SlideShare a Scribd company logo
Rationalising public procurement of
complex construction projects by
the price component selection
The 6th International Public Procurement Conference (IPPC),
August 14–16, 2014, Dublin, Ireland
Pertti Lahdenperä
VTT Technical Research Centre of Finland
227/08/2014 2
Early team
involvement
and joint
development:
Why?
 Involvement of
multidisciplinary
expertise in
critical design
 Closer team
integration and
improved
collaboration
Cost of late
design
changes
Ability to impact
cost and total
value
Quantity/volume
Involve key players here !
Accrued
costs of the
project
Uncertainty in
relation to cost
and total value
Quantity/volume
Design ConstructionConcept
ImplementationDevelopmentConception
Fix the target cost here !
Do the development jointly !
327/08/2014 3
Selection criteria – common characteristics
Preliminary price component
submitted by tenderer
Binding price component
offered by tenderer
Owner’s calculation
(tenderer’s unit prices)
Owner’s cost estimate
(same for all competitors)
Determinated by the owner
(owner’s consultant) based on
varying types of cost data:
&
Targets of assessment
· past performance
· organisation
· know-how and experience
of section managers
· project strategies, approaches
and management plans
· alliance skills and affinity
· collaboration capability
· concept design / design
commentary
Capability / Quality Comparative price
”The most economically advantageous tender”
427/08/2014 4
Case 1: Road tunnel
with junctions
527/08/2014 5
Case 1: Formulation of comparative price
Designers’ fee is
calculated as
a percentage of
direct design
costs
Direct costs
are based on
owner’s cost
estimate
Contractor’s
fee is fixed in
euros
The
comparative
price is the
sum of the
fees and costs
Direct
Design
Costs [€]
Fee [%]
Binding price component
offered by tenderer
Owner’s cost estimate
(same for all competitors)
Fee [€]
Direct
Construction
Costs [€]
+ +
+
6627/08/2014
Case 2: Water treatment plant
727/08/2014 7
Case 2: Formulation of comparative price
Fee is
calculated as
a percentage
of the sum of
other costs
Direct costs
are based on
client’s cost
estimate
The
comparative
price is the
sum of the
dollar fee and
other costs
Management
and
preliminaries
costs, risk
provision and
fee are those
tendered by
competitors
Direct Costs [$]
Preliminaries [$]
Project Overhead [$]
Fee [%]
Risk and Opportunity [$]
+
+
+
Binding price component
offered by tenderer
Owner’s cost estimate
(same for all competitors)
+
8827/08/2014
Case 3: Road bridge and surroundings
927/08/2014 9
Case 3: Formulation of comparative price
Fee is
calculated as
a percentage
of the sum of
other costs
Tenders are
binding as to
bridge and
project
overhead
costs
The
comparative
price is the
sum of the
dollar fee and
other costs
Prices of the
balance of
works are
preliminary
Bridge Target
Outturn Cost
[$]
Balance of
Works Budget
[$]
Contingency [$]
Project Overhead Target Outturn Cost [$]
Contingency [$]
Fee [%]
Project Overhead Contingency [$]
+
+
+
+
+
Binding price component
offered by tenderer
Preliminary price component
submitted by tenderer
+
10
Case 4: Arterial road with junctions
1127/08/2014 11
Case 4: Formulation of comparative price
Fee is
calculated as
a percentage
of the sum of
all other costs
Cost of
warranty work
is expressed as
a percentage
of
construction
works costs
The
comparative
price is the
sum of the
dollar fee and
other costs
Priced Works
Lump Sum [$]
(Package 1)
[$]
(2)
Defect Correction Costs [%]
Project Overhead [$]
Fee [%]
Risk and Contingency Provision [%]
+
+
+
[$]
(3)
+
[$]+ [$]+
+
Works Costs, other works [$]
+
Binding price component
offered by tenderer
Owner’s calculation
(tenderer’s unit prices)
Owner’s cost estimate
(same for all competitors)
+
Risk provision
is calculated
as a
percentage of
estimated
direct project
costs
1227/08/2014 12
Bases for definition of price components
Case 1:
Road tunnel
with junctions
Case 2:
Water
treatment plant
Case 3:
Road bridge and
surroundings
Case 4:
Arterial road with
junctions
· Fee    
· Cost escalation *  **
· Risk contingency   
· Project overhead   
· Preliminaries costs 
· Direct costs, structure-specific***  
· Direct costs, section-specific**** 
· Defect correction 
*
)
Part of risk contingency. **
)
Part of direct costs.
***
)
Direct costs are tendered in the case of certain structures of a diverse project.
****
)
Direct costs are tendered in the case of a certain section/area of a wider project.
1327/08/2014 13
Additional cost management measures
(open books process)
 Final stage competitors are subjected to financial audits where the level of
costs of realised projects can be assessed to serve as a benchmark.
 The proponents are expected to include their pricing bases in their tenders for
additional auditing and to serve as benchmarks.
 Major purchases of the project are to be jointly subjected to competitive
bidding later and, at the minimum, the prices are to be market-tested.
 An independent third-party estimator is involved to assess the
appropriateness of the target outturn cost and the cost items it consists of.
 A financial auditor is involved to verify costs incurred and financial
management in general (financial systems, reporting and invoicing).
 The owner’s budget guiding the joint development is based on two estimates
completed independently and is made strict compared to the general cost level.
 The owner has the right to terminate the project for convenience, but the
owner has to pay a fair compensation for all services carried out by then.
1427/08/2014 14
Early team involvement and joint development:
When?
 For complex projects involving a lot of uncertainties
Project type Unique, the like of which have never or very rarely
been implemented
Stakeholders Many key stakeholders with conflicting needs that are
difficult to engage with multiple proponents
Technology Requires new processes or unique application of familiar
methods e.g. due to experimental construction
Construction work Major engineering difficulties can be expected and
duration of work is hard to forecast
Risk
identification
Risks and their impacts cannot be determined and
dealing with risks requires collaboration between actors
during construction
1527/08/2014 15
Lessons learned
 Experiences from the use of price component selection have been highly
positive: other benefits overrule possible challenges
 Aim at a comprehensive comparative price may lead to the same doubts that
have been found problematic in pure price competition
 The use price components may make procurement more challenging, unless
the contents of the components have been clearly defined
 The comparison of tenders is challenging and the owner often has to work to
make the tenders commensurate before deriving genuinely comparable prices
 Price component selection is not expected to be the answer to all situations
and projects: it is for challenging projects requiring innovative approaches
 The practice should be combined with the principles of transparency of
information (open books practice) including external auditors and estimators
 An emphasis given to the creation of collaborative, trustful relationships among
the team members to make the joint development effort more effective
TECHNOLOGY FOR BUSINESS

More Related Content

What's hot

Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
Kai Yun Pang
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
Prateek Kashyap
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
efinancemanagement.com
 
Assignment - Cost Plan
Assignment - Cost PlanAssignment - Cost Plan
Assignment - Cost Plan
Kai Yun Pang
 
Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
Delhi Technological University
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
Timun Loh
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
Yudi Setiawan
 
Project evaluation and cost benefit analysis
Project evaluation and cost benefit analysisProject evaluation and cost benefit analysis
Project evaluation and cost benefit analysis
MAHONDO JAMES
 
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen ErnstHNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
Helix Nebula The Science Cloud
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting Models
This account is closed
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
Helix Nebula The Science Cloud
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
Adi Iskandar Iliyas
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
fritzlejarso
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11
cmcgoverntobin
 
CIP Ecoinnovation – how to write a successful proposal
CIP Ecoinnovation – how to write a successful proposalCIP Ecoinnovation – how to write a successful proposal
CIP Ecoinnovation – how to write a successful proposal
impulse.brussels
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
Doreen Yeo
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Moustafa Ismail Abu Dief
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Neil Mathew
 

What's hot (20)

Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Assignment - Cost Plan
Assignment - Cost PlanAssignment - Cost Plan
Assignment - Cost Plan
 
Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
 
Project evaluation and cost benefit analysis
Project evaluation and cost benefit analysisProject evaluation and cost benefit analysis
Project evaluation and cost benefit analysis
 
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen ErnstHNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
HNSciCloud Info Day, 7 Sept 2016, Legal Issues by Karen Ernst
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting Models
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11
 
contract procedure
contract procedurecontract procedure
contract procedure
 
CIP Ecoinnovation – how to write a successful proposal
CIP Ecoinnovation – how to write a successful proposalCIP Ecoinnovation – how to write a successful proposal
CIP Ecoinnovation – how to write a successful proposal
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)
 

Viewers also liked

2014 aug15 collaborative proc sv
2014 aug15 collaborative proc sv2014 aug15 collaborative proc sv
2014 aug15 collaborative proc sv
Dr. Paul Davis
 
Nephin 8 months in pictures
Nephin   8 months in picturesNephin   8 months in pictures
Nephin 8 months in pictures
Dr. Paul Davis
 
Yakovlev et al. presentation at ippc (aug 2014)
Yakovlev et al.   presentation at ippc (aug 2014)Yakovlev et al.   presentation at ippc (aug 2014)
Yakovlev et al. presentation at ippc (aug 2014)Dr. Paul Davis
 
Palmer gupta ippc purchasing card govt efficiency final
Palmer gupta ippc purchasing card govt efficiency finalPalmer gupta ippc purchasing card govt efficiency final
Palmer gupta ippc purchasing card govt efficiency final
Dr. Paul Davis
 
Stake sm es in pp ippc 2014 dublin
Stake   sm es in pp ippc 2014 dublinStake   sm es in pp ippc 2014 dublin
Stake sm es in pp ippc 2014 dublin
Dr. Paul Davis
 
Efficient pure project alliances in the public sector
Efficient pure project alliances in the public sectorEfficient pure project alliances in the public sector
Efficient pure project alliances in the public sector
Dr. Paul Davis
 
2014 ippc dublin v3
2014 ippc dublin v32014 ippc dublin v3
2014 ippc dublin v3
Dr. Paul Davis
 
Dublin presentation a.korkmaz
Dublin presentation a.korkmazDublin presentation a.korkmaz
Dublin presentation a.korkmaz
Dr. Paul Davis
 
Ippcswe dublin2014
Ippcswe dublin2014Ippcswe dublin2014
Ippcswe dublin2014
Dr. Paul Davis
 
Presentation dublin 2014 la cour oelykke final
Presentation dublin 2014 la cour   oelykke finalPresentation dublin 2014 la cour   oelykke final
Presentation dublin 2014 la cour oelykke final
Dr. Paul Davis
 
Presentation ruyi wan
Presentation ruyi wanPresentation ruyi wan
Presentation ruyi wan
Dr. Paul Davis
 
Ippc 2014
Ippc 2014Ippc 2014
Ippc 2014
Dr. Paul Davis
 
Dublin ppt
Dublin pptDublin ppt
Dublin ppt
Dr. Paul Davis
 
6th ippc km and public procurement v1.0
6th ippc km and public procurement v1.06th ippc km and public procurement v1.0
6th ippc km and public procurement v1.0
Dr. Paul Davis
 
Differentiation of strategic and tactical contracting actions by
Differentiation of strategic and tactical contracting actions byDifferentiation of strategic and tactical contracting actions by
Differentiation of strategic and tactical contracting actions by
Dr. Paul Davis
 
Caricom small market big money ippc6 2014
Caricom small market big money ippc6 2014Caricom small market big money ippc6 2014
Caricom small market big money ippc6 2014
Dr. Paul Davis
 
Ippc2014
Ippc2014Ippc2014
Ippc2014
Dr. Paul Davis
 
When practice met kraljic 130814
When practice met kraljic 130814When practice met kraljic 130814
When practice met kraljic 130814
Dr. Paul Davis
 

Viewers also liked (19)

2014 aug15 collaborative proc sv
2014 aug15 collaborative proc sv2014 aug15 collaborative proc sv
2014 aug15 collaborative proc sv
 
Nephin 8 months in pictures
Nephin   8 months in picturesNephin   8 months in pictures
Nephin 8 months in pictures
 
Yakovlev et al. presentation at ippc (aug 2014)
Yakovlev et al.   presentation at ippc (aug 2014)Yakovlev et al.   presentation at ippc (aug 2014)
Yakovlev et al. presentation at ippc (aug 2014)
 
Palmer gupta ippc purchasing card govt efficiency final
Palmer gupta ippc purchasing card govt efficiency finalPalmer gupta ippc purchasing card govt efficiency final
Palmer gupta ippc purchasing card govt efficiency final
 
Stake sm es in pp ippc 2014 dublin
Stake   sm es in pp ippc 2014 dublinStake   sm es in pp ippc 2014 dublin
Stake sm es in pp ippc 2014 dublin
 
Efficient pure project alliances in the public sector
Efficient pure project alliances in the public sectorEfficient pure project alliances in the public sector
Efficient pure project alliances in the public sector
 
2014 ippc dublin v3
2014 ippc dublin v32014 ippc dublin v3
2014 ippc dublin v3
 
Dublin presentation a.korkmaz
Dublin presentation a.korkmazDublin presentation a.korkmaz
Dublin presentation a.korkmaz
 
Ippcswe dublin2014
Ippcswe dublin2014Ippcswe dublin2014
Ippcswe dublin2014
 
Presentation dublin 2014 la cour oelykke final
Presentation dublin 2014 la cour   oelykke finalPresentation dublin 2014 la cour   oelykke final
Presentation dublin 2014 la cour oelykke final
 
Presentation ruyi wan
Presentation ruyi wanPresentation ruyi wan
Presentation ruyi wan
 
Ippc 2014
Ippc 2014Ippc 2014
Ippc 2014
 
Ippc
IppcIppc
Ippc
 
Dublin ppt
Dublin pptDublin ppt
Dublin ppt
 
6th ippc km and public procurement v1.0
6th ippc km and public procurement v1.06th ippc km and public procurement v1.0
6th ippc km and public procurement v1.0
 
Differentiation of strategic and tactical contracting actions by
Differentiation of strategic and tactical contracting actions byDifferentiation of strategic and tactical contracting actions by
Differentiation of strategic and tactical contracting actions by
 
Caricom small market big money ippc6 2014
Caricom small market big money ippc6 2014Caricom small market big money ippc6 2014
Caricom small market big money ippc6 2014
 
Ippc2014
Ippc2014Ippc2014
Ippc2014
 
When practice met kraljic 130814
When practice met kraljic 130814When practice met kraljic 130814
When practice met kraljic 130814
 

Similar to Rationalising ippc6 clean

Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavaruban
thevaraja pavaruban
 
Net challenge training_material_collaborative planning_v002
Net challenge training_material_collaborative planning_v002Net challenge training_material_collaborative planning_v002
Net challenge training_material_collaborative planning_v002netchallenge
 
Collaborative Contracting.pptx
Collaborative Contracting.pptxCollaborative Contracting.pptx
Collaborative Contracting.pptx
BharathBabu40
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
2cd
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Renewable Energy Auctions in the EU: Final findings AURES project
Renewable Energy Auctions in the EU: Final findings AURES projectRenewable Energy Auctions in the EU: Final findings AURES project
Renewable Energy Auctions in the EU: Final findings AURES project
Leonardo ENERGY
 
costanalysis.pptx
costanalysis.pptxcostanalysis.pptx
costanalysis.pptx
FriendsPark1
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
johnkirth1898
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
OECD Governance
 
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB SummitABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
Global Infrastructure Basel Foundation
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
mekuannintdemeke
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET Journal
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdf
ThanoonQasem
 
Uap Document
Uap DocumentUap Document
Uap Document
Enelai Rosal
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web readySumit Gupta
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
AprilRosal1
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
JunaidMughal34
 

Similar to Rationalising ippc6 clean (20)

Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavaruban
 
ACH 231 Lecture 05 (Design Contracts Part 1)
ACH 231 Lecture 05 (Design Contracts Part 1)ACH 231 Lecture 05 (Design Contracts Part 1)
ACH 231 Lecture 05 (Design Contracts Part 1)
 
Net challenge training_material_collaborative planning_v002
Net challenge training_material_collaborative planning_v002Net challenge training_material_collaborative planning_v002
Net challenge training_material_collaborative planning_v002
 
Collaborative Contracting.pptx
Collaborative Contracting.pptxCollaborative Contracting.pptx
Collaborative Contracting.pptx
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Renewable Energy Auctions in the EU: Final findings AURES project
Renewable Energy Auctions in the EU: Final findings AURES projectRenewable Energy Auctions in the EU: Final findings AURES project
Renewable Energy Auctions in the EU: Final findings AURES project
 
costanalysis.pptx
costanalysis.pptxcostanalysis.pptx
costanalysis.pptx
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB SummitABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction Industry
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdf
 
Uap Document
Uap DocumentUap Document
Uap Document
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 

More from Dr. Paul Davis

Yakovlev et al. presentation at ippc (aug 2014)
Yakovlev et al.   presentation at ippc (aug 2014)Yakovlev et al.   presentation at ippc (aug 2014)
Yakovlev et al. presentation at ippc (aug 2014)
Dr. Paul Davis
 
Vortrag ippc
Vortrag ippcVortrag ippc
Vortrag ippc
Dr. Paul Davis
 
The municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longerThe municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longer
Dr. Paul Davis
 
Sutthi sun ippc 6
Sutthi sun ippc 6Sutthi sun ippc 6
Sutthi sun ippc 6
Dr. Paul Davis
 
Strategies in pp essig140814
Strategies in pp essig140814Strategies in pp essig140814
Strategies in pp essig140814
Dr. Paul Davis
 
Salazar d is_publicprocurement_dev_tool
Salazar d is_publicprocurement_dev_toolSalazar d is_publicprocurement_dev_tool
Salazar d is_publicprocurement_dev_tool
Dr. Paul Davis
 
Richo improving effectiveness in bid protest mechanism ippc 6 dublin
Richo improving effectiveness in bid protest mechanism ippc 6 dublinRicho improving effectiveness in bid protest mechanism ippc 6 dublin
Richo improving effectiveness in bid protest mechanism ippc 6 dublin
Dr. Paul Davis
 
Rabiu m shuaib nura jibo
Rabiu m shuaib nura jiboRabiu m shuaib nura jibo
Rabiu m shuaib nura jibo
Dr. Paul Davis
 
Procurement efficiency jp
Procurement efficiency jpProcurement efficiency jp
Procurement efficiency jp
Dr. Paul Davis
 
Presentation
PresentationPresentation
Presentation
Dr. Paul Davis
 
Presentation slide-sakane:8-14 parallel-track_1_at_hg19
Presentation slide-sakane:8-14 parallel-track_1_at_hg19Presentation slide-sakane:8-14 parallel-track_1_at_hg19
Presentation slide-sakane:8-14 parallel-track_1_at_hg19
Dr. Paul Davis
 
Presentatie sophie dublin def
Presentatie sophie dublin defPresentatie sophie dublin def
Presentatie sophie dublin def
Dr. Paul Davis
 
Presentacion
PresentacionPresentacion
Presentacion
Dr. Paul Davis
 
Ppt ippc 2014
Ppt ippc 2014Ppt ippc 2014
Ppt ippc 2014
Dr. Paul Davis
 
Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014
Dr. Paul Davis
 
Muehle ochieng 6ippc_p2p_presentation
Muehle ochieng 6ippc_p2p_presentationMuehle ochieng 6ippc_p2p_presentation
Muehle ochieng 6ippc_p2p_presentation
Dr. Paul Davis
 
Legal foundation of electronic procurement 2
Legal foundation of electronic procurement 2Legal foundation of electronic procurement 2
Legal foundation of electronic procurement 2
Dr. Paul Davis
 
Kivistö et al_innovative procurement processes
Kivistö et al_innovative procurement processesKivistö et al_innovative procurement processes
Kivistö et al_innovative procurement processes
Dr. Paul Davis
 
Ippc2014presentation
Ippc2014presentationIppc2014presentation
Ippc2014presentation
Dr. Paul Davis
 
Ippc2014 shaffer snider
Ippc2014 shaffer sniderIppc2014 shaffer snider
Ippc2014 shaffer snider
Dr. Paul Davis
 

More from Dr. Paul Davis (20)

Yakovlev et al. presentation at ippc (aug 2014)
Yakovlev et al.   presentation at ippc (aug 2014)Yakovlev et al.   presentation at ippc (aug 2014)
Yakovlev et al. presentation at ippc (aug 2014)
 
Vortrag ippc
Vortrag ippcVortrag ippc
Vortrag ippc
 
The municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longerThe municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longer
 
Sutthi sun ippc 6
Sutthi sun ippc 6Sutthi sun ippc 6
Sutthi sun ippc 6
 
Strategies in pp essig140814
Strategies in pp essig140814Strategies in pp essig140814
Strategies in pp essig140814
 
Salazar d is_publicprocurement_dev_tool
Salazar d is_publicprocurement_dev_toolSalazar d is_publicprocurement_dev_tool
Salazar d is_publicprocurement_dev_tool
 
Richo improving effectiveness in bid protest mechanism ippc 6 dublin
Richo improving effectiveness in bid protest mechanism ippc 6 dublinRicho improving effectiveness in bid protest mechanism ippc 6 dublin
Richo improving effectiveness in bid protest mechanism ippc 6 dublin
 
Rabiu m shuaib nura jibo
Rabiu m shuaib nura jiboRabiu m shuaib nura jibo
Rabiu m shuaib nura jibo
 
Procurement efficiency jp
Procurement efficiency jpProcurement efficiency jp
Procurement efficiency jp
 
Presentation
PresentationPresentation
Presentation
 
Presentation slide-sakane:8-14 parallel-track_1_at_hg19
Presentation slide-sakane:8-14 parallel-track_1_at_hg19Presentation slide-sakane:8-14 parallel-track_1_at_hg19
Presentation slide-sakane:8-14 parallel-track_1_at_hg19
 
Presentatie sophie dublin def
Presentatie sophie dublin defPresentatie sophie dublin def
Presentatie sophie dublin def
 
Presentacion
PresentacionPresentacion
Presentacion
 
Ppt ippc 2014
Ppt ippc 2014Ppt ippc 2014
Ppt ippc 2014
 
Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014
 
Muehle ochieng 6ippc_p2p_presentation
Muehle ochieng 6ippc_p2p_presentationMuehle ochieng 6ippc_p2p_presentation
Muehle ochieng 6ippc_p2p_presentation
 
Legal foundation of electronic procurement 2
Legal foundation of electronic procurement 2Legal foundation of electronic procurement 2
Legal foundation of electronic procurement 2
 
Kivistö et al_innovative procurement processes
Kivistö et al_innovative procurement processesKivistö et al_innovative procurement processes
Kivistö et al_innovative procurement processes
 
Ippc2014presentation
Ippc2014presentationIppc2014presentation
Ippc2014presentation
 
Ippc2014 shaffer snider
Ippc2014 shaffer sniderIppc2014 shaffer snider
Ippc2014 shaffer snider
 

Recently uploaded

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 

Recently uploaded (20)

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 

Rationalising ippc6 clean

  • 1. Rationalising public procurement of complex construction projects by the price component selection The 6th International Public Procurement Conference (IPPC), August 14–16, 2014, Dublin, Ireland Pertti Lahdenperä VTT Technical Research Centre of Finland
  • 2. 227/08/2014 2 Early team involvement and joint development: Why?  Involvement of multidisciplinary expertise in critical design  Closer team integration and improved collaboration Cost of late design changes Ability to impact cost and total value Quantity/volume Involve key players here ! Accrued costs of the project Uncertainty in relation to cost and total value Quantity/volume Design ConstructionConcept ImplementationDevelopmentConception Fix the target cost here ! Do the development jointly !
  • 3. 327/08/2014 3 Selection criteria – common characteristics Preliminary price component submitted by tenderer Binding price component offered by tenderer Owner’s calculation (tenderer’s unit prices) Owner’s cost estimate (same for all competitors) Determinated by the owner (owner’s consultant) based on varying types of cost data: & Targets of assessment · past performance · organisation · know-how and experience of section managers · project strategies, approaches and management plans · alliance skills and affinity · collaboration capability · concept design / design commentary Capability / Quality Comparative price ”The most economically advantageous tender”
  • 4. 427/08/2014 4 Case 1: Road tunnel with junctions
  • 5. 527/08/2014 5 Case 1: Formulation of comparative price Designers’ fee is calculated as a percentage of direct design costs Direct costs are based on owner’s cost estimate Contractor’s fee is fixed in euros The comparative price is the sum of the fees and costs Direct Design Costs [€] Fee [%] Binding price component offered by tenderer Owner’s cost estimate (same for all competitors) Fee [€] Direct Construction Costs [€] + + +
  • 6. 6627/08/2014 Case 2: Water treatment plant
  • 7. 727/08/2014 7 Case 2: Formulation of comparative price Fee is calculated as a percentage of the sum of other costs Direct costs are based on client’s cost estimate The comparative price is the sum of the dollar fee and other costs Management and preliminaries costs, risk provision and fee are those tendered by competitors Direct Costs [$] Preliminaries [$] Project Overhead [$] Fee [%] Risk and Opportunity [$] + + + Binding price component offered by tenderer Owner’s cost estimate (same for all competitors) +
  • 8. 8827/08/2014 Case 3: Road bridge and surroundings
  • 9. 927/08/2014 9 Case 3: Formulation of comparative price Fee is calculated as a percentage of the sum of other costs Tenders are binding as to bridge and project overhead costs The comparative price is the sum of the dollar fee and other costs Prices of the balance of works are preliminary Bridge Target Outturn Cost [$] Balance of Works Budget [$] Contingency [$] Project Overhead Target Outturn Cost [$] Contingency [$] Fee [%] Project Overhead Contingency [$] + + + + + Binding price component offered by tenderer Preliminary price component submitted by tenderer +
  • 10. 10 Case 4: Arterial road with junctions
  • 11. 1127/08/2014 11 Case 4: Formulation of comparative price Fee is calculated as a percentage of the sum of all other costs Cost of warranty work is expressed as a percentage of construction works costs The comparative price is the sum of the dollar fee and other costs Priced Works Lump Sum [$] (Package 1) [$] (2) Defect Correction Costs [%] Project Overhead [$] Fee [%] Risk and Contingency Provision [%] + + + [$] (3) + [$]+ [$]+ + Works Costs, other works [$] + Binding price component offered by tenderer Owner’s calculation (tenderer’s unit prices) Owner’s cost estimate (same for all competitors) + Risk provision is calculated as a percentage of estimated direct project costs
  • 12. 1227/08/2014 12 Bases for definition of price components Case 1: Road tunnel with junctions Case 2: Water treatment plant Case 3: Road bridge and surroundings Case 4: Arterial road with junctions · Fee     · Cost escalation *  ** · Risk contingency    · Project overhead    · Preliminaries costs  · Direct costs, structure-specific***   · Direct costs, section-specific****  · Defect correction  * ) Part of risk contingency. ** ) Part of direct costs. *** ) Direct costs are tendered in the case of certain structures of a diverse project. **** ) Direct costs are tendered in the case of a certain section/area of a wider project.
  • 13. 1327/08/2014 13 Additional cost management measures (open books process)  Final stage competitors are subjected to financial audits where the level of costs of realised projects can be assessed to serve as a benchmark.  The proponents are expected to include their pricing bases in their tenders for additional auditing and to serve as benchmarks.  Major purchases of the project are to be jointly subjected to competitive bidding later and, at the minimum, the prices are to be market-tested.  An independent third-party estimator is involved to assess the appropriateness of the target outturn cost and the cost items it consists of.  A financial auditor is involved to verify costs incurred and financial management in general (financial systems, reporting and invoicing).  The owner’s budget guiding the joint development is based on two estimates completed independently and is made strict compared to the general cost level.  The owner has the right to terminate the project for convenience, but the owner has to pay a fair compensation for all services carried out by then.
  • 14. 1427/08/2014 14 Early team involvement and joint development: When?  For complex projects involving a lot of uncertainties Project type Unique, the like of which have never or very rarely been implemented Stakeholders Many key stakeholders with conflicting needs that are difficult to engage with multiple proponents Technology Requires new processes or unique application of familiar methods e.g. due to experimental construction Construction work Major engineering difficulties can be expected and duration of work is hard to forecast Risk identification Risks and their impacts cannot be determined and dealing with risks requires collaboration between actors during construction
  • 15. 1527/08/2014 15 Lessons learned  Experiences from the use of price component selection have been highly positive: other benefits overrule possible challenges  Aim at a comprehensive comparative price may lead to the same doubts that have been found problematic in pure price competition  The use price components may make procurement more challenging, unless the contents of the components have been clearly defined  The comparison of tenders is challenging and the owner often has to work to make the tenders commensurate before deriving genuinely comparable prices  Price component selection is not expected to be the answer to all situations and projects: it is for challenging projects requiring innovative approaches  The practice should be combined with the principles of transparency of information (open books practice) including external auditors and estimators  An emphasis given to the creation of collaborative, trustful relationships among the team members to make the joint development effort more effective