlined to accommodate construction stages over the next 4 years.
9. Safety First – Our #1 Priority
• Always have a site specific safety plan and site specific emergency plan.
• Ensure pre-work hazard assessments are complete and understood.
• Ensure job hazards analyses are complete and understood.
• Do everything possible to protect themselves, co-workers, and members of the
public.
• Stop work if the safety of themselves, co-workers and members of the public
cannot be assured.
• Identify and report unsafe behaviour and coach each other to make
improvements.
• Be prepared and equipped to work safely.
We train and direct staff to:
10. Construction of the
Eglinton Crosstown LRT Line
Background
• In September 2008, Metrolinx
launched a regional transportation
plan – a 25-year, $50 billion plan -- to
coordinate and integrate transportation
and transit in the Greater Toronto Area
• In 2010, City of Toronto approved the
project to build the Eglinton Crosstown
from Weston Road in the west to
Kennedy Station in the east.
• Following a competitive process,
Crosslinx Transit Solutions (CTS) was
awarded a contract in July 2015 to
design, build, finance, and maintain
the Eglinton Crosstown Light Rail
Transit (LRT).
Benefits of P3s:
• The Crosstown is being delivered using a public
private partnership model called Alternative
Financing and Procurement (AFP).
• It was procured as one design-build-finance-
maintain project to minimize integration risk –
historically, a factor for project cost overruns
under traditional models.
• Under the AFP model, CTS assumes most
project risks, including:
design, project management and sub-
contractor coordination
increases in construction material prices
and labour costs
schedule and project completion delays
maintenance and lifecycle replacement of
materials within the stations and stops,
rails, control systems, and vehicles
12. What are we building – a new modern LRT
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• A 19-kilometre route separated from regular traffic
• Communications system
• Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station
14. Design Approach: Design from City to Object
14
S i m p l i c i t y
I conog ra phy
Transparency
Ur b a n i t y
Simplicity and elegance of the design solution at all scales,
from the city to the object;
Iconography of the architectural elements to create a unique
and highly recognizable signature on Eglinton Avenue, from
the slanted portal celebrating kinetic movement, to the
profiled wing delineating shelters and waiting areas;
Transparency of the entrances and through the station to magnify
the presence of natural light, to enact as a way-finding strategy
and to uplift the passenger’s experience;
Urbanity of the signature layers from landscape to architecture,
to underline the genius loci and contextualize the stations and
stops within the civic scale of the avenue.
16. 16
Clarity and Simplicity of Architectural
Expression
Street Level – Contextual
and Inviting
An International Signature
for Toronto
Entrance – Bright & Secure
Concourse – Simple &
Pristine
Concourse – Transparent &
Open
Platform – Spacious &
Animated
17. Crosstown Design Approach
Features
• About half of the 19 km line is
tunneled
• Stations and stops are about 0.6 km
apart
• Features will include:
• time arrival information
• safe access for people walking and
biking to the station
• clear route maps, seating, bike
parking
• Available parking at the start and
end of the LRT line.
Design Approach
Comply with nine design principles developed
by City of Toronto and Metrolinx.
• Provide a legacy for generations to come.
• Have natural lighting during the day and well-lit
entrances at night.
• Have safe, clean, intuitive wayfinding at
all the stations and stops.
• Put passengers first.
• Provide visible entrances, bicycle facilities and
sustainable practices to ensure all stations
comply with Toronto Green Standard Tier.
• Landscaped entrances, including planters with
trees and ornamental grasses.
• Public plazas and retail components at some
stations.
• Clean and minimalist space at platform level.
• Accessible to passengers with disabilities, strollers, and
bicycles.
20. • Eglinton, Cedarvale and
Kennedy are
interchange stations.
• Interchange stations will
allow transit riders to
connect to the TTC
subway.
• Interchange stations,
which will be built with
the ‘Cut and Cover’
method.
Interchange Stations
Subway Station Longitudinal Section
Eglinton
21. How We’re Building: Eglinton Station
The Cut and Cover Method
Eglinton
• Twelve underground stations, including interchange
stations will use a cut and cover method to support
excavation.
• To install support of excavation, a crew will:
– remove the street pavement on one side of Eglinton
Avenue
(about 260m x 10m – roughly the size of two hockey rinks)
– dig a shallow pit
– install steel piles, braces and tie-backs around the sides of
the pit
– backfill and cover the pit with a wooden deck on the
roadway to allow traffic to travel across it
• After that, the crew moves to the other half of the
street to do the same.
• Once the shoring is installed, the crew may work
under the roadway safely, excavating to a depth of
at least 20m for the site of the station box.
22. Construction Overview
Distinct phases of construction:
• Preparatory works
• Utility relocations
• Handover of tunnel sections
• Support of excavation
• Excavation for underground stations
• Underground construction of the stations
• Track work and systems installation
• Traction power system
• Signalling system
• Testing and commissioning
• Road and area restoration
23. Preparing for Stations Construction
Since fall 2015, CTS has been preparing the line for underground stations
and stops construction.
Preparatory activities:
• Survey and monitor properties for noise and vibrations
• Assess soil condition and measure water levels along the corridor
• Locate and mark underground utilities
• Clearing/grubbing and removing shrubs/trees in the path of the Crosstown
• Demolish buildings and other infrastructure (i.e. bridge)
• Remove and store street furniture
(i.e. benches, bus shelters, planters, garbage bins)
24. • Utilities relocation and installing support of
excavation is the first step in
constructing an underground station.
• Work is permitted between the hours of
7:00 AM and 11:00 PM, seven (7) days a
week.
• The contractor may not always work during
the permitted hours, but may do so at its
discretion.
• Occasional overnight work may be required.
Metrolinx and Crosslinx Transit Solutions
will notify the public in advance and monitor
activities throughout.
What to Expect in 2016
Start of Stations Construction
25. Eglinton Station Concept
Plan View
Main
Entrance
Salvation Army
Building
Redevelopment &
LRT Emergency Exit
Connection via
TTC Entrance
Connection via
TTC Entrances
34. Eglinton Station 2016 Look Ahead
Geotechnical
Testing
Bus Depot
Demolition
Salvation Army
Community
Church
Demolition
Utilities
Relocations
Support of
Excavation
Traffic & Transit
Management Plan
Early Works
- Survey
- Monitoring
Instruments
Pedestrian
Tunnels
Today
35. Eglinton Station Construction Staging
Long-Term Construction Staging
• As early as Spring 2016, construction zones will be instated along Eglinton Ave. and Yonge
St. at various stages of demolition, utilities relocation, and support of excavation (shoring).
• Lane closures on Yonge St. and Eglinton Ave., and pedestrian tunnel closures will be required
to carry out the work.
• Due to the scope and scale of the project, there will be long term rerouting of transit for
approximately four (4) years. This includes six (6) bus stop relocations, and the re-routing of
some bus routes.
Project Stage(s) Construction Activity / Closure
Approximate Total
Duration (Months)
Starting Date
0 Early Utilities Relocation and Demolition 3-4 As early as Spring 2016
1 to 11 Shoring (Piling), Shallow Excavation, and
Deep Excavation (Main Station Box & North
TVS Shaft)
42 As early as Fall 2016
12 and up Decking Removal & Roadway
Reconstruction
8 As early as March 2020
Project duration North, East, West, and South Pedestrian
Tunnel Closures
48 As early as June 2016
36. Eglinton Station Construction Impacts
Long-Term Pedestrian Tunnel Closures
• North and East pedestrian tunnels are proposed to be closed as early as Spring
2016.
• West and South pedestrian tunnels are proposed to be closed as early as Fall 2016
and 2018, respectively.
37. Eglinton Station Construction Staging
Long-Term Proposed Bus Re-routing
• In some of the
construction stages, TTC
buses will no longer be
able to turn from
westbound Eglinton Ave.
to southbound Yonge St.
• Proposed detours for
Eglinton Ave. East Routes
(westbound only) #51, 56,
100, 103 (*under review by
TTC)
Figure 1 –Proposed Detours for Eglinton Ave East Routes (WB Only) #51, 56, 100, 103
38. Eglinton Station Construction Staging
Long-Term Proposed Bus Stop Relocations
Temporary stop
east of Dunfield
Ave.
#34, #51, #54, #100
Combined with
existing stop
#5, #32, #332
Temporary stop
east of Dunfield
Ave.
#34, #54, #56, #100
Temporary stop at
Roehampton Ave.
#97, #320
Temporary stop
to south
#320
Temporary stop at
Roehampton Ave.
#97, #320
39. Eglinton Station Construction Impacts
Upcoming Works – Utilities
All Utilities Phases
• As early as July 2016, work will start on relocating water mains, storm sewers and sanitary sewers.
• There are four (4) phases of Utilities Relocation, each lasting approximately one (1) month.
• Construction zones will be instated along Eglinton Ave. and Yonge St. at various phases of utilities
relocation. Lane closures on Yonge St. and Eglinton Ave. will be required to carry out the work.
• At least one (1) lane in each direction east-west along Eglinton Ave. and north-south along Yonge St.
will be maintained.
• All turns at the Yonge-Eglinton intersection will be restricted, except for some right turns at various
phases.
• Access to Holly St. from Eglinton Ave. will be closed.
• Please note: all upcoming works are subject to all necessary permits and approvals.
40. Eglinton Station Construction Impacts
Upcoming Works – Utilities
Phase 1
• Construction zones will be
instated on Yonge St. north
of Eglinton Ave. and Eglinton
Ave. east of Cowbell Ln.
• Crosswalk closure on the
north side of Yonge-Eglinton
intersection.
• All turns at the Yonge-
Eglinton intersection will be
restricted, except for right
turns from northbound Yonge
St. onto Eglinton Ave. and
westbound Eglinton Ave.
onto Yonge St.
• Manhole work to take place
on Roehampton Ave. and
Redpath Ave.
41. Eglinton Station Construction Impacts
Upcoming Works – Utilities
Phase 1A
• Construction zones will be
instated on Yonge St.
north of Eglinton Ave. and
on Eglinton Ave. east of
Yonge St.
• Crosswalk closure on the
north side of Yonge-
Eglinton intersection.
• All turns at the Yonge-
Eglinton intersection will
be restricted, except for
right turns from
northbound Yonge St. onto
Eglinton Ave.
42. Eglinton Station Construction Impacts
Upcoming Works – Utilities
Phase 2
• Construction zones will be
instated on Yonge St. north
of Eglinton Ave., and on
Eglinton Ave. east of Yonge
St.
• Crosswalk closure on the
north and east sides of
Yonge-Eglinton intersection.
• A temporary crosswalk will
be instated on Yonge St.
north of Eglinton Ave. for
pedestrians crossing east-
west.
43. Eglinton Station Construction Impacts
Upcoming Works – Utilities
Phase 3
• Construction zones will be
instated on Eglinton Ave.
east and west of Yonge St.,
and on Yonge St. north and
south of Eglinton Ave.
• Access to Eglinton Ave.
from Cowbell Ln. will be
closed.
• Crosswalk closure on the
south side of Yonge-
Eglinton intersection.
• Sidewalk closure on the
south side Eglinton Ave.
from Duplex Ave. to Yonge
St.
44. Eglinton Station Construction Impacts
Upcoming Works – Utilities
Phase 4
• Construction zones will be
instated on Eglinton Ave.
east and west of Yonge St.,
and on Yonge St. north and
south of Eglinton Ave.
• Access to Eglinton Ave. from
Cowbell Ln. will be closed.
• Crosswalk closure on the
south and east sides of
Yonge-Eglinton intersection.
• A temporary crosswalk will
be instated on Yonge St.
south of Eglinton Ave.
• Sidewalk closure on the
south side Eglinton Ave. from
Duplex Ave. to Yonge St.
45. Eglinton Station Construction Staging
Upcoming Works – Shoring
Shoring Overview
• As early as Fall 2016, work will start on shoring. All
phases of shoring and decking are expected to take
at least 16 months to complete.
• Construction zones will be instated along Eglinton
Ave. and Yonge St. at various stages of shoring.
• Lane closures on Yonge St. and Eglinton Ave. will be
required to carry out the work.
• At least one (1) lane in each direction east-west
along Eglinton Ave. and north-south along Yonge St.
will be maintained.
47. Experience Eglinton
Advertising and marketing initiatives, ranging
from subway and local newspapers advertisements,
to postcards, coupon booklets and flyers all focused
on encouraging residents in the neighbourhood
to shop locally.
Community Benefits
48. Commit to Social Procurement and Local Investment
− seek to maximize procurement and business opportunities to
businesses located along the Project corridor.
Community Benefits – Employment
The Eglinton Crosstown LRT is the first major infrastructure project in Ontario to
include a Community Benefits Framework.
Partner with Local Workforce Agencies
− recruit candidates from the Project corridor and from historically
disadvantaged communities.
Work with Subcontractors
− maximize opportunities for apprentices on each site.
Geotech – March
Demolitions – Beginning of April
TTMP – April 16 (for utilities), May 19 (rest)
Pedestrian Tunnels – June/July
Utilities – Late April – May
SOE – July/Aug (to December)
Excavating – at Salvation Army 2017
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.
These relocations will take place in order to allow for construction and excavation of the future station.