The economic literature ever since the dawn of modern economics has been much preoccupied with the issue of economic growth Economic growth has also been understood to establish the conditions for economic development The better-known models of economic growth such as the Lewis, Rostow Harrod Domar Solow, and Romer growth models are discussed
The economic literature ever since the dawn of modern economics has been much preoccupied with the issue of economic growth Economic growth has also been understood to establish the conditions for economic development The better-known models of economic growth such as the Lewis, Rostow Harrod Domar Solow, and Romer growth models are discussed
HOW TO EVALUATE PROJECT BY USING PROJECT APPRAISAL METHOD AT WORKPLACEAbraham Ncunge
Project appraisal is an as"
ASSESSMENT of the project in seven steps. Project appraisal is carried out in two main steps namely internal and external appraisal.
The other steps a technical,economical ,social ,political, environmental,financial commercial ,administrative
it is useful for project management students in which process of scba (social cost benefit analysis) is given in detail and these steps are simple to learn and depend on approches also and that aproches are in next presentation.
INFORMATION SYTEMS 3
Part-3: Mr. and Mrs. Rodgers House (House construction)
BUDGET AND RISK MANAGEMENT
1.0.
Overall Project Budget
A technique called Earned Value Management (EVM) compares project performance to the project baseline (Xu et al., 2018). All project managers pursuing Project Management Professional (PMP) certification learn and memorize the earned value calculations. Their application in real life is patchy, though. According to Insight, EVM is among the "critical few" best areas of practice for keeping track of a project's progress from both a schedule and cost standpoint (Vasyunina, 2017). The binary way of thinking about projects is widespread:
· On time versus late
· Over budget versus under budget.
On the project cost, both performance evaluation elements have a significant impact (Chang et al., 2022). If our costs are lower yet we are running late, EVM provides excellent facts of the matter.
Determining Earned Value
Computing EV involves:
· The sum of the up-to-date project budget, known as the planned value (PV)
· Current costs are identical to Actual Cost (AC).
· The project budget is multiplied by the proportion of execution to determine earned value (EV).
Now that we have these numbers, we can start making some computations of:
Schedule Performance Index (SPI) = EV/PV
SPI contrasts actual and anticipated progress. Whenever the SPI value had been than 1.0, fewer tasks were completed than expected. SPI > 1.0 denotes the completion of more work than anticipated.
Determining the CPI:
CPI= AC÷EV
The CPI evaluates the worth of finished work in relation to its true cost. Its score of 1.0 denotes high costs than anticipated. A CPI of greater than one shows that costs remained lower than expected.
For the SPI and CPI, >1 is favorable while 1 is unfavorable.
Remember that;
Subtracting instead of dividing allows you to rapidly determine the difference between the project budget and the timeline. Schedule variance (SV) equals EV-PV, whereas cost variance = EV-AC. You can easily execute the subtraction operation in your head, and in this case, >0 is favorable to 0 in this situation.
Except in the case of SPI or CPI, deviation is reliant on the project's scope. Therefore, we cannot compare it across construction project or across time effectively, as the budget might have changed.
Calculating the Project EAC:
CPI = EAC ÷ Overall Budget
EAC represents the prediction aggregate cost.
In summary:
· Project is halfway to its completion,
· PV = $55,000
· AC= $45,000
The calculations are as follows:
EV=100,000 ×1/2
=$50,000
SV =EV-PV
Where EV=50,000 and PV=55,000
Therefore, SP= 50,000-55,000
=-$5000
In this case, the value of SP is -$5,000, which is unfavorable for our project because it is less than 0.
SPI = EV/PV
Thus;
SP1=50,000 ÷55,000
= $0.91
However, the SPI value is less than.
Introduction to Indian Financial System ()Avanish Goel
The financial system of a country is an important tool for economic development of the country, as it helps in creation of wealth by linking savings with investments.
It facilitates the flow of funds form the households (savers) to business firms (investors) to aid in wealth creation and development of both the parties
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...Quotidiano Piemontese
Turin Startup Ecosystem 2024
Una ricerca de il Club degli Investitori, in collaborazione con ToTeM Torino Tech Map e con il supporto della ESCP Business School e di Growth Capital
If you are looking for a pi coin investor. Then look no further because I have the right one he is a pi vendor (he buy and resell to whales in China). I met him on a crypto conference and ever since I and my friends have sold more than 10k pi coins to him And he bought all and still want more. I will drop his telegram handle below just send him a message.
@Pi_vendor_247
Even tho Pi network is not listed on any exchange yet.
Buying/Selling or investing in pi network coins is highly possible through the help of vendors. You can buy from vendors[ buy directly from the pi network miners and resell it]. I will leave the telegram contact of my personal vendor.
@Pi_vendor_247
USDA Loans in California: A Comprehensive Overview.pptxmarketing367770
USDA Loans in California: A Comprehensive Overview
If you're dreaming of owning a home in California's rural or suburban areas, a USDA loan might be the perfect solution. The U.S. Department of Agriculture (USDA) offers these loans to help low-to-moderate-income individuals and families achieve homeownership.
Key Features of USDA Loans:
Zero Down Payment: USDA loans require no down payment, making homeownership more accessible.
Competitive Interest Rates: These loans often come with lower interest rates compared to conventional loans.
Flexible Credit Requirements: USDA loans have more lenient credit score requirements, helping those with less-than-perfect credit.
Guaranteed Loan Program: The USDA guarantees a portion of the loan, reducing risk for lenders and expanding borrowing options.
Eligibility Criteria:
Location: The property must be located in a USDA-designated rural or suburban area. Many areas in California qualify.
Income Limits: Applicants must meet income guidelines, which vary by region and household size.
Primary Residence: The home must be used as the borrower's primary residence.
Application Process:
Find a USDA-Approved Lender: Not all lenders offer USDA loans, so it's essential to choose one approved by the USDA.
Pre-Qualification: Determine your eligibility and the amount you can borrow.
Property Search: Look for properties in eligible rural or suburban areas.
Loan Application: Submit your application, including financial and personal information.
Processing and Approval: The lender and USDA will review your application. If approved, you can proceed to closing.
USDA loans are an excellent option for those looking to buy a home in California's rural and suburban areas. With no down payment and flexible requirements, these loans make homeownership more attainable for many families. Explore your eligibility today and take the first step toward owning your dream home.
what is the best method to sell pi coins in 2024DOT TECH
The best way to sell your pi coins safely is trading with an exchange..but since pi is not launched in any exchange, and second option is through a VERIFIED pi merchant.
Who is a pi merchant?
A pi merchant is someone who buys pi coins from miners and pioneers and resell them to Investors looking forward to hold massive amounts before mainnet launch in 2026.
I will leave the telegram contact of my personal pi merchant to trade pi coins with.
@Pi_vendor_247
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
how can i use my minded pi coins I need some funds.DOT TECH
If you are interested in selling your pi coins, i have a verified pi merchant, who buys pi coins and resell them to exchanges looking forward to hold till mainnet launch.
Because the core team has announced that pi network will not be doing any pre-sale. The only way exchanges like huobi, bitmart and hotbit can get pi is by buying from miners.
Now a merchant stands in between these exchanges and the miners. As a link to make transactions smooth. Because right now in the enclosed mainnet you can't sell pi coins your self. You need the help of a merchant,
i will leave the telegram contact of my personal pi merchant below. 👇 I and my friends has traded more than 3000pi coins with him successfully.
@Pi_vendor_247
how to sell pi coins in all Africa Countries.DOT TECH
Yes. You can sell your pi network for other cryptocurrencies like Bitcoin, usdt , Ethereum and other currencies And this is done easily with the help from a pi merchant.
What is a pi merchant ?
Since pi is not launched yet in any exchange. The only way you can sell right now is through merchants.
A verified Pi merchant is someone who buys pi network coins from miners and resell them to investors looking forward to hold massive quantities of pi coins before mainnet launch in 2026.
I will leave the telegram contact of my personal pi merchant to trade with.
@Pi_vendor_247
Currently pi network is not tradable on binance or any other exchange because we are still in the enclosed mainnet.
Right now the only way to sell pi coins is by trading with a verified merchant.
What is a pi merchant?
A pi merchant is someone verified by pi network team and allowed to barter pi coins for goods and services.
Since pi network is not doing any pre-sale The only way exchanges like binance/huobi or crypto whales can get pi is by buying from miners. And a merchant stands in between the exchanges and the miners.
I will leave the telegram contact of my personal pi merchant. I and my friends has traded more than 6000pi coins successfully
Tele-gram
@Pi_vendor_247
Latino Buying Power - May 2024 Presentation for Latino CaucusDanay Escanaverino
Unlock the potential of Latino Buying Power with this in-depth SlideShare presentation. Explore how the Latino consumer market is transforming the American economy, driven by their significant buying power, entrepreneurial contributions, and growing influence across various sectors.
**Key Sections Covered:**
1. **Economic Impact:** Understand the profound economic impact of Latino consumers on the U.S. economy. Discover how their increasing purchasing power is fueling growth in key industries and contributing to national economic prosperity.
2. **Buying Power:** Dive into detailed analyses of Latino buying power, including its growth trends, key drivers, and projections for the future. Learn how this influential group’s spending habits are shaping market dynamics and creating opportunities for businesses.
3. **Entrepreneurial Contributions:** Explore the entrepreneurial spirit within the Latino community. Examine how Latino-owned businesses are thriving and contributing to job creation, innovation, and economic diversification.
4. **Workforce Statistics:** Gain insights into the role of Latino workers in the American labor market. Review statistics on employment rates, occupational distribution, and the economic contributions of Latino professionals across various industries.
5. **Media Consumption:** Understand the media consumption habits of Latino audiences. Discover their preferences for digital platforms, television, radio, and social media. Learn how these consumption patterns are influencing advertising strategies and media content.
6. **Education:** Examine the educational achievements and challenges within the Latino community. Review statistics on enrollment, graduation rates, and fields of study. Understand the implications of education on economic mobility and workforce readiness.
7. **Home Ownership:** Explore trends in Latino home ownership. Understand the factors driving home buying decisions, the challenges faced by Latino homeowners, and the impact of home ownership on community stability and economic growth.
This SlideShare provides valuable insights for marketers, business owners, policymakers, and anyone interested in the economic influence of the Latino community. By understanding the various facets of Latino buying power, you can effectively engage with this dynamic and growing market segment.
Equip yourself with the knowledge to leverage Latino buying power, tap into their entrepreneurial spirit, and connect with their unique cultural and consumer preferences. Drive your business success by embracing the economic potential of Latino consumers.
**Keywords:** Latino buying power, economic impact, entrepreneurial contributions, workforce statistics, media consumption, education, home ownership, Latino market, Hispanic buying power, Latino purchasing power.
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...Amil baba
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
2. CHAPTER OUTLINE:
Part 1:
1. Introduction to project evaluation.
2. Stages in project evaluation.
3. Methods of evaluation.
4. Cost-Benefit analysis.
5. Evaluation on the basis of cost benefit criteria.
6. The Net Present Value criteria ( NPV).
7. The internal Rate of Return (IRR).
Part 2:
1. Relationship between NPV & IRR.
2. The Social Rate of Discount.
3. Evaluation on the basis of Benefits.
4. Evaluation on the basis of costs.
5. Importance of data for evaluation.
6. Limitation of Cost- Benefit analysis.
7. Use of Cost-Benefit analysis in Developing
Countries.
4. Introduction to project evaluation:
Meaning: ( What, How, Who, Why)
What: It is a specialized planning process which involves systematic, objective and comprehensive
appraisal of development programmes for individual commodities and/or projects.
How: it is conducted by assessing or apprising it's operational efficiency; technically, economically,
financially and managerially.
Who: It is usually conducted by a group of outside experts
Why? It is done in order to find out projects achievement and weaknesses and to suggest (
recommend) ways and mean to overcoming the weakness and to improve its operation
In summary: It is a process of evaluating the rate of return on a project, its social profitability and its side
effects on the growth rate of population, on employment , on labor and management training and on
rate of reinvestment.
5. Stages in project evaluation:
Project evaluation involves 4 stages:
1. Review: Review of the situation before the project is actually started
2. Appraisal: This is done in order to find out how much has ben accomplished
and what remains to be accomplished
3. Recommendation: Suggestions on ways and means to improve its operation
further and to plug loopholes
4. Evaluation: Evaluation of the end achieved by the project when it is complete
and is in full operation
6. Methods of evaluation:
This involves 4 areas:
1. Description: of the technical and economic characteristic of each project.
2. Estimation: of the influence of project on the economy , both during
construction , operation period and when the investment is completed and the
newly productive capacity is in operation.
3. Evaluation: of the project’s consequences both direct and indirect
4. Formulation: of the criterion for the selection of the project.
7. Cost-Benefit analysis:
It is the most popular and appropriate method of apprising projects from the
national stand point of view
It helps the planning authority in making correct investment decisions to achieve
optimum resource allocation by maximizing the difference between the present
value of benefits and cost of a project
It purports to describe and quantify the social advantages and disadvantages of a
policy in terms of the common monetary unit.
Its objective function, Net Social Benefit , NSB, is expressed as:
NSB= Benefits – Costs
Note: Benefits and cost are expressed in terms of ‘Shadow’ or ‘accounting’ prices of
inputs and outputs
8. Evaluation on the basis of cost benefit
criteria:
There are 4 benefit-cost criteria;
1. B-C
2. B-C/I
3.
4. B/C
Note:
I relates to direct investment and is increment or marginal change
B/ C
9. Evaluation on the basis of cost benefit
criteria:
B-C Criterion
This favors large projects and makes
small and medium size projects less
beneficial.
Therefore, can only be used in the
determination of the scale of the project
on the basis of the maximization of the
difference between B & C
B-C/I Criterion
Used in determining the total annual
returns on a particular investment to the
economy as a whole irrespective of the
those accrue
Note: I does not include the private
investment that my have to be incurred
by the beneficiaries of the project
10. Evaluation on the basis of cost benefit
criteria:
B/C Criterion
This is the best criterion.
This benefit-cost ratio is the measure for
evaluation of a project.
If B/C= 1, the project is marginal
If B/C > 1, the benefits are more that the
cost
If B/C< 1 , the benefits are less that the
cost
Criterion
This is meant to determine the size of a
project that has already been selected and
is not for selecting a project
11. Evaluation on the basis of cost benefit
criteria:
Note:
The benefit cost ratio formula does not take into account the time horizon of the project
.
Future benefits and costs cannot be treated at per with present benefit and costs
Therefore , the need for discounting the future benefits and costs because society
prefers the present to future.
For this reason economist have come up with a number of ‘decision rules’ or criteria.
For this course we will focus our attention on 2 criteria;
1. Present Value criterion
2. Internal rate of return.
12. The Net Present Value criteria (NPV):
NPV = Present value of benefits – (Present value of operating + Maintenance
cost + Initial outlay)
OR
Net present value of benefits (NPVB)= Gross present value of benefits – Gross
present value of cost
A project is socially profitable if the NPVB>0 .
It there are a number of mutually exclusive projects, the project with the highest net
present value of benefits will be choosen.
13. The Net Present Value criteria (NPV):
Backside:
The explanation of the NPV criterion in terms of benefits and costs is not a correct
method fro project evaluation because it neglects the time horizon.
Therefore future benefits cannot be equal with the present benefits and costs
Note:
Since society gives preference to the present over the future, it becomes essential to
discount future benefits and costs of projects.
The discount factor is expressed as;
D= (1/( 1 + i)^t ; i=social discount rate, t- time period
14. The Net Present Value criteria (NPV):
Thus;
NPV= {B1 / (1 + i) + B2/( 1+i)2 +… + Bn /( 1+i)n }- {C1 / (1 + i) + C2/( 1+i)2 +…+ Cn /( 1+i)n }
Where;
B1 ,B2,…,Bn are series of gross present benefits in years 1,2,..,n and,
C1 ,C2,…,Cn are series of gross present costs in years 1,2,..,n, and,
i is the social rate of discount for annual compounding
15. The Net Present Value criteria (NPV):
In making a choice among projects either of the following two rules may be
followed
Only those projects should be selected in which the present value of benefits exceed
the present value of costs, i.e.
{B1 / (1 + i) + B2/( 1+i)2 +…+ Bn /( 1+i)n } > {C1 / (1 + i) + C2/( 1+i)2 +… + Cn /( 1+i)n }
All projects where the ratio of the present value of benefits to the present value of
costs is greater than one, i.e
( {B1 / (1 + i) + B2/( 1+i)2 +…+ Bn /( 1+i)n } / {C1 / (1 + i) + C2/( 1+i)2 +…+ Cn /( 1+i)n })> 1
Note:
NPV criterion is considered as the most appropriate rule for project evaluation
16. The internal Rate of Return (IRR):
This criterion refers to the percentage rate of return implicit in the flow of benefits
and costs of projects
Marglin defines it as where the discount rate at which the present value of returns
minus costs is zero, i.e.
{(B1-C1) / (1 + r) + (B2-C2) / (1 + r)2 + … + (Bn-Cn) / (1 + r)n} = 0
Where;
r is the internal rate of return.
In the case of mutually exclusive projects , the project which should be selected is
the one which has the highest rate of return
17. The internal Rate of Return (IRR):
Limitations:
1. Once a rate of return is assumed for a project, it cannot be changed.
2. It is difficult to calculate the rate of return on long term projects which only yield
benefits after a number of years.
3. If projects are mutually exclusive, this criterion favors the one with lower cost.
4. IRR used in public investment does not yield the correct decision because from the
definition of IRR.
5. It is difficult to calculate IRR for investment whose entire investment outlay cannot be
made in the first period.
6. This criterion is suitable for projects which are independent of others.
7. Projects cannot be ranked on the basis of ranking in order of returns.Such can only be
selected on the basis of their net present value.
18. The internal Rate of Return (IRR):
Note: IRR depends on the social rate of discount.
Example: If NPV of two alternative projects are given, the choice of the project will
depend on the discount rate.
NPV
A
A
B
0 R1R2R3 R
a
b
19. END OF PART 1:
PROJECT EVALUATION AND COST-BENEFIT ANALYSIS
21. Relationship between NPV & IRR:
Note: IRR depends on the social rate of discount.
Example: If NPV of two alternative projects are given, the choice of the project will
depend on the discount rate.
NPV
A
0 R5% 10%
22. The Social Rate of Discount :
Introduction:
Whether planners use the NPV or IRR criterion, a rate of discount is needed for
discounting all costs and benefits.
Controversy arises in choosing such a rate because the discount rate is required to
solve two problems;
1. Proper allocation of resources between public and private sector
2. Allocation of resources between the provision of present and future goods and
services
Note:
The rate used to solve the 2nd problem above is called the social discount rate or social
time preference rate
23. The Social Rate of Discount :
The Social discount rate is the premium which the society puts for preferring the
present consumption to future consumption as explained by the diagram below
0
Future
Present
C1
C2
E
S1
24. The Social Rate of Discount:
Note:
The slope of the transformation curve represents the rate of return of investment and
the social indifference curve represents the rate of time preference.
Therefore, the social discount curve rate is determined with the equality of the rate of
return on investment and the rate of time preference at point E.
The social rate of discount is constant over time.
The choice of a discount rate affects the project to be undertaken.
The discount rate of 5% might lead to twice as much investment as one of 10%,
together with equivalent reduction in consumption.
If the discount rate is high ,short period projects with higher net benefits are
preferred and when it is low, long term period projects with lower net benefit are
considered
25. The problem of choosing a Social Discount
Rate:
The social discount rate to be chosen cannot be the market rate of interest in a mixed
economy.
Given there are varieties of securities with corresponding multiplicity of interest rates, the
social discount rate should therefore equal the government borrowing rate on long-term
securities.
Critics agree that;
1. There are numerous borrowing rates on government securities relating to different time
periods, thus presenting a challenge of selecting which one to use arises.
2. Government borrowing is influenced by such factors as monetary policy.
3. The choice of such a social discount rate would lead to very awkward problem that
different rates of interest would be used in the public and private sector.
4. Likelihood of considerable inefficiencies in the allocation of funds inside the investment
sector.
26. Views of different economists on determination
of the Social Discount Rate:
1. Pigou & Dobb :view the society as a continuous entity & has a collective responsibility
for the future generation.
2. Hirschleifer et al : Use the social opportunity cost to measure the social discount rate.
3. Feldstein: Suggests a method of combining social opportunity cost and social time
preference.
4. Mishan: Suggests that if the government has the power to invest in the private
sector, the social opportunity cost rate can be used as the social discount rate.
5. Marglin et al: Argue for synthetic discount rate which is a weighted average of the
social time preference rate and the social opportunity cost rate.
6. Baumol: Regards choice of rates as indeterminate.
7. Pearce: suggests the answer lies in using both the social time preference and the
social opportunity cost.
27. Evaluation on the basis of Benefits:
Introduction:
Under this, a project is evaluated on the basis of the benefits accruing from it.
Benefits refer to the addition to the flow of national output accruing from a project.
A project is beneficial to the extent it tends to increase the income of people.
Increase in income being measured by the actual increase in the production and
consumption.
Benefits may be real or nominal and direct or indirect.
28. Evaluation on the basis of Benefits:
Note:
Real Benefits: In cost benefit analysis, we are concerned wit the real rather than
nominal benefits flowing from a project.
Direct and Indirect Benefits:
I. Direct benefits; are those benefits which are immediate and directly obtained from a
project
II. Indirect benefits or secondary benefits; are the values added to the direct benefits as a
result of the activities stemming from the project.
Tangible and Intangible Benefits:
I. Tangible benefits; are those which can be computed and measured in terms of money
II. Intangible benefits; are those which cannot be measured in monetary terms.
29. Evaluation on the basis of Costs:
Introduction:
Project costs are the values of the resources used in constructing , maintaining and
operating a project.
They relate to the cost of labor, capital, intermediate goods, natural resources etc.
Types of Costs:
1. Associated costs:
2. Real and nominal costs:
3. Primary/Direct costs;
4. Indirect/Secondary costs
30. Importance of data for evaluation:
Introduction:
In project evaluation, detailed data extending over a long period are required.
These data can be divided into two categories;
1. Data on investment or gestation period.
2. Data on operation or production period.
The above date describes;
1. The number of workers and other personnel involved.
2. The amount of raw materials required.
3. The quantity of the products expected to be produced etc.
Note: Data collected are compared with other projects elsewhere and in terms of their
costs and benefits.
31. Limitation of Cost- Benefit analysis:
1. Difficulties in cost assessment.
2. Difficulties in cost assessment.
3. Arbitrary discount rate.
4. Neglects joint benefits and costs.
5. Ignores opportunity cost.
6. Adjustment for risk and uncertainty.
7. The problem of externalities.
32. Use of Cost-Benefit analysis in Developing
Countries :
Benefits of Cost Benefits analysis to LDCs according to Stephen Marglin:
1. It helps in reducing differences in the marginal effectiveness of alternative measures
for accomplishing such objectives.
2. It helps in assessing the costs of facilitating one objective in terms of benefits
sacrificed with respect to others.
3. It has political advantages.
Other benefits:
1. It permits decentralized decision making from the vast technical information needed
to be decided on in a number of specific projects.
2. It is a practical way of assessing the desirability of projects.
33. Difficulties of Cost-Benefit analysis in
Developing Countries :
1. Based on conditions of developed countries, this technique is based on the basic
assumptions that investment is made in a framework of ;
I. Economic stability.
II. Steady growth.
III. Predominantly capitalistic competitive economy.
IV. Constant prices.
V. Flexible wages.
VI. Perfect mobility of factors of Production.
VII. Full employment of factors of production.
2. Difficulty in collecting data.
3. Difficulty in cost assessment.
34. Elements to assign weight to in Cost-
Benefit analysis in project evaluation:
1. Variation of inputs overtime.
2. Variation of the range of commodities produced.
3. Scale and location effects.
4. Non-market effects of production differences between projects.
35. Use of Cost-Benefit analysis
in Developing Countries:
FISH FARMING ENTERPRISE PRODUCTIVITY PROGRAM (FFEPP)
HTTP://WWW.UNUFTP.IS/STATIC/FELLOWS/DOCUMENT/MOSES15PRF.PDF
36. The case of implementation of the aquaculture development
component in meru county: Moses Mwangangi Wambua
Research Problem:
Those with responsibility for spending public money need to know that they are
choosing the best option (FAO, 1986).
Before massive expansion of the FFEPP project is implemented, various economic
assessments should be made in order to answer vital questions In project evaluation,
detailed data extending over a long period are required.
The project should only continue if its long-term benefits outweigh the costs.
To this end, a Cost Benefit Analysis (CBA) was conducted for this project
General Research Objectives :
The main objective of this study is to provide an economic analysis of the FFEPP
project as implemented in Meru County and make recommendations based on the
outcomes of the cost benefit analysis.
37. Framework for Analysis:
The study examines the scenario of implementing the FFEPP project against the usual scenario where the
local communities of Meru region continue to use their land for alternative farm activities. This CBA is
premised on the following:
The lifespan of the project is assumed to be 15 years. This presumes that the 15-year period is long
enough to highlight all of the consequences of changes in land use that promote aquaculture,
Kenya Shillings (Kshs) have been used to monetize all values in the calculations. Adjustments are made
for inflation and all amounts expressed in their latest value (2016).
The estimated total amount of funding that was invested in the project is KSh 149 million.
A social discount rate averaged at 7% after adjustment for inflation is used to calculate the NPV of this
project. This discount rate is equivalent to the real interest rate on Kenya’s sovereign debt.
The rationale for applying this approach in discounting is that it would significantly correspond to the
borrowing cost of the government that would, in most cases, be responsible for funding the project
(Warusawitharana, 2014).
By using the sovereign borrowing rate as the social discount rate enables one to match the projected cash
inflows from the project to the cash outflows for the government responsible for financing it.
38. The case of implementation of the aquaculture development
component in meru county: Moses Mwangangi Wambua
39. The NPV, BCR and IRR of the project
From the table above ,the payback period of the project is 11 years, occurring in
2019
The present value of the net benefits (NPV) of the FFEPP project expected in its
15-year lifespan is Kshs 59 million,
The Benefits to Cost Ratio (BCR) is 1.05
The Internal Rate of Return (IRR) is 10%.
If the project is left to continue to infinity, assuming that all factors remain
constant and that there would be periodic costs every 15 years to revamp the
remaining ponds, the project would reach a terminal NPV of Kshs 197.9 million
with a terminal IRR of 13.2%..
40. Interpretation of the NPV, BCR and IRR
of the project
BCR: The BCR of 1.05 indicates that the project is economically efficient and
beneficial; the stream of benefits exceeds the costs incurred over the project
life.
IRR: The IRR of 10% for the 15-year period and 13.2% for an infinite period
indicates a good return on the investment into the project compared with the
cost of the funds that the government has invested in to the project.
Payback: The pay-back period of the project is 11 years.1 This is acceptable as it
occurs within the project period.
Optimally, in order to determine the extent of success of the FFEPP in Meru, we
would need to compare the current outcomes of the projects with the intended
project outcomes.
41. Direct and Indirect economic benefits of
the program :
Direct benefits: improvement in livelihoods through creating a new source of income
from revenues of harvests sold. It is also expected to improve food security among
the locals and in the region from the alternative source of food offered by the fish
from the ponds.
Indirect benefits: Creation of new job opportunities in the aquaculture enterprises,
hatchery production, and trade of fish as well as value addition activities along the
value chain.
42. END OF PART 2:
PROJECT EVALUATION AND COST-BENEFIT ANALYSIS