SlideShare a Scribd company logo
1 of 1
Download to read offline
Ways to Measure Your
                                                         Reliability Centered Commissioning Program
                                                         Maturity Matrix
                                               Elements                 LEVEL1
                                                                         LEVEL 1                                  LEVEL2
                                                                                                                   LEVEL 2                                 LEVEL 3                                LEVEL4
                                                                                                                                                                                                   LEVEL 4                                  LEVEL5
                                                                                                                                                                                                                                             LEVEL 5
                                                                     NOT ENGAGED
                                                                      NOT ENGAGED                             EXPERIMENTING
                                                                                                               EXPERIMENTING                             ENLIGHTENED                           GOOD PRACTICE
                                                                                                                                                                                                GOOD PRACTICE                            BEST PRACTICE
                                                                                                                                                                                                                                          BEST PRACTICE

                                            Commissioning                                                    An unwritten or uncoordinated set of                                                                                       Enhanced commissioning with retro-
                                                                    No explicit commissioning policy.                                                 Fundamental commissioning Policy.         Enhanced commissioning Policy.
                                            Management Policy                                                            guidelines.                                                                                                          commissioning Policy.

                                                                                                                                                                                                                                            Enhanced commissioning is
                                                                                                                                                          Fundamental commissioning                 Enhanced commissioning
                                                                                                              Some of the building components                                                                                            performed on all building systems,
                                            Commissioning
Commissioning Management Program Elements




                                                                      Building and systems are not                                                         is performed on all building            is performed on all building
                                                                                                             and systems are commissioned but                                                                                            adhere to ASHRAE commissioning
                                            Program                          commissioned.                                                              systems and adhere to ASHRAE            systems and adhere to ASHRAE
                                                                                                                no formal format is followed.                                                                                              guidelines and utilize reliability
                                                                                                                                                            commissioning guidelines.               commissioning guidelines.
                                                                                                                                                                                                                                                    technologies.

                                                                                                                                                                                                                                         Retro-commissioning as warranted
                                                                                                                                                                                               Retro-commissioning building and
                                            Retro-Commissioning    Building and systems are not retro-       Retro-commissioning buildings and         Retro-commissioning building and                                                  through evaluation of the reliability
                                                                                                                                                                                               systems every 1,3, or 5 years as
                                            Program                          commissioned.                    systems only as problems occur.              systems every 10 years.                                                       technologies or measurement and
                                                                                                                                                                                                 scheduled by management.
                                                                                                                                                                                                                                                verification warrant.

                                            Reliability Centered
                                            Commissioning                     No integration.                  Spot check or troubleshooting.          Single technology quality checks.       Multiple technology quality check.                Design for reliability.
                                            Technologies
                                                                                                               Cost reporting based on invoice                                                M&V reports for individual premises       Comprehensive systems set targets,
                                                                                                                                                        M&V reports based on supply
                                            Measurement and            No information system. No              details. Engineer compiles reports                                                  are based on sub metering.              monitor consumption, identify
                                                                                                                                                      meter data. Energy unit has ad hoc
                                            Verification Program   accounting for energy consumption.          for internal use within technical                                                 Achieved performance against             defects, quantify savings, and
                                                                                                                                                        involvement in budget setting.
                                                                                                                         department.                                                          targets reported effectively to users.        provide budget tracking.

                                            Commissioning/                                                    Few buildings and systems have           Some buildings and systems have            Most buildings and systems              All buildings and systems have
                                                                     No criticality matrix prepared for        a criticality matrix to assist with      a criticality matrix to assist with     have a criticality matrix to assist       a criticality matrix to assist with
                                            Retro-Commissioning          buildings and systems.              commissioning/retro-commissioning        commissioning/retro-commissioning           with Commissioning/Retro-             commissioning/retro-commissioning
                                            Criticality Program                                                         Capex projects.                          Capex projects.                Commissioning Capex projects.                      Capex projects.

                                                                                                                                                                                                 Investment using longer-term              Investment using long-term
                                                                                                                                                         Investment using short-term             payback criteria (5-10 years).           payback criteria (10-20 years).
                                            Investment                   No investment strategy.             Only low-cost measures considered.       payback criteria (0-5 years). Simple     Complete Life Cycle Cost analysis        Energy Efficency, Sustainibility and
                                                                                                                                                         payback calculations utilized.          using Equest or equal energy           Carbon Footprint considered during
                                                                                                                                                                                                      modeling software.                            evaluation.


                                            Commissioning                                                                                                                                                                                     Departments have written
                                                                     No evidence of assignment of              Unwritten set of commissioning/          Departments have some written          Departments have comprehensive
                                                                                                                                                                                                                                        commissioning/retro-commissioning
                                            Management             commissioning/retro-commissioning          retro-commissioning responsibility      commissioning/retro-commissioning          written commissioning/retro-
                                                                                                                                                                                                                                        responsibilities and have designated
                                            Responsibilities               tasks and duties.                            assignments.                           responsibilities.                commissioning responsibilities.
                                                                                                                                                                                                                                            staff assigned for these task.
Reliability in Design




                                                                                                                                                      Commissioning/retro-commissioning       Commissioning/retro-commissioning         Commissioning/retro-commissioning
                                            Commissioning          No staff have explicit responsibilities   Commissioning/retro-commissioning
                                                                                                                                                       task are presented to staff on an        task are presented to staff on a         tasks are presented to staff on a
                                            Awareness                           or duties.                     measures are rarely promoted.
                                                                                                                                                                 annual basis.                          bi-annual basis.                        continuous basis.

                                                                                                              Reporting is done but there is no        Reporting is done utilizing standard   Reporting is done utilizing standard      Reporting is done utilizing standard
                                                                                                              standard report procedures and          report procedures but historical data    report procedures and historical          ASHRAE report procedures and
                                            Reporting Procedures               No reporting.
                                                                                                              historical data is not collected for      is not collected for establishing a   data is collected for establishing a        historical data is collected for
                                                                                                                   establishing a baseline.                          baseline.                             baseline.                         establishing a baseline.

                                                                                                                                                                                                                                           O&M startup training documents
                                                                                                                                                                                                O&M startup training documents             and onsite training is preformed.
                                                                                                              O&M startup training documents          O&M startup training documents are
                                                                        No O&M startup training is                                                                                              and onsite training is preformed.       The onsite training is video taped for
                                            O&M Startup Training              performed.
                                                                                                             are provided in written form with no      provided in written form and onsite
                                                                                                                                                                                              The onsite training is video taped for     future training. Follow up training is
                                                                                                                   onsite training provided.                   training provided.
                                                                                                                                                                                                         future training.                provided on a bi-annual basis to all
                                                                                                                                                                                                                                                  maintenance staff.

                                                                                                             Owner/Designer only involved in the       Commissioning agent involved in        Commissioning agent involved in all       Multi discipline Commissioning Team
                                            Design Development      No design development process.
                                                                                                                development of the design.                final stages of design.                    stages of design.                    involved in all stages of design.
Technical ElementsProcess




                                                                                                                                                                                              Commissioning agent involved in all          Multi discipline Commissioning
                                                                                                                                                       Commissioning agent involved in
                                            Design Review               No design review process.                  Owner/Designer review.
                                                                                                                                                        final stages of design review.
                                                                                                                                                                                               stages of design review including        Team involved in all stages of design
                                                                                                                                                                                                     design for reliability.            review including design for reliability.
      Reliability in




                                                                                                                                                                                                                                        Multi discipline Commissioning Team
                                                                                                                                                      Commissioning agent reviews only          Commissioning agent reviews all
                                            Submittal Review          No submittal review process.           Owner/Designer review submittals.
                                                                                                                                                        major component submittals.                      submittals.
                                                                                                                                                                                                                                          reviews all submittals including
                                                                                                                                                                                                                                                 design for reliability.
                                                                                                                                                                                                                                            Pre-functional check list are
                                            Pre-Functional Check    No pre-functional or manufacturer            Manufacturers check list are             Pre-functional check list are           Pre-functional check list are
                                                                                                                                                                                                                                        provided on all systems and building
                                            List                         check list are provided.                      followed only.                   provided on major system only.             provided on all systems.
                                                                                                                                                                                                                                                   components.
                                                                                                                                                                                                                                         Functional check list are provided
                                                                   No functional or manufacturer check           Manufacturers check list are         Functional check list are provided on   Functional check list are provided on
                                            Functional Testing               list are provided.                        followed only.                         major system only.                          all systems.
                                                                                                                                                                                                                                           on all systems and building
                                                                                                                                                                                                                                                   components.
                                                                                                               O&M strategy on major systems                                                    O&M strategy on major systems
                                            Reliability O&M        No O&M strategy or reliability O&M                                                 O&M strategy on all systems with no                                                O&M strategy on all systems with
                                                                                                             only with no reliability O&M Strategy                                              only with reliability O&M strategy
                                            Strategy                    strategy implemented.                                                         reliability O&M strategy integration.                                             reliability O&M strategy integration.
                                                                                                                          integration.                                                                     integration.

                                                                                                                                                                                                Original building and all system          All building and system design,
                                                                                                              Original building and major system        Original building and all system           design and commissioning                   commissioning and retro-
                                            Documentation &            No documentation or record
                                                                                                             design documents are recorded and        design documents are recorded and       documents are recorded and stored            commissioning documents are
                                            Record Keeping                     keeping.
                                                                                                                  stored for future reference.            stored for future reference.        for future reference with only major        kept and continually updated as
                                                                                                                                                                                                     systems being updated.                          necessary.
RESULTS / SCORECARDS
Results/Scorecards




                                                                                                                                                                                                                                         O&M with reliability O&M strategies
                                            O&M procedures               No O&M procedures are                O&M strategies for most systems          O&M strategies for all systems are      O&M with reliability O&M strategies
                                                                                                                                                                                                                                        for all systems are documented and
                                            documentation                    documented.                             are documented.                            documented.                     for all systems are documented.
                                                                                                                                                                                                                                            on-going training is provided.

                                                                                                                                                                                                                                         All systems are zoned and metered
                                                                                                                                                                                               All systems are zoned and metered
                                            Measurement and        No measurement and verification is           Major systems are zoned and           All systems are zoned and metered                                                 separately. Utility usage is constantly
                                                                                                                                                                                              separately. Utility usage is constantly
                                            Verification                     preformed.                           metered separately only.                        separately.                                                              monitored and compared to the
                                                                                                                                                                                                           monitored.
                                                                                                                                                                                                                                                      baseline.

                                                                                                                                                                                                                                         Energy analysis and life-cycle cost
                                                                                                               Energy analysis is preformed on         Energy analysis and life-cycle cost     Energy analysis and life-cycle cost      analysis are preformed on all Capex
                                            Energy analysis/         No energy analysis or baseline
                                                                                                             facility but Capex projects life cycle     analysis are preformed only on        analysis are preformed on all Capex         projects. These analysis utilize
                                            Baseline analysis             analysis is utilized.
                                                                                                                cost analysis are not utilized.             major Capex projects.                           projects.                    baseline analysis for evaluation of
                                                                                                                                                                                                                                                       results.




                                                                                                                                                                                                                 4200 Faber Place Drive
                                                                                                 101 South Spring Street
                                                                                                                                                                                                                  Charleston, SC 29405
                                                                                                  Little Rock, AR 72201
                                                                                                                                                                                                                    o. 888.335.8276
                                                                                                     o. 501.372.2900
                                                                                                                                                                                                                    f. 843.414.5779
                                                                                                   www.cromwell.com
                                                                                                                                                                                                                   www.gpallied.com

More Related Content

What's hot

NG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapNG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapLeanleaders.org
 
NG BB 54 Sustain the Gain
NG BB 54 Sustain the GainNG BB 54 Sustain the Gain
NG BB 54 Sustain the GainLeanleaders.org
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniquesEmerson Exchange
 
NG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeNG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeLeanleaders.org
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Emerson Exchange
 
NG BB 32 Failure Modes and Effects Analysis
NG BB 32 Failure Modes and Effects AnalysisNG BB 32 Failure Modes and Effects Analysis
NG BB 32 Failure Modes and Effects AnalysisLeanleaders.org
 
Adbd Offset Tpm Implementation Program [Compatibility Mode]
Adbd Offset Tpm Implementation Program [Compatibility Mode]Adbd Offset Tpm Implementation Program [Compatibility Mode]
Adbd Offset Tpm Implementation Program [Compatibility Mode]abir014
 
Tools Processes And Training
Tools Processes And TrainingTools Processes And Training
Tools Processes And Trainingdgholden
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapLeanleaders.org
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundationEmerson Exchange
 
NG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsNG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsLeanleaders.org
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Emerson Exchange
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Emerson Exchange
 
Cost of Quality How to Save Money
Cost of Quality How to Save MoneyCost of Quality How to Save Money
Cost of Quality How to Save MoneyIosif Itkin
 
NG BB 22 Process Measurement
NG BB 22 Process MeasurementNG BB 22 Process Measurement
NG BB 22 Process MeasurementLeanleaders.org
 
How to Get Started With Advanced Contro
How to Get Started With Advanced ControHow to Get Started With Advanced Contro
How to Get Started With Advanced ControEmerson Exchange
 
Boot camp advanced tools and techniques
Boot camp   advanced tools and techniquesBoot camp   advanced tools and techniques
Boot camp advanced tools and techniquesEmerson Exchange
 

What's hot (19)

NG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapNG BB 12 High-Level Process Map
NG BB 12 High-Level Process Map
 
NG BB 54 Sustain the Gain
NG BB 54 Sustain the GainNG BB 54 Sustain the Gain
NG BB 54 Sustain the Gain
 
Environmental stress screening
Environmental stress screeningEnvironmental stress screening
Environmental stress screening
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniques
 
NG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeNG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - Attribute
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...
 
NG BB 32 Failure Modes and Effects Analysis
NG BB 32 Failure Modes and Effects AnalysisNG BB 32 Failure Modes and Effects Analysis
NG BB 32 Failure Modes and Effects Analysis
 
Adbd Offset Tpm Implementation Program [Compatibility Mode]
Adbd Offset Tpm Implementation Program [Compatibility Mode]Adbd Offset Tpm Implementation Program [Compatibility Mode]
Adbd Offset Tpm Implementation Program [Compatibility Mode]
 
Tools Processes And Training
Tools Processes And TrainingTools Processes And Training
Tools Processes And Training
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL Roadmap
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundation
 
NG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsNG BB 18 Theory of Constraints
NG BB 18 Theory of Constraints
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2
 
NG BB 26 Control Charts
NG BB 26 Control ChartsNG BB 26 Control Charts
NG BB 26 Control Charts
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
 
Cost of Quality How to Save Money
Cost of Quality How to Save MoneyCost of Quality How to Save Money
Cost of Quality How to Save Money
 
NG BB 22 Process Measurement
NG BB 22 Process MeasurementNG BB 22 Process Measurement
NG BB 22 Process Measurement
 
How to Get Started With Advanced Contro
How to Get Started With Advanced ControHow to Get Started With Advanced Contro
How to Get Started With Advanced Contro
 
Boot camp advanced tools and techniques
Boot camp   advanced tools and techniquesBoot camp   advanced tools and techniques
Boot camp advanced tools and techniques
 

Similar to Reliability Centered Commissioning Maturity Matrix

Energy Management Program Maturity Matrix
Energy Management Program Maturity MatrixEnergy Management Program Maturity Matrix
Energy Management Program Maturity MatrixRicky Smith CMRP, CMRT
 
Energy Management Program Maturity Matrix
Energy Management Program Maturity MatrixEnergy Management Program Maturity Matrix
Energy Management Program Maturity MatrixRicky Smith CMRP, CMRT
 
Reliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixReliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixRicky Smith CMRP, CMRT
 
Reliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixReliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixRicky Smith CMRP, CMRT
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009Glen Alleman
 
Novaces General Brochure
Novaces General BrochureNovaces General Brochure
Novaces General Brochureza6smbb
 
Linkroad Corporate Snapshot
Linkroad Corporate SnapshotLinkroad Corporate Snapshot
Linkroad Corporate Snapshotmelvinyou
 

Similar to Reliability Centered Commissioning Maturity Matrix (8)

Energy Management Program Maturity Matrix
Energy Management Program Maturity MatrixEnergy Management Program Maturity Matrix
Energy Management Program Maturity Matrix
 
Energy Management Program Maturity Matrix
Energy Management Program Maturity MatrixEnergy Management Program Maturity Matrix
Energy Management Program Maturity Matrix
 
Reliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixReliability Engineering Maturity Matrix
Reliability Engineering Maturity Matrix
 
Reliability Engineering Maturity Matrix
Reliability Engineering Maturity MatrixReliability Engineering Maturity Matrix
Reliability Engineering Maturity Matrix
 
SAM Advantage Product Guide
SAM Advantage Product GuideSAM Advantage Product Guide
SAM Advantage Product Guide
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009
 
Novaces General Brochure
Novaces General BrochureNovaces General Brochure
Novaces General Brochure
 
Linkroad Corporate Snapshot
Linkroad Corporate SnapshotLinkroad Corporate Snapshot
Linkroad Corporate Snapshot
 

More from Ricky Smith CMRP, CMRT

Skills of a Proactive Maintenance Technician
Skills of a Proactive Maintenance TechnicianSkills of a Proactive Maintenance Technician
Skills of a Proactive Maintenance TechnicianRicky Smith CMRP, CMRT
 
Day in the Life (DILO) of a Proactive Maintenance Manager
Day in the Life (DILO) of a Proactive Maintenance ManagerDay in the Life (DILO) of a Proactive Maintenance Manager
Day in the Life (DILO) of a Proactive Maintenance ManagerRicky Smith CMRP, CMRT
 
Day in the Life of a Proactive Maintenance Planner
Day in the Life of a Proactive Maintenance PlannerDay in the Life of a Proactive Maintenance Planner
Day in the Life of a Proactive Maintenance PlannerRicky Smith CMRP, CMRT
 
Day in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorDay in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorRicky Smith CMRP, CMRT
 
How to know if your maintenance planning and scheduling is not effective
How to know if your maintenance planning and scheduling is not effectiveHow to know if your maintenance planning and scheduling is not effective
How to know if your maintenance planning and scheduling is not effectiveRicky Smith CMRP, CMRT
 
Day in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorDay in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorRicky Smith CMRP, CMRT
 
Day in the Life of a Proactive Maintenance Technician Article
Day in the Life of a Proactive Maintenance Technician  ArticleDay in the Life of a Proactive Maintenance Technician  Article
Day in the Life of a Proactive Maintenance Technician ArticleRicky Smith CMRP, CMRT
 
Best Maintenance Repair Practices Article
Best Maintenance Repair Practices ArticleBest Maintenance Repair Practices Article
Best Maintenance Repair Practices ArticleRicky Smith CMRP, CMRT
 
Tool Box Talk - Maintenance Parts Checkout
Tool Box Talk - Maintenance Parts CheckoutTool Box Talk - Maintenance Parts Checkout
Tool Box Talk - Maintenance Parts CheckoutRicky Smith CMRP, CMRT
 
Tool Box Talk - Lubrication of Bearings
Tool Box Talk - Lubrication of BearingsTool Box Talk - Lubrication of Bearings
Tool Box Talk - Lubrication of BearingsRicky Smith CMRP, CMRT
 
Tool Box Talk - Maintenance Planning and Scheduling
Tool Box Talk - Maintenance Planning and SchedulingTool Box Talk - Maintenance Planning and Scheduling
Tool Box Talk - Maintenance Planning and SchedulingRicky Smith CMRP, CMRT
 
Top 7 Reasons why Maintenance Work Orders are Closed Out Accurately
Top 7 Reasons why Maintenance Work Orders are Closed Out AccuratelyTop 7 Reasons why Maintenance Work Orders are Closed Out Accurately
Top 7 Reasons why Maintenance Work Orders are Closed Out AccuratelyRicky Smith CMRP, CMRT
 
Tool Box Talk - How to Stop Hydraulic Leaks and Why
Tool Box Talk - How to Stop Hydraulic Leaks and WhyTool Box Talk - How to Stop Hydraulic Leaks and Why
Tool Box Talk - How to Stop Hydraulic Leaks and WhyRicky Smith CMRP, CMRT
 
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive MaintenancePM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive MaintenanceRicky Smith CMRP, CMRT
 
How to Develop an Effective Maintenance Skills Training Program
How to Develop an Effective Maintenance Skills Training ProgramHow to Develop an Effective Maintenance Skills Training Program
How to Develop an Effective Maintenance Skills Training ProgramRicky Smith CMRP, CMRT
 
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 -  Fundamentals of Preventive MaintenancePM Tool Box Talk 101 -  Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive MaintenanceRicky Smith CMRP, CMRT
 
Day in the Life of (DILO) of a Proactive Maintenance Technician
Day in the Life of (DILO) of a Proactive Maintenance TechnicianDay in the Life of (DILO) of a Proactive Maintenance Technician
Day in the Life of (DILO) of a Proactive Maintenance TechnicianRicky Smith CMRP, CMRT
 

More from Ricky Smith CMRP, CMRT (20)

Skills of a Proactive Maintenance Technician
Skills of a Proactive Maintenance TechnicianSkills of a Proactive Maintenance Technician
Skills of a Proactive Maintenance Technician
 
Day in the Life (DILO) of a Proactive Maintenance Manager
Day in the Life (DILO) of a Proactive Maintenance ManagerDay in the Life (DILO) of a Proactive Maintenance Manager
Day in the Life (DILO) of a Proactive Maintenance Manager
 
Day in the Life of a Proactive Maintenance Planner
Day in the Life of a Proactive Maintenance PlannerDay in the Life of a Proactive Maintenance Planner
Day in the Life of a Proactive Maintenance Planner
 
Day in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorDay in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance Supervisor
 
How to know if your maintenance planning and scheduling is not effective
How to know if your maintenance planning and scheduling is not effectiveHow to know if your maintenance planning and scheduling is not effective
How to know if your maintenance planning and scheduling is not effective
 
Day in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance SupervisorDay in the life of a Proactive Maintenance Supervisor
Day in the life of a Proactive Maintenance Supervisor
 
Day in the Life of a Proactive Maintenance Technician Article
Day in the Life of a Proactive Maintenance Technician  ArticleDay in the Life of a Proactive Maintenance Technician  Article
Day in the Life of a Proactive Maintenance Technician Article
 
Best Maintenance Repair Practices Article
Best Maintenance Repair Practices ArticleBest Maintenance Repair Practices Article
Best Maintenance Repair Practices Article
 
Tool Box Talk - Maintenance Parts Checkout
Tool Box Talk - Maintenance Parts CheckoutTool Box Talk - Maintenance Parts Checkout
Tool Box Talk - Maintenance Parts Checkout
 
Tool Box Talk - Lubrication of Bearings
Tool Box Talk - Lubrication of BearingsTool Box Talk - Lubrication of Bearings
Tool Box Talk - Lubrication of Bearings
 
Tool Box Talk - Maintenance Planning and Scheduling
Tool Box Talk - Maintenance Planning and SchedulingTool Box Talk - Maintenance Planning and Scheduling
Tool Box Talk - Maintenance Planning and Scheduling
 
Top 7 Reasons why Maintenance Work Orders are Closed Out Accurately
Top 7 Reasons why Maintenance Work Orders are Closed Out AccuratelyTop 7 Reasons why Maintenance Work Orders are Closed Out Accurately
Top 7 Reasons why Maintenance Work Orders are Closed Out Accurately
 
Tool Box Talk - How to Stop Hydraulic Leaks and Why
Tool Box Talk - How to Stop Hydraulic Leaks and WhyTool Box Talk - How to Stop Hydraulic Leaks and Why
Tool Box Talk - How to Stop Hydraulic Leaks and Why
 
Maintenance of Hydraulic Systems
Maintenance of Hydraulic SystemsMaintenance of Hydraulic Systems
Maintenance of Hydraulic Systems
 
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive MaintenancePM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
 
How to Develop an Effective Maintenance Skills Training Program
How to Develop an Effective Maintenance Skills Training ProgramHow to Develop an Effective Maintenance Skills Training Program
How to Develop an Effective Maintenance Skills Training Program
 
What is Lean Maintenance
What is Lean MaintenanceWhat is Lean Maintenance
What is Lean Maintenance
 
Best Maintenance Repair Practices
Best Maintenance Repair PracticesBest Maintenance Repair Practices
Best Maintenance Repair Practices
 
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 -  Fundamentals of Preventive MaintenancePM Tool Box Talk 101 -  Fundamentals of Preventive Maintenance
PM Tool Box Talk 101 - Fundamentals of Preventive Maintenance
 
Day in the Life of (DILO) of a Proactive Maintenance Technician
Day in the Life of (DILO) of a Proactive Maintenance TechnicianDay in the Life of (DILO) of a Proactive Maintenance Technician
Day in the Life of (DILO) of a Proactive Maintenance Technician
 

Reliability Centered Commissioning Maturity Matrix

  • 1. Ways to Measure Your Reliability Centered Commissioning Program Maturity Matrix Elements LEVEL1 LEVEL 1 LEVEL2 LEVEL 2 LEVEL 3 LEVEL4 LEVEL 4 LEVEL5 LEVEL 5 NOT ENGAGED NOT ENGAGED EXPERIMENTING EXPERIMENTING ENLIGHTENED GOOD PRACTICE GOOD PRACTICE BEST PRACTICE BEST PRACTICE Commissioning An unwritten or uncoordinated set of Enhanced commissioning with retro- No explicit commissioning policy. Fundamental commissioning Policy. Enhanced commissioning Policy. Management Policy guidelines. commissioning Policy. Enhanced commissioning is Fundamental commissioning Enhanced commissioning Some of the building components performed on all building systems, Commissioning Commissioning Management Program Elements Building and systems are not is performed on all building is performed on all building and systems are commissioned but adhere to ASHRAE commissioning Program commissioned. systems and adhere to ASHRAE systems and adhere to ASHRAE no formal format is followed. guidelines and utilize reliability commissioning guidelines. commissioning guidelines. technologies. Retro-commissioning as warranted Retro-commissioning building and Retro-Commissioning Building and systems are not retro- Retro-commissioning buildings and Retro-commissioning building and through evaluation of the reliability systems every 1,3, or 5 years as Program commissioned. systems only as problems occur. systems every 10 years. technologies or measurement and scheduled by management. verification warrant. Reliability Centered Commissioning No integration. Spot check or troubleshooting. Single technology quality checks. Multiple technology quality check. Design for reliability. Technologies Cost reporting based on invoice M&V reports for individual premises Comprehensive systems set targets, M&V reports based on supply Measurement and No information system. No details. Engineer compiles reports are based on sub metering. monitor consumption, identify meter data. Energy unit has ad hoc Verification Program accounting for energy consumption. for internal use within technical Achieved performance against defects, quantify savings, and involvement in budget setting. department. targets reported effectively to users. provide budget tracking. Commissioning/ Few buildings and systems have Some buildings and systems have Most buildings and systems All buildings and systems have No criticality matrix prepared for a criticality matrix to assist with a criticality matrix to assist with have a criticality matrix to assist a criticality matrix to assist with Retro-Commissioning buildings and systems. commissioning/retro-commissioning commissioning/retro-commissioning with Commissioning/Retro- commissioning/retro-commissioning Criticality Program Capex projects. Capex projects. Commissioning Capex projects. Capex projects. Investment using longer-term Investment using long-term Investment using short-term payback criteria (5-10 years). payback criteria (10-20 years). Investment No investment strategy. Only low-cost measures considered. payback criteria (0-5 years). Simple Complete Life Cycle Cost analysis Energy Efficency, Sustainibility and payback calculations utilized. using Equest or equal energy Carbon Footprint considered during modeling software. evaluation. Commissioning Departments have written No evidence of assignment of Unwritten set of commissioning/ Departments have some written Departments have comprehensive commissioning/retro-commissioning Management commissioning/retro-commissioning retro-commissioning responsibility commissioning/retro-commissioning written commissioning/retro- responsibilities and have designated Responsibilities tasks and duties. assignments. responsibilities. commissioning responsibilities. staff assigned for these task. Reliability in Design Commissioning/retro-commissioning Commissioning/retro-commissioning Commissioning/retro-commissioning Commissioning No staff have explicit responsibilities Commissioning/retro-commissioning task are presented to staff on an task are presented to staff on a tasks are presented to staff on a Awareness or duties. measures are rarely promoted. annual basis. bi-annual basis. continuous basis. Reporting is done but there is no Reporting is done utilizing standard Reporting is done utilizing standard Reporting is done utilizing standard standard report procedures and report procedures but historical data report procedures and historical ASHRAE report procedures and Reporting Procedures No reporting. historical data is not collected for is not collected for establishing a data is collected for establishing a historical data is collected for establishing a baseline. baseline. baseline. establishing a baseline. O&M startup training documents O&M startup training documents and onsite training is preformed. O&M startup training documents O&M startup training documents are No O&M startup training is and onsite training is preformed. The onsite training is video taped for O&M Startup Training performed. are provided in written form with no provided in written form and onsite The onsite training is video taped for future training. Follow up training is onsite training provided. training provided. future training. provided on a bi-annual basis to all maintenance staff. Owner/Designer only involved in the Commissioning agent involved in Commissioning agent involved in all Multi discipline Commissioning Team Design Development No design development process. development of the design. final stages of design. stages of design. involved in all stages of design. Technical ElementsProcess Commissioning agent involved in all Multi discipline Commissioning Commissioning agent involved in Design Review No design review process. Owner/Designer review. final stages of design review. stages of design review including Team involved in all stages of design design for reliability. review including design for reliability. Reliability in Multi discipline Commissioning Team Commissioning agent reviews only Commissioning agent reviews all Submittal Review No submittal review process. Owner/Designer review submittals. major component submittals. submittals. reviews all submittals including design for reliability. Pre-functional check list are Pre-Functional Check No pre-functional or manufacturer Manufacturers check list are Pre-functional check list are Pre-functional check list are provided on all systems and building List check list are provided. followed only. provided on major system only. provided on all systems. components. Functional check list are provided No functional or manufacturer check Manufacturers check list are Functional check list are provided on Functional check list are provided on Functional Testing list are provided. followed only. major system only. all systems. on all systems and building components. O&M strategy on major systems O&M strategy on major systems Reliability O&M No O&M strategy or reliability O&M O&M strategy on all systems with no O&M strategy on all systems with only with no reliability O&M Strategy only with reliability O&M strategy Strategy strategy implemented. reliability O&M strategy integration. reliability O&M strategy integration. integration. integration. Original building and all system All building and system design, Original building and major system Original building and all system design and commissioning commissioning and retro- Documentation & No documentation or record design documents are recorded and design documents are recorded and documents are recorded and stored commissioning documents are Record Keeping keeping. stored for future reference. stored for future reference. for future reference with only major kept and continually updated as systems being updated. necessary. RESULTS / SCORECARDS Results/Scorecards O&M with reliability O&M strategies O&M procedures No O&M procedures are O&M strategies for most systems O&M strategies for all systems are O&M with reliability O&M strategies for all systems are documented and documentation documented. are documented. documented. for all systems are documented. on-going training is provided. All systems are zoned and metered All systems are zoned and metered Measurement and No measurement and verification is Major systems are zoned and All systems are zoned and metered separately. Utility usage is constantly separately. Utility usage is constantly Verification preformed. metered separately only. separately. monitored and compared to the monitored. baseline. Energy analysis and life-cycle cost Energy analysis is preformed on Energy analysis and life-cycle cost Energy analysis and life-cycle cost analysis are preformed on all Capex Energy analysis/ No energy analysis or baseline facility but Capex projects life cycle analysis are preformed only on analysis are preformed on all Capex projects. These analysis utilize Baseline analysis analysis is utilized. cost analysis are not utilized. major Capex projects. projects. baseline analysis for evaluation of results. 4200 Faber Place Drive 101 South Spring Street Charleston, SC 29405 Little Rock, AR 72201 o. 888.335.8276 o. 501.372.2900 f. 843.414.5779 www.cromwell.com www.gpallied.com