PROJECT GOVERNANCE
SURAJ ARVAPALLY
Student ID: 117062
1
ContentsObjectives.
Conclusions / Recommendations
Introduction.
Literature review
Case study.
Analysis of case study
References
2
Objective of the study
• To understand the concept of project governance.
• To understand the implementation of the principles of project governance
in construction organizations.
• To analyze the principles by implementing them on case study.
3
INTRODUCTION
4
What is project governance ?
• Project governance is the management framework within which
decisions of the project are made.
Project
governance
Policies
Regulations
FunctionsProcedure
Portfolios
Confident and
transparent
5
INTRODUCTION
CORPORATE GOVERNANCE
PROJECT MANAGEMENT
PROJECT
GOVERNANCE
RELATION
• Provides the structure through
which the objectives of the
company are set.
• It is the system by which
companies are directed and
controlled.
company’s
management
Its board
Its
shareholders
Other
stakeholders
6
Why project governance?
Set out lines of responsibility and accountability within the Authority for the delivery of the
project;
Give the stakeholders the ability to manage their interest in the project;
Provide a forum for issue resolution;
Communicate information by reporting to stakeholders so that they can effectively fulfil
their roles
Provide a framework for project disclosures.
7
Literature review
8
INVESTMENT DECISION GROUP
PROJECT TEAM
STRATEGIC
ADVISORS
PROJECT
MANAGER SHAREHOLDER
WORKING
GROUP
SENIOR SUPPLIERPROJECT OWNER
PROJECT
DIRECTOR
SENIOR USER
PROJECT GOVERNANCE FRAMEWORK
9
Project owner/sponsor
• The project sponsor usually chairs the project steering committee and is the link
between the organization's senior executive body and the project.
• Owner is ultimately accountable for
the success of the project.
Senior
executive
body
Owner Project
10
Project
sponsor
Project leadership
The sponsor provides:
timely decisions, clarifies decision
making framework, clarifies business
priorities and strategy, communicates
business issues, provides resources,
engenders trust, manages
relationships.
Project management
• The project sponsor engages
stakeholders.
• governs stakeholder
communications,
• Manages client relationships and
governance of users and suppliers.
• arbitrates between stakeholders.
Stakeholder management
The sponsor provides leadership on culture and
values, owns the business case, working with the
steering committee keeps the project aligned with
the organization's strategy, governs project risk,
focuses on benefits.
11
The responsibilities of the project sponsor are:
• Securing budgets and ensuring appropriate financial controls are in place
• Supporting the project manager to successfully deliver the project.
• Prescribing the project both internally and externally.
• Ensuring a project is undertaken according to the Project Management Framework.
• Appointing the project management team including other members of the Project
Board
• Signing off project deliverables
12
Project Board
• It provides direction and management for the project.
• Final decision is made by the project owner.
• Project board meeting is often organized for project board members for
decision making on reports of the project director and project manager
SENIOR SUPPLIERPROJECT OWNER
PROJECT
DIRECTOR
SENIOR USER
13
Project Director
• The project director acts as a representative of project owner and
responsible for empowering project manager.
• The project director is a core member of the project steering committee or
project board.
Skills
project
management
.
Risk
management
Relation
management
14
Project manager
• He ensures that the project outcomes are of required quality.
• Develops and updates the project management plan.
• Have to manage day-to-day aspects of project on behalf of project owner.
• Project management also resolves planning, implementation issues and
manage progress and budget of the project.
15
Responsibilities of project manager:
Directing the project team
Maintaining the risk register, issue.
Managing the project plan.
Reporting on progress to the project sponsor and other stakeholders
Ensuring the project is managed in accordance with agreed processes and tolerances
approving minor variations to budget, schedule or scope, within agreed tolerances
16
Investment Decision Group
• This group provides platform to stakeholders to give any kind of input to
the project.
• No validity for life span of the group. (Entire life of the project)
• Internal or external of organization.
• Stakeholders may be invited to participate but often they will not report to
the organization and cannot be forced to participate.
• Called to support project board (Rarely)
17
5 Questions for Governance team
• (Includes both on and off project activities.)
Are we on track – to plan/schedule?
• (Includes required business decisions and escalation issues.)
What decisions need to be made?
• (Includes required inter-dependency issues, resource issues, proposed scope
changes.)
What issues are there – inside or outside the
project?
• (Includes expenditure, financial commitments, AND benefit value driver
changes and benefits realized to date.)
Are we on track – to budget and benefits plans?
• (Includes project, benefits delivery and business impact risks and critical success
factors status.)
Has the objectives of the project changed?
18
2.2 PRINCIPLES OF EFFECTIVE PROJECT GOVERNANCE:
1: Ensure a single point of accountability.
2: Service delivery ownership determines project ownership
3: Ensure separation of stakeholder management and project
decision-making
4: Ensure separation of project governance and organizational
governance structures
19
1: Ensure a single point of accountability
• Ensures clarity of decision making and empowers the accountable person
within the organization.
• Consistency of accountability throughout the project’s life ensures proper
decision-making – the focus of the project, its objectives and the benefits it
seeks remain consistent throughout its life, or at least are not changed
without due process.
• The project governance framework is a document prepared for each project
outlining who has responsibility and authority to make decisions which
ensures there is clearly defined accountability for all aspects of the project.
20
Effective accountability requires everyone within the project to know:
Note: Care should be taken to ensure individuals who join the project
receive sufficient introduction to this framework.
What they are responsible for.
The limits of their authority and tolerance levels.
When tasks have to be achieved.
Communication, reporting and monitoring lines.
21
2: Service delivery ownership determines project ownership
• Organizations have to be more competitive by continuously increasing their
quality of service
• Services can be delivered directly or indirectly by products.
• For example, construction material producers provide services to a housing
developer through construction materials they produce, and the way that
they serve is considered on quality, schedule, cost, etc,
• Changes on technology may support the service or the project which delivers
the service. For example, precast concrete panel can shorten construction
schedule of the project;
22
The project as a transition mechanism
Equal importance to project ownership and (service and Asset delivery)
23
3: Ensure separation of stakeholder management and project
decision-making
Increase in size of the committee.
The detailed understanding of each attendee of the critical project issues
reduces
Many members within the assembly raise more opinions, Questions
because they consider that being members of the assembly they are entitled
to do so.
They just use the meeting to get updated about the project issues
stakeholder Management (Project board - decision making)
24
4: Ensure separation of project governance and organizational
governance structures
• The project governance is ineffective if there are many layers in the project
decision making process.
• Organization structures generally do not provide the necessary framework to
deliver a project.
• Adoption of this principle will minimize multi layered decision making and
the time delays.
• Empower Project decision making body to make decisions in a timely
manner.
25
What happens if governance is not good?
Failure to communicate fully and appropriately on a timely basis.
Failure to specify or accept decision making authority and responsibilities.
Confusing contract management and decision making.
Over emphasis on reporting that reduces meetings to status updates rather than interactive decision making.
Non-alignment of key stakeholders.
Confusion between the project and organizational decision-making structures.
lack of project direction and control.
26
“STAR SERVICE CENTER”
27
Introduction
• In 2009, the board of directors decided to invest in the project SSC. It is a five
storey office building located on plot A-01, star road, in Star Commercial Complex
(SCC), Dilshuknagar, Hyderabad city, Telangana, India with its main objective of
initiating the master project SCC and of providing office services to tenants as well
as for STAR itself. Total land area of the building is 6,634.03m2.
• Total construction schedule of the project is 638 days starting from December 17,
2009 and completed on September 16, 2011, delayed 286 days as per the project
plan.
28
SSC
STRUCTURAL
Main building
ARCHITECTURAL
ParkingInfrastructure
M/E
Fire prevention and fighting
system
Electrical
works
Plumbing/ Water supply
Land Scaping
WORK BREAK DOWN STRUCTURE
• 2,787.5 m2
• Five floors
• RCC
• Internal
traffic
• RCC road
• 280 bikes
• 50 cars
• RCC
• Sump
• Over head
tank
• Supply
560KVA
• Generator
• Installation of smoke
detectors, sprinklers
etc.,
• 20%
29
Project cost
Total project cost is classified into eight packages:
Original Cost:- 43615USD
Liquidated Cost:- 53544USD
Original Cost:- 113464USD
Liquidated Cost:- 136157USD
Original Cost:- 1076514USD
Liquidated Cost:- 1076514USD
Original Cost:- 44180USD
Liquidated Cost:- 46899USD
4:Perfect construction work package
3. Package of transformer and underground water
tank:
2. Construction supervision and construction
management package:
1. Design package:
30
Original Cost:- 1123183USD
Liquidated Cost:- 1104384USD
4:Perfect construction work package
Original Cost:- 136969USD
Liquidated Cost:- 151713USD
4:Perfect construction work package
Original Cost:- 31490USD
Liquidated Cost:- 22190USD
Original Cost:- 3147USD
Liquidated Cost:- 3219USD
5. M&E work:
6. Infrastructure and parking shed package:
8. Landscaping work:
7. Retaining wall package:
31
THE PROJECT GOVERNANCE FRAMEWORK
The Project Director
(Engineering Manager)
The Project Owner
(President)
The Senior User
(Department Managers)
The senior Supplier (Designer and Interior Contractors) Project Board
Investment Decision Group (Board of Directors)
Project Manager appointed by Senior Supplier
Project team (architect, civil engineer, M&E engineer and interior engineer)
32
PROJECT SPONSOR
• The sponsor of SSC is STAR
• The management assigned the president of organization as sponsor of the
project.
• He is the head of the project board responsible for project success.
• He assigned project director and other staff of project board.
• He involved in the project board and solved many issues within project
board.
• He reported the information directly to the investment decision group.
33
SENIOR USER
• The first defined user of SSC is STAR itself using 900 m2 of building area.
• The sponsor assigned manager of the site management department to act as
the Senior user of the building after completion of construction.
• Operation and maintenance.
• Other users are customers having office demand. They are undefined users.
• As this manager is not the member of project board.
• There is no manual of users requirement from early stage of the project.
34
SENIOR SUPPLIER
• The project sponsor decided to choose the senior suppliers from outside of the
organization.
• Company A was assigned as the designer of the project.
• Company B was selected for main construction packages through bidding process.
• Company C was nominated by owner for sub-construction works like transformer,
underground water tank and retaining walls.
• Company D was nominated for infrastructure and parking sheds by sponsor.
• Company E was nominated by sponsor for landscaping.
It is reminded that all of the senior suppliers nominated by owner are professional in the allotted works
35
PROJECT DIRECTOR
• The project owner appointed the manger of the engineering department as
the project director.
• He is the member of the project board and reports the information directly
to the project owner and also the project manager.
• The project director nominated two engineers in the engineering department
to act as project engineers for the SSC.
• The project director presented daily in the project to keep the project
supported.
• The project director is expertise in construction management, so he could
assist the project owner to drive the project successfully.
36
PROJECT BOARD
• The project board was established as per the decision of the project owner.
• Members of the project board are the project owner, the project director, and the
senior supplier.
• The project board was lack of senior user as discussed in the above article senior
user.
• The main objective of the project board is decision making.
• Weekly meeting are held. (Project budget, project quality, project work scope,
material changes, budget changes.)
37
PROJECT MANAGER
• Project manager was assigned by senior supplier and approved by sponsor.
• Position of project manager has changed based on the stages of the project.
• The project manager is responsible to deliver the project within the time, cost and
money mentioned in contract.
• The project manager worked closely with the project director to make sure that the
project delivery meets the project’s owner’s needs.
• There was 5 main project managers represented by companies A,B,C,D and E.
38
INVESTMENT DECISION GROUP
• The project owner with support from the project board submitted budget
plan to the investment decision group (the board of directors) for approval.
• In case of budget change, the project board was responsible to consider and
give instruction whether it approves for the change. The investment
• decision group in this case study includes a chairman, a vice chairman and six
directors.
39
PROJECT TEAM
• The project team comprised engineers assigned by senior suppliers
• Members of the project team worked and reported directly with the project
manager.
Project
team
architects
civil
engg,
M&E
engg Responsible for
Detail activities
40
ANALYSIS OF CASE STUDY
41
PRINCIPLES OF EFFECTIVE PROJECT
GOVERNANCE:
1: Ensure a single point of accountability for the success of the
project.
2: Service delivery ownership determines project ownership
3: Ensure separation of stakeholder management and project
decision-making
4: Ensure separation of project governance and organizational
governance structures
42
CONSIDERATION ON THE PRINCIPLE 1 OF EFFECTIVE PROJECT
GOVERNANCE
“Ensure a single point of accountability”
The management assigned the president of organization as
sponsor of the project.
He is the head of the project board responsible for project
success.
He assigned project director and other staff of project board.
He involved in the project board and solved many issues within
project board.
He signed the liquidated damages.
43
CONSIDERATION OF THE PRINCIPLE 2 OF EFFECTIVE PROJECT
GOVERNANCE
“Service Delivery Ownership Determines Project Ownership”
No senior user from the beginning of the project.
User needs are not defined. No proper project targets
was prepared by owner from early stage of the project.
Problems in project investment related to
ineffectiveness of parking and space for advertising
demands was aroused.
44
CONSIDERATION OF THE PRINCIPLE 3 OF EFFECTIVE
PROJECT GOVERNANCE
“Ensure Separation Of Stakeholder Management And Project Decision
Making Activities”
• Project governance framework of this project met the requirement of the
principle 3.
Project
board
Project
owner
Project
director
Senior
supplier
Therefore, all of the project
board meetings were aimed to
project decision making.
45
CONSIDERATION OF THE PRINCIPLE 4 OF EFFECTIVE
PROJECT GOVERNANCE
Ensure separation of project governance and organizational governance
structures
Slow
decision
making
Sponsor
President/
Sponsor
External
issues
Director
Manager of
engg dept/
Director
Lot of
work load
DELAY
46
Conclusions/ Recommendations
Every organization must follow the project governance framework
independent of its size.
All the projects should have the project governance framework and also
satisfy all the 4 principles of the project governance.
Ensure that the person who is selected for the sponsor of the project
should have enough ability to manage the framework and project issues.
Try to avoid playing multi roles at the same time. Due to which this project
have been delayed.
47
REFERENCES
• Alessia D’Amato and Nigel Roome (2009), Leadership of organizational change toward an integrated model of
leadership for corporate responsibility and sustainable development: a process model of corporate responsibility
beyond management innovation, Corporate Governance, Vol.9 No 4, pp. 421-434
• Karim S. Rebeiz and Zeina Salameh (2006), Relationship between Governance Structure andFinancial Performance in
Construction, Journal of Management in Engineering, Vol. 22, No.1, pp. 20-26.
• Charles Y.J. Cheah and Micharl J. Garvin (2004). An open framework for corporate strategy in construction,
Engineering, Construction and Architectural Management Vol. 11 No. 3, pp.176-188
• Pearce, J. A., and Zaha, S. A. (1991). “The relative power of CEOs and boards of directors: Association with
corporate performance.: Strategic Manage. J., 12, pp. 135-153 Pfeffer, J. (1972). “Size and composition of corporate
boards of directors.” Adm. Sci. Q., 17, 218-228
48
“THANK YOU”
49

More Related Content

What's hot

Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesSlideTeam
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMOBusiness Beam
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesErin Jones
 
Project management
Project managementProject management
Project managementNihal Ranjan
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)Dilawar Abbas
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardJavid Hamdard
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...Edureka!
 

What's hot (20)

Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
 
Project management
Project managementProject management
Project management
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Project Health Checks
Project Health ChecksProject Health Checks
Project Health Checks
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Prince2 Methodology
Prince2 MethodologyPrince2 Methodology
Prince2 Methodology
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 

Viewers also liked

Project Governance Model
Project Governance ModelProject Governance Model
Project Governance ModelConstient
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAssociation for Project Management
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementMichal Augustini
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and FailureMichael Krigsman
 
Project Governance
Project GovernanceProject Governance
Project Governanceosswatch
 
Corporate Governance to Project Governance
Corporate Governance to Project GovernanceCorporate Governance to Project Governance
Corporate Governance to Project GovernanceRichard_01
 
Project Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge ManagementProject Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge Managementsubramanian K
 
IT Project Governance Overview
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance OverviewSteve Gerick
 
Webinar: How to Drive Business Value in Financial Services with MongoDB
Webinar: How to Drive Business Value in Financial Services with MongoDBWebinar: How to Drive Business Value in Financial Services with MongoDB
Webinar: How to Drive Business Value in Financial Services with MongoDBMongoDB
 
The importance of Program Management and Change Management in eHealth
The importance of Program Management and Change Management in eHealthThe importance of Program Management and Change Management in eHealth
The importance of Program Management and Change Management in eHealthBart de Witte
 
How can you influence your Board to adopt good governance of project / change...
How can you influence your Board to adopt good governance of project / change...How can you influence your Board to adopt good governance of project / change...
How can you influence your Board to adopt good governance of project / change...Association for Project Management
 
Серводвигатели серии SR Sicme motori
Серводвигатели серии SR Sicme motoriСерводвигатели серии SR Sicme motori
Серводвигатели серии SR Sicme motoriArve
 

Viewers also liked (20)

Project Governance Model
Project Governance ModelProject Governance Model
Project Governance Model
 
Project governance
Project governanceProject governance
Project governance
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio Management
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and Failure
 
Project Governance
Project GovernanceProject Governance
Project Governance
 
Corporate Governance to Project Governance
Corporate Governance to Project GovernanceCorporate Governance to Project Governance
Corporate Governance to Project Governance
 
Directing agile change - governance of project management
Directing agile change - governance of  project managementDirecting agile change - governance of  project management
Directing agile change - governance of project management
 
Project Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge ManagementProject Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge Management
 
IT Project Governance Overview
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance Overview
 
Erp-PMO
Erp-PMOErp-PMO
Erp-PMO
 
Good governance of the project portfolio
Good governance of the project portfolioGood governance of the project portfolio
Good governance of the project portfolio
 
Tips and techniques for effective project portfolio management
Tips and techniques for effective project portfolio managementTips and techniques for effective project portfolio management
Tips and techniques for effective project portfolio management
 
Project management
Project managementProject management
Project management
 
Webinar: How to Drive Business Value in Financial Services with MongoDB
Webinar: How to Drive Business Value in Financial Services with MongoDBWebinar: How to Drive Business Value in Financial Services with MongoDB
Webinar: How to Drive Business Value in Financial Services with MongoDB
 
The importance of Program Management and Change Management in eHealth
The importance of Program Management and Change Management in eHealthThe importance of Program Management and Change Management in eHealth
The importance of Program Management and Change Management in eHealth
 
How can you influence your Board to adopt good governance of project / change...
How can you influence your Board to adopt good governance of project / change...How can you influence your Board to adopt good governance of project / change...
How can you influence your Board to adopt good governance of project / change...
 
Серводвигатели серии SR Sicme motori
Серводвигатели серии SR Sicme motoriСерводвигатели серии SR Sicme motori
Серводвигатели серии SR Sicme motori
 

Similar to Project governance

Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project ManagementInam Khosa
 
project integration mgmt.pdf
project integration mgmt.pdfproject integration mgmt.pdf
project integration mgmt.pdfIvarsLinde1
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1Mohamed , PMP
 
Project Management Framework.pptx
Project Management Framework.pptxProject Management Framework.pptx
Project Management Framework.pptxvamsnrsfdevuqsrtmy
 
Project management
Project managementProject management
Project managementobsession56
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project managementprakashnachnani
 
Project management
Project managementProject management
Project managementBiswa Prusty
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdfGourhariBiswas1
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project ProposalJo Balucanag - Bitonio
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptxagathamarlinee
 
Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycleAli Adil
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planningAbubeker mukemil
 
Project Planning and Development Intro.pptx
Project Planning and Development Intro.pptxProject Planning and Development Intro.pptx
Project Planning and Development Intro.pptxJo Balucanag - Bitonio
 
Getting Really Good at Projects with Salesforce!.pptx
Getting Really Good at Projects with Salesforce!.pptxGetting Really Good at Projects with Salesforce!.pptx
Getting Really Good at Projects with Salesforce!.pptxRizwanQureshi64
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management Yesica Adicondro
 

Similar to Project governance (20)

Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 
project integration mgmt.pdf
project integration mgmt.pdfproject integration mgmt.pdf
project integration mgmt.pdf
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1
 
Project Management Framework.pptx
Project Management Framework.pptxProject Management Framework.pptx
Project Management Framework.pptx
 
ICT 4109.pdf
ICT 4109.pdfICT 4109.pdf
ICT 4109.pdf
 
Project management
Project managementProject management
Project management
 
Pmi dec 13
Pmi dec 13Pmi dec 13
Pmi dec 13
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 
Project management
Project managementProject management
Project management
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
 
executing process group.pdf
executing process group.pdfexecuting process group.pdf
executing process group.pdf
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project Proposal
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycle
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planning
 
Project Planning and Development Intro.pptx
Project Planning and Development Intro.pptxProject Planning and Development Intro.pptx
Project Planning and Development Intro.pptx
 
Getting Really Good at Projects with Salesforce!.pptx
Getting Really Good at Projects with Salesforce!.pptxGetting Really Good at Projects with Salesforce!.pptx
Getting Really Good at Projects with Salesforce!.pptx
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
PM FrameWork: Module 3
PM FrameWork: Module 3PM FrameWork: Module 3
PM FrameWork: Module 3
 

Recently uploaded

The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsCIToolkit
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingCIToolkit
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsCIToolkit
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONsivani14565220
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBusiness of Software Conference
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesMassimo Canducci
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsCIToolkit
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfcoolsnoopy1
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Conny Dethloff
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Nagarjuna Reddy Aturi
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Designshakkardaddy
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationPMIUKChapter
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Managementshakkardaddy
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teamsshakkardaddy
 

Recently uploaded (20)

The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data Insights
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-Making
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human Resources
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data Sets
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdf
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram Analysis
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentation
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Management
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teams
 

Project governance

  • 2. ContentsObjectives. Conclusions / Recommendations Introduction. Literature review Case study. Analysis of case study References 2
  • 3. Objective of the study • To understand the concept of project governance. • To understand the implementation of the principles of project governance in construction organizations. • To analyze the principles by implementing them on case study. 3
  • 5. What is project governance ? • Project governance is the management framework within which decisions of the project are made. Project governance Policies Regulations FunctionsProcedure Portfolios Confident and transparent 5
  • 6. INTRODUCTION CORPORATE GOVERNANCE PROJECT MANAGEMENT PROJECT GOVERNANCE RELATION • Provides the structure through which the objectives of the company are set. • It is the system by which companies are directed and controlled. company’s management Its board Its shareholders Other stakeholders 6
  • 7. Why project governance? Set out lines of responsibility and accountability within the Authority for the delivery of the project; Give the stakeholders the ability to manage their interest in the project; Provide a forum for issue resolution; Communicate information by reporting to stakeholders so that they can effectively fulfil their roles Provide a framework for project disclosures. 7
  • 9. INVESTMENT DECISION GROUP PROJECT TEAM STRATEGIC ADVISORS PROJECT MANAGER SHAREHOLDER WORKING GROUP SENIOR SUPPLIERPROJECT OWNER PROJECT DIRECTOR SENIOR USER PROJECT GOVERNANCE FRAMEWORK 9
  • 10. Project owner/sponsor • The project sponsor usually chairs the project steering committee and is the link between the organization's senior executive body and the project. • Owner is ultimately accountable for the success of the project. Senior executive body Owner Project 10
  • 11. Project sponsor Project leadership The sponsor provides: timely decisions, clarifies decision making framework, clarifies business priorities and strategy, communicates business issues, provides resources, engenders trust, manages relationships. Project management • The project sponsor engages stakeholders. • governs stakeholder communications, • Manages client relationships and governance of users and suppliers. • arbitrates between stakeholders. Stakeholder management The sponsor provides leadership on culture and values, owns the business case, working with the steering committee keeps the project aligned with the organization's strategy, governs project risk, focuses on benefits. 11
  • 12. The responsibilities of the project sponsor are: • Securing budgets and ensuring appropriate financial controls are in place • Supporting the project manager to successfully deliver the project. • Prescribing the project both internally and externally. • Ensuring a project is undertaken according to the Project Management Framework. • Appointing the project management team including other members of the Project Board • Signing off project deliverables 12
  • 13. Project Board • It provides direction and management for the project. • Final decision is made by the project owner. • Project board meeting is often organized for project board members for decision making on reports of the project director and project manager SENIOR SUPPLIERPROJECT OWNER PROJECT DIRECTOR SENIOR USER 13
  • 14. Project Director • The project director acts as a representative of project owner and responsible for empowering project manager. • The project director is a core member of the project steering committee or project board. Skills project management . Risk management Relation management 14
  • 15. Project manager • He ensures that the project outcomes are of required quality. • Develops and updates the project management plan. • Have to manage day-to-day aspects of project on behalf of project owner. • Project management also resolves planning, implementation issues and manage progress and budget of the project. 15
  • 16. Responsibilities of project manager: Directing the project team Maintaining the risk register, issue. Managing the project plan. Reporting on progress to the project sponsor and other stakeholders Ensuring the project is managed in accordance with agreed processes and tolerances approving minor variations to budget, schedule or scope, within agreed tolerances 16
  • 17. Investment Decision Group • This group provides platform to stakeholders to give any kind of input to the project. • No validity for life span of the group. (Entire life of the project) • Internal or external of organization. • Stakeholders may be invited to participate but often they will not report to the organization and cannot be forced to participate. • Called to support project board (Rarely) 17
  • 18. 5 Questions for Governance team • (Includes both on and off project activities.) Are we on track – to plan/schedule? • (Includes required business decisions and escalation issues.) What decisions need to be made? • (Includes required inter-dependency issues, resource issues, proposed scope changes.) What issues are there – inside or outside the project? • (Includes expenditure, financial commitments, AND benefit value driver changes and benefits realized to date.) Are we on track – to budget and benefits plans? • (Includes project, benefits delivery and business impact risks and critical success factors status.) Has the objectives of the project changed? 18
  • 19. 2.2 PRINCIPLES OF EFFECTIVE PROJECT GOVERNANCE: 1: Ensure a single point of accountability. 2: Service delivery ownership determines project ownership 3: Ensure separation of stakeholder management and project decision-making 4: Ensure separation of project governance and organizational governance structures 19
  • 20. 1: Ensure a single point of accountability • Ensures clarity of decision making and empowers the accountable person within the organization. • Consistency of accountability throughout the project’s life ensures proper decision-making – the focus of the project, its objectives and the benefits it seeks remain consistent throughout its life, or at least are not changed without due process. • The project governance framework is a document prepared for each project outlining who has responsibility and authority to make decisions which ensures there is clearly defined accountability for all aspects of the project. 20
  • 21. Effective accountability requires everyone within the project to know: Note: Care should be taken to ensure individuals who join the project receive sufficient introduction to this framework. What they are responsible for. The limits of their authority and tolerance levels. When tasks have to be achieved. Communication, reporting and monitoring lines. 21
  • 22. 2: Service delivery ownership determines project ownership • Organizations have to be more competitive by continuously increasing their quality of service • Services can be delivered directly or indirectly by products. • For example, construction material producers provide services to a housing developer through construction materials they produce, and the way that they serve is considered on quality, schedule, cost, etc, • Changes on technology may support the service or the project which delivers the service. For example, precast concrete panel can shorten construction schedule of the project; 22
  • 23. The project as a transition mechanism Equal importance to project ownership and (service and Asset delivery) 23
  • 24. 3: Ensure separation of stakeholder management and project decision-making Increase in size of the committee. The detailed understanding of each attendee of the critical project issues reduces Many members within the assembly raise more opinions, Questions because they consider that being members of the assembly they are entitled to do so. They just use the meeting to get updated about the project issues stakeholder Management (Project board - decision making) 24
  • 25. 4: Ensure separation of project governance and organizational governance structures • The project governance is ineffective if there are many layers in the project decision making process. • Organization structures generally do not provide the necessary framework to deliver a project. • Adoption of this principle will minimize multi layered decision making and the time delays. • Empower Project decision making body to make decisions in a timely manner. 25
  • 26. What happens if governance is not good? Failure to communicate fully and appropriately on a timely basis. Failure to specify or accept decision making authority and responsibilities. Confusing contract management and decision making. Over emphasis on reporting that reduces meetings to status updates rather than interactive decision making. Non-alignment of key stakeholders. Confusion between the project and organizational decision-making structures. lack of project direction and control. 26
  • 28. Introduction • In 2009, the board of directors decided to invest in the project SSC. It is a five storey office building located on plot A-01, star road, in Star Commercial Complex (SCC), Dilshuknagar, Hyderabad city, Telangana, India with its main objective of initiating the master project SCC and of providing office services to tenants as well as for STAR itself. Total land area of the building is 6,634.03m2. • Total construction schedule of the project is 638 days starting from December 17, 2009 and completed on September 16, 2011, delayed 286 days as per the project plan. 28
  • 29. SSC STRUCTURAL Main building ARCHITECTURAL ParkingInfrastructure M/E Fire prevention and fighting system Electrical works Plumbing/ Water supply Land Scaping WORK BREAK DOWN STRUCTURE • 2,787.5 m2 • Five floors • RCC • Internal traffic • RCC road • 280 bikes • 50 cars • RCC • Sump • Over head tank • Supply 560KVA • Generator • Installation of smoke detectors, sprinklers etc., • 20% 29
  • 30. Project cost Total project cost is classified into eight packages: Original Cost:- 43615USD Liquidated Cost:- 53544USD Original Cost:- 113464USD Liquidated Cost:- 136157USD Original Cost:- 1076514USD Liquidated Cost:- 1076514USD Original Cost:- 44180USD Liquidated Cost:- 46899USD 4:Perfect construction work package 3. Package of transformer and underground water tank: 2. Construction supervision and construction management package: 1. Design package: 30
  • 31. Original Cost:- 1123183USD Liquidated Cost:- 1104384USD 4:Perfect construction work package Original Cost:- 136969USD Liquidated Cost:- 151713USD 4:Perfect construction work package Original Cost:- 31490USD Liquidated Cost:- 22190USD Original Cost:- 3147USD Liquidated Cost:- 3219USD 5. M&E work: 6. Infrastructure and parking shed package: 8. Landscaping work: 7. Retaining wall package: 31
  • 32. THE PROJECT GOVERNANCE FRAMEWORK The Project Director (Engineering Manager) The Project Owner (President) The Senior User (Department Managers) The senior Supplier (Designer and Interior Contractors) Project Board Investment Decision Group (Board of Directors) Project Manager appointed by Senior Supplier Project team (architect, civil engineer, M&E engineer and interior engineer) 32
  • 33. PROJECT SPONSOR • The sponsor of SSC is STAR • The management assigned the president of organization as sponsor of the project. • He is the head of the project board responsible for project success. • He assigned project director and other staff of project board. • He involved in the project board and solved many issues within project board. • He reported the information directly to the investment decision group. 33
  • 34. SENIOR USER • The first defined user of SSC is STAR itself using 900 m2 of building area. • The sponsor assigned manager of the site management department to act as the Senior user of the building after completion of construction. • Operation and maintenance. • Other users are customers having office demand. They are undefined users. • As this manager is not the member of project board. • There is no manual of users requirement from early stage of the project. 34
  • 35. SENIOR SUPPLIER • The project sponsor decided to choose the senior suppliers from outside of the organization. • Company A was assigned as the designer of the project. • Company B was selected for main construction packages through bidding process. • Company C was nominated by owner for sub-construction works like transformer, underground water tank and retaining walls. • Company D was nominated for infrastructure and parking sheds by sponsor. • Company E was nominated by sponsor for landscaping. It is reminded that all of the senior suppliers nominated by owner are professional in the allotted works 35
  • 36. PROJECT DIRECTOR • The project owner appointed the manger of the engineering department as the project director. • He is the member of the project board and reports the information directly to the project owner and also the project manager. • The project director nominated two engineers in the engineering department to act as project engineers for the SSC. • The project director presented daily in the project to keep the project supported. • The project director is expertise in construction management, so he could assist the project owner to drive the project successfully. 36
  • 37. PROJECT BOARD • The project board was established as per the decision of the project owner. • Members of the project board are the project owner, the project director, and the senior supplier. • The project board was lack of senior user as discussed in the above article senior user. • The main objective of the project board is decision making. • Weekly meeting are held. (Project budget, project quality, project work scope, material changes, budget changes.) 37
  • 38. PROJECT MANAGER • Project manager was assigned by senior supplier and approved by sponsor. • Position of project manager has changed based on the stages of the project. • The project manager is responsible to deliver the project within the time, cost and money mentioned in contract. • The project manager worked closely with the project director to make sure that the project delivery meets the project’s owner’s needs. • There was 5 main project managers represented by companies A,B,C,D and E. 38
  • 39. INVESTMENT DECISION GROUP • The project owner with support from the project board submitted budget plan to the investment decision group (the board of directors) for approval. • In case of budget change, the project board was responsible to consider and give instruction whether it approves for the change. The investment • decision group in this case study includes a chairman, a vice chairman and six directors. 39
  • 40. PROJECT TEAM • The project team comprised engineers assigned by senior suppliers • Members of the project team worked and reported directly with the project manager. Project team architects civil engg, M&E engg Responsible for Detail activities 40
  • 41. ANALYSIS OF CASE STUDY 41
  • 42. PRINCIPLES OF EFFECTIVE PROJECT GOVERNANCE: 1: Ensure a single point of accountability for the success of the project. 2: Service delivery ownership determines project ownership 3: Ensure separation of stakeholder management and project decision-making 4: Ensure separation of project governance and organizational governance structures 42
  • 43. CONSIDERATION ON THE PRINCIPLE 1 OF EFFECTIVE PROJECT GOVERNANCE “Ensure a single point of accountability” The management assigned the president of organization as sponsor of the project. He is the head of the project board responsible for project success. He assigned project director and other staff of project board. He involved in the project board and solved many issues within project board. He signed the liquidated damages. 43
  • 44. CONSIDERATION OF THE PRINCIPLE 2 OF EFFECTIVE PROJECT GOVERNANCE “Service Delivery Ownership Determines Project Ownership” No senior user from the beginning of the project. User needs are not defined. No proper project targets was prepared by owner from early stage of the project. Problems in project investment related to ineffectiveness of parking and space for advertising demands was aroused. 44
  • 45. CONSIDERATION OF THE PRINCIPLE 3 OF EFFECTIVE PROJECT GOVERNANCE “Ensure Separation Of Stakeholder Management And Project Decision Making Activities” • Project governance framework of this project met the requirement of the principle 3. Project board Project owner Project director Senior supplier Therefore, all of the project board meetings were aimed to project decision making. 45
  • 46. CONSIDERATION OF THE PRINCIPLE 4 OF EFFECTIVE PROJECT GOVERNANCE Ensure separation of project governance and organizational governance structures Slow decision making Sponsor President/ Sponsor External issues Director Manager of engg dept/ Director Lot of work load DELAY 46
  • 47. Conclusions/ Recommendations Every organization must follow the project governance framework independent of its size. All the projects should have the project governance framework and also satisfy all the 4 principles of the project governance. Ensure that the person who is selected for the sponsor of the project should have enough ability to manage the framework and project issues. Try to avoid playing multi roles at the same time. Due to which this project have been delayed. 47
  • 48. REFERENCES • Alessia D’Amato and Nigel Roome (2009), Leadership of organizational change toward an integrated model of leadership for corporate responsibility and sustainable development: a process model of corporate responsibility beyond management innovation, Corporate Governance, Vol.9 No 4, pp. 421-434 • Karim S. Rebeiz and Zeina Salameh (2006), Relationship between Governance Structure andFinancial Performance in Construction, Journal of Management in Engineering, Vol. 22, No.1, pp. 20-26. • Charles Y.J. Cheah and Micharl J. Garvin (2004). An open framework for corporate strategy in construction, Engineering, Construction and Architectural Management Vol. 11 No. 3, pp.176-188 • Pearce, J. A., and Zaha, S. A. (1991). “The relative power of CEOs and boards of directors: Association with corporate performance.: Strategic Manage. J., 12, pp. 135-153 Pfeffer, J. (1972). “Size and composition of corporate boards of directors.” Adm. Sci. Q., 17, 218-228 48

Editor's Notes

  1. Key role
  2. 1.Ensures clarity in decision making. 2.Feelling responsible throughout the project life. It clearly mentions who has responsibility to make decisions.