How to Model Cost Risk for
Monte Carlo Analysis
Intaver Institute Inc.
400, 7015, Macleod Trail,
Calgary, AB, Canada
Tel: +1 (403.) 692-2252
www.intaver.com
Two Sources of Cost
Fixed Costs
• Not time dependent
• Can represent any costs
• Are not calculated based on
Work
Resource Costs
• Associated with work, material
and cost resources
• Can be time dependent and
calculated based on Work
Two Sources of Risk
Uncertainty
• 3 point estimate (low, most
likely, high)
• Statistical Distribution
(triangular, lognormal, BetaPert,
etc)
Risk events
• Probability
• Impact (Fixed or Relative)
• Defined in Risk Register
Uncertainties in Fixed Costs
Inputs
Low:$950 Most Likely:$1000 High:$1110
Add cost uncertainty by adding Low,
Most Likely, and High estimates with a
statistical distribution
Results
The result on a single cost item with
different distributions
Triangular
Lognormal
ResultsInputs
Risk Events and Fixed Costs
Add risk events with Probability, Impact
Type (fixed or relative), and Statistical
Distribution (if required)
Single Impact
Ranged Impact
Fixed cost increase of $1,500
Chance 35%
Fixed cost increase
between $1,200 and $1,900
Chance 35%
Work Cost Calculation
This resource has a rate of $100/hr
The resource has been assigned to a 5 day task
The resource allocation of 100% generates 40 hrs
of work
The cost of the resource = (Hours Work x Rate)
40 hours x $100/hr = $4000
Work rate based resources are time dependent!
Results
Time Dependent Resource Costs
Inputs
Schedule Risk Event
Schedule Uncertainty
Results
Rate Risks
Input
Rate increase risk (work type resource only)
Material Costs Calculation
This material resource has a rate of
$750
The material resource does not
generate Work hrs
Materials costs are calculated using
Units, e.g. 1.5 tons
The cost of the resource =
Units allocated x Rate1.5 tons x $750
= $1,125
Material resource costs are not time dependent
Results
Material Risks
Input
• White Papers and Articles: http://intaver.com/technology/articles-and-white-
papers/
• Online Tutorials: http://intaver.com/RiskyProjectTutorial
• Risk and Decision Analysis Books: http://www.projectdecisions.org
Contact Details
Michael Trumper
Intaver Institute Inc.
mtrumper@intaver.com
403.692.2252
Additional Resources
Additional Resources
Project Think:
Why Good
Managers Make
Poor Project
Choices
Project Decisions: The
Art and Science
Introduction to Project
Risk Management and
Decision Analysis
Project Risk Analysis
Made Ridiculously
Simple

More Related Content

Similar to Project Cost Analysis

Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security InstituteTips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Hernan Huwyler, MBA CPA
 
riskmanagement-170228074706trrrrrrrr.pdf
riskmanagement-170228074706trrrrrrrr.pdfriskmanagement-170228074706trrrrrrrr.pdf
riskmanagement-170228074706trrrrrrrr.pdf
AteedOlaiya
 
Risk management
Risk managementRisk management
Risk management
Harold Malamion
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
Serdar Temiz
 
From Raw Data to Deployed Product. Fast & Agile with CRISP-DM
From Raw Data to Deployed Product. Fast & Agile with CRISP-DMFrom Raw Data to Deployed Product. Fast & Agile with CRISP-DM
From Raw Data to Deployed Product. Fast & Agile with CRISP-DM
Michał Łopuszyński
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
KareemRasmy1
 
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
PAPIs.io
 
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
Rahul Guhathakurta
 
Top 10 Data Science Practitioner Pitfalls
Top 10 Data Science Practitioner PitfallsTop 10 Data Science Practitioner Pitfalls
Top 10 Data Science Practitioner Pitfalls
Sri Ambati
 
Machine learning and_nlp
Machine learning and_nlpMachine learning and_nlp
Machine learning and_nlp
ankit_ppt
 
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
Dr. Haxel Consult
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
p6academy
 
Kaggle Gold Medal Case Study
Kaggle Gold Medal Case StudyKaggle Gold Medal Case Study
Kaggle Gold Medal Case Study
Alon Bochman, CFA
 
Pricing Pitfalls...and How to Counter Them
Pricing Pitfalls...and How to Counter ThemPricing Pitfalls...and How to Counter Them
Pricing Pitfalls...and How to Counter Them
Gus Prestera
 
Practical deep learning for computer vision
Practical deep learning for computer visionPractical deep learning for computer vision
Practical deep learning for computer vision
Eran Shlomo
 
Deep Feature Synthesis
Deep Feature SynthesisDeep Feature Synthesis
Deep Feature Synthesis
Martin Eastwood
 
Scientific Revenue USF 2016 talk
Scientific Revenue USF 2016 talkScientific Revenue USF 2016 talk
Scientific Revenue USF 2016 talk
ScientificRevenue
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
Intaver Insititute
 
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security InstituteTips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Hernan Huwyler, MBA CPA
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi
 

Similar to Project Cost Analysis (20)

Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security InstituteTips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
 
riskmanagement-170228074706trrrrrrrr.pdf
riskmanagement-170228074706trrrrrrrr.pdfriskmanagement-170228074706trrrrrrrr.pdf
riskmanagement-170228074706trrrrrrrr.pdf
 
Risk management
Risk managementRisk management
Risk management
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
From Raw Data to Deployed Product. Fast & Agile with CRISP-DM
From Raw Data to Deployed Product. Fast & Agile with CRISP-DMFrom Raw Data to Deployed Product. Fast & Agile with CRISP-DM
From Raw Data to Deployed Product. Fast & Agile with CRISP-DM
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
 
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
A business level introduction to Artificial Intelligence - Louis Dorard @ PAP...
 
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
Advance Supply Chain Management : Holistic Overview with respect to an ERP an...
 
Top 10 Data Science Practitioner Pitfalls
Top 10 Data Science Practitioner PitfallsTop 10 Data Science Practitioner Pitfalls
Top 10 Data Science Practitioner Pitfalls
 
Machine learning and_nlp
Machine learning and_nlpMachine learning and_nlp
Machine learning and_nlp
 
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
AI-SDV 2022: Possibilities and limitations of AI-boosted multi-categorization...
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Kaggle Gold Medal Case Study
Kaggle Gold Medal Case StudyKaggle Gold Medal Case Study
Kaggle Gold Medal Case Study
 
Pricing Pitfalls...and How to Counter Them
Pricing Pitfalls...and How to Counter ThemPricing Pitfalls...and How to Counter Them
Pricing Pitfalls...and How to Counter Them
 
Practical deep learning for computer vision
Practical deep learning for computer visionPractical deep learning for computer vision
Practical deep learning for computer vision
 
Deep Feature Synthesis
Deep Feature SynthesisDeep Feature Synthesis
Deep Feature Synthesis
 
Scientific Revenue USF 2016 talk
Scientific Revenue USF 2016 talkScientific Revenue USF 2016 talk
Scientific Revenue USF 2016 talk
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security InstituteTips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
Tips for IT Risk Management Prof. Hernan Huwyler Information Security Institute
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 

More from Intaver Insititute

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
Intaver Insititute
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
Intaver Insititute
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
Intaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
Intaver Insititute
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Intaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
Intaver Insititute
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
Intaver Insititute
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
Intaver Insititute
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Intaver Insititute
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
Intaver Insititute
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
Intaver Insititute
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
Intaver Insititute
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
Intaver Insititute
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
Intaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
Intaver Insititute
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
Intaver Insititute
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
Intaver Insititute
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
Intaver Insititute
 

More from Intaver Insititute (20)

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rus
 

Recently uploaded

Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdfEnhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
GetInData
 
The Building Blocks of QuestDB, a Time Series Database
The Building Blocks of QuestDB, a Time Series DatabaseThe Building Blocks of QuestDB, a Time Series Database
The Building Blocks of QuestDB, a Time Series Database
javier ramirez
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
g4dpvqap0
 
State of Artificial intelligence Report 2023
State of Artificial intelligence Report 2023State of Artificial intelligence Report 2023
State of Artificial intelligence Report 2023
kuntobimo2016
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
Timothy Spann
 
Everything you wanted to know about LIHTC
Everything you wanted to know about LIHTCEverything you wanted to know about LIHTC
Everything you wanted to know about LIHTC
Roger Valdez
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Kiwi Creative
 
My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.
rwarrenll
 
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
nyfuhyz
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
aqzctr7x
 
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
mzpolocfi
 
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
74nqk8xf
 
Global Situational Awareness of A.I. and where its headed
Global Situational Awareness of A.I. and where its headedGlobal Situational Awareness of A.I. and where its headed
Global Situational Awareness of A.I. and where its headed
vikram sood
 
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
74nqk8xf
 
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
u86oixdj
 
Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...
Bill641377
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
Lars Albertsson
 
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
slg6lamcq
 
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
v3tuleee
 
Challenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more importantChallenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more important
Sm321
 

Recently uploaded (20)

Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdfEnhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
 
The Building Blocks of QuestDB, a Time Series Database
The Building Blocks of QuestDB, a Time Series DatabaseThe Building Blocks of QuestDB, a Time Series Database
The Building Blocks of QuestDB, a Time Series Database
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证如何办理
 
State of Artificial intelligence Report 2023
State of Artificial intelligence Report 2023State of Artificial intelligence Report 2023
State of Artificial intelligence Report 2023
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
 
Everything you wanted to know about LIHTC
Everything you wanted to know about LIHTCEverything you wanted to know about LIHTC
Everything you wanted to know about LIHTC
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
 
My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.
 
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
一比一原版(UMN文凭证书)明尼苏达大学毕业证如何办理
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
 
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
一比一原版(Chester毕业证书)切斯特大学毕业证如何办理
 
Global Situational Awareness of A.I. and where its headed
Global Situational Awareness of A.I. and where its headedGlobal Situational Awareness of A.I. and where its headed
Global Situational Awareness of A.I. and where its headed
 
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
一比一原版(牛布毕业证书)牛津布鲁克斯大学毕业证如何办理
 
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
 
Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
 
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
 
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
 
Challenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more importantChallenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more important
 

Project Cost Analysis

  • 1. How to Model Cost Risk for Monte Carlo Analysis Intaver Institute Inc. 400, 7015, Macleod Trail, Calgary, AB, Canada Tel: +1 (403.) 692-2252 www.intaver.com
  • 2. Two Sources of Cost Fixed Costs • Not time dependent • Can represent any costs • Are not calculated based on Work Resource Costs • Associated with work, material and cost resources • Can be time dependent and calculated based on Work
  • 3. Two Sources of Risk Uncertainty • 3 point estimate (low, most likely, high) • Statistical Distribution (triangular, lognormal, BetaPert, etc) Risk events • Probability • Impact (Fixed or Relative) • Defined in Risk Register
  • 4. Uncertainties in Fixed Costs Inputs Low:$950 Most Likely:$1000 High:$1110 Add cost uncertainty by adding Low, Most Likely, and High estimates with a statistical distribution Results The result on a single cost item with different distributions Triangular Lognormal
  • 5. ResultsInputs Risk Events and Fixed Costs Add risk events with Probability, Impact Type (fixed or relative), and Statistical Distribution (if required) Single Impact Ranged Impact Fixed cost increase of $1,500 Chance 35% Fixed cost increase between $1,200 and $1,900 Chance 35%
  • 6. Work Cost Calculation This resource has a rate of $100/hr The resource has been assigned to a 5 day task The resource allocation of 100% generates 40 hrs of work The cost of the resource = (Hours Work x Rate) 40 hours x $100/hr = $4000 Work rate based resources are time dependent!
  • 7. Results Time Dependent Resource Costs Inputs Schedule Risk Event Schedule Uncertainty
  • 8. Results Rate Risks Input Rate increase risk (work type resource only)
  • 9. Material Costs Calculation This material resource has a rate of $750 The material resource does not generate Work hrs Materials costs are calculated using Units, e.g. 1.5 tons The cost of the resource = Units allocated x Rate1.5 tons x $750 = $1,125 Material resource costs are not time dependent
  • 11. • White Papers and Articles: http://intaver.com/technology/articles-and-white- papers/ • Online Tutorials: http://intaver.com/RiskyProjectTutorial • Risk and Decision Analysis Books: http://www.projectdecisions.org Contact Details Michael Trumper Intaver Institute Inc. mtrumper@intaver.com 403.692.2252 Additional Resources
  • 12. Additional Resources Project Think: Why Good Managers Make Poor Project Choices Project Decisions: The Art and Science Introduction to Project Risk Management and Decision Analysis Project Risk Analysis Made Ridiculously Simple

Editor's Notes

  1. Welcome to Intaver Institutes video : How to Model Cost Risk for Monte Carlo Analysis. We are going to be taking a detailed look at how costs are calculated and how to apply risks and uncertainties to your cost model for Monte Carlo risk analysis.
  2. In RiskyProject, costs can be divided in the two main categories. Fixed Costs. Fixed costs can be used to represent any costs are not time related due to resource allocation. Typically, they will represent costs that are not related to specific resources. Resources costs: Resource costs are based on the hourly rates or cost per use of resources assigned to activities. Resource costs can be used to calculate time dependent costs using resource rates. * Cost Type resources are a special case as they are a way of allocating cost to a specific activity and are a hybrid method that shares characteristics of both fixed costs and resource costs.
  3. When creating a cost risk model, we can apply two types of risk to our costs: Uncertainty and Risk Events Uncertainty is characterized by 3 point estimates (low, most likely, and high) combined with a statistical distribution. Uncertainty can be applied to both duration and costs for the purpose of cost analysis. Risk events are also sometime referred to as “risk drivers” and are characterized by a probability of occurrence and impacts. For cost risk analysis, both fixed cost and schedule impacts can be used.
  4. Here we show how we can apply uncertainty to a fixed cost. The Base or Most Likely cost is $1000. The low or optimistic is $950 and the High or pessimistic is $1100. A visual representation of the these estimates with a triangular statistical distribution is shown on the left. On the right, we can see can see the results of an analysis using two different types of statistical distributions. Different distributions can affect statistical measures like standard deviation. On the top example, we can see that the triangular distribution has “fatter” tails or results have a higher probability of landing farther from the Most Likely value than in the Lognormal distribution.
  5. Risk events are risks that are found in the risk register. The have a probability of occurring and an impact. Probabilities are between 0 and 100%. Impacts can be fixed or relative (a % of the base cost) Impacts can be a discrete value or can be modeled as an uncertainty with a range of values defined by a statistical distribution. In the first example with a discrete impact, the risk appears as a single bar in the histogram. In the second example, with a ranged impact, the risk appears as a small distribution to the right of the base estimate. As we can see, the way we choose to model the risks can have a significant impact on the results.
  6. Work is the fundamental unit of the time dependent cost calculation. Work is a function of the resource allocation. Resource units indicates the level of allocation or % of the activity duration that the resource will be working on an activity. For the purposes of this discussion, we are using the commonly used “fixed unit” task type, which keeps resource allocations (units) fixed and recalculates work if duration is modified. We will discuss the appropriate use of other task types in a future video. In this example we can see how the base costs for a resource assigned to a task is calculated. If we lowered the Max units to 50%, the Work performed by the resource over the same period would be reduced to 20 hours at a cost of $2000. The other thing to take note is that if the duration changes, work and therefore resource costs are adjusted accordingly. In this way resources can be used to model time dependent costs.
  7. Work based resource costs can be risked as part of integrated approach of cost and schedule risk analysis. Both schedule uncertainty and risk events impact work based resource costs. In these examples we show how schedule uncertainty and riska are presented on a combined histogram and cumulative probability chart.
  8. Work based risks can also be affected by non schedule risks. These are called rate increase risks where we can apply either a relative or fixed impacts to the resource rate. In this way, you can account for uncertainty in labour rate. As with the previous examples, we can see the results of the rate uncertainty on the probable cost of the activity. Rate risks are assigned in the Resource Information dialog box > Risks tab. Once the risk has been assigned to the resource, the risk is applied or “broadcasted” to all of the activities to which the resource is assigned.
  9. Another type of resource are material costs. Material costs are not based on work, and therefore, not time dependent. Material resource costs are calculated on a rate/unit. For example in a particular activity, you could have a materials costs of $X/ton. The material resource is assigned to an activity with a Unit value. The cost is then allocated to the activity based on the rate and units.
  10. Material costs are treated similarly as a fixed costs when it comes to risk events. Material cost can be risked using the Outcome type “Fixed Cost Increase” Relative cost increase outcome type does not work in this case. In this example, we can see how we can apply a range of possible rates for the material and its presentation on the chart. In addition, if you are using Cost Type resources, which are similar to Material costs, cost type resources can be risked for each specific activity using the same method.
  11. Thank you for watching our video on Cost Modeling for Monte Carlo Risk Analysis. Please visit our site at intaver.com to learn more about risk analysis and our upcoming videos and webinars.
  12. If you are interested in finding out more about Decision Analysis and Risk Management a list of our publications and a variety of resources can be found at our website Project Decisions.org