SlideShare a Scribd company logo
Transport Economic
Evaluation
17 May 2016
by: Sok-Tharath CHREUNG, Transport Economist
TA 8784-CAM: Second Road Asset
Management Project
CAM: Proposed Second Road
Asset Management Project
1. Introduction
2. Traffic Study
3. Economic Evaluation Methodology
4.Result of Cost Benefit Analysis
Contents
i. The general approach to the economic evaluation of the road improvements
being considered. Previous studies were consulted to assist in the calibration of
the HDM4 model and mid-2015 unit prices were collected. The approach
follows conventional economic appraisal methodology for road improvement
schemes. It takes into account the capital cost of the road maintenance costs,
the potential level of benefit per vehicle, and forecast volumes of traffic.
ii. Traffic study (Traffic Count (TC) and Origin-Destination (OD) Survey) were
conducted on 5 proposed project roads in April 2015. Moving observation
traffic counts were also done to determine appropriated areas of Traffic Count
and OD Survey. The classified traffic counts carried out by MPWT between June
2014 and January 2015 were also collected for 5 project roads, but none was
available for OD survey. Base on the traffic study, the estimation of future traffic
demand were calculated for target years 2035.
iii. Economic analysis covers 2017-2037 periods as the sections of the roads were
getting completed from 2017 onwards. A full 20 years analysis has been carried
out on the base price year 2015. All costs and benefits have been discounted at
12%. Economic price calculated by applying shadow price conversion factor for
all the traded good and services and domestic market prices net of the
domestic taxes and subsidies for non-traded goods.
1. Introduction
2. Traffic Study
ST1: at KM2+500 after Bridge
- OD survey (12hrs)
-TC (24hrs)
ST2: at KM56
-TC (12hrs) ST3: at KM97
-TC (12hrs)
NR8 (AC):
Total Length 125km
Project Length 98km
NR76 (DBST):
Total Length 306km
Project Length 88km
ST4: at KM1 after Junction NR7
- OD survey (12hrs)
-TC (24hrs) ST5 at KM61
-TC (12hrs)
ST6 at KM42
-TC (12hrs)
NR78 (DBST, 121km & AC):
Total Length 191km
Project Length 153km
(Start Km 38: DBST 83km & AC 70km)
ST7: at KM75
- OD survey (12hrs)
-TC (24hrs)
ST8: at KM118
-TC (12hrs)
NR64 (DBST):
Total Length 112km
Project Length 92 km
(Start Km 20 from NR6)
ST10: at KM11
- OD survey (12hrs)
-TC (24hrs)
ST9 at KM 111
-TC (24hrs)
NR67 (DBST):
Total Length 135km
Project Length 135 km
ST11: at KM 1
- OD survey (12hrs)
-TC (24hrs)
ST12 at KM 122
-TC (12hrs)
Schedule of Traffic Survey
(1) VEHICLE
CATEGORIES
A. ESTIMATES OF
BASE YEAR TRAFFIC
(AADT: Annual Average
Daily Traffic)
i. 24 hour adjustment
factor (if the count is
less than 24 hours).
ii. Daily Traffic Variation
factor.
iii. Seasonal Variation
factor.
Traffic Count
TRAFFIC COUNT RESULT - AADT
O-D INTEVIEW SURVEY
((1) Survey Items
Trip Information of interviewee vehicle (Driver & Passenger) mainly focus on:
i. Origin and destination of the trip
ii. Number of passengers
iii. Trip purpose
iv. Contents and weight of freight
(2) Survey Method
The OD interview surveys were conducted to understand the passenger’s and
freight’s movement by road transportation with the questionnaires. The interviewee
vehicles were selected for each vehicle type (only Motorized Vehicles of 15 types as
in traffic count sheet) at the regular sampling rate which depends on the traffic
volume. The standard requirement of sampling rate shall be least 10% of traffic
volume of the same period at each location. The assistance of traffic police to select
the interviewee vehicle was arranged by the Consultant with coordination of
Provincial Department of Public Work and Transport.
(3) Survey Coverage
Survey points along the Project Road are shown in the above Maps. The number of
survey sites, their survey time and sampling rate are as follows:
12 hours: 5 sites, 1 day from 06:00 am to 18:00 pm on weekday (as shown in
Schedule above).
Zone Codes of OD
The OD zoning
system used 208
traffic zones of
which 194 zones are
for districts and 24
zones are for
provinces within
Cambodia; and 14
zones are for cross
border points to
neighboring
countries (These
Zone Codes are
adopted by JICA).
O-D Survey Result
The sampling rate of OD Interview Survey conducted on NR8, NR76, NR78, NR64 and NR67
were achieved more than 10% in total; however the sampling numbers of motorcycle of
NR8, and NR 76 were less than 10%, but other stations were more than 10%. Light vehicles
and trucks were more than 10% considering 12h traffic volume of traffic count of each
station. Table below illustrates the summary of sample rates of 5 locations. The detail
cleaned data of the 5 stations are used for traffic demand forecast.
3. Economic Evaluation Methodology
Procedure of Evaluation
1
Traffic Survey
Computed AADT
Traffic Demand Forecast
Road Improvement to
DBST
(With Project)
Without Improvement
(Without Project)
Estimation of
Financial Costs
RUC (VOC & TTC)
Without Project With Project
Calculation of Benefit Calculation of Economic Cost
Conversion to
Economic Cost
Economic Evaluation
(EIRR, NPV, B/C)
Application of HDM-4
HDM 4
• The Highway Development and Management Tool (HDM-4) has
been used to analyze the upgrading works. This model was
developed by the International Study of Highway Development and
Management (ISOHDM), funded by the World Bank, Asian
Development Bank, and other sponsors. The objective was to
produce a standard model to be used throughout the world to
prepare road investment programs and to analyze road network
strategies. The latest version available for general use is version
2.08, and this has been used in this Study.
• The HDM-4 model simulates road condition for each road section,
year-by-year, using three sets of sub-models:
a. Road Deterioration - which predicts pavement deterioration
and surface roughness;
b. Works Effects - which simulate the effects of road works on
pavement condition and determines the corresponding
costs;
c. Road User Effects - which determine costs of vehicle
operation and travel time.
4. Result of Cost and Benefit Analysis
Code
Length
(km)
Economic Indicators
NPV
($ Mill.)
B/C
Ratio
EIRR
(%)
NR8 98 29.88 2.81 32.5
NR76 88 3.57 1.28 16.4
NR78-1 83 0.11 1.00 12.2
NR78-2 70 8.78 1.80 23.6
NR64 92 0.04 1.00 12.1
NR67 135 3.17 1.21 15.4
Cost Benefit Analysis for all Project Roads
All Road Sections Indicators
EIRR (Economic Rate of Return)
(%)
20.4
B/C Ratio 1.58
Net Present Value (US $ million) 45.55
SENSITIVITY ANALYSIS
• In this study, the conducts of risk and sensitivity analyses are
followed from the ADB's Guidelines for Economic Analysis of
Projects (1997). Quantitative risk analysis provides a means of
estimating the probability that the project NPV will fall below zero,
or that the project EIRR will fall below the opportunity cost of
capital.
• The EIRR was analyzed with respect to changes in the benefit and
cost streams. The tests applied were carried out as the following
manners:
a. Construction costs increased by 20%
b. Vehicle operating costs (VOC) reduced by 20%
c. Construction costs increased by 20% and VOC reduced
by 20%
d. Base year traffic reduced by 20%
e. Traffic growth rates reduced by 20%
f. Value of time benefits excluded
RESULT OF SENSITIVITY ANALYSIS
The Results of Sensitivity Analysis are shown in the following table:
Scenario EIRR (%)
NPV
(US$ million)
Switching
Value (%)
Sensitivity
Indicator
Base Case 20.4 45.55 - -
Costs +20% 17.1 30.86 62.01 1.61
VOC -20% 17.1 25.47 -45.36 -2.20
Traffic Growth Rate -20% 17.5 27.75 -51.17 -1.95
Base traffic - 20% 10.2 -7.76 - -
No time benefits 16.5 22.23 - -
Costs +20% & VOC-20% 13.9 10.78 - -
Conclusion: As the results of sensitivity analysis, the EIRR is most
sensitive to variation in traffic. In case base traffic reduce 20%, the
EIRR will be less than the margin of 12%.
THANK YOU FOR YOUR PAY
ATTENTION!

More Related Content

What's hot

Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
Zawad khalil
 
Traffic studies ORIGIN AND DESTINATION STUDIES
Traffic studies ORIGIN AND DESTINATION STUDIESTraffic studies ORIGIN AND DESTINATION STUDIES
Traffic studies ORIGIN AND DESTINATION STUDIES
Davinderpal Singh
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
Accident study (Traffic Engineering) | Jameel Academy
Accident study (Traffic Engineering) | Jameel AcademyAccident study (Traffic Engineering) | Jameel Academy
Accident study (Traffic Engineering) | Jameel Academy
Jameel Academy
 
Unit 3
Unit 3Unit 3
Introduction of vissim software
Introduction of vissim softwareIntroduction of vissim software
Introduction of vissim software
ashahit
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
VATSAL PATEL
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
Sai Santosh Yakkali
 
Traffic volume-study-presentation-final
Traffic volume-study-presentation-finalTraffic volume-study-presentation-final
Traffic volume-study-presentation-final
Stone Rayhan
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
Md. Abdul Kader
 
Transport engineering copy
Transport engineering copyTransport engineering copy
Transport engineering copy
Wendimu Tefari
 
Highway planning
Highway planningHighway planning
Highway planning
Dhrubajyoti Majumdar
 
Traffic studies volume study
Traffic studies volume studyTraffic studies volume study
Traffic studies volume study
Aglaia Connect
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow Parameters
Hossam Shafiq I
 
Modal split analysis
Modal split analysis Modal split analysis
Modal split analysis
ashahit
 
Fundamentals of traffic Engg
Fundamentals of traffic EnggFundamentals of traffic Engg
Fundamentals of traffic Engg
kiransomase1
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
Pralhad Kore
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section
Rana Ibrahim
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
Kavin Raval
 

What's hot (20)

Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 
Traffic studies ORIGIN AND DESTINATION STUDIES
Traffic studies ORIGIN AND DESTINATION STUDIESTraffic studies ORIGIN AND DESTINATION STUDIES
Traffic studies ORIGIN AND DESTINATION STUDIES
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Accident study (Traffic Engineering) | Jameel Academy
Accident study (Traffic Engineering) | Jameel AcademyAccident study (Traffic Engineering) | Jameel Academy
Accident study (Traffic Engineering) | Jameel Academy
 
Unit 3
Unit 3Unit 3
Unit 3
 
Introduction of vissim software
Introduction of vissim softwareIntroduction of vissim software
Introduction of vissim software
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
 
Traffic volume-study-presentation-final
Traffic volume-study-presentation-finalTraffic volume-study-presentation-final
Traffic volume-study-presentation-final
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
Transport engineering copy
Transport engineering copyTransport engineering copy
Transport engineering copy
 
Highway planning
Highway planningHighway planning
Highway planning
 
Traffic studies volume study
Traffic studies volume studyTraffic studies volume study
Traffic studies volume study
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow Parameters
 
Modal split analysis
Modal split analysis Modal split analysis
Modal split analysis
 
Fundamentals of traffic Engg
Fundamentals of traffic EnggFundamentals of traffic Engg
Fundamentals of traffic Engg
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 

Similar to Presentation transport economics 17_may2106

Final Defence (3).pptx
Final Defence (3).pptxFinal Defence (3).pptx
Final Defence (3).pptx
SohaibHaiderKhan
 
2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx
YogeshShah95
 
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET Journal
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
Stone Rayhan
 
IRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic SignalIRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic Signal
IRJET Journal
 
Session 7b: Part II-Decarbonising freight - ITF
Session 7b: Part II-Decarbonising freight - ITFSession 7b: Part II-Decarbonising freight - ITF
Session 7b: Part II-Decarbonising freight - ITF
OECD Environment
 
tG04 06 5255
tG04 06 5255tG04 06 5255
Sustainable Transportation Strategies for Nagpur City
Sustainable Transportation Strategies for Nagpur CitySustainable Transportation Strategies for Nagpur City
Sustainable Transportation Strategies for Nagpur City
International Journal of Engineering Inventions www.ijeijournal.com
 
Traffic analysis and Road Widening
Traffic analysis and Road WideningTraffic analysis and Road Widening
Traffic analysis and Road Widening
Abhinav Pateriya
 
Traffic analysis and Widening of Roads
Traffic analysis and Widening of RoadsTraffic analysis and Widening of Roads
Traffic analysis and Widening of RoadsAbhinav Pateriya
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
IRJET Journal
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant Water
IRJET Journal
 
Rmtsp 2721303 170900713008_bhavya
Rmtsp 2721303 170900713008_bhavyaRmtsp 2721303 170900713008_bhavya
Rmtsp 2721303 170900713008_bhavya
Bhavya Patel
 
Exit Presentation 2.pptx
Exit Presentation 2.pptxExit Presentation 2.pptx
Exit Presentation 2.pptx
YitbarekSisay
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
Kalpataru Das
 
Una introducción a HDM-4
Una introducción a HDM-4Una introducción a HDM-4
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisSadegh Tabatabaei
 
Assignment No 01 Transportation Engg.docx
Assignment No 01 Transportation Engg.docxAssignment No 01 Transportation Engg.docx
Assignment No 01 Transportation Engg.docx
AhmadAbbas171386
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1Sneha Kaira
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highway
snehakaira
 

Similar to Presentation transport economics 17_may2106 (20)

Final Defence (3).pptx
Final Defence (3).pptxFinal Defence (3).pptx
Final Defence (3).pptx
 
2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx
 
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 
IRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic SignalIRJET- Study of Design Traffic Signal
IRJET- Study of Design Traffic Signal
 
Session 7b: Part II-Decarbonising freight - ITF
Session 7b: Part II-Decarbonising freight - ITFSession 7b: Part II-Decarbonising freight - ITF
Session 7b: Part II-Decarbonising freight - ITF
 
tG04 06 5255
tG04 06 5255tG04 06 5255
tG04 06 5255
 
Sustainable Transportation Strategies for Nagpur City
Sustainable Transportation Strategies for Nagpur CitySustainable Transportation Strategies for Nagpur City
Sustainable Transportation Strategies for Nagpur City
 
Traffic analysis and Road Widening
Traffic analysis and Road WideningTraffic analysis and Road Widening
Traffic analysis and Road Widening
 
Traffic analysis and Widening of Roads
Traffic analysis and Widening of RoadsTraffic analysis and Widening of Roads
Traffic analysis and Widening of Roads
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant Water
 
Rmtsp 2721303 170900713008_bhavya
Rmtsp 2721303 170900713008_bhavyaRmtsp 2721303 170900713008_bhavya
Rmtsp 2721303 170900713008_bhavya
 
Exit Presentation 2.pptx
Exit Presentation 2.pptxExit Presentation 2.pptx
Exit Presentation 2.pptx
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 
Una introducción a HDM-4
Una introducción a HDM-4Una introducción a HDM-4
Una introducción a HDM-4
 
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost Analysis
 
Assignment No 01 Transportation Engg.docx
Assignment No 01 Transportation Engg.docxAssignment No 01 Transportation Engg.docx
Assignment No 01 Transportation Engg.docx
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highway
 

More from Sok-Tharath CHREUNG

08. economics (tharath 20170120) 2nd workshop_v3_kh
08. economics  (tharath 20170120) 2nd workshop_v3_kh08. economics  (tharath 20170120) 2nd workshop_v3_kh
08. economics (tharath 20170120) 2nd workshop_v3_kh
Sok-Tharath CHREUNG
 
G economics (tharath 20170121)_2nd workshop
G economics (tharath 20170121)_2nd workshopG economics (tharath 20170121)_2nd workshop
G economics (tharath 20170121)_2nd workshop
Sok-Tharath CHREUNG
 
Cam presentation current status & master plan_rd_05_jan18
Cam presentation current status & master plan_rd_05_jan18Cam presentation current status & master plan_rd_05_jan18
Cam presentation current status & master plan_rd_05_jan18
Sok-Tharath CHREUNG
 
Status of Cambodian Railway- July, 2015
Status of Cambodian Railway- July, 2015Status of Cambodian Railway- July, 2015
Status of Cambodian Railway- July, 2015
Sok-Tharath CHREUNG
 
Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012
Sok-Tharath CHREUNG
 
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
Sok-Tharath CHREUNG
 
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Sok-Tharath CHREUNG
 
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
Sok-Tharath CHREUNG
 
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
Sok-Tharath CHREUNG
 
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Sok-Tharath CHREUNG
 

More from Sok-Tharath CHREUNG (10)

08. economics (tharath 20170120) 2nd workshop_v3_kh
08. economics  (tharath 20170120) 2nd workshop_v3_kh08. economics  (tharath 20170120) 2nd workshop_v3_kh
08. economics (tharath 20170120) 2nd workshop_v3_kh
 
G economics (tharath 20170121)_2nd workshop
G economics (tharath 20170121)_2nd workshopG economics (tharath 20170121)_2nd workshop
G economics (tharath 20170121)_2nd workshop
 
Cam presentation current status & master plan_rd_05_jan18
Cam presentation current status & master plan_rd_05_jan18Cam presentation current status & master plan_rd_05_jan18
Cam presentation current status & master plan_rd_05_jan18
 
Status of Cambodian Railway- July, 2015
Status of Cambodian Railway- July, 2015Status of Cambodian Railway- July, 2015
Status of Cambodian Railway- July, 2015
 
Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012
 
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
Presentation on Cambodia Railway Master Plan for the 36th ASEAN Railway CEO's...
 
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
 
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
Cambodia China Asean Infrastructure Interconnection Seminar, Beijing, July 2013
 
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.
 
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
Presentation of Cambodian Railway Development & on Costing and Pricing of Rai...
 

Recently uploaded

Predicting Product Ad Campaign Performance: A Data Analysis Project Presentation
Predicting Product Ad Campaign Performance: A Data Analysis Project PresentationPredicting Product Ad Campaign Performance: A Data Analysis Project Presentation
Predicting Product Ad Campaign Performance: A Data Analysis Project Presentation
Boston Institute of Analytics
 
一比一原版(BU毕业证)波士顿大学毕业证成绩单
一比一原版(BU毕业证)波士顿大学毕业证成绩单一比一原版(BU毕业证)波士顿大学毕业证成绩单
一比一原版(BU毕业证)波士顿大学毕业证成绩单
ewymefz
 
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
ewymefz
 
Tabula.io Cheatsheet: automate your data workflows
Tabula.io Cheatsheet: automate your data workflowsTabula.io Cheatsheet: automate your data workflows
Tabula.io Cheatsheet: automate your data workflows
alex933524
 
Investigate & Recover / StarCompliance.io / Crypto_Crimes
Investigate & Recover / StarCompliance.io / Crypto_CrimesInvestigate & Recover / StarCompliance.io / Crypto_Crimes
Investigate & Recover / StarCompliance.io / Crypto_Crimes
StarCompliance.io
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
ewymefz
 
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
correoyaya
 
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
nscud
 
社内勉強会資料_LLM Agents                              .
社内勉強会資料_LLM Agents                              .社内勉強会資料_LLM Agents                              .
社内勉強会資料_LLM Agents                              .
NABLAS株式会社
 
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
John Andrews
 
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
NABLAS株式会社
 
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Subhajit Sahu
 
Ch03-Managing the Object-Oriented Information Systems Project a.pdf
Ch03-Managing the Object-Oriented Information Systems Project a.pdfCh03-Managing the Object-Oriented Information Systems Project a.pdf
Ch03-Managing the Object-Oriented Information Systems Project a.pdf
haila53
 
Best best suvichar in gujarati english meaning of this sentence as Silk road ...
Best best suvichar in gujarati english meaning of this sentence as Silk road ...Best best suvichar in gujarati english meaning of this sentence as Silk road ...
Best best suvichar in gujarati english meaning of this sentence as Silk road ...
AbhimanyuSinha9
 
The affect of service quality and online reviews on customer loyalty in the E...
The affect of service quality and online reviews on customer loyalty in the E...The affect of service quality and online reviews on customer loyalty in the E...
The affect of service quality and online reviews on customer loyalty in the E...
jerlynmaetalle
 
standardisation of garbhpala offhgfffghh
standardisation of garbhpala offhgfffghhstandardisation of garbhpala offhgfffghh
standardisation of garbhpala offhgfffghh
ArpitMalhotra16
 
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
axoqas
 
Jpolillo Amazon PPC - Bid Optimization Sample
Jpolillo Amazon PPC - Bid Optimization SampleJpolillo Amazon PPC - Bid Optimization Sample
Jpolillo Amazon PPC - Bid Optimization Sample
James Polillo
 
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
axoqas
 
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
Tiktokethiodaily
 

Recently uploaded (20)

Predicting Product Ad Campaign Performance: A Data Analysis Project Presentation
Predicting Product Ad Campaign Performance: A Data Analysis Project PresentationPredicting Product Ad Campaign Performance: A Data Analysis Project Presentation
Predicting Product Ad Campaign Performance: A Data Analysis Project Presentation
 
一比一原版(BU毕业证)波士顿大学毕业证成绩单
一比一原版(BU毕业证)波士顿大学毕业证成绩单一比一原版(BU毕业证)波士顿大学毕业证成绩单
一比一原版(BU毕业证)波士顿大学毕业证成绩单
 
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
一比一原版(UPenn毕业证)宾夕法尼亚大学毕业证成绩单
 
Tabula.io Cheatsheet: automate your data workflows
Tabula.io Cheatsheet: automate your data workflowsTabula.io Cheatsheet: automate your data workflows
Tabula.io Cheatsheet: automate your data workflows
 
Investigate & Recover / StarCompliance.io / Crypto_Crimes
Investigate & Recover / StarCompliance.io / Crypto_CrimesInvestigate & Recover / StarCompliance.io / Crypto_Crimes
Investigate & Recover / StarCompliance.io / Crypto_Crimes
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单
 
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
Innovative Methods in Media and Communication Research by Sebastian Kubitschk...
 
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
一比一原版(CBU毕业证)卡普顿大学毕业证成绩单
 
社内勉強会資料_LLM Agents                              .
社内勉強会資料_LLM Agents                              .社内勉強会資料_LLM Agents                              .
社内勉強会資料_LLM Agents                              .
 
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...
 
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
【社内勉強会資料_Octo: An Open-Source Generalist Robot Policy】
 
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
 
Ch03-Managing the Object-Oriented Information Systems Project a.pdf
Ch03-Managing the Object-Oriented Information Systems Project a.pdfCh03-Managing the Object-Oriented Information Systems Project a.pdf
Ch03-Managing the Object-Oriented Information Systems Project a.pdf
 
Best best suvichar in gujarati english meaning of this sentence as Silk road ...
Best best suvichar in gujarati english meaning of this sentence as Silk road ...Best best suvichar in gujarati english meaning of this sentence as Silk road ...
Best best suvichar in gujarati english meaning of this sentence as Silk road ...
 
The affect of service quality and online reviews on customer loyalty in the E...
The affect of service quality and online reviews on customer loyalty in the E...The affect of service quality and online reviews on customer loyalty in the E...
The affect of service quality and online reviews on customer loyalty in the E...
 
standardisation of garbhpala offhgfffghh
standardisation of garbhpala offhgfffghhstandardisation of garbhpala offhgfffghh
standardisation of garbhpala offhgfffghh
 
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
做(mqu毕业证书)麦考瑞大学毕业证硕士文凭证书学费发票原版一模一样
 
Jpolillo Amazon PPC - Bid Optimization Sample
Jpolillo Amazon PPC - Bid Optimization SampleJpolillo Amazon PPC - Bid Optimization Sample
Jpolillo Amazon PPC - Bid Optimization Sample
 
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
 
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
1.Seydhcuxhxyxhccuuxuxyxyxmisolids 2019.pptx
 

Presentation transport economics 17_may2106

  • 1. Transport Economic Evaluation 17 May 2016 by: Sok-Tharath CHREUNG, Transport Economist TA 8784-CAM: Second Road Asset Management Project CAM: Proposed Second Road Asset Management Project
  • 2. 1. Introduction 2. Traffic Study 3. Economic Evaluation Methodology 4.Result of Cost Benefit Analysis Contents
  • 3. i. The general approach to the economic evaluation of the road improvements being considered. Previous studies were consulted to assist in the calibration of the HDM4 model and mid-2015 unit prices were collected. The approach follows conventional economic appraisal methodology for road improvement schemes. It takes into account the capital cost of the road maintenance costs, the potential level of benefit per vehicle, and forecast volumes of traffic. ii. Traffic study (Traffic Count (TC) and Origin-Destination (OD) Survey) were conducted on 5 proposed project roads in April 2015. Moving observation traffic counts were also done to determine appropriated areas of Traffic Count and OD Survey. The classified traffic counts carried out by MPWT between June 2014 and January 2015 were also collected for 5 project roads, but none was available for OD survey. Base on the traffic study, the estimation of future traffic demand were calculated for target years 2035. iii. Economic analysis covers 2017-2037 periods as the sections of the roads were getting completed from 2017 onwards. A full 20 years analysis has been carried out on the base price year 2015. All costs and benefits have been discounted at 12%. Economic price calculated by applying shadow price conversion factor for all the traded good and services and domestic market prices net of the domestic taxes and subsidies for non-traded goods. 1. Introduction
  • 4. 2. Traffic Study ST1: at KM2+500 after Bridge - OD survey (12hrs) -TC (24hrs) ST2: at KM56 -TC (12hrs) ST3: at KM97 -TC (12hrs) NR8 (AC): Total Length 125km Project Length 98km NR76 (DBST): Total Length 306km Project Length 88km ST4: at KM1 after Junction NR7 - OD survey (12hrs) -TC (24hrs) ST5 at KM61 -TC (12hrs) ST6 at KM42 -TC (12hrs) NR78 (DBST, 121km & AC): Total Length 191km Project Length 153km (Start Km 38: DBST 83km & AC 70km) ST7: at KM75 - OD survey (12hrs) -TC (24hrs) ST8: at KM118 -TC (12hrs) NR64 (DBST): Total Length 112km Project Length 92 km (Start Km 20 from NR6) ST10: at KM11 - OD survey (12hrs) -TC (24hrs) ST9 at KM 111 -TC (24hrs) NR67 (DBST): Total Length 135km Project Length 135 km ST11: at KM 1 - OD survey (12hrs) -TC (24hrs) ST12 at KM 122 -TC (12hrs)
  • 6. (1) VEHICLE CATEGORIES A. ESTIMATES OF BASE YEAR TRAFFIC (AADT: Annual Average Daily Traffic) i. 24 hour adjustment factor (if the count is less than 24 hours). ii. Daily Traffic Variation factor. iii. Seasonal Variation factor. Traffic Count
  • 8. O-D INTEVIEW SURVEY ((1) Survey Items Trip Information of interviewee vehicle (Driver & Passenger) mainly focus on: i. Origin and destination of the trip ii. Number of passengers iii. Trip purpose iv. Contents and weight of freight (2) Survey Method The OD interview surveys were conducted to understand the passenger’s and freight’s movement by road transportation with the questionnaires. The interviewee vehicles were selected for each vehicle type (only Motorized Vehicles of 15 types as in traffic count sheet) at the regular sampling rate which depends on the traffic volume. The standard requirement of sampling rate shall be least 10% of traffic volume of the same period at each location. The assistance of traffic police to select the interviewee vehicle was arranged by the Consultant with coordination of Provincial Department of Public Work and Transport. (3) Survey Coverage Survey points along the Project Road are shown in the above Maps. The number of survey sites, their survey time and sampling rate are as follows: 12 hours: 5 sites, 1 day from 06:00 am to 18:00 pm on weekday (as shown in Schedule above).
  • 9. Zone Codes of OD The OD zoning system used 208 traffic zones of which 194 zones are for districts and 24 zones are for provinces within Cambodia; and 14 zones are for cross border points to neighboring countries (These Zone Codes are adopted by JICA).
  • 10. O-D Survey Result The sampling rate of OD Interview Survey conducted on NR8, NR76, NR78, NR64 and NR67 were achieved more than 10% in total; however the sampling numbers of motorcycle of NR8, and NR 76 were less than 10%, but other stations were more than 10%. Light vehicles and trucks were more than 10% considering 12h traffic volume of traffic count of each station. Table below illustrates the summary of sample rates of 5 locations. The detail cleaned data of the 5 stations are used for traffic demand forecast.
  • 11. 3. Economic Evaluation Methodology
  • 12. Procedure of Evaluation 1 Traffic Survey Computed AADT Traffic Demand Forecast Road Improvement to DBST (With Project) Without Improvement (Without Project) Estimation of Financial Costs RUC (VOC & TTC) Without Project With Project Calculation of Benefit Calculation of Economic Cost Conversion to Economic Cost Economic Evaluation (EIRR, NPV, B/C) Application of HDM-4
  • 13. HDM 4 • The Highway Development and Management Tool (HDM-4) has been used to analyze the upgrading works. This model was developed by the International Study of Highway Development and Management (ISOHDM), funded by the World Bank, Asian Development Bank, and other sponsors. The objective was to produce a standard model to be used throughout the world to prepare road investment programs and to analyze road network strategies. The latest version available for general use is version 2.08, and this has been used in this Study. • The HDM-4 model simulates road condition for each road section, year-by-year, using three sets of sub-models: a. Road Deterioration - which predicts pavement deterioration and surface roughness; b. Works Effects - which simulate the effects of road works on pavement condition and determines the corresponding costs; c. Road User Effects - which determine costs of vehicle operation and travel time.
  • 14. 4. Result of Cost and Benefit Analysis Code Length (km) Economic Indicators NPV ($ Mill.) B/C Ratio EIRR (%) NR8 98 29.88 2.81 32.5 NR76 88 3.57 1.28 16.4 NR78-1 83 0.11 1.00 12.2 NR78-2 70 8.78 1.80 23.6 NR64 92 0.04 1.00 12.1 NR67 135 3.17 1.21 15.4
  • 15. Cost Benefit Analysis for all Project Roads All Road Sections Indicators EIRR (Economic Rate of Return) (%) 20.4 B/C Ratio 1.58 Net Present Value (US $ million) 45.55
  • 16. SENSITIVITY ANALYSIS • In this study, the conducts of risk and sensitivity analyses are followed from the ADB's Guidelines for Economic Analysis of Projects (1997). Quantitative risk analysis provides a means of estimating the probability that the project NPV will fall below zero, or that the project EIRR will fall below the opportunity cost of capital. • The EIRR was analyzed with respect to changes in the benefit and cost streams. The tests applied were carried out as the following manners: a. Construction costs increased by 20% b. Vehicle operating costs (VOC) reduced by 20% c. Construction costs increased by 20% and VOC reduced by 20% d. Base year traffic reduced by 20% e. Traffic growth rates reduced by 20% f. Value of time benefits excluded
  • 17. RESULT OF SENSITIVITY ANALYSIS The Results of Sensitivity Analysis are shown in the following table: Scenario EIRR (%) NPV (US$ million) Switching Value (%) Sensitivity Indicator Base Case 20.4 45.55 - - Costs +20% 17.1 30.86 62.01 1.61 VOC -20% 17.1 25.47 -45.36 -2.20 Traffic Growth Rate -20% 17.5 27.75 -51.17 -1.95 Base traffic - 20% 10.2 -7.76 - - No time benefits 16.5 22.23 - - Costs +20% & VOC-20% 13.9 10.78 - - Conclusion: As the results of sensitivity analysis, the EIRR is most sensitive to variation in traffic. In case base traffic reduce 20%, the EIRR will be less than the margin of 12%.
  • 18. THANK YOU FOR YOUR PAY ATTENTION!