SlideShare a Scribd company logo
6/21/2016
Tom Burnett & Nikhil Kumar
Intertek
Risk Based Inspection for Power Plants
AWARE UGM 2016
222
Evolving Business Models
Centralized 
Distributed
CapEx  OpEx
Static/Dumb 
Connected/Smart
3
Intertek Smart Platform
AWARE + CostCom
Condition
Assessment
Failure
Analysis/
BTFR
High Energy
Piping
Flow
Accelerated
Corrosion
Power Plant
Cycling
Fitness for
Service
Econometrics
Life Extension
(Risk
Adjusted)
4
Why do RBI
• Improve plant and worker safety – Avoidance of catastrophic failure
• Increased availability and reliability of equipment
• Better understanding of equipment and processes
• Focus resources in correct areas
• Save money
• Improved turnaround planning
• Specific inspection and maintenance activities
• Avoid failures and downtime
• Detailed equipment inspection plans
• Follow industry best practices
• Make informed management decisions
5
Hazard versus Risk
Hazard Risk
6
What is Risk
Cost
Reliability
Reliability Analysis
Total Cost
Outage Cost
Capital & Maintenance
Cost
Risk = (Likelihood of Failure) x (Consequence of Failure)
7
What about API compliance?
API RP 580 was intended to provide guidance and provide basic elements for
developing and implementing a RBI program. It is an introduction to concepts and
principles of RBI, with the intent of producing a documented methodology.
AWARE is fully compliant with these guidelines.
API 581 has been updated over time and now includes step by step analysis
procedures similar to ASME FFS-1 as well as ASME Section VIII
8
Why was RBI Developed
• Most pressure equipment contain flaws
• Most flaws are innocuous - Don’t cause problems
• Few flaws cause catastrophic failure
• Must find (inspect) those critical flaws in high risk service - Cost effectively
• Typically 80% of the risk is associated with < 20% of the pressure
equipment
Loss of containment events resulting in major
insurance losses in petrochemical process plants.
Only about half of the causes of loss of containment
can be influenced by inspection activities (41% of
mechanical failures plus some portion of the “unknown”
failures). Other mitigation actions are required.
9
• As with other industries, the goal for
the electric generation industry as a
whole is to predict and prevent
failures before they occur.
• The implementations rely on both
Qualitative Risk Analysis, as well as
a Quantitative Risk Analysis, which
includes in-depth reliability and
financial analysis.
• Level I – Qualitative risk, simple
• Level II – Qualitative risk analysis,
supplemented with quantitative
methods
• Level III – Quantitative risk analysis,
in depth analysis
RBI – Qualitative or Quantitative?
Rank
Process
Units
Review and
Adjust COF
Rating
Identify
Consequence
Modifiers
Calculate
Preliminary
Consequence Index
Gather Data for
Consequence
Estimate
Review of
Process and
Operational Data
Consequence
of Failure
(COF)
Risk Rank = COF
x LOF
Development of Equipment
Worksheet
Equipment
Documentation
Review
Review and
Adjust LOF
Rating
Calculate Initial
Damage Rank
Identify
Failure
Modes
Identify Potential
Damage
Mechanisms
Identify Industry Specific
Unit Exp.(Interviews -
Process, Maint.
Engrs./Insp.)
Likelihood of
Failure (LOF)
Risk
Directed
Inspection
Plan -
Scope &
10
What does inspection planning involve:
• Determining risk in terms of
likelihood of failure and
consequence of failure
• Inspection scope, schedule, and
cost planning and risk reduction
estimations
• Presentation of the results in
terms of a risk matrix
• Evaluation of the costs and risk
reduction of countermeasures
Inspection Planning
11
Intertek Approach
AWARE
Decision
Analysis
No detection +
No Repair
Equipment
Failure
Equipment
Risk
Assessment
No detection +
No Repair
Detection + No
Repair
Detection +
Repair
Detection + No
Repair
Equipment
Failure
Equipment
Risk
Assessment
No detection +
No Repair
Detection + No
Repair
Detection +
Repair
No detection +
No Repair
Equipment
Failure
Equipment
Risk
AssessmentDetection +
Repair
Risk
Mitigation
Plan
Inspection
Plan
Risk Matrix
Data
Analysis
[Determine
POF/COF]
Data Input
in AWARE
Data
Collection
12
Factors:
• Incorrect Design
• Incorrect Material (size, schedule,
metallurgy)
• Construction Defects (lay-up,
welds)
• In Service Induced Defects
(corrosion, erosion, fatigue, creep,
creep/fatigue, etc.)
• Cycling
• Operational and Maintenance
Caused Defects
• Define Damage Potential
• Identify Potential Failure Mechanisms
• Determine Potential Failure Modes for
Damage Mechanisms
• Assign Damage Rank Based on:
• Possibility of Occurrence
• Failure Mode if Undetected
• Consider Mitigating/Aggravating Factors
and Assign an Overall Likelihood of Failure
Rank to Component Considering:
• Corrosion, erosion, fatigue, creep,
creep/fatigue, etc.
• Operating Considerations
• Thermal Cycles, Stress Cycles,
Transients and Off Normal Operations
• Inspection Considerations - Scope,
Frequency, and Technique
• Quality of Documentation and Plant
Experience
Likelihood of Failure
13
− Reliability Models for
certain key equipment
(High Energy Piping or
Pressure Vessels),
where damage
mechanisms and
uncertainties are well
understood and
statistical distributions
are available. In this
scenario, the model uses
the following equation to
determine POF:
• 𝑃𝑓 𝑡 = 𝑔𝑓𝑓. 𝐷𝑓 𝑡 . 𝐹 𝑀,
where 𝑃𝑓 𝑡 is the function
of a generic failure
frequency 𝑔𝑓𝑓, damage
factor 𝐷𝑓(𝑡), and a
management system
factor 𝐹 𝑀
− Statistical Models. These
models are based on
generic data collected
either using frequencies
available in the AWARE
database or other models
developed by Intertek
Engineering. We will also
rely on EPRI data to
develop and determine the
POF.
• Where appropriate, two
parameter Weibull models
will be used to estimate
failure frequency, 𝑃𝑓 𝑡 =
1 − exp[−
𝑡
𝐶𝐿′
𝐵
] ; where:
CL’ is the updated
characteristic life and B is the
shape factor
• For some key boiler pressure
parts Intertek’s probabilistic
failure rate damage models
such as TUBETECH or
SAFESEAM, or SAFEGIRTH
will be used to estimate the
likelihood (i.e., probability,
frequency) of failure
− Expert Judgment. will be
relied upon when the
information on likely
damage mechanism or
failure frequency is
found inadequate.
Likelihood of Failure
14
Possible Consequence:
(a) formation of a vapor cloud that could
ignite, causing injury and equipment
damage
(b) release of a toxic chemical that could
cause health problems
(c) a spill that could cause environmental
damage
(d) a rapid release of superheated steam
that could cause damage and injury
(e) a forced unit shutdown that could
have an adverse economic impact
(f) minimal safety, health, environmental,
and/or economic impact
• Calculate Consequence Value
• Worst Case Pressure &
Temperature
• Volume of Contained Fluid/Gas
• Density Factor
• NFPA Factors (Flammability,
Toxicity, Reactivity, Other)
• Assign Consequence Rank to
Component Considering
Mitigating/Aggravating Factors
• Location Relative to Other
Equipment
• Location Relative to Concentrations
of Personnel
• Environmental Factors (Reportable
Release Quantities)
Consequence of Failure
15
• Calculate Preliminary Consequence
Value (PCV)
• Product of Worst Case: Temperature,
Volume, Pressure and Density
factors.
• Sum of MSDS Factors: Flammability,
Toxicity, Reactivity, Other (steam).
• Final Product (PCV)
• Modify PCV by considering Mitigating,
Aggravating Factors
• Location Relative to Other Equipment
• Location Relative to Concentrations of
Personnel
• Environmental Factors (Reportable
Release Quantities)
• Fire detection and suppression
devices
Estimating Consequence
Four Categories Based Consistent With
Industry Approach
Consequence
of Component
Failure
Considerable 1
Serious 2
Some 3
Minor or No Impact on Personnel 4
Rank Consequence Based on
Potential For Harm to Site
Personnel & Environment
16
RBI pitfalls
RBI will not compensate for
• inaccurate or missing information
• inadequate design or faulty equipment
• improper installation and/or operation
• operating outside the acceptable design envelope
• not effectively implementing the inspection plan
• lack of qualified personnel or team work
• lack of sound engineering or operational judgment
• failure to promptly take corrective action or implement appropriate mitigation
strategies
17
Risk Management
Reducing likelihood of failure is not only restricted to inspections:
• Inspection and Maintenance
• Understanding damage
• Correct NDE techniques
• MOC/Record Keeping/Report
• Repair, Replace, Control
• Operational Controls
• Online Monitoring
• Materials
RBI focuses on “inspectable risk”. RBI is not intended to replace
other practices that have proven satisfactory or substitute for the
judgment of a responsible, qualified inspector or engineer.
18
Life Optimization Program
• What is Intertek’s AIM Life
Optimization Program:
• API 580 Compliant
• System Risk Analysis Tool
• Justification for future maintenance
costs and maintenance planning aid
• A Living document
• Flexible and adaptable to changing
management and operations
• Easy to use and inexpensive, with a
quick ROI.
A typical RBI implementation results in an inspection plan as the primary output. Instead, Intertek’s program
goes beyond the basic requirements of RBI and its objectives are:
• Organizing and maintaining key inspection and overhaul reports from past years
• Developing inspection and real-time data acquisition plans needed to assess equipment health
• Developing a database structure to organize the vast data in a way that is easily retrieved and
disseminated

More Related Content

What's hot

Risk Solutions for the Manager
Risk Solutions for the ManagerRisk Solutions for the Manager
Risk Solutions for the Manager
Edwin A Merrick
 
ADEPP Monitor & Risk Based Design
ADEPP Monitor & Risk Based DesignADEPP Monitor & Risk Based Design
ADEPP Monitor & Risk Based DesignFabienne Salimi
 
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical IntegrityWebinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
Stork
 
Introduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBIIntroduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBI
Edwin A Merrick
 
ADEPP &amp; Other Software
ADEPP &amp; Other SoftwareADEPP &amp; Other Software
ADEPP &amp; Other SoftwareFabienne Salimi
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process Safety
Chandrashekhar Kulkarni
 
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaakingTcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
Mintra Trainingportal - Training for the Oil and Gas Industry
 
Simmco Presentation
Simmco PresentationSimmco Presentation
Simmco Presentation
simmco
 
Managing your OnStream Inspection Program and External vs Internal inspections
Managing your OnStream Inspection Program and External vs Internal inspectionsManaging your OnStream Inspection Program and External vs Internal inspections
Managing your OnStream Inspection Program and External vs Internal inspections
Edwin A Merrick
 
Basic plc course
Basic plc course Basic plc course
Basic plc course
Ausinet Training
 
Risk Based Design &amp; SCE
Risk Based Design &amp; SCERisk Based Design &amp; SCE
Risk Based Design &amp; SCEadepp
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisAnas Momen
 
20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R SargeantRoy Sargeant
 
Ocs training calendar 2022
Ocs training calendar 2022Ocs training calendar 2022
Ocs training calendar 2022
Muanisa Waras
 

What's hot (18)

Risk Solutions for the Manager
Risk Solutions for the ManagerRisk Solutions for the Manager
Risk Solutions for the Manager
 
kshitij_resume_Ln
kshitij_resume_Lnkshitij_resume_Ln
kshitij_resume_Ln
 
ADEPP Monitor & Risk Based Design
ADEPP Monitor & Risk Based DesignADEPP Monitor & Risk Based Design
ADEPP Monitor & Risk Based Design
 
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical IntegrityWebinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
 
Introduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBIIntroduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBI
 
ADEPP &amp; Other Software
ADEPP &amp; Other SoftwareADEPP &amp; Other Software
ADEPP &amp; Other Software
 
ADEPP Training 2009
ADEPP Training 2009ADEPP Training 2009
ADEPP Training 2009
 
CV
CVCV
CV
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process Safety
 
UAV flyer
UAV flyerUAV flyer
UAV flyer
 
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaakingTcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
Tcd 2014 onsdag_03 ocean rig_presight_tp i risikoovervaaking
 
Simmco Presentation
Simmco PresentationSimmco Presentation
Simmco Presentation
 
Managing your OnStream Inspection Program and External vs Internal inspections
Managing your OnStream Inspection Program and External vs Internal inspectionsManaging your OnStream Inspection Program and External vs Internal inspections
Managing your OnStream Inspection Program and External vs Internal inspections
 
Basic plc course
Basic plc course Basic plc course
Basic plc course
 
Risk Based Design &amp; SCE
Risk Based Design &amp; SCERisk Based Design &amp; SCE
Risk Based Design &amp; SCE
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
 
20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant20150426-LinkedIn_CV - R Sargeant
20150426-LinkedIn_CV - R Sargeant
 
Ocs training calendar 2022
Ocs training calendar 2022Ocs training calendar 2022
Ocs training calendar 2022
 

Viewers also liked

ROPA DE DEPORTE
ROPA DE DEPORTEROPA DE DEPORTE
ROPA DE DEPORTE
rouse22
 
Autmotive Technician Career Fair Powerpoint with Video
Autmotive Technician Career Fair Powerpoint with VideoAutmotive Technician Career Fair Powerpoint with Video
Autmotive Technician Career Fair Powerpoint with VideoQueena Poon
 
Jeg vil ha politikere med absolutte krav til barnehagene!
Jeg vil ha politikere med absolutte krav til barnehagene!Jeg vil ha politikere med absolutte krav til barnehagene!
Jeg vil ha politikere med absolutte krav til barnehagene!Lars Grimstad
 
INSIDE OUT FINAL ARTICLE 2016
INSIDE OUT FINAL ARTICLE 2016INSIDE OUT FINAL ARTICLE 2016
INSIDE OUT FINAL ARTICLE 2016Helen Culhane
 
environmental impact assessment(919857132323)Kira 3
environmental impact assessment(919857132323)Kira 3environmental impact assessment(919857132323)Kira 3
environmental impact assessment(919857132323)Kira 3
MANOJ THAKUR
 
Electric Vehicle University - 210a EV BATTERY TECHNOLOGY
Electric Vehicle University - 210a EV BATTERY TECHNOLOGYElectric Vehicle University - 210a EV BATTERY TECHNOLOGY
Electric Vehicle University - 210a EV BATTERY TECHNOLOGY
EVANNEX Aftermarket Tesla Accessories
 
Roles and Functions of Educational Technology in the 21st Century Education
Roles and Functions of Educational Technology in the 21st Century EducationRoles and Functions of Educational Technology in the 21st Century Education
Roles and Functions of Educational Technology in the 21st Century Education
Kie Ibano
 
3 page Fluor Stork brochure
3 page Fluor Stork brochure3 page Fluor Stork brochure
3 page Fluor Stork brochureRobert Bonner
 
Sociaal Economische Scan Rijk van Nijmegen
Sociaal Economische Scan Rijk van NijmegenSociaal Economische Scan Rijk van Nijmegen
Sociaal Economische Scan Rijk van Nijmegen
RvN2025
 
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
RvN2025
 
Мастер - класс технологии критического мышления: "Кластер".
Мастер - класс технологии критического мышления: "Кластер".Мастер - класс технологии критического мышления: "Кластер".
Мастер - класс технологии критического мышления: "Кластер".
diana diana
 

Viewers also liked (12)

ROPA DE DEPORTE
ROPA DE DEPORTEROPA DE DEPORTE
ROPA DE DEPORTE
 
Autmotive Technician Career Fair Powerpoint with Video
Autmotive Technician Career Fair Powerpoint with VideoAutmotive Technician Career Fair Powerpoint with Video
Autmotive Technician Career Fair Powerpoint with Video
 
Jeg vil ha politikere med absolutte krav til barnehagene!
Jeg vil ha politikere med absolutte krav til barnehagene!Jeg vil ha politikere med absolutte krav til barnehagene!
Jeg vil ha politikere med absolutte krav til barnehagene!
 
INSIDE OUT FINAL ARTICLE 2016
INSIDE OUT FINAL ARTICLE 2016INSIDE OUT FINAL ARTICLE 2016
INSIDE OUT FINAL ARTICLE 2016
 
environmental impact assessment(919857132323)Kira 3
environmental impact assessment(919857132323)Kira 3environmental impact assessment(919857132323)Kira 3
environmental impact assessment(919857132323)Kira 3
 
Electric Vehicle University - 210a EV BATTERY TECHNOLOGY
Electric Vehicle University - 210a EV BATTERY TECHNOLOGYElectric Vehicle University - 210a EV BATTERY TECHNOLOGY
Electric Vehicle University - 210a EV BATTERY TECHNOLOGY
 
Roles and Functions of Educational Technology in the 21st Century Education
Roles and Functions of Educational Technology in the 21st Century EducationRoles and Functions of Educational Technology in the 21st Century Education
Roles and Functions of Educational Technology in the 21st Century Education
 
3 page Fluor Stork brochure
3 page Fluor Stork brochure3 page Fluor Stork brochure
3 page Fluor Stork brochure
 
Sociaal Economische Scan Rijk van Nijmegen
Sociaal Economische Scan Rijk van NijmegenSociaal Economische Scan Rijk van Nijmegen
Sociaal Economische Scan Rijk van Nijmegen
 
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
Nieuwsbrief RvN2025 nr. 6 - 14 oktober 2016
 
cv-eok
cv-eokcv-eok
cv-eok
 
Мастер - класс технологии критического мышления: "Кластер".
Мастер - класс технологии критического мышления: "Кластер".Мастер - класс технологии критического мышления: "Кластер".
Мастер - класс технологии критического мышления: "Кластер".
 

Similar to RBI for Power Generation

Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
aashir14
 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered Maintenance
Nafis Ahmad
 
Preventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.pptPreventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.ppt
Mamoonurrasheed9
 
Rbi
RbiRbi
13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections
ssusereb347d
 
Root Cause Analysis .pdf
Root Cause Analysis .pdfRoot Cause Analysis .pdf
Root Cause Analysis .pdf
ssuser089410
 
Root Cause Analysis.pdf
Root Cause Analysis.pdfRoot Cause Analysis.pdf
Root Cause Analysis.pdf
WaheebAlkubati2
 
Reliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During OperationsReliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During Operations
Lloyd's Register Energy
 
Operational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss PreventionOperational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss Prevention
Michael Marshall, PE
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...Verhaert Masters in Innovation
 
SGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdfSGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdf
MuhammadNasirAbbas4
 
Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Mike Poland, CMRP
 
computer system validation
computer system validationcomputer system validation
computer system validation
Gopal Patel
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
Prashant Rasekar
 
On the nature of FMECA... An introduction
On the nature of FMECA... An introductionOn the nature of FMECA... An introduction
On the nature of FMECA... An introduction
MartGerrand
 
Preventive Maintenance Process and Program
Preventive Maintenance Process and ProgramPreventive Maintenance Process and Program
Preventive Maintenance Process and Program
Ricky Smith CMRP
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategy
gumma alsgier
 
EESS 2018 Day 1 - Tim Gray
EESS 2018 Day 1 - Tim GrayEESS 2018 Day 1 - Tim Gray
EESS 2018 Day 1 - Tim Gray
NSW Environment and Planning
 

Similar to RBI for Power Generation (20)

Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered Maintenance
 
Preventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.pptPreventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.ppt
 
Rbi
RbiRbi
Rbi
 
13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections
 
Root Cause Analysis .pdf
Root Cause Analysis .pdfRoot Cause Analysis .pdf
Root Cause Analysis .pdf
 
Root Cause Analysis.pdf
Root Cause Analysis.pdfRoot Cause Analysis.pdf
Root Cause Analysis.pdf
 
Reliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During OperationsReliability Levels of Subsea Production Systems During Operations
Reliability Levels of Subsea Production Systems During Operations
 
Operational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss PreventionOperational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss Prevention
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
 
SGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdfSGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdf
 
SBP
SBPSBP
SBP
 
Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.
 
RCM
RCMRCM
RCM
 
computer system validation
computer system validationcomputer system validation
computer system validation
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
 
On the nature of FMECA... An introduction
On the nature of FMECA... An introductionOn the nature of FMECA... An introduction
On the nature of FMECA... An introduction
 
Preventive Maintenance Process and Program
Preventive Maintenance Process and ProgramPreventive Maintenance Process and Program
Preventive Maintenance Process and Program
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategy
 
EESS 2018 Day 1 - Tim Gray
EESS 2018 Day 1 - Tim GrayEESS 2018 Day 1 - Tim Gray
EESS 2018 Day 1 - Tim Gray
 

RBI for Power Generation

  • 1. 6/21/2016 Tom Burnett & Nikhil Kumar Intertek Risk Based Inspection for Power Plants AWARE UGM 2016
  • 2. 222 Evolving Business Models Centralized  Distributed CapEx  OpEx Static/Dumb  Connected/Smart
  • 3. 3 Intertek Smart Platform AWARE + CostCom Condition Assessment Failure Analysis/ BTFR High Energy Piping Flow Accelerated Corrosion Power Plant Cycling Fitness for Service Econometrics Life Extension (Risk Adjusted)
  • 4. 4 Why do RBI • Improve plant and worker safety – Avoidance of catastrophic failure • Increased availability and reliability of equipment • Better understanding of equipment and processes • Focus resources in correct areas • Save money • Improved turnaround planning • Specific inspection and maintenance activities • Avoid failures and downtime • Detailed equipment inspection plans • Follow industry best practices • Make informed management decisions
  • 6. 6 What is Risk Cost Reliability Reliability Analysis Total Cost Outage Cost Capital & Maintenance Cost Risk = (Likelihood of Failure) x (Consequence of Failure)
  • 7. 7 What about API compliance? API RP 580 was intended to provide guidance and provide basic elements for developing and implementing a RBI program. It is an introduction to concepts and principles of RBI, with the intent of producing a documented methodology. AWARE is fully compliant with these guidelines. API 581 has been updated over time and now includes step by step analysis procedures similar to ASME FFS-1 as well as ASME Section VIII
  • 8. 8 Why was RBI Developed • Most pressure equipment contain flaws • Most flaws are innocuous - Don’t cause problems • Few flaws cause catastrophic failure • Must find (inspect) those critical flaws in high risk service - Cost effectively • Typically 80% of the risk is associated with < 20% of the pressure equipment Loss of containment events resulting in major insurance losses in petrochemical process plants. Only about half of the causes of loss of containment can be influenced by inspection activities (41% of mechanical failures plus some portion of the “unknown” failures). Other mitigation actions are required.
  • 9. 9 • As with other industries, the goal for the electric generation industry as a whole is to predict and prevent failures before they occur. • The implementations rely on both Qualitative Risk Analysis, as well as a Quantitative Risk Analysis, which includes in-depth reliability and financial analysis. • Level I – Qualitative risk, simple • Level II – Qualitative risk analysis, supplemented with quantitative methods • Level III – Quantitative risk analysis, in depth analysis RBI – Qualitative or Quantitative? Rank Process Units Review and Adjust COF Rating Identify Consequence Modifiers Calculate Preliminary Consequence Index Gather Data for Consequence Estimate Review of Process and Operational Data Consequence of Failure (COF) Risk Rank = COF x LOF Development of Equipment Worksheet Equipment Documentation Review Review and Adjust LOF Rating Calculate Initial Damage Rank Identify Failure Modes Identify Potential Damage Mechanisms Identify Industry Specific Unit Exp.(Interviews - Process, Maint. Engrs./Insp.) Likelihood of Failure (LOF) Risk Directed Inspection Plan - Scope &
  • 10. 10 What does inspection planning involve: • Determining risk in terms of likelihood of failure and consequence of failure • Inspection scope, schedule, and cost planning and risk reduction estimations • Presentation of the results in terms of a risk matrix • Evaluation of the costs and risk reduction of countermeasures Inspection Planning
  • 11. 11 Intertek Approach AWARE Decision Analysis No detection + No Repair Equipment Failure Equipment Risk Assessment No detection + No Repair Detection + No Repair Detection + Repair Detection + No Repair Equipment Failure Equipment Risk Assessment No detection + No Repair Detection + No Repair Detection + Repair No detection + No Repair Equipment Failure Equipment Risk AssessmentDetection + Repair Risk Mitigation Plan Inspection Plan Risk Matrix Data Analysis [Determine POF/COF] Data Input in AWARE Data Collection
  • 12. 12 Factors: • Incorrect Design • Incorrect Material (size, schedule, metallurgy) • Construction Defects (lay-up, welds) • In Service Induced Defects (corrosion, erosion, fatigue, creep, creep/fatigue, etc.) • Cycling • Operational and Maintenance Caused Defects • Define Damage Potential • Identify Potential Failure Mechanisms • Determine Potential Failure Modes for Damage Mechanisms • Assign Damage Rank Based on: • Possibility of Occurrence • Failure Mode if Undetected • Consider Mitigating/Aggravating Factors and Assign an Overall Likelihood of Failure Rank to Component Considering: • Corrosion, erosion, fatigue, creep, creep/fatigue, etc. • Operating Considerations • Thermal Cycles, Stress Cycles, Transients and Off Normal Operations • Inspection Considerations - Scope, Frequency, and Technique • Quality of Documentation and Plant Experience Likelihood of Failure
  • 13. 13 − Reliability Models for certain key equipment (High Energy Piping or Pressure Vessels), where damage mechanisms and uncertainties are well understood and statistical distributions are available. In this scenario, the model uses the following equation to determine POF: • 𝑃𝑓 𝑡 = 𝑔𝑓𝑓. 𝐷𝑓 𝑡 . 𝐹 𝑀, where 𝑃𝑓 𝑡 is the function of a generic failure frequency 𝑔𝑓𝑓, damage factor 𝐷𝑓(𝑡), and a management system factor 𝐹 𝑀 − Statistical Models. These models are based on generic data collected either using frequencies available in the AWARE database or other models developed by Intertek Engineering. We will also rely on EPRI data to develop and determine the POF. • Where appropriate, two parameter Weibull models will be used to estimate failure frequency, 𝑃𝑓 𝑡 = 1 − exp[− 𝑡 𝐶𝐿′ 𝐵 ] ; where: CL’ is the updated characteristic life and B is the shape factor • For some key boiler pressure parts Intertek’s probabilistic failure rate damage models such as TUBETECH or SAFESEAM, or SAFEGIRTH will be used to estimate the likelihood (i.e., probability, frequency) of failure − Expert Judgment. will be relied upon when the information on likely damage mechanism or failure frequency is found inadequate. Likelihood of Failure
  • 14. 14 Possible Consequence: (a) formation of a vapor cloud that could ignite, causing injury and equipment damage (b) release of a toxic chemical that could cause health problems (c) a spill that could cause environmental damage (d) a rapid release of superheated steam that could cause damage and injury (e) a forced unit shutdown that could have an adverse economic impact (f) minimal safety, health, environmental, and/or economic impact • Calculate Consequence Value • Worst Case Pressure & Temperature • Volume of Contained Fluid/Gas • Density Factor • NFPA Factors (Flammability, Toxicity, Reactivity, Other) • Assign Consequence Rank to Component Considering Mitigating/Aggravating Factors • Location Relative to Other Equipment • Location Relative to Concentrations of Personnel • Environmental Factors (Reportable Release Quantities) Consequence of Failure
  • 15. 15 • Calculate Preliminary Consequence Value (PCV) • Product of Worst Case: Temperature, Volume, Pressure and Density factors. • Sum of MSDS Factors: Flammability, Toxicity, Reactivity, Other (steam). • Final Product (PCV) • Modify PCV by considering Mitigating, Aggravating Factors • Location Relative to Other Equipment • Location Relative to Concentrations of Personnel • Environmental Factors (Reportable Release Quantities) • Fire detection and suppression devices Estimating Consequence Four Categories Based Consistent With Industry Approach Consequence of Component Failure Considerable 1 Serious 2 Some 3 Minor or No Impact on Personnel 4 Rank Consequence Based on Potential For Harm to Site Personnel & Environment
  • 16. 16 RBI pitfalls RBI will not compensate for • inaccurate or missing information • inadequate design or faulty equipment • improper installation and/or operation • operating outside the acceptable design envelope • not effectively implementing the inspection plan • lack of qualified personnel or team work • lack of sound engineering or operational judgment • failure to promptly take corrective action or implement appropriate mitigation strategies
  • 17. 17 Risk Management Reducing likelihood of failure is not only restricted to inspections: • Inspection and Maintenance • Understanding damage • Correct NDE techniques • MOC/Record Keeping/Report • Repair, Replace, Control • Operational Controls • Online Monitoring • Materials RBI focuses on “inspectable risk”. RBI is not intended to replace other practices that have proven satisfactory or substitute for the judgment of a responsible, qualified inspector or engineer.
  • 18. 18 Life Optimization Program • What is Intertek’s AIM Life Optimization Program: • API 580 Compliant • System Risk Analysis Tool • Justification for future maintenance costs and maintenance planning aid • A Living document • Flexible and adaptable to changing management and operations • Easy to use and inexpensive, with a quick ROI. A typical RBI implementation results in an inspection plan as the primary output. Instead, Intertek’s program goes beyond the basic requirements of RBI and its objectives are: • Organizing and maintaining key inspection and overhaul reports from past years • Developing inspection and real-time data acquisition plans needed to assess equipment health • Developing a database structure to organize the vast data in a way that is easily retrieved and disseminated