The geometric design of roads is the branch of highway engineering concerned with the positioning of the physical elements of the roadway according to standards and constraints.
Road Geometric Design-The alignment is the route of the road, defined as a series of horizontal tangents and curves.
1. 2. GEOMETRIC DESIGN OF ROAD
2.1 Introduction to road alignment
2.2 Road cross sectional elements
2.3 Sight distance
2.4 Horizontal and vertical alignments
2.5. Road intersections
2. Road Surveys and Location
Selecting the location of a proposed road is an
important initial step in its design. The decision
to select a particular location is usually based on
topography, soil characteristics, environmental
factors such as noise and air pollution,
and economic factors
3. Principles of road location
The road location process involves four phases:
Office study of existing information
Reconnaissance survey
Preliminary location survey
Final location survey
4. Office Study of Existing Information
The first phase in any road location study is the
examination of all available data of the area in
which the road is to be constructed .
The type and amount of data collected and
examined depend on the type of road being
considered, but in general, data should be
obtained on the following characteristics of the
area.
5. • Engineering, including topography, geology, climate,
and traffic volumes
• Social and demographic, including land use and zoning
patterns
• Environmental, including types of wildlife; location of
recreational, historic, and
archeological sites; and the possible effects of air, noise,
and water pollution
• Economic, including unit costs for construction and the
trend of agricultural, commercial, and industrial
activities
At the completion of this phase of the study, the engineer
will be able to select general areas through which the
road can traverse
6. Reconnaissance Survey
The object of this phase of the study is to identify several feasible routes, each
within a band of a limited width. Feasible routes are identified by a
stereoscopic examination of the aerial photographs, taking into consideration
factors such as:
• Terrain and soil conditions
•Serviceability of route to industrial and population areas
• Crossing of other transportation facilities, such as rivers, railroads, and roads
• Directness of route
Control points between the two endpoints are determined for each feasible
route. For example, a unique bridge site with no alternative may be taken as a
primary control point. The feasible routes identified are then plotted on
photographic base maps.
7. 3 Preliminary Location Survey
During this phase of the study, the positions of
the feasible routes are set as closely as
possible by establishing all the control points
and determining preliminary vertical
and horizontal alignments for each. Preliminary
alignments are used to evaluate the
economic and environmental feasibility of the
alternative routes.
8. Economic Evaluation
Economic evaluation of each alternative route is carried
out to determine the future
effect of investing the resources necessary to construct
the road
Factors usually taken into consideration include road
user costs, construction
costs, maintenance costs, road user benefits, and any
disbenefits, which may include
adverse impacts due to dislocation of families,
businesses, and so forth
9. For example, these results will provide
information on the economic
resources that will be gained or lost if
a particular location is selected.
This information is also used to aid the
policy maker in determining whether
the road should be built, and if so,
what type of road it should be.
10. Environmental Evaluation
A road is therefore an integral part of the local environment
and must be considered as such.
This environment includes plant, animal, and human
communities and encompasses social, physical, natural,
and man-made variables.
The construction of a road at a given location may result in
significant changes in one or more variables, which in turn
may offset the equilibrium and result in significant adverse
effects on the environment
11. The environmental impact statements should
include:
• A detailed description of alternatives
• The probable environmental impact, including the
assessment of positive and negative effects
• An analysis of short-term impact as differentiated
from long-term impact
• Any secondary effects, which may be in the form
of changes in the patterns of social and economic
activities
• Probable adverse environmental effects that cannot
be avoided if the project is constructed
• Any irreversible and irretrievable resources that
have been committed
12. In cases where an environmental impact study is
required, it is conducted at this stage to
determine the environmental impact of each
alternative route. Such a study will determine the
negative and/or positive effects the road facility
will have on the environment
For example, the construction of a freeway at
grade through an urban area may result in an
unacceptable noise level for the residents of the
area (negative impact), or the road facility may
be located so that it provides better access to jobs
and recreation centers (positive impact)
13. Preliminary Location Survey
Environmental Evaluation
Public hearings are also held at this stage to
provide an opportunity for constituents to give their
views on the positive and negative impacts of the
proposed alternatives.
The best alternative, based on all the factors
considered, is then selected as the
preliminary alignment of the road
14. Final Location Survey
The final location survey is a detailed layout of the
selected route.
The horizontal and vertical alignments are
determined, and the positions of structures and
drainage channels are located.
Detailed design of the vertical and horizontal
alignments is then carried out to obtain both the
deflection angles for horizontal curves and the cuts
or fills for vertical curves and straight sections of
the road.
15. ROAD SURVEY METHODS
Surveying techniques can be grouped into three general
categories:
• Ground surveys
• Remote sensing
• Computer graphics
Ground surveys are the basic location technique for roads.
The total station is used for measuring angles in both
vertical and horizontal planes, distances, and changes in
elevation through the use of trigonometric levels; the level
is used for measuring changes in elevation only .
16. Remote sensing
Remote sensing is the measurement of distances and
elevations by using devices located above the earth,
such as airplanes or orbiting satellites using Global
Positioning Satellite systems (GPS).
The most commonly used remote-sensing method is
photogrammetry, which utilizes aerial photography
17. Computer Graphics
Computer graphics, when used for road
location, is usually the combination of
photogrammetry and computer techniques.
With the use of mapping software, line styles,
and feature tables, objects and photographic
features can be recorded digitally and stored in
a computer file. This file can then either be
plotted out in map form or sent on to the
design unit.
19. Geometric Design of road Facilities
Geometric design deals with the
dimensioning of the elements of
roads, such as vertical and
horizontal curves, cross sections,
truck climbing lanes, bicycle paths,
and parking facilities.
20. FACTORS INFLUENCING road DESIGN
Road design is based on specified design standards and
controls which depend on the following roadway system
factors:
• Functional classification
• Design hourly traffic volume and vehicle mix
• Design speed
• Design vehicle
• Cross section of the road, such as lanes, shoulders, and
medians
• Presence of heavy vehicles on steep grades
• Topography of the area that the road traverses
• Level of service
• Available funds
• Safety
• Social and environmental factors
22. Cross slope or Camber
Cross slope or camber is the slope provided to the road
surface in the transverse direction to drain off the rain
water from the road surface.
The cross slope is provided because of the following
reasons:
• To prevent the entry of water into the bituminous
pavement layers
• To prevent the entry of surface water into the subgrade
soil through pavement.
• To remove the rain water from the pavement surface as
quickly as possible and to allow the pavement to get dry
soon after the rain
23. Cross slope or Camber
The required camber of pavement depends on;
The type of pavement surface
The amount of rainfall
Recommended rates of cross slopes are 1.5 to 2.5 percent
for high-type pavements and 2 to 6 percent for low-type
pavements.
High-type pavements have wearing surfaces that can
adequately support the expected traffic load without visible
distress due to fatigue and are not susceptible to weather
conditions.
Low-type pavements are used mainly for low-cost roads
and have wearing surfaces ranging from untreated loose
material to surface-treated earth.
.
24. Width of pavement or carriageway
The width of carriageway for various classes of roads standardized by
IRC (Indian Roads Congress) are given in the table below
Class of road Width of
carriageway
1 Single lane 3.75m
2 Two lanes without raised kerbs 7.0m
3 Two lanes with raised kerbs 7.5m
4 Intermediate carriageway 5.5m
5 Multi-lane pavement 3.5/lane
25. Curbs (Am: Kerbs)
• Curb indicates the boundary between the pavement
and shoulder or sometimes islands; foot path or
parking space.
Curbs may be mainly divided into 3 groups based on
their functions
• Low or mountable curb which encourage traffic to
remain in the through traffic lanes.
The height of this type of shoulder curbs is about 10cm
above the pavement edge with a slope (or batter) to
help vehicles climb the curb easily
26. Curbs (Am: Kerbs) ctd
• ii. Semi barrier provided on the roadway where the
pedestrian traffic is high. This type of curbs has a
height of about 15cm above the pavement edge with
a batter of 1:1 on the top 7.5cm
• iii. Barrier kerb is provided in built up area adjacent
to foot path with considerable pedestrian traffic. The
height of stone is about 20cm above the pavement
edge with a steep batter of 1 vertical 0.25 horizontal.
27. Sight distance
• Sight distance is the roadway ahead that is visible to the
driver. Various sight distance criteria exist in road geometric
design to provide drivers with sufficient warning of potential
obstacle or conflict ahead.
• Stopping Sight Distance
• Decision Sight Distance
• Passing Sight Distance on Two-Lane Road
Criteria for Measuring Sight Distance
The Sight Distance is dependent on the height of the driver’s eye
above the road surface, the object height (or size) above the
road surface, and the height and lateral position of sight
obstructions within the driver’s line of sight. These have effect
on the design of horizontal and vertical curve
28. Stopping Sight Distance
Where:
SSD = Stopping sight distance (m)
BRD = Brake Reaction Distance (m) = vt
BD = Braking Distance (m) = v2/2gf
V = Design speed
t = time
f = Coefficient of friction
g = Gravity acceleration
29. Stopping Sight Distance When we have an
ascending or a descending grade
SSD = vt + v2/2g(f+n%)
Where:
V = Design speed
t = time
f = Coefficient of friction
g = Gravity acceleration
n = is the grade (negative when descending, positive when ascending)
32. 3. While descending a -7% grade at a speed of 90
km/h, George notices a large object in the roadway
ahead of him. Without thinking about any alternatives,
George stabs his brakes and begins to slow
down. Assuming that George is so paralyzed with fear
that he won't engage in an avoidance maneuver,
calculate the minimum distance at which George must
have seen the object in order to avoid colliding with it
. You can assume that the roadway surface is concrete
and that the surface is wet so that the coefficient of
friction was 0.29 . You can also assume that George
has a brake reaction time of 0.9 seconds because he is
always alert on this stretch of the road.
33. Solution
First, we need to calculate the distance that George
traveled during his brake reaction time. This is
done using the equation D = VT from
physics. Since George's brake reaction time was 0.9
seconds and his velocity was 25 m/sec (90 km/h),
the distance he traveled during his brake reaction
time was 22.5 meters. Second, we need to
calculate the distance George will travel while
braking. This is done using the equation shown
below.
d = V2/(2g(f + G))
34. Where:
V = George's Velocity, 25 m/sec (90 km/h)
g = Acceleration due to gravity, 9.81 m/sec2
f = Coefficient of friction, 0.29 ( we'll use the value for
96 km/h (60 mph) just to be conservative)
G = The grade of the road, -0.07 (-7%)
Solving the equation yields a distance of 145
meters. Summing the distance traveled while braking
and the distance traveled during the brake reaction time
yields a total stopping sight distance of 168
meters. George needed to be about 168 meters away
from the object at the instant he first saw it in order to
avoid a collision
35. Design of horizontal alignment
• The horizontal alignment includes the straight (tangent)
sections of the roadway and the circular curves that connect
their change in direction.
• The plan view gives the horizontal alignment of a road. The
length of the road is measured along the plan view, on a
horizontal plane.
• The objectives of horizontal alignment design is to provide a
smooth transition between two straight road sections that
also provide proper cross sectional drainage, ensure
vehicle/driver safety while traveling at a design speed
36. Various design factors to be considered in the horizontal
alignment are: Design speed; Radius of circular curves, types
and length of transition curves, superelevation and widening of
pavement on curves
Design speed (is the speed selected to be used in the design
calculations )
The design speed of roads depends upon
• Class of the road
• Terrain
Terrain classification (IRC) Cross slope of country per cent
Plain 0-10
Rolling 10-25
Mountainous 25-60
Steep Greater than 60
37. Terrain classification according to
overseas road note 6
• Level (0-10 five metre ground contours per kilometre). Level or
gently rolling terrain with largely unrestricted horizontal and vertical
alignment. Minimum values of alignment will rarely be necessary.
Roads will, for the most part, follow the ground contours and
amounts of cut and fill will be very small.
• Rolling (11-25 five metre ground contours per kilometre). Rolling
terrain with low hills introducing moderate levels of rise and fall
with some restrictions on vertical alignment. Whilst low standard
roads will be able to follow the ground contours with small amounts
of cut and fill, the higher standards will require more substantial
amounts.
• Mountainous (Greater than 25 five metre ground contours per
kilometre). Rugged, hilly and mountainous with substantial
restrictions in both horizontal and vertical alignment. Higher
standard roads will generally require large amounts of cut and fill
38. ROAD TYPE TERRAIN
DESIGN SPEED
(Km/h)
Primary road
(National,
Expressway)
1.Flat area 80-110
2. Hilly 55-80
3.Mountainous 40-55
Secondary road
(State, district roads )
1.Flat area 60-80
2. Hilly 50-60
3.Mountainous 35-50
Tertiary roads
(Village, others )
1.Flat area 50-60
2. Hilly 35-50
3.Mountainous 25-35
42. SUPER ELEVATION
Super elevation. Super elevation is the amount
of cross slope or "bank" provided on a horizontal
curve to help counterbalance the outward pull
of a vehicle traversing the curve.
The maximum rate of super elevation (emax)
depends on several factors including climatic
conditions, terrain conditions and type of area
(rural or urban).
43.
44. • 1.Super elevation Transition Length/ development Length.
The super elevation transition length is the distance required
to transition the roadway from a normal crown section to the
full super elevation needed. Super elevation transition length
is the sum of the tangent run out and super elevation runoff.
• 2. Tangent Run out/runoff. AASHTO defines tangent run out
as the change from a normal crown section to a point where
the adverse cross slope of the outside lane or lanes is
removed (i.e., the outside lane(s) is level).
• 3. Super elevation Runoff. AASHTO defines super elevation
runoff as the change in cross slope from the end of tangent
run out (adverse crown removed) to a section that is fully
super elevated.
45. • 4.Axis of Rotation. The super elevation axis of rotation is the
line about which the pavement is revolved to super elevate
the roadway. This line will maintain the normal road profile
throughout the curve, and it is known as the construction
centreline or control edge.
• 5. Super elevation Rollover. Super elevation "rollover" is the
algebraic difference between the travel lane cross slope and
shoulder cross slope on the outside of a horizontal curve.
• 6. Normal Crown (NC): The typical cross section on a tangent
section (i.e., no super elevation).
• 7. Remove Crown (RC): A super elevated cross section which
is sloped across the entire travelled way in the same direction
and at a rate equal to the typical cross slope on a tangent
section (e.g., 2.0%)
46. Super elevation attainment
• The available options for rotating travelled ways to attain
super elevation are graphically shown in Figures A to D below.
These are:
1. Revolving a travelled way with normal cross slopes about the
centreline profile.
2. Revolving a travelled way with normal cross slope about the
inside-edge profile.
3. Revolving a travelled way with normal cross slopes about the
outside-edge profile.
4. Revolving a straight cross-slope travelled way around the
inside edge profile lines
47.
48. SIGHT DISTANCE ON HORIZONTAL
CURVE
When a driver travels along a horizontal curve, his sight
distance is limited by a physical obstruction, such as
sidewall, slope or building, at the inside of the curve.
Figure below illustrates this point, where M is the offset
from the centre line of the inside lane to the
obstruction.
For design purpose, the stopping sight distance is the
length of curve along the centre line of the inside lane,
where the vehicle will be traveling or braking (with the
vehicle in full control).
52. SIGHT DISTANCE ON HORIZONTAL CURVE
Example: A sound wall is to be constructed at
the edge of shoulder, along the inside of a
horizontal curve of an urban freeway. The inside
lane is 3.8 m wide, with a shoulder of 1.20 m.
The radius of the curve, measured up to the
outer edge of the shoulder is 45 m. Determine
the sight distance of this section of the curve
with the sound wall.
58. HORIZONTAL TRANSITION CURVE
A transition curve differs from a circular curve in
that its radius is always changing.
Purpose of Transition Curves
• They Provide path for vehicle to move from
straight to a circular curve
• They Improve appearance of curve to driver
• They allow introduction of super elevation and
pavement widening
61. Characteristics of Transition Curve
The transition curve must satisfy the following
characteristics:
• Should have constant rate of change of radius
of curvature
• Transition should be equal to zero at start of
straight and equal to radius of curvature at
circular curve
• Allows passengers to adjust to change in rate
of curvature
62. Functions of transition curve
• It provides a convenient length of road over which super
elevation and/or widening is applied,
• It can improve the appearance of a road, particularly on a
bridge where a rigid handrail follows the exact road
alignment,
• It can improve the appearance of the road where a curve is
visible in plan at the end of a long straight.
• It provides a length of road over which steering adjustment
can be made, particularly in reverse curve situations
• It provides a length of road over which speed adjustments
may be made between curves of different radii.
63.
64.
65. Forms of Transition Curves
• Clothoid – the one that we will examine in
more detail, most commonly used
• Lemniscate – used for large deflection angles
on high speed roads
• Cubic Parabola –unsuitable for large deflection
angles
67. Calculation of Transition Length (Lp
or L)
Transition curves are normally of spiral
(clothoid) form
The length of plan transition (Lp or L) is
determined by
• The rate of change of radial acceleration.
• Rate of change of rotation of pavement
68.
69. Radial Acceleration Method
• The length of a Transition Curve Required to
Minimise Passenger Discomfort is given by
70. Radial Acceleration Method
The value Radial acceleration C will vary with
design speed and design authority. Typical
values for C lie between (0.6 -0.3 m/sec3) for V
from 40-140km/hr respectively
• C = 0.6m/sec3 for V= 40km/hr to 70 km/hr
• C = 0.45m/sec3 for V= 80km/hr to 120 km/hr
• C = 0.3m/sec3 for V >120 km/hr
71. Radial Acceleration Method
A value above 0.6 can result in instability in the
vehicle while values less than 0.3 will lead to
excessively long transition curves leading to
general geometric difficulties. The design
process usually commences with an initial value
of 0.3 being utilised, with this value being
increased gradually if necessary towards its
upper ceiling.
74. Radial Acceleration Method
If a series of angles and chord lengths are used,
the spiral is the preferred form. If, as is the case
here, x and y co-ordinates are being used, then
any point on the transition curve can be
estimated using the following equation of the
curve which takes the form of a cubic parabola
(Figure below)
83. Rate of change of rotation of
pavement
Minimum Lp or L = Le – 0.4V
Note: (e in %) and (V in km/h)
84. CURVE WIDENING(EXTRAWIDENING)
Extra widening refers to the additional width of
carriageway that is required on a curved section
of a road over and above that required on a
straight alignment.
85. Factors of extra widening
• Vehicles travelling on a curve occupy a greater
width of pavement than they do on a straight.
At low speeds the rear wheels track inside the
front wheels and at high speeds the rear
wheels track outside the front wheels.
• Vehicles tend to deviate more from the
centreline of the traffic lane on a curve than
on a straight.
86. Factors of extra widening
and Types of widening
• To maintain clearances between vehicles to
those on straight sections of road.
• Other factors, such as overhang of the front of
the vehicle, wheelbase and track width, also
contribute to the need for curve widening.
Types of widening
• Mechanical widening
• Psychological widening
87. Mechanical widening
The reasons for the mechanical widening are: When a
vehicle negotiates a horizontal curve, the rear wheels
follow a path of shorter radius than the front wheels as
shown in figure below. This phenomenon is called off-
tracking, and has the effect of increasing the effective
width of a road space required by the vehicle.
Therefore, to provide the same clearance between
vehicles traveling in opposite direction on curved roads
as is provided on straight sections, there must be extra
width of carriageway available.
89. Let R1 is the radius of the outer track line of the
rear wheel, R2 is the radius of the outer track
line of the front wheel l is the distance between
the front and rear wheel, n is the number of
lanes, then the mechanical widening Wm (refer
figure below) is derive below.
90. Therefore the widening needed for a single lane
road is:
If the road has n lanes, the extra widening
should be provided on each lane. Therefore, the
extra widening of a road with n lanes is given by
Please note that for large radius, R2 = R, which is
the mean radius of the curve, and then Wm is
given by:
91. Psychological widening
• Widening of pavements has to be done for
some psychological reasons also. There is a
tendency for the drivers to drive close to the
edges of the pavement on curves. Some extra
space is to be provided for more clearance for
the crossing and overtaking operations on
curves. An empirical relation for the
psychological widening at horizontal curves is
Wps
94. Design of super-elevation
EXERCISE:
A national road passing through a rolling terrain
has two horizontal curves of radius 450 m and
150 m. Design the required superelevation for
the curves if the ruling design speed is 80 kmph.
The coefficient of lateral friction f=0.15.
95. DESIGN OF VERTICAL ALIGNMENT
The purpose of vertical alignment design is to
determine the elevation of selected points along
the roadway, to ensure proper drainage, safety,
and ride comfort.
A vertical alignment is the elevation or profile of
the centre line of the road; it consists of grades,
and vertical curve
97. Gradient and Vertical curves
Gradient
The gradient is the rate of rise or fall along the length of
the road with respect to the horizontal. It is expressed
as a ratio of 1 in x (1 vertical unit to x horizontal units)
sometimes the gradient is also expressed as a
percentage, n i.e n in 100.
Note that an uphill is expressed in a positive gradient
while a downhill is expressed in a negative gradient
A vertical curve provides a smooth transition between
two tangent grades. There are two types of vertical
curves: crest vertical curves and sag vertical curves
98.
99. Vertical curves
A vertical curve starts at the point of vertical
curvature (PVC) and ends at the point of vertical
tangent (PVT). The length of road between PVC
and PVT is L: The initial and final grades are
denoted by G1 and G2; respectively, expressed in
%. Based on the equation of a parabolic curve,
the vertical offset y at any distance x from the
projected initial gradient is
102. Vertical curves
Example
A road must traverse a 6% followed by a -2%
grade. The length of the crest vertical curve is
2040 m. calculate the elevation for the first 600
m of the vertical curve at 100 m intervals, and
the highest point of the curve.
105. Criteria to be considered in calculate
minimum lengths of vertical curves
To calculate minimum lengths of vertical curves
one of the following will govern
• Sight distance
• Appearance criterion
• Comfort criterion:
110. Which violates the assumption of L < S:
Therefore we should use L = 3214.29 m.
In vertical curve, for stopping sight distance, the
height of object is normally taken to be 0.150 m.
For passing sight distance, the height of object
used by AASHTO is 1.300 m. Height of eye is
assumed to be 1.070 m
111. SSD, Sag Vertical Curve
Figure below shows the driver’s sight limitation
when approaching a sag vertical curve. The
problem is more obvious during the night time
when the sight of the driver is restricted by the
area projected by the headlight beams of
his/her vehicle. Hence, the angle of the beam
from the horizontal plane is also important. This
design control criteria is known as headlight
sight distance.
116. The curve length to satisfy this criterion is
usually about half the length that is needed to
meet the stopping sight distance criteria.
117. Appearance criterion:
• Minimum vertical curve standards for roads
may also be based on appearance.
• This problem arises because short vertical
curves tend to look like kinks when viewed
from a distance. Appearance standards vary
from agency to agency. Current California
standards, for instance, require a minimum
vertical curve length of 60 m where grade
breaks are less than 2 per cent or design
speeds are less than 60 km/h.
118. Where the grade break is greater than 2 per
cent and the design speed is greater than 60
km/h, the minimum vertical curve is given by L =
2V, where L in the vertical curve length in
meters and V is the design speed in km/h.
119. Sight Distance at under crossings
• Sight distance on the roadway that is the
lower tier of a grade separated intersection
should also consider obstruction of the sight
pose by the structure. Most of the roadways
at the lower tier of an interchange are
designed as sag vertical curves. Figure: below
illustrates a typical design situation.
120. • The general equation for a sag vertical curve length at an
undercrossing is
• Where C is the vertical clearance from the road surface to the
bottom of the obstructing structure.
• The above equations have several applications. In deciding the
length of the vertical curve for a given A; the design may select
the sight distance S to cater for, with appropriate h1 and h2 to
calculate L: The designed curve length should be at least L: On
other hand, given a designed curve length L; A and C; the
designer may check whether S satisfies the sight distance criteria
(with corresponding h1 and h2).
• Also, given L; A; S; h1 and h2; the designer may use these
equations to decide the minimum clearance C
121. Exercise:
• Determine the minimum length of curve required to connect a
descending 4% grade to an ascending 3% grade. The vertical
clearance should be 5.1 m and the required sight distance is 300
m. The height of eye for a commercial vehicle is 1.83 m and the
hazardous object is 0.46 m above the pavement surface.
• Solution: Given h1 =1.83 m, h2= 0.46 m, S=300 m, C= 5.1 m, G1 =
-4%; G2 = +3%
123. road INTERSECTIONS
Introduction
A road intersection is required to control conflicting
and merging streams of traffic so that delay is
minimized. This is achieved through choice of geo-
metric parameters that control and regulate the
vehicle paths through the intersection. These
determine priority so that all movements take place
with safety.
The three main types of junction dealt with in this
part are:
• Priority intersections
• Signalized intersections
• Roundabouts.
124. Major/minor priority intersections
A priority intersection occurs between two
roads; one termed the ‘major’ road and the
other the ‘minor’ road. The major road is the
one assigned a permanent priority of traffic
movement over that of the minor road. The
minor road must give priority to the major road
with traffic from it only entering the major road
when appropriate gaps appear. The principal
advantage of this type of junction is that the
traffic on the major route is not delayed.
125. Priority intersections can be in the form of simple T-junctions, staggered junctions or
crossroads, though the last form should be avoided where possible as drivers exiting
the minor road can misunderstand the traffic priorities. This may lead to increased
accidents
126. Simple junctions: A T-junction or staggered junction without any ghost or
physical islands in the major road and without channelling islands in the
minor road approach.
127. Ghost island junctions: Usually a T-junction or staggered junction within
which an area is marked on the carriageway, shaped and located so as to
direct traffic movement
128. Single lane dualling: Usually a T-junction or staggered junction within which
central reservation islands are shaped and located so as to direct traffic
movement
129. Mini-roundabout
Mini-roundabouts can be extremely successful in improving
existing urban junctions where side road delay and safety are a
concern
Mini-roundabouts consist of a 1-way circulatory carriageway
around a reflectorised, flush/slightly raised circular island less
than 4 m in diameter which can be overrun with ease by the
wheels of heavy vehicles. Mini- roundabouts are used
predominantly in urban areas with speed limits not exceeding
48 km/h (50 mph).
130. Normal roundabout
A normal roundabout is defined as a roundabout having a 1-
way circulatory carriageway around a kerbed central island at
least 4 m in diameter, with an inscribed circle diameter (ICD) of
at least 28 m and with flared approaches to allow for multiple
vehicle entry. The number of recommended entry arms is
either three or four. If the number is above four, the
roundabout becomes larger with the probability that higher
circulatory speeds will be generated. In such situations double
roundabouts may provide a solution
131. Double roundabout
A double roundabout can be defined as an individual junction
with two normal/mini-roundabouts either contiguous or
connected by a central link road or kerbed island.
132. • Other forms
Other roundabout
configurations include two-
bridge roundabouts, dumbbell
roundabouts, ring junctions and
signalised roundabouts.