WHO ARE WE?
 The Augustus Group, LLC (TAG)
 Materials Technology Consulting Company
 Operation >10 Years, Founded 2003
 100’s Years Experience in…
 Bolting Technology and Leak Management
 Non-Destructive Examination, and
 Risk Based Inspection
 Petroleum/Chemical, Fossil/Nuclear Upstream & Downstream
 MI/RBI Programs
 Wrote Chemical Manufacturer’s Association’s MI Program Trained >
300 Companies
 > 30 RBI Implementations Worldwide
 First Known Refinery RBI Program at BHP Hawaii in 1995
 Developed APTECH’s (Now Intertek) RBI Program and Software
 Experienced with Most Major Software Packages – Tischuk, Meridium, The
Welding Institute, Capstone, Aptech, and API
Areas of Specialty Operating Company Former
Employee
Jim Towers Pipelines, Litigation Exxon, Conoco
Peter Hunt Refinery Management, MI/QAQC Shell
Bob Blackstone Stress Analysis, Fracture Mechanics, Welding,
Fatigue, Design
ABS
Gene Rak Corrosion, MI Exxon
Scott Miller NDE Saudi Aramco
Edwin Merrick RBI, Materials Technology, Welding, Bolting, Leak
Management
TVA, Aptech
Scott Merrick Education, Training City of Nashville
Dick Jones Corrosion, PSM, MI, Chemical Plant Management US Steel/ Aristech
Joel Olener PSM
Les Loushin MI, Materials Technology Arco Chemical, Sunoco
Gene Silverman AST Integrity, Eagle System INTANK
Alan Judkins Business Development US Steel/ Aristech
David Sanders Inspection Program Management & Site
Implementation
Petrochem
Marvin Mehler Corrosion Engineering NCRA
James Waldrop TA Planning Citgo
Paul Rose NDE, Data Analysis (EVA, etc.)
Mike Fox Maintenance, MI Implementation, Safety Program
Management
Honeywell
Dave Holthaus NDE Jacobs Engineering
Frank Simpton Inspection Program Management & Implementation,
Corrosion, Damage Management, On-stream
Inspections
Acuren, Hovensa, Saudi Aramco
ENGINEERING CONSULTANTS
WHAT WE DO?
 Seminars, Webinars & Audits
 Procedures
 Mechanical Integrity
 Risk Based Inspection
 Fitness for Service/Suitability for Service
 QC Support For Maintenance and Contractors –
TA’s, New Build’s, etc.
 Use of Manufacturing Excellence Principals for
Asset Integrity, Compliance, and Reliability
Improvement
 2/19 - Improving your Turnaround
Performance by Managing for Leak Free
Startup – Webinar
 2/26 11am CST, Use Risk Based Inspection
Tools for Optimizing Performance – Webinar
 3/5, 11am CST, Managing Your On-Stream
Inspection Program and External Versus
Internal Inspections - Webinar
 3/12, 11am CST, Managing Corrosion Under
Insulation - Webinar
 3/17 & 3/18 – MI for PSM Compliance
SEMINAR
 MORE TO BE SCHEDULED, CHECK
WWW.THEAUGUSTUSGROUP.NET
WEBINAR/SEMINAR SERIES – AIMED AT
ALIGNMENT WITH BUSINESS OBJECTIVES
Risk Based Inspection Tools
for Optimizing Performance
Manufacturing Manager:
 Plant Manager
 Operations
 Maintenance
 Engineering
**The Use of Risk Based Tools
to Improve Your Paycheck
RISK MANAGEMENT?
CONSEQUENCES ARE BAD BUT
MITIGATED
RISK MANAGEMENT DURING IKE
Even Augustus Himself Could
not Manage the Likelihood of
this Happening – All is Left is to
Deal with the Consequences
I’m Gonna Try a Walk in
Your Shoes –
And I Thought Running a
Small Business Was a
Challenge !!!!
OPERATIONS
SAFETY
INSPECTION
MAINTENANCE
SUPERVISOR
ENGINEERING
PLANT
MANAGER’S
OFFICE
MANUFACTURING MANAGER’s –
Daily Challenges
MANUFACTURING MANAGER’s –
Daily Challenges
 SAFETY – Needs immediate
attention – correct an unsafe
condition on a work platform.
 ENVIRONMENT – Need to stock
spare parts for Waste Gas
Incinerator.
 OPERATIONS – Lost the main
pump; want Mx to jump on it and
work overtime till completed.
MANUFACTURING MANAGER’s –
Daily Challenges
 INSPECTION – Need to inspect furnace tubes
at the TA.
 ENGINEERING – Want someone to take
vibration reading on the spare pump that
operation has just put on. Missed it last month
as the pump was not in service……
 MAINTENANCE SUPERVISOR – Two mechanics
just called in sick…
 PLANT MANAGER’S SECRETARY – There is an
emergency. The toilet is plugged…
MANUFACTURING MANAGER…
WHAT NEXT?
CONTRACTORS???
You Using
All the
Available
Tools???
e.g. Quality
Control/Assurance,
RISK
PRIORITIZATION
and/or
RISK BASED
INSPECTION
RISK PRIORITIZATION AND OR
e.g. RISK BASED INSPECTION
 By Now we’ve all Seen the Customary
Risk Matrix in Some Format
 Do You have a RBI Program?
 Developed and in Place?
 Do You Understand its Potential?
 Are you Using it to Prioritize your Actions and
Deliver on?
 Or Does Your Company Implement a
Qualitative Approach??
 RISK MANAGEMENT IS A KEY
Consequence Ranking
ABCDE
1
2
3
4
5
ProbabilityRanking
HIGH
MED HIGH
MEDIUM
LOW
MANY COMPANIES HAVE OR/ARE
MAKING THE TRANSITION
NFPA Diamond Discrimination
Engineering
Analysis
RBI
Expert
Opinion
High
Low
High
RCM
Consequence Ranking
ABCDE
1
2
3
4
5
ProbabilityRanking
HIGH
MED HIGH
MEDIUM
LOW
Risk Based Mechanical
Integrity
Using FFS and Advanced
NDE When Needed
Conventional
MI Program
AUGUSTUS Tennessee 4-Step
SURGICAL Risk Based Inspection Program
1. Integrate Qualitative Risk Analysis into the
Process Hazard Analysis
This Will Institutionalize Your RBI Program
2. Focus on Quantifying Consequence by Process
System
3. High & Low Consequence Items Quantitative
RBI Analysis
20 - 30% of Your Equipment Gets the Special
Attention it Needs
4. Medium Consequence Items Are Treated in
Conventional Program Manner
**Augustus Uses Our Custom Sharepoint/Reliasoft
Solution To Make It Happen
WHAT DO WE GET FROM AN
RBI IMPLEMENTATION
Equipment
Data Collection
Process
System
Corrosion
Analysis
Qualitative
Analysis
Data Entry
Quantitative
Analysis
QC and
Equipment
Integrity
Review
RBI Plan
Approval
Action
(Inspections
etc)
Results
Analysis
Criticality and
Plan Update
RISKLEVEL
COST TO REDUCE RISK
RESIDUAL RISK
 Keep it Simple Make Sure You
Identify the OBVIOUS
 RISK ISSUES and
 OPPORTUNITIES
 USE THE EVIDENCE
 DEVELOP/EXECUTE ACTION
PLANS FOR IMPROVEMENT
RISK MANAGEMENT IS A KEY –
Take the Action
QUALITATIVE RISK MATRIX FOR
EVERYDAY USE
 At Every Management
Level
 Best Practice is to Manage
Based on Risk
 Situational Decision
Making
 Inputs
 Your RBI Program Data
 Results from a Qualitative
Review During the PHA
SO HOW IS IT DONE??
 Identify
 Business Drivers
 Business Impacts For Each Driver
 Establish Business Risk = Impact X
Event Likelihood
 Identify Best Action For Business Need
 Use at Local Management Level or
Ideally Institutionalize Methodology For
 Sustainable Performance and
 Continuous Improvement
BUSINESS DRIVERS – IMPACTS
 Personnel Impact
 Environmental Impact
 Public Disruption Impact
 Business Interruption Impact
 Asset Damage Impact
 Reputation Impact
ACTION LEVELS- Even if the Likelihood is High for All Events,
the Impacts Affect the Business Risk and Subsequent Action
Impacts Event Likelihood RISK ACTION
> 24 HRS
MAJOR
HIGH HIGH
Emergency, Rounds, Monthly
PdM, critical spares, RCA
> 8 HRS
MODERATE
HIGH
MEDIUM
HIGH
Urgent, Quarterly PdM, select
spares
4 – 8 HRS
MINOR
HIGH MEDIUM Routine, Annual PdM, JIT
< 4 HRS
NEGLIGIBLE
HIGH LOW Routine, No PdM, JIT
Impacts Event Likelihood RISK ACTION
> 24 HRS
MAJOR
HIGH HIGH
Emergency, Rounds, Monthly
PdM, critical spares, RCA
> 8 HRS
MAJOR
HIGH HIGH
Emergency, Rounds, Monthly
PdM, critical spares, RCA
4 – 8 HRS
MAJOR
HIGH HIGH
Emergency, Rounds, Monthly
PdM, critical spares, RCA
< 4 HRS
MODERATE
HIGH
MEDIUM
HIGH
Urgent, Quarterly PdM, select
spares
RISK MATRIX – Applications
 SAFETY – Need immediate attention – correct an
unsafe condition on a work platform.
 Risk Ranked – D1
 Action – Urgent Priority; Within next 5 days
 ENVIRONMENT – Need to stock spare parts for
waste gas incinerator.
 Risk Ranked – C4
 Action – Least Critical; Spare parts not required
 OPERATIONS – Lost the main pump; want Mx to
jump on it and work overtime till completed.
 Risk Ranked – D2
 Action – Routine Priority; No overtime
RISK MATRIX – Applications
 INSPECTION – Need to inspect furnace tubes at
the TA.
 Risk Ranked – D1
 Action – On hold
 ENGINEERING – Want someone to take vibration
on the spare pump that operation has just put on.
Missed it last month as the pump was not in
service……
 Risk Ranked – D3
 Action – Low Criticality; Reduce frequency of vibration
monitoring
 PLANT MANAGER’S SECRETARY – There is an
emergency. The toilet is plugged…
 Risk Ranked – High!!!
 Action – Rush mechanic immediately!!!
RISK MATRIX – Applications
CONSEQUENCES
MAJOR Fatality or Disabling Injury, Major fire/explosion
requiring off-site response, Toxic/flammable gas release,
Permit exceedance or RQ release of chemicals to air, water
or ground, Production loss (unit shutdown or partial) > 24
hrs, Repair costs >$100K
1
MODERATE OSHA recordable Injury, Minor fire/explosion
requiring plant fire brigade/ERT response, Minor release of
chemicals to air, water or ground requiring ERT response,
Production loss (unit shutdown or partial) between 12 and
24 hrs, Repair costs between $50K to $100K
2
MINOR First aid injury, Local fire requiring operator
response only, Minor release of chemicals to air, water or
ground manageable by routine staffing, Production loss
(unit shutdown or partial) less than 12 hrs, Repair costs
between $10K to $50K
3
NEGLIGIBLE No health, safety and environmental
impact, Minor recoverable production loss, Repair costs < $
10K
4
MOST CRITICAL LESS CRITICAL
CRITICAL LEAST CRITICAL
ASSET CRITICALITY LIKELIHOOD OF FAILURE
E D C B A
Extremely
Unlikely
Unlikely Possible Some
what
likely
Very Likely
Reliability
Excellent
> 5 yrs
Reliability
– Good
3–5yrs
Reliability –
Fair
1–3 yrs
Reliability
– Poor
1 yr
Reliability
Very Poor
<1 yr
CONSEQUENCES
MAJOR Fatality or Disabling Injury, Major fire/explosion
requiring off-site response, Toxic/flammable gas release,
Permit exceedance or RQ release of chemicals to air, water
or ground, Production loss (unit shutdown or partial) > 24
hrs, Repair costs >$100K
1
MODERATE OSHA recordable Injury, Minor fire/explosion
requiring plant fire brigade/ERT response, Minor release of
chemicals to air, water or ground requiring ERT response,
Production loss (unit shutdown or partial) between 12 and
24 hrs, Repair costs between $50K to $100K
2
MINOR First aid injury, Local fire requiring operator
response only, Minor release of chemicals to air, water or
ground manageable by routine staffing, Production loss
(unit shutdown or partial) less than 12 hrs, Repair costs
between $10K to $50K
3
NEGLIGIBLE No health, safety and environmental
impact, Minor recoverable production loss, Repair costs < $
10K
4
LIKELIHOOD OF FAILURE
E D C B A
Extremely
Unlikely
Unlikely Possible Some
what
likely
Very Likely
Reliability
Excellent
> 5 yrs
Reliability
– Good
3–5yrs
Reliability –
Fair
1–3 yrs
Reliability
– Poor
1 yr
Reliability
Very Poor
<1 yr
Emergency Work Start
Immediately; OT
approved
Routine Priority < 3 wks
Urgent Priority – Within 1
week
When resources are
available; within 6 months
WORK SCHEDULING
CONSEQUENCES
MAJOR Fatality or Disabling Injury, Major fire/explosion
requiring off-site response, Toxic/flammable gas release,
Permit exceedance or RQ release of chemicals to air, water
or ground, Production loss (unit shutdown or partial) > 24
hrs, Repair costs >$100K
1
MODERATE OSHA recordable Injury, Minor fire/explosion
requiring plant fire brigade/ERT response, Minor release of
chemicals to air, water or ground requiring ERT response,
Production loss (unit shutdown or partial) between 12 and
24 hrs, Repair costs between $50K to $100K
2
MINOR First aid injury, Local fire requiring operator
response only, Minor release of chemicals to air, water or
ground manageable by routine staffing, Production loss
(unit shutdown or partial) less than 12 hrs, Repair costs
between $10K to $50K
3
NEGLIGIBLE No health, safety and environmental
impact, Minor recoverable production loss, Repair costs < $
10K
4
TURNAROUND
MUST DO
NOT
NECESSARY
SHOULD DO
NEVER
JUSTIFIED
LIKELIHOOD OF FAILURE
E D C B A
Extremely
Unlikely
Unlikely Possible Some
what
likely
Very Likely
Reliability
Excellent
> 5 yrs
Reliability
– Good
3–5yrs
Reliability –
Fair
1–3 yrs
Reliability
– Poor
1 yr
Reliability
Very Poor
<1 yr
1. Clarifying the PSM exemption for atmospheric storage tanks;
2. Oil- and Gas-Well Drilling and Servicing;
3. Oil- and Gas-Production Facilities; way behind Implementing; don’t follow 510 & 570
4. Expanding PSM Coverage and Requirements for Reactivity Hazards;
5. Updating the List of Highly Hazardous Chemicals in Appendix A of the PSM Standard;
6. Revising the PSM Standard to Require Additional Management-System Elements;
7. Amending Paragraph (d) of the PSM Standard to Require Evaluation of Updates to
Applicable recognized and generally accepted good engineering practices (RAGAGEP);
whatever API or standards writing organizations put out
8. Clarifying the PSM Standard by Adding a Definition for RAGAGEP;
9. Expanding the Scope of Paragraph (j) of the PSM Standard to Cover the Mechanical
Integrity of Any Safety-Critical Equipment;
10. Clarifying Paragraph (l) of the PSM Standard with an Explicit Requirement that
Employers Manage Organizational Changes;
11. Revising Paragraph (n) of the PSM Standard to Require Coordination of Emergency
Planning with Local Emergency-Response Authorities;
12. Revising Paragraph (o) of the PSM Standard to Require Third-
Party Compliance Audits;
13. Expanding the Requirements of §1910.109 to Cover Dismantling and Disposal of
Explosives, Blasting Agents, and Pyrotechnics;
14. Updating §§1910.106 and 1910.107 Based on the Latest Applicable Consensus
Standards;
15. Updating the Regulations Addressing the Storage, Handling, and Management of
Ammonium Nitrate;
16. Changing Enforcement Policy of the PSM Exemption for Retail Facilities; and
17. Changing Enforcement Policy for Highly Hazardous Chemicals Listed in Appendix A of
the PSM Standard without Specific Concentrations.
OSHA PSM RFI signed in August 2013 – potential candidates for
rulemaking or enforcement policy changes – Still Under Review
RISK MANAGEMENT – Consider
Augustus’ MI Seminar in March

More Related Content

What's hot

The Leak Management Opportunity
The Leak Management OpportunityThe Leak Management Opportunity
The Leak Management Opportunity
Edwin A Merrick
 
Augustus Asset55 Joint Integrity Webinar July2015 r2
Augustus Asset55 Joint Integrity Webinar July2015 r2Augustus Asset55 Joint Integrity Webinar July2015 r2
Augustus Asset55 Joint Integrity Webinar July2015 r2
Edwin A Merrick
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made Simple
Ricky Smith CMRP, CMRT
 
Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Chad Broussard
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Cairn India Limited
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
Doruk Kimyasal Yönetim Sistemeri
 
Risk-Based Inspection (RBI) by aminul islam
Risk-Based Inspection (RBI) by aminul islamRisk-Based Inspection (RBI) by aminul islam
Risk-Based Inspection (RBI) by aminul islam
Md.Aminul Islam ,CMRP,CSSBB
 
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Cairn India Limited
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
360factors
 
Safety Standards
Safety Standards Safety Standards
Safety Standards
Arjun Aarzoo
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered Maintenance
Nandhagopal Muralithar
 
Best practice for risk based inspection
Best practice for risk based inspectionBest practice for risk based inspection
Best practice for risk based inspection
Osama Lari
 
Rbi
RbiRbi
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
Triumvirate Environmental
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
idell bryan
 
Kp bloch psm preparedness final rev
Kp bloch psm preparedness final revKp bloch psm preparedness final rev
Kp bloch psm preparedness final rev
Ann-Marie Roche
 
Reliability-Centered Maintenance's Role in Asset Performance Management
Reliability-Centered Maintenance's Role in Asset Performance ManagementReliability-Centered Maintenance's Role in Asset Performance Management
Reliability-Centered Maintenance's Role in Asset Performance Management
USC Consulting Group
 

What's hot (19)

The Leak Management Opportunity
The Leak Management OpportunityThe Leak Management Opportunity
The Leak Management Opportunity
 
Augustus Asset55 Joint Integrity Webinar July2015 r2
Augustus Asset55 Joint Integrity Webinar July2015 r2Augustus Asset55 Joint Integrity Webinar July2015 r2
Augustus Asset55 Joint Integrity Webinar July2015 r2
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made Simple
 
Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
Risk-Based Inspection (RBI) by aminul islam
Risk-Based Inspection (RBI) by aminul islamRisk-Based Inspection (RBI) by aminul islam
Risk-Based Inspection (RBI) by aminul islam
 
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
 
Safety Standards
Safety Standards Safety Standards
Safety Standards
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered Maintenance
 
Hse oil and gas management services
Hse oil and gas management servicesHse oil and gas management services
Hse oil and gas management services
 
Risk Based Inspection
Risk Based InspectionRisk Based Inspection
Risk Based Inspection
 
Best practice for risk based inspection
Best practice for risk based inspectionBest practice for risk based inspection
Best practice for risk based inspection
 
Rbi
RbiRbi
Rbi
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
Kp bloch psm preparedness final rev
Kp bloch psm preparedness final revKp bloch psm preparedness final rev
Kp bloch psm preparedness final rev
 
Reliability-Centered Maintenance's Role in Asset Performance Management
Reliability-Centered Maintenance's Role in Asset Performance ManagementReliability-Centered Maintenance's Role in Asset Performance Management
Reliability-Centered Maintenance's Role in Asset Performance Management
 

Similar to Risk Solutions for the Manager

Business Continuity Workshop Final
Business Continuity Workshop   FinalBusiness Continuity Workshop   Final
Business Continuity Workshop Final
Bill Lisse
 
Root Cause Analysis - Omaintec 2023, Riyadh
Root Cause Analysis - Omaintec 2023, RiyadhRoot Cause Analysis - Omaintec 2023, Riyadh
Root Cause Analysis - Omaintec 2023, Riyadh
SultanAlMaskari
 
Oil Spill Crisis Action Team Back Up, Relief 052410
Oil Spill Crisis Action Team Back Up, Relief 052410Oil Spill Crisis Action Team Back Up, Relief 052410
Oil Spill Crisis Action Team Back Up, Relief 052410arainold
 
Risk Management
Risk Management Risk Management
Risk Management Kapil Rode
 
Business Continuity & Disaster Recovery
Business Continuity & Disaster RecoveryBusiness Continuity & Disaster Recovery
Business Continuity & Disaster Recovery
EC-Council
 
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
Ed Sattar
 
TPM - Total Productive Maintenance
TPM - Total Productive MaintenanceTPM - Total Productive Maintenance
TPM - Total Productive Maintenance
RAHMAT EIE
 
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
FMMUG
 
TPM&amp;Kaizen(Junu)
TPM&amp;Kaizen(Junu)TPM&amp;Kaizen(Junu)
TPM&amp;Kaizen(Junu)pjunwoo365
 
ArvindMahuli_EHS 2016
ArvindMahuli_EHS 2016ArvindMahuli_EHS 2016
ArvindMahuli_EHS 2016Arvind Mahuli
 
Enterprise governance risk_compliance_fcm slides
Enterprise governance risk_compliance_fcm slidesEnterprise governance risk_compliance_fcm slides
Enterprise governance risk_compliance_fcm slides
EnterpriseGRC Solutions, Inc.
 
Risk mgmt key to security certifications v2
Risk mgmt key to security certifications v2Risk mgmt key to security certifications v2
Risk mgmt key to security certifications v2
Jorge Sebastiao
 
Bi reporting final
Bi reporting finalBi reporting final
Bi reporting final
Corey Horohoe
 
Harpreet Singh-Resume-QA
Harpreet Singh-Resume-QAHarpreet Singh-Resume-QA
Harpreet Singh-Resume-QAHarpreet Singh
 
Introducing mark lynch
Introducing mark lynchIntroducing mark lynch
Introducing mark lynchmelynch
 
ERM LCPL overview
ERM LCPL overviewERM LCPL overview
ERM LCPL overviewkarld
 
BiznetGio Presentation Business Continuity
BiznetGio Presentation Business ContinuityBiznetGio Presentation Business Continuity
BiznetGio Presentation Business Continuity
Yusuf Hadiwinata Sutandar
 
Hammad Ashraf CV
Hammad Ashraf CVHammad Ashraf CV
Hammad Ashraf CVHammad Khan
 

Similar to Risk Solutions for the Manager (20)

Business Continuity Workshop Final
Business Continuity Workshop   FinalBusiness Continuity Workshop   Final
Business Continuity Workshop Final
 
Root Cause Analysis - Omaintec 2023, Riyadh
Root Cause Analysis - Omaintec 2023, RiyadhRoot Cause Analysis - Omaintec 2023, Riyadh
Root Cause Analysis - Omaintec 2023, Riyadh
 
Oil Spill Crisis Action Team Back Up, Relief 052410
Oil Spill Crisis Action Team Back Up, Relief 052410Oil Spill Crisis Action Team Back Up, Relief 052410
Oil Spill Crisis Action Team Back Up, Relief 052410
 
Risk Management
Risk Management Risk Management
Risk Management
 
Business Continuity & Disaster Recovery
Business Continuity & Disaster RecoveryBusiness Continuity & Disaster Recovery
Business Continuity & Disaster Recovery
 
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
ASSE Safety 2016: Ed Sattar Speaks about Operational Risk and Regulatory Chan...
 
TPM - Total Productive Maintenance
TPM - Total Productive MaintenanceTPM - Total Productive Maintenance
TPM - Total Productive Maintenance
 
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
 
TPM&amp;Kaizen(Junu)
TPM&amp;Kaizen(Junu)TPM&amp;Kaizen(Junu)
TPM&amp;Kaizen(Junu)
 
ArvindMahuli_EHS 2016
ArvindMahuli_EHS 2016ArvindMahuli_EHS 2016
ArvindMahuli_EHS 2016
 
Enterprise governance risk_compliance_fcm slides
Enterprise governance risk_compliance_fcm slidesEnterprise governance risk_compliance_fcm slides
Enterprise governance risk_compliance_fcm slides
 
Maximo Overview
Maximo OverviewMaximo Overview
Maximo Overview
 
Risk mgmt key to security certifications v2
Risk mgmt key to security certifications v2Risk mgmt key to security certifications v2
Risk mgmt key to security certifications v2
 
Bi reporting final
Bi reporting finalBi reporting final
Bi reporting final
 
RCFA Pro Brochure ver1
RCFA Pro Brochure ver1RCFA Pro Brochure ver1
RCFA Pro Brochure ver1
 
Harpreet Singh-Resume-QA
Harpreet Singh-Resume-QAHarpreet Singh-Resume-QA
Harpreet Singh-Resume-QA
 
Introducing mark lynch
Introducing mark lynchIntroducing mark lynch
Introducing mark lynch
 
ERM LCPL overview
ERM LCPL overviewERM LCPL overview
ERM LCPL overview
 
BiznetGio Presentation Business Continuity
BiznetGio Presentation Business ContinuityBiznetGio Presentation Business Continuity
BiznetGio Presentation Business Continuity
 
Hammad Ashraf CV
Hammad Ashraf CVHammad Ashraf CV
Hammad Ashraf CV
 

Recently uploaded

Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

Risk Solutions for the Manager

  • 2. WHO ARE WE?  The Augustus Group, LLC (TAG)  Materials Technology Consulting Company  Operation >10 Years, Founded 2003  100’s Years Experience in…  Bolting Technology and Leak Management  Non-Destructive Examination, and  Risk Based Inspection  Petroleum/Chemical, Fossil/Nuclear Upstream & Downstream  MI/RBI Programs  Wrote Chemical Manufacturer’s Association’s MI Program Trained > 300 Companies  > 30 RBI Implementations Worldwide  First Known Refinery RBI Program at BHP Hawaii in 1995  Developed APTECH’s (Now Intertek) RBI Program and Software  Experienced with Most Major Software Packages – Tischuk, Meridium, The Welding Institute, Capstone, Aptech, and API
  • 3. Areas of Specialty Operating Company Former Employee Jim Towers Pipelines, Litigation Exxon, Conoco Peter Hunt Refinery Management, MI/QAQC Shell Bob Blackstone Stress Analysis, Fracture Mechanics, Welding, Fatigue, Design ABS Gene Rak Corrosion, MI Exxon Scott Miller NDE Saudi Aramco Edwin Merrick RBI, Materials Technology, Welding, Bolting, Leak Management TVA, Aptech Scott Merrick Education, Training City of Nashville Dick Jones Corrosion, PSM, MI, Chemical Plant Management US Steel/ Aristech Joel Olener PSM Les Loushin MI, Materials Technology Arco Chemical, Sunoco Gene Silverman AST Integrity, Eagle System INTANK Alan Judkins Business Development US Steel/ Aristech David Sanders Inspection Program Management & Site Implementation Petrochem Marvin Mehler Corrosion Engineering NCRA James Waldrop TA Planning Citgo Paul Rose NDE, Data Analysis (EVA, etc.) Mike Fox Maintenance, MI Implementation, Safety Program Management Honeywell Dave Holthaus NDE Jacobs Engineering Frank Simpton Inspection Program Management & Implementation, Corrosion, Damage Management, On-stream Inspections Acuren, Hovensa, Saudi Aramco ENGINEERING CONSULTANTS
  • 4. WHAT WE DO?  Seminars, Webinars & Audits  Procedures  Mechanical Integrity  Risk Based Inspection  Fitness for Service/Suitability for Service  QC Support For Maintenance and Contractors – TA’s, New Build’s, etc.  Use of Manufacturing Excellence Principals for Asset Integrity, Compliance, and Reliability Improvement
  • 5.  2/19 - Improving your Turnaround Performance by Managing for Leak Free Startup – Webinar  2/26 11am CST, Use Risk Based Inspection Tools for Optimizing Performance – Webinar  3/5, 11am CST, Managing Your On-Stream Inspection Program and External Versus Internal Inspections - Webinar  3/12, 11am CST, Managing Corrosion Under Insulation - Webinar  3/17 & 3/18 – MI for PSM Compliance SEMINAR  MORE TO BE SCHEDULED, CHECK WWW.THEAUGUSTUSGROUP.NET WEBINAR/SEMINAR SERIES – AIMED AT ALIGNMENT WITH BUSINESS OBJECTIVES
  • 6. Risk Based Inspection Tools for Optimizing Performance Manufacturing Manager:  Plant Manager  Operations  Maintenance  Engineering **The Use of Risk Based Tools to Improve Your Paycheck
  • 8. CONSEQUENCES ARE BAD BUT MITIGATED
  • 10. Even Augustus Himself Could not Manage the Likelihood of this Happening – All is Left is to Deal with the Consequences
  • 11. I’m Gonna Try a Walk in Your Shoes – And I Thought Running a Small Business Was a Challenge !!!! OPERATIONS SAFETY INSPECTION MAINTENANCE SUPERVISOR ENGINEERING PLANT MANAGER’S OFFICE MANUFACTURING MANAGER’s – Daily Challenges
  • 12. MANUFACTURING MANAGER’s – Daily Challenges  SAFETY – Needs immediate attention – correct an unsafe condition on a work platform.  ENVIRONMENT – Need to stock spare parts for Waste Gas Incinerator.  OPERATIONS – Lost the main pump; want Mx to jump on it and work overtime till completed.
  • 13. MANUFACTURING MANAGER’s – Daily Challenges  INSPECTION – Need to inspect furnace tubes at the TA.  ENGINEERING – Want someone to take vibration reading on the spare pump that operation has just put on. Missed it last month as the pump was not in service……  MAINTENANCE SUPERVISOR – Two mechanics just called in sick…  PLANT MANAGER’S SECRETARY – There is an emergency. The toilet is plugged…
  • 15. You Using All the Available Tools??? e.g. Quality Control/Assurance, RISK PRIORITIZATION and/or RISK BASED INSPECTION
  • 16. RISK PRIORITIZATION AND OR e.g. RISK BASED INSPECTION  By Now we’ve all Seen the Customary Risk Matrix in Some Format  Do You have a RBI Program?  Developed and in Place?  Do You Understand its Potential?  Are you Using it to Prioritize your Actions and Deliver on?  Or Does Your Company Implement a Qualitative Approach??  RISK MANAGEMENT IS A KEY Consequence Ranking ABCDE 1 2 3 4 5 ProbabilityRanking HIGH MED HIGH MEDIUM LOW
  • 17. MANY COMPANIES HAVE OR/ARE MAKING THE TRANSITION NFPA Diamond Discrimination Engineering Analysis RBI Expert Opinion High Low High RCM Consequence Ranking ABCDE 1 2 3 4 5 ProbabilityRanking HIGH MED HIGH MEDIUM LOW Risk Based Mechanical Integrity Using FFS and Advanced NDE When Needed Conventional MI Program
  • 18. AUGUSTUS Tennessee 4-Step SURGICAL Risk Based Inspection Program 1. Integrate Qualitative Risk Analysis into the Process Hazard Analysis This Will Institutionalize Your RBI Program 2. Focus on Quantifying Consequence by Process System 3. High & Low Consequence Items Quantitative RBI Analysis 20 - 30% of Your Equipment Gets the Special Attention it Needs 4. Medium Consequence Items Are Treated in Conventional Program Manner **Augustus Uses Our Custom Sharepoint/Reliasoft Solution To Make It Happen
  • 19. WHAT DO WE GET FROM AN RBI IMPLEMENTATION Equipment Data Collection Process System Corrosion Analysis Qualitative Analysis Data Entry Quantitative Analysis QC and Equipment Integrity Review RBI Plan Approval Action (Inspections etc) Results Analysis Criticality and Plan Update
  • 20. RISKLEVEL COST TO REDUCE RISK RESIDUAL RISK  Keep it Simple Make Sure You Identify the OBVIOUS  RISK ISSUES and  OPPORTUNITIES  USE THE EVIDENCE  DEVELOP/EXECUTE ACTION PLANS FOR IMPROVEMENT RISK MANAGEMENT IS A KEY – Take the Action
  • 21. QUALITATIVE RISK MATRIX FOR EVERYDAY USE  At Every Management Level  Best Practice is to Manage Based on Risk  Situational Decision Making  Inputs  Your RBI Program Data  Results from a Qualitative Review During the PHA
  • 22. SO HOW IS IT DONE??  Identify  Business Drivers  Business Impacts For Each Driver  Establish Business Risk = Impact X Event Likelihood  Identify Best Action For Business Need  Use at Local Management Level or Ideally Institutionalize Methodology For  Sustainable Performance and  Continuous Improvement
  • 23. BUSINESS DRIVERS – IMPACTS  Personnel Impact  Environmental Impact  Public Disruption Impact  Business Interruption Impact  Asset Damage Impact  Reputation Impact
  • 24. ACTION LEVELS- Even if the Likelihood is High for All Events, the Impacts Affect the Business Risk and Subsequent Action Impacts Event Likelihood RISK ACTION > 24 HRS MAJOR HIGH HIGH Emergency, Rounds, Monthly PdM, critical spares, RCA > 8 HRS MODERATE HIGH MEDIUM HIGH Urgent, Quarterly PdM, select spares 4 – 8 HRS MINOR HIGH MEDIUM Routine, Annual PdM, JIT < 4 HRS NEGLIGIBLE HIGH LOW Routine, No PdM, JIT Impacts Event Likelihood RISK ACTION > 24 HRS MAJOR HIGH HIGH Emergency, Rounds, Monthly PdM, critical spares, RCA > 8 HRS MAJOR HIGH HIGH Emergency, Rounds, Monthly PdM, critical spares, RCA 4 – 8 HRS MAJOR HIGH HIGH Emergency, Rounds, Monthly PdM, critical spares, RCA < 4 HRS MODERATE HIGH MEDIUM HIGH Urgent, Quarterly PdM, select spares
  • 25. RISK MATRIX – Applications  SAFETY – Need immediate attention – correct an unsafe condition on a work platform.  Risk Ranked – D1  Action – Urgent Priority; Within next 5 days  ENVIRONMENT – Need to stock spare parts for waste gas incinerator.  Risk Ranked – C4  Action – Least Critical; Spare parts not required  OPERATIONS – Lost the main pump; want Mx to jump on it and work overtime till completed.  Risk Ranked – D2  Action – Routine Priority; No overtime
  • 26. RISK MATRIX – Applications  INSPECTION – Need to inspect furnace tubes at the TA.  Risk Ranked – D1  Action – On hold  ENGINEERING – Want someone to take vibration on the spare pump that operation has just put on. Missed it last month as the pump was not in service……  Risk Ranked – D3  Action – Low Criticality; Reduce frequency of vibration monitoring
  • 27.  PLANT MANAGER’S SECRETARY – There is an emergency. The toilet is plugged…  Risk Ranked – High!!!  Action – Rush mechanic immediately!!! RISK MATRIX – Applications
  • 28. CONSEQUENCES MAJOR Fatality or Disabling Injury, Major fire/explosion requiring off-site response, Toxic/flammable gas release, Permit exceedance or RQ release of chemicals to air, water or ground, Production loss (unit shutdown or partial) > 24 hrs, Repair costs >$100K 1 MODERATE OSHA recordable Injury, Minor fire/explosion requiring plant fire brigade/ERT response, Minor release of chemicals to air, water or ground requiring ERT response, Production loss (unit shutdown or partial) between 12 and 24 hrs, Repair costs between $50K to $100K 2 MINOR First aid injury, Local fire requiring operator response only, Minor release of chemicals to air, water or ground manageable by routine staffing, Production loss (unit shutdown or partial) less than 12 hrs, Repair costs between $10K to $50K 3 NEGLIGIBLE No health, safety and environmental impact, Minor recoverable production loss, Repair costs < $ 10K 4 MOST CRITICAL LESS CRITICAL CRITICAL LEAST CRITICAL ASSET CRITICALITY LIKELIHOOD OF FAILURE E D C B A Extremely Unlikely Unlikely Possible Some what likely Very Likely Reliability Excellent > 5 yrs Reliability – Good 3–5yrs Reliability – Fair 1–3 yrs Reliability – Poor 1 yr Reliability Very Poor <1 yr
  • 29. CONSEQUENCES MAJOR Fatality or Disabling Injury, Major fire/explosion requiring off-site response, Toxic/flammable gas release, Permit exceedance or RQ release of chemicals to air, water or ground, Production loss (unit shutdown or partial) > 24 hrs, Repair costs >$100K 1 MODERATE OSHA recordable Injury, Minor fire/explosion requiring plant fire brigade/ERT response, Minor release of chemicals to air, water or ground requiring ERT response, Production loss (unit shutdown or partial) between 12 and 24 hrs, Repair costs between $50K to $100K 2 MINOR First aid injury, Local fire requiring operator response only, Minor release of chemicals to air, water or ground manageable by routine staffing, Production loss (unit shutdown or partial) less than 12 hrs, Repair costs between $10K to $50K 3 NEGLIGIBLE No health, safety and environmental impact, Minor recoverable production loss, Repair costs < $ 10K 4 LIKELIHOOD OF FAILURE E D C B A Extremely Unlikely Unlikely Possible Some what likely Very Likely Reliability Excellent > 5 yrs Reliability – Good 3–5yrs Reliability – Fair 1–3 yrs Reliability – Poor 1 yr Reliability Very Poor <1 yr Emergency Work Start Immediately; OT approved Routine Priority < 3 wks Urgent Priority – Within 1 week When resources are available; within 6 months WORK SCHEDULING
  • 30. CONSEQUENCES MAJOR Fatality or Disabling Injury, Major fire/explosion requiring off-site response, Toxic/flammable gas release, Permit exceedance or RQ release of chemicals to air, water or ground, Production loss (unit shutdown or partial) > 24 hrs, Repair costs >$100K 1 MODERATE OSHA recordable Injury, Minor fire/explosion requiring plant fire brigade/ERT response, Minor release of chemicals to air, water or ground requiring ERT response, Production loss (unit shutdown or partial) between 12 and 24 hrs, Repair costs between $50K to $100K 2 MINOR First aid injury, Local fire requiring operator response only, Minor release of chemicals to air, water or ground manageable by routine staffing, Production loss (unit shutdown or partial) less than 12 hrs, Repair costs between $10K to $50K 3 NEGLIGIBLE No health, safety and environmental impact, Minor recoverable production loss, Repair costs < $ 10K 4 TURNAROUND MUST DO NOT NECESSARY SHOULD DO NEVER JUSTIFIED LIKELIHOOD OF FAILURE E D C B A Extremely Unlikely Unlikely Possible Some what likely Very Likely Reliability Excellent > 5 yrs Reliability – Good 3–5yrs Reliability – Fair 1–3 yrs Reliability – Poor 1 yr Reliability Very Poor <1 yr
  • 31. 1. Clarifying the PSM exemption for atmospheric storage tanks; 2. Oil- and Gas-Well Drilling and Servicing; 3. Oil- and Gas-Production Facilities; way behind Implementing; don’t follow 510 & 570 4. Expanding PSM Coverage and Requirements for Reactivity Hazards; 5. Updating the List of Highly Hazardous Chemicals in Appendix A of the PSM Standard; 6. Revising the PSM Standard to Require Additional Management-System Elements; 7. Amending Paragraph (d) of the PSM Standard to Require Evaluation of Updates to Applicable recognized and generally accepted good engineering practices (RAGAGEP); whatever API or standards writing organizations put out 8. Clarifying the PSM Standard by Adding a Definition for RAGAGEP; 9. Expanding the Scope of Paragraph (j) of the PSM Standard to Cover the Mechanical Integrity of Any Safety-Critical Equipment; 10. Clarifying Paragraph (l) of the PSM Standard with an Explicit Requirement that Employers Manage Organizational Changes; 11. Revising Paragraph (n) of the PSM Standard to Require Coordination of Emergency Planning with Local Emergency-Response Authorities; 12. Revising Paragraph (o) of the PSM Standard to Require Third- Party Compliance Audits; 13. Expanding the Requirements of §1910.109 to Cover Dismantling and Disposal of Explosives, Blasting Agents, and Pyrotechnics; 14. Updating §§1910.106 and 1910.107 Based on the Latest Applicable Consensus Standards; 15. Updating the Regulations Addressing the Storage, Handling, and Management of Ammonium Nitrate; 16. Changing Enforcement Policy of the PSM Exemption for Retail Facilities; and 17. Changing Enforcement Policy for Highly Hazardous Chemicals Listed in Appendix A of the PSM Standard without Specific Concentrations. OSHA PSM RFI signed in August 2013 – potential candidates for rulemaking or enforcement policy changes – Still Under Review
  • 32. RISK MANAGEMENT – Consider Augustus’ MI Seminar in March