SlideShare a Scribd company logo
Reasoning the Major power disturbance
in India - 30th, 31st July 2012
Siva Prasad Katru
sivakatru@gmail.com
Contents
•   Indian power sector at a glance
•   What happened on 30th, 31st July 2012
•   Background - Power Swings, Distance relays
•   Analysis of Grid Disturbance on 30th July
•   Analysis of Grid Disturbance on 31st July
•   Role of distance relay
•   Conclusion
Indian power sector at a glance
      Grid                 MW
  Northern                 56058
  Western                  66757
  Eastern                  26838
  North               2454.94
  Eastern                                    Agra
  Southern            54898.1
                                         Gwalior
            Total 2,07,006.04
                                      Bina
  per capita annual avg.        kWh
      consumption

  India                         778
  European Union            6200
  Worldwide                 2600

Census 2001 - 44% of households
do not have access to electricity.
Mission 2012: Power for All
What happened on 30th & 31st July 2012
• On 30th July 2012, there was a grid
  disturbance in the NEW grid at 02:33:11 IST
• NR grid collapsed
• load of about 36,000 MW effected

• Another major disturbance took place on
  31st July 2012 in the NEW grid at 13:00:13
  IST
• NR, ER and NER grids collapsed
• load of about 48,000 MW effected



Major power blackout
• The outage must not be planned by the
  service provider.
• There must be at least 1,000,000 person-
  hours of disruption.
Power swings

• The rotors of synchronous machines inter-connected by AC lines
  tend to run at the same electrical speed in steady state due to the
  underlying physics of this system.

• When this system experiences small disturbances, restorative
  torques bring back the machines to synchronism (i.e., the same
  electrical speed).

• This response is an oscillatory behavior = a spring-mass system. The
  oscillations are called “swings” and are seen in practically all
  parameters including line power flows.

• For large disturbances (e.g faults, loss of critical transmission links),
  the behavior is non-linear and the electrical torques may be unable
  to bring all the generators to the same electrical speed. If this
  happens the angular difference between the generators goes on
  increasing (Transient Instability or Angular Separation). This
  causes large variations in voltage and power flow in lines.
Role of distance relay

• The impedance per mile is fairly constant
• These relays sees the impedance from the
  relay location to fault location
• Observes the values of voltage and current
• Used to identify the fault location
Analysis of Grid Disturbance on 30th July, 2012
        Committee analyzed the output of DRs, ELs, PMUs, WAFMS, SCADA data
        and reports submitted by various SLDCs , RLDCs, POWERGRID and
        generation utilities to arrive at the sequence of events

      Prior to disturbance conditions

                                                32636 MW
                                                   NR                                               1367 MW
                                                                  38322MW                             NER
                                                                                                              1314MW
NR constituents were instructed by NRLDC
                                                    Agra Gorakhpur
WRLDC also issued for reduction in generation.
                                  Zerda-Bhinmal                          Patna – Balia
                                  369MW       1055MW
                                                x                         x
                                                                     x
                                            x                        Muzaffarpur
               33024 MW                   Bina Gwalior        x
                  WR                      1450MW

                                                         Balia – Biharsharif             12452 MW
                                                                                             ER

             28053MW
                                                                                     12213MW
Analysis of Grid Disturbance on 31st July, 2012
                                                                   In the both cases, at the time of tripping of
   Internal power swings, under
                                                                   distance relay:
   frequency and overvoltage at
                                                                  • Because of Overload, voltage to current ratio
   different places lead to
                                                                     seen by the relay is low
   collapse of NR-ER-NER
                                                                  • Although there is no fault, treated it as a fault
Prior to disturbance conditions                                   • This phenomenon is called “Load
                                                                     encroachment”.
                                                29884MW
                                                   NR                                             1014 MW
                                                                 33945MW                            NER   1226MW

NR constituents were instructed by NRLDC
                                                  Agra Gorakhpur
WRLDC also issued for reduction in generation.

                                                                       Patna – Balia
                                                                        x
                                                                   x
                                            x                      Muzaffarpur
               32612 MW                   Bina Gwalior
                  WR
                                                         Balia – Biharsharif           13524 MW
                                                                                           ER
                                                 Sipat xRanchi
                                                       -
                                                 Rajgarh xRourkela
                                                         -
             28053MW
                                                                                   13179MW
References
1)   http://www.powermin.nic.in/pdf/GRID_ENQ_REP_16_8_12.pdf
2)   http://en.wikipedia.org/wiki/Electricity_sector_in_India
3)   http://www.bbc.co.uk/news/world-asia-india-19060279
4)   100 million Indonesians affected by power outage. AP
5)   "The Darkest Night". Archived from the original on 2009-05-13.
     Retrieved 2010-10-08.
6)   The great 2003 North America blackout. CBC
7)   Italy's blackout raises questions. The Guardian
8)   The 'Great Northeastern Blackout' of 1965. CBC

More Related Content

What's hot

A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
Rohitashav Goyal
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
Arijit Basu
 
46584589 substation-design-data
46584589 substation-design-data46584589 substation-design-data
46584589 substation-design-data
Sailappan Sivagamasundari
 
Industrial Training Presentation
Industrial Training PresentationIndustrial Training Presentation
Industrial Training Presentation
kumarmayursinha
 
Emergingtrends
EmergingtrendsEmergingtrends
Emergingtrends
mkanth
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
SIIT, Jaipur
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
Asafak Husain
 
Report
ReportReport
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
giriraj bairwa
 
Step up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor DriveStep up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor Drive
Editor IJMTER
 
Electrical System in Jordan
Electrical System in JordanElectrical System in Jordan
Electrical System in Jordan
Osama Al-Nabulsi
 
My training
My trainingMy training
My training
skysunilyadav
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
Sanjay Kumar Sharma
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
Prannay Kumar Giri
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
farazrafi87
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
Dashrath047
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
Pankaj Rawal
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
Mayur Dhanaji Rane
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
Subhash Mahla
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments
Anuj Gupta
 

What's hot (20)

A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
46584589 substation-design-data
46584589 substation-design-data46584589 substation-design-data
46584589 substation-design-data
 
Industrial Training Presentation
Industrial Training PresentationIndustrial Training Presentation
Industrial Training Presentation
 
Emergingtrends
EmergingtrendsEmergingtrends
Emergingtrends
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
 
Report
ReportReport
Report
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 
Step up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor DriveStep up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor Drive
 
Electrical System in Jordan
Electrical System in JordanElectrical System in Jordan
Electrical System in Jordan
 
My training
My trainingMy training
My training
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments
 

Similar to Reasoning the recent power blackouts in India

1.2 power plant module2 batch3
1.2 power plant module2 batch31.2 power plant module2 batch3
1.2 power plant module2 batch3
daisydhei
 
Training report on DVC
Training report on DVCTraining report on DVC
Training report on DVC
Linkon Khan
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
Vaibhav Jain
 
Ricky sulaniya
Ricky sulaniyaRicky sulaniya
Ricky sulaniya
Ricky Sulaniya
 
Nuclear energy sop_14
Nuclear energy sop_14Nuclear energy sop_14
Nuclear energy sop_14
Anas Vj
 
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Dharmpal Yadav
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistan
Muhammad Imran Azam
 
Jitendra final ppt
Jitendra final pptJitendra final ppt
Jitendra final ppt
jitendra9694
 
GENERATOR PROTECTIONS
GENERATOR PROTECTIONS GENERATOR PROTECTIONS
GENERATOR PROTECTIONS
DHAVALKUMAR JULASANA
 
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Chandan Kumar
 
132 kv gss sitapura jaipur by mirza
132 kv gss  sitapura jaipur by mirza132 kv gss  sitapura jaipur by mirza
132 kv gss sitapura jaipur by mirza
MIRZA SARMAD BAIG
 
Nuclear power plant FUNDAMENTAL
Nuclear power plant FUNDAMENTALNuclear power plant FUNDAMENTAL
Nuclear power plant FUNDAMENTAL
AG04894
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
IPPAI
 
132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur
kishankky
 
Grid PPT-1 and 2 (1).pptx
Grid PPT-1 and 2 (1).pptxGrid PPT-1 and 2 (1).pptx
Grid PPT-1 and 2 (1).pptx
SudipDutta53
 
Power System electrical and electronics .pptx
Power System electrical and electronics .pptxPower System electrical and electronics .pptx
Power System electrical and electronics .pptx
MUKULKUMAR210
 
Structure of Transmission System in India
Structure of Transmission System in IndiaStructure of Transmission System in India
Structure of Transmission System in India
Himanshu Pathak
 
southern grid
southern grid southern grid
southern grid
Molla Morshad
 
pptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdfpptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdf
Thien Phan Bản
 
Kumaresh_ISLANDING.pptx
Kumaresh_ISLANDING.pptxKumaresh_ISLANDING.pptx
Kumaresh_ISLANDING.pptx
Rishikabhakat
 

Similar to Reasoning the recent power blackouts in India (20)

1.2 power plant module2 batch3
1.2 power plant module2 batch31.2 power plant module2 batch3
1.2 power plant module2 batch3
 
Training report on DVC
Training report on DVCTraining report on DVC
Training report on DVC
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
Ricky sulaniya
Ricky sulaniyaRicky sulaniya
Ricky sulaniya
 
Nuclear energy sop_14
Nuclear energy sop_14Nuclear energy sop_14
Nuclear energy sop_14
 
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistan
 
Jitendra final ppt
Jitendra final pptJitendra final ppt
Jitendra final ppt
 
GENERATOR PROTECTIONS
GENERATOR PROTECTIONS GENERATOR PROTECTIONS
GENERATOR PROTECTIONS
 
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...
 
132 kv gss sitapura jaipur by mirza
132 kv gss  sitapura jaipur by mirza132 kv gss  sitapura jaipur by mirza
132 kv gss sitapura jaipur by mirza
 
Nuclear power plant FUNDAMENTAL
Nuclear power plant FUNDAMENTALNuclear power plant FUNDAMENTAL
Nuclear power plant FUNDAMENTAL
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
 
132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur
 
Grid PPT-1 and 2 (1).pptx
Grid PPT-1 and 2 (1).pptxGrid PPT-1 and 2 (1).pptx
Grid PPT-1 and 2 (1).pptx
 
Power System electrical and electronics .pptx
Power System electrical and electronics .pptxPower System electrical and electronics .pptx
Power System electrical and electronics .pptx
 
Structure of Transmission System in India
Structure of Transmission System in IndiaStructure of Transmission System in India
Structure of Transmission System in India
 
southern grid
southern grid southern grid
southern grid
 
pptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdfpptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdf
 
Kumaresh_ISLANDING.pptx
Kumaresh_ISLANDING.pptxKumaresh_ISLANDING.pptx
Kumaresh_ISLANDING.pptx
 

Recently uploaded

Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.
IsmaelVazquez38
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
zuzanka
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
 
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
TechSoup
 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
nitinpv4ai
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
سمير بسيوني
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
Nguyen Thanh Tu Collection
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
PsychoTech Services
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
 
How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17
Celine George
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Henry Hollis
 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
nitinpv4ai
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
Payaamvohra1
 
How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
Celine George
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 

Recently uploaded (20)

Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
 
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
 
How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
 
How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 

Reasoning the recent power blackouts in India

  • 1. Reasoning the Major power disturbance in India - 30th, 31st July 2012 Siva Prasad Katru sivakatru@gmail.com
  • 2. Contents • Indian power sector at a glance • What happened on 30th, 31st July 2012 • Background - Power Swings, Distance relays • Analysis of Grid Disturbance on 30th July • Analysis of Grid Disturbance on 31st July • Role of distance relay • Conclusion
  • 3. Indian power sector at a glance Grid MW Northern 56058 Western 66757 Eastern 26838 North 2454.94 Eastern Agra Southern 54898.1 Gwalior Total 2,07,006.04 Bina per capita annual avg. kWh consumption India 778 European Union 6200 Worldwide 2600 Census 2001 - 44% of households do not have access to electricity. Mission 2012: Power for All
  • 4. What happened on 30th & 31st July 2012 • On 30th July 2012, there was a grid disturbance in the NEW grid at 02:33:11 IST • NR grid collapsed • load of about 36,000 MW effected • Another major disturbance took place on 31st July 2012 in the NEW grid at 13:00:13 IST • NR, ER and NER grids collapsed • load of about 48,000 MW effected Major power blackout • The outage must not be planned by the service provider. • There must be at least 1,000,000 person- hours of disruption.
  • 5. Power swings • The rotors of synchronous machines inter-connected by AC lines tend to run at the same electrical speed in steady state due to the underlying physics of this system. • When this system experiences small disturbances, restorative torques bring back the machines to synchronism (i.e., the same electrical speed). • This response is an oscillatory behavior = a spring-mass system. The oscillations are called “swings” and are seen in practically all parameters including line power flows. • For large disturbances (e.g faults, loss of critical transmission links), the behavior is non-linear and the electrical torques may be unable to bring all the generators to the same electrical speed. If this happens the angular difference between the generators goes on increasing (Transient Instability or Angular Separation). This causes large variations in voltage and power flow in lines.
  • 6. Role of distance relay • The impedance per mile is fairly constant • These relays sees the impedance from the relay location to fault location • Observes the values of voltage and current • Used to identify the fault location
  • 7. Analysis of Grid Disturbance on 30th July, 2012 Committee analyzed the output of DRs, ELs, PMUs, WAFMS, SCADA data and reports submitted by various SLDCs , RLDCs, POWERGRID and generation utilities to arrive at the sequence of events Prior to disturbance conditions 32636 MW NR 1367 MW 38322MW NER 1314MW NR constituents were instructed by NRLDC Agra Gorakhpur WRLDC also issued for reduction in generation. Zerda-Bhinmal Patna – Balia 369MW 1055MW x x x x Muzaffarpur 33024 MW Bina Gwalior x WR 1450MW Balia – Biharsharif 12452 MW ER 28053MW 12213MW
  • 8. Analysis of Grid Disturbance on 31st July, 2012 In the both cases, at the time of tripping of Internal power swings, under distance relay: frequency and overvoltage at • Because of Overload, voltage to current ratio different places lead to seen by the relay is low collapse of NR-ER-NER • Although there is no fault, treated it as a fault Prior to disturbance conditions • This phenomenon is called “Load encroachment”. 29884MW NR 1014 MW 33945MW NER 1226MW NR constituents were instructed by NRLDC Agra Gorakhpur WRLDC also issued for reduction in generation. Patna – Balia x x x Muzaffarpur 32612 MW Bina Gwalior WR Balia – Biharsharif 13524 MW ER Sipat xRanchi - Rajgarh xRourkela - 28053MW 13179MW
  • 9. References 1) http://www.powermin.nic.in/pdf/GRID_ENQ_REP_16_8_12.pdf 2) http://en.wikipedia.org/wiki/Electricity_sector_in_India 3) http://www.bbc.co.uk/news/world-asia-india-19060279 4) 100 million Indonesians affected by power outage. AP 5) "The Darkest Night". Archived from the original on 2009-05-13. Retrieved 2010-10-08. 6) The great 2003 North America blackout. CBC 7) Italy's blackout raises questions. The Guardian 8) The 'Great Northeastern Blackout' of 1965. CBC