SlideShare a Scribd company logo
1 of 9
Download to read offline
11/18/2020 SNJV432@GMAIL.COM 1
RECORD KEEPING
• Appropriate records should be compiled and maintained throughout
the duration of construction projects. This creates a
contemporaneous history of what happened at what point during the
course of the project that can be referred to if necessary.
• This not only establishes a ‘memory’ or ‘paper trail’ for the project
through which activities and decisions can be reviewed, it allows for
the reconstruction, review and analysis of events and timelines
should a dispute arise. Disputes are often determined by the available
records, rather than by the facts, and so it is commercially very
important to the parties involved that good records are kept.
11/18/2020 SNJV432@GMAIL.COM 2
• There are a number of reasons for record keeping:
• Legal requirements.
• Contractual requirements.
• To control work.
• To provide data for future work.
11/18/2020 SNJV432@GMAIL.COM 3
• The extent of the record keeping required will depend on the type of
project. A balance must be maintained between keeping adequate
records in preparation for a dispute arising, and attempting to record
everything, which is can be difficult, time consuming and costly.
• Some record-keeping requirements, such as recording the minutes of
meetings for example, may be carried out at the discretion of the
individual organisation, with different frequency rates, levels of detail,
and time for which records must be kept, appropriate for different
situations. Other records may be a legal or contractual requirement,
following prescribed rules.
11/18/2020 SNJV432@GMAIL.COM 4
• For example, under the Construction Industry Scheme (CIS),
contractors must keep a record of the gross amount of each payment
invoiced by subcontractors, excluding VAT and any deductions made
from subcontractor payments. These details must be kept for at least
3 years after the end of the tax year they relate to.
• Ultimately, when the completed building is handed over to the client,
a set of record information should be passed to them so they are able
to operate the building.
11/18/2020 SNJV432@GMAIL.COM 5
• It is important that the standard of records kept is high, or they may not
provide the expected information when they are actually required. In
particular, records should be dated (including incoming records) and where
appropriate, signed, and a document management system should be in
place to allow efficient storage and retrieval.
• Information is now generally managed using specialist software, and apps
that make the preparation of records easier and more reliable are also
available. This can, for example allow records to be made on site using a
mobile phone, which are then automatically uploaded to a project
document management system.
11/18/2020 SNJV432@GMAIL.COM 6
• Increasingly, project information is prepared in the form of a building
information model (BIM), and this may include project records as well
as design and specification information. An as-built or as-constructed
building information model might be prepared on completion of
construction works, consisting of documentation, non- graphical
information and graphical information defining the delivered project.
• During operation, this might be described as an Asset Information
Model (AIM), that is, a model that provides all the data and
information related to, or required for the operation of the completed
built asset.
11/18/2020 SNJV432@GMAIL.COM 7
List of records
• A range of records that might be kept on construction projects is presented below.
• Tenders and contracts:
• Original contract tender documents.
• Tender negotiations and revisions.
• Sub-contractor tenders, contracts, purchase orders and correspondence.
• Contract administration:
• Instructions.
• Variations and estimates.
• Contractual certificates.
11/18/2020 SNJV432@GMAIL.COM 8
• Contract notices.
• Requests for information.
• Resources:
• Daily time records.
• Daily equipment use.
• Daily production logs.
• Material delivery and use.
• Labour use.
• Inventories of tools, plant and equipment.
11/18/2020 SNJV432@GMAIL.COM 9

More Related Content

What's hot

8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.pptPedadaSaikumar
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...A Makwana
 
Cost management plan
Cost management planCost management plan
Cost management planJody R Flower
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingSubash Bhattarai
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Material management on construction site
Material management on construction siteMaterial management on construction site
Material management on construction siteRonak Jain
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxssuserc0bf9b
 

What's hot (20)

8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...
 
Cost management plan
Cost management planCost management plan
Cost management plan
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Material management on construction site
Material management on construction siteMaterial management on construction site
Material management on construction site
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 

Similar to RECORD KEEPING

A630-AMK-NZA-00-Z-BIM-47118
A630-AMK-NZA-00-Z-BIM-47118A630-AMK-NZA-00-Z-BIM-47118
A630-AMK-NZA-00-Z-BIM-47118Mandeep Singh
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
City of Edmonton Permitting Presentation Spring 2019
City of Edmonton Permitting Presentation Spring 2019City of Edmonton Permitting Presentation Spring 2019
City of Edmonton Permitting Presentation Spring 2019Justin Quinn
 
Baseline Condition Assessment
Baseline Condition AssessmentBaseline Condition Assessment
Baseline Condition AssessmentGrantWhittle
 
Auditing the quality system for data integrity
Auditing the quality system for data integrityAuditing the quality system for data integrity
Auditing the quality system for data integrityJeremiah Genest
 
Fico course content
Fico course contentFico course content
Fico course contentnasimh
 
Contract matching presentation 02-11-13
Contract matching presentation  02-11-13Contract matching presentation  02-11-13
Contract matching presentation 02-11-13Danielson Samuel
 
eBUILD ERP - Software for Builders & Contractors
eBUILD ERP - Software for Builders & ContractorseBUILD ERP - Software for Builders & Contractors
eBUILD ERP - Software for Builders & ContractorsPackt Publishing
 
Deloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction SummitDeloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction Summitaakash malhotra
 
AIA BIM Contracts
AIA BIM ContractsAIA BIM Contracts
AIA BIM ContractsJairoGuzmn2
 
Notebook Manufacturing Plant Project Report 2024
Notebook Manufacturing Plant Project Report 2024Notebook Manufacturing Plant Project Report 2024
Notebook Manufacturing Plant Project Report 2024AlinaEllis1
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
RealEstatePro-Real Estate Suite for D365
RealEstatePro-Real Estate Suite for D365RealEstatePro-Real Estate Suite for D365
RealEstatePro-Real Estate Suite for D365PRAVINSATHISH
 
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid Them
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid ThemIT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid Them
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid ThemMeyers Nave
 
FED GOV CON - DOD & INTEL Conference
FED GOV CON - DOD & INTEL ConferenceFED GOV CON - DOD & INTEL Conference
FED GOV CON - DOD & INTEL ConferenceJSchaus & Associates
 
Project systems Presentation.pptx
Project systems Presentation.pptxProject systems Presentation.pptx
Project systems Presentation.pptxKattaVenkateswarlu2
 
Construction management use case by Maikel.pdf
Construction management use case by Maikel.pdfConstruction management use case by Maikel.pdf
Construction management use case by Maikel.pdfObortech
 

Similar to RECORD KEEPING (20)

A630-AMK-NZA-00-Z-BIM-47118
A630-AMK-NZA-00-Z-BIM-47118A630-AMK-NZA-00-Z-BIM-47118
A630-AMK-NZA-00-Z-BIM-47118
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
City of Edmonton Permitting Presentation Spring 2019
City of Edmonton Permitting Presentation Spring 2019City of Edmonton Permitting Presentation Spring 2019
City of Edmonton Permitting Presentation Spring 2019
 
Baseline Condition Assessment
Baseline Condition AssessmentBaseline Condition Assessment
Baseline Condition Assessment
 
Sppt chap002
Sppt chap002Sppt chap002
Sppt chap002
 
Auditing the quality system for data integrity
Auditing the quality system for data integrityAuditing the quality system for data integrity
Auditing the quality system for data integrity
 
Fico course content
Fico course contentFico course content
Fico course content
 
Contract matching presentation 02-11-13
Contract matching presentation  02-11-13Contract matching presentation  02-11-13
Contract matching presentation 02-11-13
 
eBUILD ERP - Software for Builders & Contractors
eBUILD ERP - Software for Builders & ContractorseBUILD ERP - Software for Builders & Contractors
eBUILD ERP - Software for Builders & Contractors
 
Deloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction SummitDeloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction Summit
 
AIA BIM Contracts
AIA BIM ContractsAIA BIM Contracts
AIA BIM Contracts
 
Anthony_M._Antigulas
Anthony_M._AntigulasAnthony_M._Antigulas
Anthony_M._Antigulas
 
Notebook Manufacturing Plant Project Report 2024
Notebook Manufacturing Plant Project Report 2024Notebook Manufacturing Plant Project Report 2024
Notebook Manufacturing Plant Project Report 2024
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
RealEstatePro-Real Estate Suite for D365
RealEstatePro-Real Estate Suite for D365RealEstatePro-Real Estate Suite for D365
RealEstatePro-Real Estate Suite for D365
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid Them
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid ThemIT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid Them
IT Equipment and Services Agreements: Contractual Pitfalls and How to Avoid Them
 
FED GOV CON - DOD & INTEL Conference
FED GOV CON - DOD & INTEL ConferenceFED GOV CON - DOD & INTEL Conference
FED GOV CON - DOD & INTEL Conference
 
Project systems Presentation.pptx
Project systems Presentation.pptxProject systems Presentation.pptx
Project systems Presentation.pptx
 
Construction management use case by Maikel.pdf
Construction management use case by Maikel.pdfConstruction management use case by Maikel.pdf
Construction management use case by Maikel.pdf
 

More from SANJEEV Wazir

Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONSANJEEV Wazir
 
Use of bim in project management
Use of bim in project managementUse of bim in project management
Use of bim in project managementSANJEEV Wazir
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsSANJEEV Wazir
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...SANJEEV Wazir
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation WorksSANJEEV Wazir
 
impact field work report
 impact field work report impact field work report
impact field work reportSANJEEV Wazir
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdfSANJEEV Wazir
 
How to calculate quantity of steel in slab
How to calculate quantity of steel in slabHow to calculate quantity of steel in slab
How to calculate quantity of steel in slabSANJEEV Wazir
 
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESHOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESSANJEEV Wazir
 

More from SANJEEV Wazir (20)

Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Use of bim in project management
Use of bim in project managementUse of bim in project management
Use of bim in project management
 
Lean costruction
Lean costructionLean costruction
Lean costruction
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
impact field work report
 impact field work report impact field work report
impact field work report
 
canal regulators
 canal regulators canal regulators
canal regulators
 
energy dissipators
energy dissipatorsenergy dissipators
energy dissipators
 
energy dissipators
energy dissipatorsenergy dissipators
energy dissipators
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
 
DIVERSION HEAD WORK
DIVERSION HEAD WORKDIVERSION HEAD WORK
DIVERSION HEAD WORK
 
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
 
How to calculate quantity of steel in slab
How to calculate quantity of steel in slabHow to calculate quantity of steel in slab
How to calculate quantity of steel in slab
 
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESHOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
 
Timber
TimberTimber
Timber
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

RECORD KEEPING

  • 2. RECORD KEEPING • Appropriate records should be compiled and maintained throughout the duration of construction projects. This creates a contemporaneous history of what happened at what point during the course of the project that can be referred to if necessary. • This not only establishes a ‘memory’ or ‘paper trail’ for the project through which activities and decisions can be reviewed, it allows for the reconstruction, review and analysis of events and timelines should a dispute arise. Disputes are often determined by the available records, rather than by the facts, and so it is commercially very important to the parties involved that good records are kept. 11/18/2020 SNJV432@GMAIL.COM 2
  • 3. • There are a number of reasons for record keeping: • Legal requirements. • Contractual requirements. • To control work. • To provide data for future work. 11/18/2020 SNJV432@GMAIL.COM 3
  • 4. • The extent of the record keeping required will depend on the type of project. A balance must be maintained between keeping adequate records in preparation for a dispute arising, and attempting to record everything, which is can be difficult, time consuming and costly. • Some record-keeping requirements, such as recording the minutes of meetings for example, may be carried out at the discretion of the individual organisation, with different frequency rates, levels of detail, and time for which records must be kept, appropriate for different situations. Other records may be a legal or contractual requirement, following prescribed rules. 11/18/2020 SNJV432@GMAIL.COM 4
  • 5. • For example, under the Construction Industry Scheme (CIS), contractors must keep a record of the gross amount of each payment invoiced by subcontractors, excluding VAT and any deductions made from subcontractor payments. These details must be kept for at least 3 years after the end of the tax year they relate to. • Ultimately, when the completed building is handed over to the client, a set of record information should be passed to them so they are able to operate the building. 11/18/2020 SNJV432@GMAIL.COM 5
  • 6. • It is important that the standard of records kept is high, or they may not provide the expected information when they are actually required. In particular, records should be dated (including incoming records) and where appropriate, signed, and a document management system should be in place to allow efficient storage and retrieval. • Information is now generally managed using specialist software, and apps that make the preparation of records easier and more reliable are also available. This can, for example allow records to be made on site using a mobile phone, which are then automatically uploaded to a project document management system. 11/18/2020 SNJV432@GMAIL.COM 6
  • 7. • Increasingly, project information is prepared in the form of a building information model (BIM), and this may include project records as well as design and specification information. An as-built or as-constructed building information model might be prepared on completion of construction works, consisting of documentation, non- graphical information and graphical information defining the delivered project. • During operation, this might be described as an Asset Information Model (AIM), that is, a model that provides all the data and information related to, or required for the operation of the completed built asset. 11/18/2020 SNJV432@GMAIL.COM 7
  • 8. List of records • A range of records that might be kept on construction projects is presented below. • Tenders and contracts: • Original contract tender documents. • Tender negotiations and revisions. • Sub-contractor tenders, contracts, purchase orders and correspondence. • Contract administration: • Instructions. • Variations and estimates. • Contractual certificates. 11/18/2020 SNJV432@GMAIL.COM 8
  • 9. • Contract notices. • Requests for information. • Resources: • Daily time records. • Daily equipment use. • Daily production logs. • Material delivery and use. • Labour use. • Inventories of tools, plant and equipment. 11/18/2020 SNJV432@GMAIL.COM 9