This production schedule outlines the tasks and timeline for a project taking place from September 2016 through December 2016. It includes pre-production activities like research, concept development, and drafting to be done by James H at various locations using a computer. Filming is scheduled for two days in November outside and at a golf club with James H, Elliot K, and Joe Elliott using a camera. Post-production such as editing the digipack cover, back, and inner content will be completed by James Head using Photoshop across multiple weeks in November and December.