SlideShare a Scribd company logo
Intaver Institute Inc.
303, 6707, Elbow Drive S.W.,
Calgary AB Canada T2V 0E5
www.intaver.com
Quantitative Risk Analysis for Aerospace
Industry
Common Issues with Space System Projects
• Multiple risks and uncertainties
• Many uncertainties are event-driven
• Historical data mining should include relevance analysis
Existing Methodologies
• PERT
• Monte Carlo Simulation
• Bayesian approach
• Scenario analysis and Decision Trees
Project Example
Laser Interferometer Space Antenna (LISA) project
Calendar Year ==>
Project Phasing
NASA HQ Milestones
Mission Reviews
SE&I Contractor Acquisition
Technology
LISA Test Package (SM2)
ST7 DRS (SM2)
Interferometry Measurement
System
System Verification
Disturbance Reduction
System
Payload
Spacecraft
Observatory I&T
Constellation Testing
Launch Campaign
Pre-Phase A Phase A Phase B Phase C/D
FAD ICR/CA
NAR ESA MOU (F)
PCA
FAD HQ
Briefing
MDR
SRR
SCR
TRR
PDR CDR
S/C1 PER
Obs 1 PER
MOR
ORR
PSR
MRR
FRR
LRR
Prep Phase Execution PhasePartnering Phase
RFI RFP D Sel RFP Sel
LISA Demo
CDR Deliver to SM2 SM2 Launch
DRS Demo
PDR CDR Deliver to SM2 SM2 Launch
Trades Subs
Assy Test
TRL5 TRL6
Model Envr R1 Model Envr R2 Model Envr R3
Testbed Demos
Trades
Tgt Std
Subs
Assy Test
GRS TRL5 GRS TRL6
Rqts/Architecture/Trades
Design Build / Test
PDR CDR EM 1 2 3
ESA Definition Phase
ITT Award ITT Award PDR CDR
ESA Implementation Phase
EM 1 2 3
Preps
Observatory I&T
EM 1 2 3
Preps
1 2
Constellation Testing
3
Launch Preps
LRD
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
The document is courtesy of NASA/Goddard Space Flight Center
Heuristics and Biases in Project Management
The Bank of Sweden Prize in
Economic Sciences in
Memory of Alfred Nobel 2002
Daniel Kahneman
Decision makers use
“heuristics”, or general
rules of thumb, to arrive
at their judgments.
In certain instances, this
will lead to systemic
biases.
Examples of Heuristics in Project Management
• Representativeness – unwanted appeal to detailed scenarios
• Availability – access the probability of an event by the ease
with which instances can be brought to mind
• Anchoring – human tendency is to remain close to the initial
estimate
Event Chain Methodology
Event Chain Methodology is a method of
modeling uncertainties for different time-related
business and technological processes including
project management for space systems.
Moment of Risk and State of Activity
An activity (task) in most real life processes is not a continuous
uniform procedure. Tasks are affected by external events,
which transform an activity from one state to another.
Event Chains
Events can cause other events, which will
create event chains. These event chains
can significantly affect the course of the
project.
Monte Carlo Simulations
Once events and event chains are defined, quantitative
analysis using Monte Carlo simulation can be performed to
quantify the cumulative impact of the events.
Information regarding the uncertainties
expressed as an event is supplemented
with distributions related to duration,
start time, cost, and other parameters
Critical Chains of Events
The single events or the event chains that have the most
potential to affect the projects are the “critical events” or
“critical chains of events.”
History Matching and Relevance Analysis
• Similar events or event chains are found based on historical
data
• Analysis based on Bayesian approach is performed and
relevance parameter is calculated
• Project manager defines relevance of each event or event chain
for the current project
• Both calculated and user defined relevance parameters are
used to determine probability and impact of the events for the
current project
Performance Tracking with Event and Event Cha
During the course of the project, the probability and time of the
events can be recalculated based on actual data.
Actual performance data and
original estimate is used
forecast duration of activity
with risks
Event Chain Diagrams
Event Chain Diagrams are visualizations that show the
relationships between events and activities and how the events
affect each other
Repeated Activities
Common scenario for real life projects: sometimes a previous
activity must be repeated based on the results of event in a
succeeding activity
Event Chains and Risk Mitigation
Mitigation plan can be assigned to an event or event chain. These
small schedules will be triggered when an event chain occurs.
Resource Allocation Based on Events
Event: the reassignment of a resource from one activity to
another
Example: if an activity requires more resources to complete it
within a fixed period, this will trigger an event to reallocate the
resource from another activity.
Project Management Workflow using Event Cha
Methodology
1. Define a detailed project schedule with resources and costs
assigned to the activities
2. Define a detailed risk breakdown structure and assign risks to
the activities. The probability of each event can be taken from
historical data.
3. Define the activities associated with mitigation efforts and
then assign costs and resources to them.
4. Perform a quantitative risk analysis using Monte Carlo
simulations.
5. Analyze the results of the quantitative risk analysis: perform a
sensitivity analysis and identify the crucial tasks and critical
risks.
Project Management Workflow using Event
Chain Methodology
6. Perform reality checks: compare the results of analysis with
outside independent expert reviews and historical experience.
7. Monitor the course of the project on a regular basis, perform
repeated quantitative risk analysis, reassess the event and
event chain parameters
Project Management Workflow using Event
Chain Methodology
Acknowledgements
Intaver Institute Inc. is thankful to Kevin N. Miller, Deputy Project
Manager/Resources, Laser Interferometer Space Antenna (LISA)
Project, NASA/Goddard Space Flight Center, for providing data
necessary to illustrate the methodology discussed in the paper.

More Related Content

Similar to Project Risk Analysis in Aerospace Industry

An integrated event summarization approach for complex system management
An integrated event summarization approach for complex system managementAn integrated event summarization approach for complex system management
An integrated event summarization approach for complex system management
Venkat Projects
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
Glen Alleman
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Robert Byrd
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
InSync Conference
 
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
ASQ Reliability Division
 

Similar to Project Risk Analysis in Aerospace Industry (20)

Mythbusters: Event Stream Processing v. Complex Event Processing
Mythbusters: Event Stream Processing v. Complex Event ProcessingMythbusters: Event Stream Processing v. Complex Event Processing
Mythbusters: Event Stream Processing v. Complex Event Processing
 
An integrated event summarization approach for complex system management
An integrated event summarization approach for complex system managementAn integrated event summarization approach for complex system management
An integrated event summarization approach for complex system management
 
An integrated event summarization approach for complex system management
An integrated event summarization approach for complex system managementAn integrated event summarization approach for complex system management
An integrated event summarization approach for complex system management
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
Testing Event Driven Architecture Presentation
Testing Event Driven Architecture PresentationTesting Event Driven Architecture Presentation
Testing Event Driven Architecture Presentation
 
Testing Event Driven Architecture Presentation
Testing Event Driven Architecture PresentationTesting Event Driven Architecture Presentation
Testing Event Driven Architecture Presentation
 
CEP: Event-Decision Architecture for PredictiveBusiness, July 2006
CEP: Event-Decision Architecture for PredictiveBusiness, July 2006CEP: Event-Decision Architecture for PredictiveBusiness, July 2006
CEP: Event-Decision Architecture for PredictiveBusiness, July 2006
 
Reaction RuleML 1.0
Reaction RuleML 1.0Reaction RuleML 1.0
Reaction RuleML 1.0
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
 
Achievement for wireless
Achievement for wirelessAchievement for wireless
Achievement for wireless
 
Product assurance
Product assurance Product assurance
Product assurance
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
Dynamic vs. Traditional Probabilistic Risk Assessment Methodologies - by Huai...
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Open Source Event Processing for Sensor Fusion Applications
Open Source Event Processing for Sensor Fusion ApplicationsOpen Source Event Processing for Sensor Fusion Applications
Open Source Event Processing for Sensor Fusion Applications
 
An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Crime Risk Forecasting and Predictive Analytics - Esri UC
Crime Risk Forecasting and Predictive Analytics - Esri UCCrime Risk Forecasting and Predictive Analytics - Esri UC
Crime Risk Forecasting and Predictive Analytics - Esri UC
 

More from Intaver Insititute

More from Intaver Insititute (20)

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - Reporting
 
Project Cost Analysis
Project Cost AnalysisProject Cost Analysis
Project Cost Analysis
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 

Recently uploaded

Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Peter Udo Diehl
 

Recently uploaded (20)

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024
 
AI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří KarpíšekAI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří Karpíšek
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
 
Free and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
Free and Effective: Making Flows Publicly Accessible, Yumi IbrahimzadeFree and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
Free and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCustom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
 
Powerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara LaskowskaPowerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara Laskowska
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 

Project Risk Analysis in Aerospace Industry

  • 1. Intaver Institute Inc. 303, 6707, Elbow Drive S.W., Calgary AB Canada T2V 0E5 www.intaver.com Quantitative Risk Analysis for Aerospace Industry
  • 2. Common Issues with Space System Projects • Multiple risks and uncertainties • Many uncertainties are event-driven • Historical data mining should include relevance analysis
  • 3. Existing Methodologies • PERT • Monte Carlo Simulation • Bayesian approach • Scenario analysis and Decision Trees
  • 4. Project Example Laser Interferometer Space Antenna (LISA) project Calendar Year ==> Project Phasing NASA HQ Milestones Mission Reviews SE&I Contractor Acquisition Technology LISA Test Package (SM2) ST7 DRS (SM2) Interferometry Measurement System System Verification Disturbance Reduction System Payload Spacecraft Observatory I&T Constellation Testing Launch Campaign Pre-Phase A Phase A Phase B Phase C/D FAD ICR/CA NAR ESA MOU (F) PCA FAD HQ Briefing MDR SRR SCR TRR PDR CDR S/C1 PER Obs 1 PER MOR ORR PSR MRR FRR LRR Prep Phase Execution PhasePartnering Phase RFI RFP D Sel RFP Sel LISA Demo CDR Deliver to SM2 SM2 Launch DRS Demo PDR CDR Deliver to SM2 SM2 Launch Trades Subs Assy Test TRL5 TRL6 Model Envr R1 Model Envr R2 Model Envr R3 Testbed Demos Trades Tgt Std Subs Assy Test GRS TRL5 GRS TRL6 Rqts/Architecture/Trades Design Build / Test PDR CDR EM 1 2 3 ESA Definition Phase ITT Award ITT Award PDR CDR ESA Implementation Phase EM 1 2 3 Preps Observatory I&T EM 1 2 3 Preps 1 2 Constellation Testing 3 Launch Preps LRD 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 The document is courtesy of NASA/Goddard Space Flight Center
  • 5. Heuristics and Biases in Project Management The Bank of Sweden Prize in Economic Sciences in Memory of Alfred Nobel 2002 Daniel Kahneman Decision makers use “heuristics”, or general rules of thumb, to arrive at their judgments. In certain instances, this will lead to systemic biases.
  • 6. Examples of Heuristics in Project Management • Representativeness – unwanted appeal to detailed scenarios • Availability – access the probability of an event by the ease with which instances can be brought to mind • Anchoring – human tendency is to remain close to the initial estimate
  • 7. Event Chain Methodology Event Chain Methodology is a method of modeling uncertainties for different time-related business and technological processes including project management for space systems.
  • 8. Moment of Risk and State of Activity An activity (task) in most real life processes is not a continuous uniform procedure. Tasks are affected by external events, which transform an activity from one state to another.
  • 9. Event Chains Events can cause other events, which will create event chains. These event chains can significantly affect the course of the project.
  • 10. Monte Carlo Simulations Once events and event chains are defined, quantitative analysis using Monte Carlo simulation can be performed to quantify the cumulative impact of the events. Information regarding the uncertainties expressed as an event is supplemented with distributions related to duration, start time, cost, and other parameters
  • 11. Critical Chains of Events The single events or the event chains that have the most potential to affect the projects are the “critical events” or “critical chains of events.”
  • 12. History Matching and Relevance Analysis • Similar events or event chains are found based on historical data • Analysis based on Bayesian approach is performed and relevance parameter is calculated • Project manager defines relevance of each event or event chain for the current project • Both calculated and user defined relevance parameters are used to determine probability and impact of the events for the current project
  • 13. Performance Tracking with Event and Event Cha During the course of the project, the probability and time of the events can be recalculated based on actual data. Actual performance data and original estimate is used forecast duration of activity with risks
  • 14. Event Chain Diagrams Event Chain Diagrams are visualizations that show the relationships between events and activities and how the events affect each other
  • 15. Repeated Activities Common scenario for real life projects: sometimes a previous activity must be repeated based on the results of event in a succeeding activity
  • 16. Event Chains and Risk Mitigation Mitigation plan can be assigned to an event or event chain. These small schedules will be triggered when an event chain occurs.
  • 17. Resource Allocation Based on Events Event: the reassignment of a resource from one activity to another Example: if an activity requires more resources to complete it within a fixed period, this will trigger an event to reallocate the resource from another activity.
  • 18. Project Management Workflow using Event Cha Methodology 1. Define a detailed project schedule with resources and costs assigned to the activities 2. Define a detailed risk breakdown structure and assign risks to the activities. The probability of each event can be taken from historical data. 3. Define the activities associated with mitigation efforts and then assign costs and resources to them.
  • 19. 4. Perform a quantitative risk analysis using Monte Carlo simulations. 5. Analyze the results of the quantitative risk analysis: perform a sensitivity analysis and identify the crucial tasks and critical risks. Project Management Workflow using Event Chain Methodology
  • 20. 6. Perform reality checks: compare the results of analysis with outside independent expert reviews and historical experience. 7. Monitor the course of the project on a regular basis, perform repeated quantitative risk analysis, reassess the event and event chain parameters Project Management Workflow using Event Chain Methodology
  • 21. Acknowledgements Intaver Institute Inc. is thankful to Kevin N. Miller, Deputy Project Manager/Resources, Laser Interferometer Space Antenna (LISA) Project, NASA/Goddard Space Flight Center, for providing data necessary to illustrate the methodology discussed in the paper.