SUMMER PRACTICAL TRAINING
AT
SUBMITTED BY:-
RANJAN KUMAR
14EAIEE079
B.Tech. IV Yr. VII SEM
SUBMITTED TO :-
Mr. Deepak Sharma
Head of Department
Electrical Engineering
NATIONAL THERMAL POWER CORPORATION LTD. ( NTPC )
KAHALGAON (BIHAR)
CONTENTS :-
1. Introduction
2. Coal Handling System
3. Ash Handling System
4. Boiler and its auxiliaries
5. Turbine and its auxiliaries
6. Off-Site Department
7. Electric Generator and its auxiliaries
8. Electric Transformer
9. Switchyard
10.Control and Instrumentation Department
1
1. Introduction about NTPC :-
2
NTPC Limited is the largest thermal power generating company of India.
Established in 7 November 1975.
In 1997, Government of India granted NTPC status of “Navratna” company.
NTPC became a “Maharatna”company in May, 2010, one of the only four
companies to be awarded this status in India.
 Present installed Capacity of NTPC is 51,635 MW .
Total 48 NTPC in India.
 It has 20 coal based power stations (38,755 MW) .
7 gas based power stations (4,017 MW)
9 Joint Ventures based power stations (7,216 MW).
11 renewable energy based power plant(845 MW)
Annual turnover of Rs. 73,904 cr. with profit of Rs. 13,834 Cr. for the year 2013-14.
It contributes 28.60% of total power .
National Thermal Power Corporation LTD. (NTPC)
3
Introduction about NTPC Kahalgaon Bihar :-
Location : Kahalgaon , District-Bhagalpur (Bihar) , 813214
Total Land : 3,360 acres
Land for plant : 883 acres
Land for township : 432 acres
Land for Ash dyke :1395 acres
Source of water : Ganga River
Source of coal : Rajmahal coal field of ECL (Lalmatia , Jharkhand)
 Configuration: stage -1 has 4 unit (each unit capacity 210 MW) , which
was established by Russia in 1991.
stage -2 has 3 unit (each unit capacity 500 MW) , which
was established by BHEL in 1996.
Total installed capacity : 2340 MW
Fuel Requirement : 4.1 million ton per year stage -1
: 6.62 million ton per year for stage -2 ( phase-1 )
: 3 million ton per year for stage -2 ( phase-2 )
4
5
2. Coal Handling System Equipment :
6
Wagon
 Tripler
Conveyor Belt
Pulleys
Magnetic separator
Crushing house
Vibrating screen
Pulverized coal
Storage of coal
The function of coal handling plant is automatic feeding of coal to the boiler
 A thermal power plant burns enormous amounts of coal.
 In NTPC Kahalgaon 2340MW Plant may require around 23400 tons of coal daily.
Step in coal handling plant:
7
Why Coal?
Coal
55%
Gas
10%
Diesel
1%
Hydel
26%
RES
5%
Nuclear
3%
Share of Coal in Power Generation
Advantages of Coal Fuel
•Abundantly available in India
•Low cost
•Technology for Power Generation well
developed.
•Easy to handle, transport, store and use
•India’s Coal Reserves are estimated to be 206 billion tones. Present consumption is
about 450 million tones.
•Cost of coal for producing 1 unit of electricity is Rs 0.75.
•Cost of Gas for producing 1 unit of electricity is Rs 1.20. 8
3. Ash Handling System:
 WHAT IS ASH ?
Ash is the collection of residuals producing after the combustion of coal at
constant weight under standard conditions.
Ash is oxidized form of the mineral matters present in coal.
Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc.
 WHY ASH HANDLING?
 Ash content of Indian coal used in power station is about 30 to 40 %.
 A typical 2000 MW station produce around 9000T to 12000T of ash per day.
 This huge amount of ash needs to be disposed off continuously.
 Necessary care to be taken for preventing pollution. 9
 Bottom ash can be collected at furnace bottom as Wet or Dry form.
 Bottom ash is the heavier portion of coal ash that settles on the ground in the boiler.
 Bottom ash is part of the non-combustible residue of combustion in a furnace or
incinerator.
 Approximately 80% of bottom ash consist overall of coal ash content.
1. Bottom Ash:
10
2. Fly Ash:
• Fly ash, also known as “pulverized fuel ash”.
• Ash generated in the ESP which got carried out with the flue gas is
generally known as fly ash.
• It consist of air preheater ash and economizer ash.
• Approximately 20% of fly ash consist overall of coal ash content.
• FA is collected from Air heater hopper, Eco hopper and ESP hopper.
Use of ash:
• In concrete production
• In cement production
• In stabilization of soft soils
• In bricks production
• Road construction
• Other applications include cosmetics, toothpaste, ceiling tiles, bowling balls,
flotation devices, PVC pipe, picture frames, doors, window frames, park benches
railroad ties.
11
Coal Seam
Surge Pile
Pulverize (-150)
Overburden
Fly Ash
Flue Gas
Electrostatic Precipitator
Flue Gas
Boiler
Fly Ash Bottom
Ash
Smoke
Stack
Fly Ash
Bottom Ash
12
Boiler:-
 Boiler is a long column where coal is fired to produce heat and to convert water into superheated steam.
 In NTPC – Kahalgaon, the height of the boiler is 90 meter.
 Type of boiler used in NTPC SSTPS in Stage-I and II are Water tube boilers.
 Maximum Temperature and pressure of main steam for stage -1 is 540ºc and 140 bar respectively.
 Maximum Temperature and pressure of main steam for stage -2 is 545ºc and 170 bar respectively.
 MAIN PART OF BOILER:
1. Economizer 4. super-heater
2. Deaerator 5. Re-heater
3. Furnace 6. Different type of fan
13
14
A steam turbine is a rotating device which converts thermal energy into mechanical energy.
In NTPC Kahalgaon LMZ (Russia) type steam turbine is used.
There are 3 types of Turbines used in Thermal Power Plants:
1. High pressure turbine (HP Turbine)
2. Intermediate pressure turbine (IP Turbine)
3. Low pressure turbine (LP Turbine)
 Turbine blade is air foil shape.
TURBINE :-
15
1. High Pressure Turbine:
16
1.HIGH PRESSURE TURBINE:-
 Single Flow Cylinder
 Double Casing
 Thermal expansion up to 16mm
2. Intermediate Pressure Turbine
17
2.INTERMEDIATE PRESSURE TURBINE:-
 Double Flow
 Double Casing
 Axially Split Design in both Casings
 Rigid Coupling
 Blade Shrouded & Inverted T-Root
Design
3. Low Pressure Turbine:
18
3.LOW PRESSURE TURBINE:-
 Largest Turbine
 Pressure is Very Less
 Three Shell Design
 Double Flow
 All Casings Axially Split
 Exhaust Hood Spray Arrangement
 2 Free Standing Blades in the end
19
1. Water Treatment Plant/DM plant:
Why water treatment?
 Raw water contains many dissolved minerals and organic materials.
 For removal of total solids such as Ca , Mg ,Na ,Cl , Alkalinity , silica etc.
 At high temperature certain minerals left scaling on the tube metal of the boiler and cause permanent damage.
 Some dissolved minerals leads to corrosion of tube metals.
 At high pressure and temperature an element, silica can be carried away with steam causing damage to turbine
low pressure stage.
 The performance and life expectancy of the station greatly depends on water chemistry compliance.
6. Off-Site Department:
1. Water Treatment (DM Plant)
2. Cooling Tower
 Steps of treatment process:
1. Aeration of raw water
2. Adding chemicals for bacteria removal
3. Adding chemicals for sedimentation of suspended particles
4. Flocculation
5. Filtration
6. Ion Exchange process
20
2. Cooling Tower:
A cooling tower is a heat rejection device that rejects waste heat to the atmosphere through
the cooling of a water stream to a lower temperature.
21
7. Electric Generator and its auxiliaries:
 A turbo generator is the combination of a turbine directly connected to an electric generator
for the generation of electric power.
 An electric generator is a device that converts mechanical energy to electrical energy.
 It is based upon the principle of electromagnetic induction.
 Turbogenerator:
Cooling of Generator :
 Hydrogen cooling: - Rotor core and Rotor winding.
 DM Water cooling:- Stator core and Stator winding.
 Excitation System:
 Maintain the reactive power.
 Wear and Tear problem will be minimize.
 In NTPC Kahalgaon brushless excitation is used. 22
Capacity 210 KW
Power Factor 0.85 lagging
KVA 588,000
Stator Voltage 15.75 KV
Stator current 9.03 KA
Rotor Voltage 303 V
Rotor current 2.330 KA
RPM 3000
Frequency 50 HZ
Phase 3
Connection YY
Coolant Water & Hydrogen
Gas Pressure 4 Bar
Insulation Class B
Type TG-HH-0500-2
Make Russia
Stage-1 Turbogenerator Rating:-
Capacity 500 KW
Power Factor 0.85 lagging
KVA 588,000
Stator Voltage 21 KV
Stator current 16.2 KA
Rotor Voltage 340 V
Rotor current 4040 A
RPM 3000
Frequency 50 HZ
Phase 3
Connection YY
Coolant Water & Hydrogen
Gas Pressure 4 Bar
Insulation Class B
Type TG-HH-0500-2
Make BHEL Haridwar
Stage-2 Turbogenerator Rating:-
23
8. Electric Transformer:
 A transformer is a device that transfer electrical energy from one electrical circuit to another circuit through the
medium Of magnetic field without change in frequency.
WORKING PRINCIPLE:
Definition:
 It works on FARADAY’S LAW OF
ELECTROMAGNETIC INDUCTION
(self or mutual induction depending on the type of
transformer).
Transformer used in NTPC Kahalgaon:
1. Generator transformer
2. Station transformer
3. Unit Auxiliary transformer (UAT)
4. Other Electric transformer
24
9. Switchyard:
 ELECTRICAL EQUIPMENTS:
1. Bus-Bar
2. Lightning Arrester
3. Wave Trap
4. Capacitive Voltage Transformer
5. Relay
6. Circuit Breaker
7. Instrument Transformer
8. Earthing Rod
9. PLCC
10. INSULATORS
25
 Distribution System:
Figure: Single Line Diagram of NTPC Kahalgaon 400/132 KV Switchyard
26
10. Control and Instrumentation Department:
 The main functions of the C&I dept. at
NTPC Kahalgaon are:
1. Measurement and display of various parameters.
2. To control the various parameters by Automatic
feedback controlling which involves the taking of
decision based on inputs from measurements by the
processor.
3. Protection of various equipment’s (pumps, generators
etc.) and workers from hazards by automatically tripping
a cycle when hazardous conditions are reached.
4. Alarm generation in case of a mechanical or an
electrical failure. 27
28
29

More Related Content

What's hot

Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
pratikguptateddy
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
Ranjan kumar
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
Ashish Uppu
 
ntpc dadri
ntpc dadri ntpc dadri
ntpc dadri
Himanika Arora
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
Milind Punj
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
Vimal Tripathi
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
Ishant Gautam.
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
Dheeraj Kashyap
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
vocational training presentation on korba ntpc
 vocational training presentation on korba ntpc vocational training presentation on korba ntpc
vocational training presentation on korba ntpc
VIKASH BAGHEL
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
ADITYA ARYAN
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
kirbadh
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VIKASH BAGHEL
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
abdul mohammad
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
Ram Narayan Shah
 
Power Plant Familiarization
Power Plant FamiliarizationPower Plant Familiarization
Power Plant Familiarization
Aanand Kumar
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
Devanshu Yadav
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
Shivam Singh
 

What's hot (20)

Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
ntpc dadri
ntpc dadri ntpc dadri
ntpc dadri
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
vocational training presentation on korba ntpc
 vocational training presentation on korba ntpc vocational training presentation on korba ntpc
vocational training presentation on korba ntpc
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
Power Plant Familiarization
Power Plant FamiliarizationPower Plant Familiarization
Power Plant Familiarization
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 

Similar to Ranjan NTPC KAHALGAON ppt

NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
Aditya Shekhar
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
Aditya Shekhar
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
Tarun Kumar
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
Abhishek Awasthi
 
V.T ppt
V.T pptV.T ppt
V.T ppt
Aditi Tiwari
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
Shrey Dhasmana
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
Ajmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
Ajmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
Ajmal Khan
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
Abhishek Kumar
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
Anubhav Ghosh
 
adi ntpc.pptx
adi ntpc.pptxadi ntpc.pptx
adi ntpc.pptx
AdityaRaj873503
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
Báppådìtÿâ Màîtÿ
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
Chandra veer singh
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview report
ASHOKKUMARPAL1
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
Shishupal03012015
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
Utkarsh Chaubey
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
guru nanak institute of technology
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakarapar
naitik997
 
Ppt on tenughat thermal power plant
Ppt on tenughat thermal power plantPpt on tenughat thermal power plant
Ppt on tenughat thermal power plant
Abhinaw kapoor
 

Similar to Ranjan NTPC KAHALGAON ppt (20)

NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
adi ntpc.pptx
adi ntpc.pptxadi ntpc.pptx
adi ntpc.pptx
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview report
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakarapar
 
Ppt on tenughat thermal power plant
Ppt on tenughat thermal power plantPpt on tenughat thermal power plant
Ppt on tenughat thermal power plant
 

More from Ranjan kumar

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
Ranjan kumar
 
Seminar report main page 2
Seminar report main page 2Seminar report main page 2
Seminar report main page 2
Ranjan kumar
 
Seminar report main page 1
Seminar report main page 1Seminar report main page 1
Seminar report main page 1
Ranjan kumar
 
Seminar report cover page
Seminar report cover pageSeminar report cover page
Seminar report cover page
Ranjan kumar
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentation
Ranjan kumar
 
Project report
Project reportProject report
Project report
Ranjan kumar
 
Project report
Project reportProject report
Project report
Ranjan kumar
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
Ranjan kumar
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
Ranjan kumar
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
Ranjan kumar
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
Ranjan kumar
 
Project cover page
Project cover pageProject cover page
Project cover page
Ranjan kumar
 
Project cover page
Project cover pageProject cover page
Project cover page
Ranjan kumar
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
Ranjan kumar
 
NTPC KAHALGAON Cover page
NTPC KAHALGAON Cover pageNTPC KAHALGAON Cover page
NTPC KAHALGAON Cover page
Ranjan kumar
 
Ranjan resume
Ranjan  resumeRanjan  resume
Ranjan resume
Ranjan kumar
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
Ranjan kumar
 
RANJAN RESUME 1
RANJAN RESUME 1RANJAN RESUME 1
RANJAN RESUME 1
Ranjan kumar
 

More from Ranjan kumar (18)

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Seminar report main page 2
Seminar report main page 2Seminar report main page 2
Seminar report main page 2
 
Seminar report main page 1
Seminar report main page 1Seminar report main page 1
Seminar report main page 1
 
Seminar report cover page
Seminar report cover pageSeminar report cover page
Seminar report cover page
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentation
 
Project report
Project reportProject report
Project report
 
Project report
Project reportProject report
Project report
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
 
Project cover page
Project cover pageProject cover page
Project cover page
 
Project cover page
Project cover pageProject cover page
Project cover page
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
 
NTPC KAHALGAON Cover page
NTPC KAHALGAON Cover pageNTPC KAHALGAON Cover page
NTPC KAHALGAON Cover page
 
Ranjan resume
Ranjan  resumeRanjan  resume
Ranjan resume
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
 
RANJAN RESUME 1
RANJAN RESUME 1RANJAN RESUME 1
RANJAN RESUME 1
 

Recently uploaded

spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
ssuser13ffe4
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
Celine George
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
PsychoTech Services
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
B. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdfB. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdf
BoudhayanBhattachari
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 

Recently uploaded (20)

spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
B. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdfB. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdf
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 

Ranjan NTPC KAHALGAON ppt

  • 1. SUMMER PRACTICAL TRAINING AT SUBMITTED BY:- RANJAN KUMAR 14EAIEE079 B.Tech. IV Yr. VII SEM SUBMITTED TO :- Mr. Deepak Sharma Head of Department Electrical Engineering NATIONAL THERMAL POWER CORPORATION LTD. ( NTPC ) KAHALGAON (BIHAR)
  • 2. CONTENTS :- 1. Introduction 2. Coal Handling System 3. Ash Handling System 4. Boiler and its auxiliaries 5. Turbine and its auxiliaries 6. Off-Site Department 7. Electric Generator and its auxiliaries 8. Electric Transformer 9. Switchyard 10.Control and Instrumentation Department 1
  • 3. 1. Introduction about NTPC :- 2 NTPC Limited is the largest thermal power generating company of India. Established in 7 November 1975. In 1997, Government of India granted NTPC status of “Navratna” company. NTPC became a “Maharatna”company in May, 2010, one of the only four companies to be awarded this status in India.  Present installed Capacity of NTPC is 51,635 MW . Total 48 NTPC in India.  It has 20 coal based power stations (38,755 MW) . 7 gas based power stations (4,017 MW) 9 Joint Ventures based power stations (7,216 MW). 11 renewable energy based power plant(845 MW) Annual turnover of Rs. 73,904 cr. with profit of Rs. 13,834 Cr. for the year 2013-14. It contributes 28.60% of total power .
  • 4. National Thermal Power Corporation LTD. (NTPC) 3
  • 5. Introduction about NTPC Kahalgaon Bihar :- Location : Kahalgaon , District-Bhagalpur (Bihar) , 813214 Total Land : 3,360 acres Land for plant : 883 acres Land for township : 432 acres Land for Ash dyke :1395 acres Source of water : Ganga River Source of coal : Rajmahal coal field of ECL (Lalmatia , Jharkhand)  Configuration: stage -1 has 4 unit (each unit capacity 210 MW) , which was established by Russia in 1991. stage -2 has 3 unit (each unit capacity 500 MW) , which was established by BHEL in 1996. Total installed capacity : 2340 MW Fuel Requirement : 4.1 million ton per year stage -1 : 6.62 million ton per year for stage -2 ( phase-1 ) : 3 million ton per year for stage -2 ( phase-2 ) 4
  • 6. 5
  • 7. 2. Coal Handling System Equipment : 6 Wagon  Tripler Conveyor Belt Pulleys Magnetic separator Crushing house Vibrating screen Pulverized coal Storage of coal The function of coal handling plant is automatic feeding of coal to the boiler  A thermal power plant burns enormous amounts of coal.  In NTPC Kahalgaon 2340MW Plant may require around 23400 tons of coal daily. Step in coal handling plant:
  • 8. 7
  • 9. Why Coal? Coal 55% Gas 10% Diesel 1% Hydel 26% RES 5% Nuclear 3% Share of Coal in Power Generation Advantages of Coal Fuel •Abundantly available in India •Low cost •Technology for Power Generation well developed. •Easy to handle, transport, store and use •India’s Coal Reserves are estimated to be 206 billion tones. Present consumption is about 450 million tones. •Cost of coal for producing 1 unit of electricity is Rs 0.75. •Cost of Gas for producing 1 unit of electricity is Rs 1.20. 8
  • 10. 3. Ash Handling System:  WHAT IS ASH ? Ash is the collection of residuals producing after the combustion of coal at constant weight under standard conditions. Ash is oxidized form of the mineral matters present in coal. Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc.  WHY ASH HANDLING?  Ash content of Indian coal used in power station is about 30 to 40 %.  A typical 2000 MW station produce around 9000T to 12000T of ash per day.  This huge amount of ash needs to be disposed off continuously.  Necessary care to be taken for preventing pollution. 9
  • 11.  Bottom ash can be collected at furnace bottom as Wet or Dry form.  Bottom ash is the heavier portion of coal ash that settles on the ground in the boiler.  Bottom ash is part of the non-combustible residue of combustion in a furnace or incinerator.  Approximately 80% of bottom ash consist overall of coal ash content. 1. Bottom Ash: 10
  • 12. 2. Fly Ash: • Fly ash, also known as “pulverized fuel ash”. • Ash generated in the ESP which got carried out with the flue gas is generally known as fly ash. • It consist of air preheater ash and economizer ash. • Approximately 20% of fly ash consist overall of coal ash content. • FA is collected from Air heater hopper, Eco hopper and ESP hopper. Use of ash: • In concrete production • In cement production • In stabilization of soft soils • In bricks production • Road construction • Other applications include cosmetics, toothpaste, ceiling tiles, bowling balls, flotation devices, PVC pipe, picture frames, doors, window frames, park benches railroad ties. 11
  • 13. Coal Seam Surge Pile Pulverize (-150) Overburden Fly Ash Flue Gas Electrostatic Precipitator Flue Gas Boiler Fly Ash Bottom Ash Smoke Stack Fly Ash Bottom Ash 12
  • 14. Boiler:-  Boiler is a long column where coal is fired to produce heat and to convert water into superheated steam.  In NTPC – Kahalgaon, the height of the boiler is 90 meter.  Type of boiler used in NTPC SSTPS in Stage-I and II are Water tube boilers.  Maximum Temperature and pressure of main steam for stage -1 is 540ºc and 140 bar respectively.  Maximum Temperature and pressure of main steam for stage -2 is 545ºc and 170 bar respectively.  MAIN PART OF BOILER: 1. Economizer 4. super-heater 2. Deaerator 5. Re-heater 3. Furnace 6. Different type of fan 13
  • 15. 14
  • 16. A steam turbine is a rotating device which converts thermal energy into mechanical energy. In NTPC Kahalgaon LMZ (Russia) type steam turbine is used. There are 3 types of Turbines used in Thermal Power Plants: 1. High pressure turbine (HP Turbine) 2. Intermediate pressure turbine (IP Turbine) 3. Low pressure turbine (LP Turbine)  Turbine blade is air foil shape. TURBINE :- 15
  • 17. 1. High Pressure Turbine: 16 1.HIGH PRESSURE TURBINE:-  Single Flow Cylinder  Double Casing  Thermal expansion up to 16mm
  • 18. 2. Intermediate Pressure Turbine 17 2.INTERMEDIATE PRESSURE TURBINE:-  Double Flow  Double Casing  Axially Split Design in both Casings  Rigid Coupling  Blade Shrouded & Inverted T-Root Design
  • 19. 3. Low Pressure Turbine: 18 3.LOW PRESSURE TURBINE:-  Largest Turbine  Pressure is Very Less  Three Shell Design  Double Flow  All Casings Axially Split  Exhaust Hood Spray Arrangement  2 Free Standing Blades in the end
  • 20. 19
  • 21. 1. Water Treatment Plant/DM plant: Why water treatment?  Raw water contains many dissolved minerals and organic materials.  For removal of total solids such as Ca , Mg ,Na ,Cl , Alkalinity , silica etc.  At high temperature certain minerals left scaling on the tube metal of the boiler and cause permanent damage.  Some dissolved minerals leads to corrosion of tube metals.  At high pressure and temperature an element, silica can be carried away with steam causing damage to turbine low pressure stage.  The performance and life expectancy of the station greatly depends on water chemistry compliance. 6. Off-Site Department: 1. Water Treatment (DM Plant) 2. Cooling Tower  Steps of treatment process: 1. Aeration of raw water 2. Adding chemicals for bacteria removal 3. Adding chemicals for sedimentation of suspended particles 4. Flocculation 5. Filtration 6. Ion Exchange process 20
  • 22. 2. Cooling Tower: A cooling tower is a heat rejection device that rejects waste heat to the atmosphere through the cooling of a water stream to a lower temperature. 21
  • 23. 7. Electric Generator and its auxiliaries:  A turbo generator is the combination of a turbine directly connected to an electric generator for the generation of electric power.  An electric generator is a device that converts mechanical energy to electrical energy.  It is based upon the principle of electromagnetic induction.  Turbogenerator: Cooling of Generator :  Hydrogen cooling: - Rotor core and Rotor winding.  DM Water cooling:- Stator core and Stator winding.  Excitation System:  Maintain the reactive power.  Wear and Tear problem will be minimize.  In NTPC Kahalgaon brushless excitation is used. 22
  • 24. Capacity 210 KW Power Factor 0.85 lagging KVA 588,000 Stator Voltage 15.75 KV Stator current 9.03 KA Rotor Voltage 303 V Rotor current 2.330 KA RPM 3000 Frequency 50 HZ Phase 3 Connection YY Coolant Water & Hydrogen Gas Pressure 4 Bar Insulation Class B Type TG-HH-0500-2 Make Russia Stage-1 Turbogenerator Rating:- Capacity 500 KW Power Factor 0.85 lagging KVA 588,000 Stator Voltage 21 KV Stator current 16.2 KA Rotor Voltage 340 V Rotor current 4040 A RPM 3000 Frequency 50 HZ Phase 3 Connection YY Coolant Water & Hydrogen Gas Pressure 4 Bar Insulation Class B Type TG-HH-0500-2 Make BHEL Haridwar Stage-2 Turbogenerator Rating:- 23
  • 25. 8. Electric Transformer:  A transformer is a device that transfer electrical energy from one electrical circuit to another circuit through the medium Of magnetic field without change in frequency. WORKING PRINCIPLE: Definition:  It works on FARADAY’S LAW OF ELECTROMAGNETIC INDUCTION (self or mutual induction depending on the type of transformer). Transformer used in NTPC Kahalgaon: 1. Generator transformer 2. Station transformer 3. Unit Auxiliary transformer (UAT) 4. Other Electric transformer 24
  • 26. 9. Switchyard:  ELECTRICAL EQUIPMENTS: 1. Bus-Bar 2. Lightning Arrester 3. Wave Trap 4. Capacitive Voltage Transformer 5. Relay 6. Circuit Breaker 7. Instrument Transformer 8. Earthing Rod 9. PLCC 10. INSULATORS 25
  • 27.  Distribution System: Figure: Single Line Diagram of NTPC Kahalgaon 400/132 KV Switchyard 26
  • 28. 10. Control and Instrumentation Department:  The main functions of the C&I dept. at NTPC Kahalgaon are: 1. Measurement and display of various parameters. 2. To control the various parameters by Automatic feedback controlling which involves the taking of decision based on inputs from measurements by the processor. 3. Protection of various equipment’s (pumps, generators etc.) and workers from hazards by automatically tripping a cycle when hazardous conditions are reached. 4. Alarm generation in case of a mechanical or an electrical failure. 27
  • 29. 28
  • 30. 29